This document is a Scope of Work (SOW) for an equipment operator certification training project at U.S. Coast Guard Base Guam. The intent is to furnish labor, materials, equipment, professional services, and supervision necessary to conduct OSHA certification training on weight handling equipment for Coast Guard personnel.
The SOW requires OSHA certified training for 10 Base Guam members on three types of equipment: telehandler with lifting suspended loads, sit-down rider forklift, and Kalmar rough terrain forklift. The training will include classroom instruction and practical testing, with OSHA certificates provided upon completion. The contractor is responsible for all aspects of the training and any damage to government property. The project will be overseen by the designated Project Manager, and access to the Coast Guard facility must comply with security requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
USCG BASE GUAM
1 VICTOR PIER
SANTA RITA, GU 96915
25 JUNE 2024
SCOPE OF WORK FOR
EQUIPMENT OPERATOR CERTIFICATIONS
PROJECT
AT
BASE GUAM
SANTA RITA, GUAM
PART 1 GENERAL
1.01 INTENT: Furnish all labor, materials, equipment, professional services, and supervision necessary to conduct OSHA certification training on weight handling equipment.
1.02 LOCATION: U.S. Coast Guard Base Guam, 1 Victor Pier, Santa Rita, Guam.
1.03 LIAISON: The Project Manager (PM) is CWO Barry Marseglia. He can be reached at (671) 787-9988 and/or via email at barry.a.marseglia@uscg.mil.
1.04 CONTRACTOR SECURITY REQUIREMENTS: The contractor shall provide a list of all on-site personnel, including sub-contractors (including second and third-tier subcontractors), to the PM prior to any site visit. Contractor personnel will be restricted to designated working areas. Any personnel violating this policy may lose access to the Coast Guard Facility. Contractor personnel shall have photo identification at all times while working on Coast Guard Facilities. Contractor shall coordinate access to Naval Base Guam (NBG) with NBG Visitor Control Center (VCC) and adhere to all NBG visitors’ policies.
1.05 CONTINUITY OF FACILITIES OPERATION: Schedule work to minimize interference with the facility’s normal operations. Notify the Contracting Officer and PM 24 hours in advance of any shutdowns. Coordinate work hours desired for all on-site work with PM.
1.06 SAFETY: During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29CFR Part 1926 – Safety and Health Regulations.
1.07 SCOPE: This contract covers a service agreement that meets or exceeds the requirements covered herein and detailed in section A below.
A. U.S. Coast Guard Base Guam: Provide OSHA certification for equipment operators.
1) OSHA certified Training of Telehandler with lifting suspended loads for 10 Base Guam Members.
2) OSHA Certified Training of Sit-Down Rider Forklift for 10 Base Guam Members.
3) OSHA Certified Training of Kalmar rough terrain forklift for 10 Base Guam Members.
4) Includes classroom instructions and practical testing on each of their type forklifts for 10 Base Guam Members.
5) Upon completion provide OSHA Certificate for each qualified member.
1.08 CONTRACTOR FURNISHED: Furnish all labor, materials, equipment, professional services, and supervision necessary to conduct Inspection and Load Test for Base Guam.
1.09 DAMAGE TO GOVERNMENT PROPERTY: Any damage caused to Government property shall be corrected at the Contractor’s expense.
1.010 TEMPORARY FACILITIES
A. SANITARY FACILITIES: Toilet facilities are available for Contractor use at or near the job site. The Contractor shall ensure the facilities remain clean or permission shall be revoked.
B. WATER AND ELECTRICITY: Normal quantities of water and electricity are available at no cost to the Contractor. Cost of these utility connections and disconnections shall be the responsibility of the Contractor.
PART 2 INSPECTIONS AND ACCEPTANCE
2.01 Inspection: The PM or person designated by the PM will accompany Contractor for duration of service visit. Contractor will provide all required documentation for service visit at the conclusion of servicing to the PM.