About this file
This is a Statement of Work (SOW) for construction services issued by the U.S. General Services Administration (GSA) Public Buildings Service for the U.S. Fish and Wildlife Service (FWS).
The project involves the removal of four existing divider doors from the FWS conference room located at Tudor Business Center (Building ID AK3177ZZ), 1011 E. Tudor Road, Anchorage, Alaska 99503. The doors are no longer in use per local fire inspector requirements. The contract is firm-fixed price and covers contract management and construction services including materials, labor, and supervision. Specific project requirements include: providing floor protection for existing carpet tile finishes; carefully detaching the four divider doors from the overhead ceiling track without damaging track components; leaving the existing ceiling track fully intact, clean, and anchored in place; and hauling away and properly disposing of door panels off-site. The contractor must visit the site prior to bid submission to examine conditions and verify all project information. All work must be performed during normal working hours (8:00 AM to 4:30 PM Monday through Friday), with daily cleanup of work areas and maintenance of clean corridors and hallways. The contractor shall provide a detailed work schedule after contract award, obtain necessary licenses and permits, comply with all applicable Federal, State, and municipal laws and regulations, participate in required pre-installation meetings, and complete all punch list items prior to project closeout. A final inspection must be performed after all construction is complete, with key contractor personnel required to attend in-person.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. General Services Administration
Public Buildings Service
Statement of Work for Construction Services Lite
PROJECT IDENTIFICATION
Project Title: FWS Conference Room Divider Door Removal Building: Tudor Business Center Building ID #: AK3177ZZ Building Location: 1011 E. Tudor Road, Anchorage AK 99503
Project Control Number: N/A GSA Work Items: N/A
RWA #: N3848007
Kahua Number: TBD
SOW Author: Michael Luu
Construction Services Lite Statement of Work, V8.0 [FWS Conference Room Divider Door Removal, Tudor Business Center, AK3177ZZ]
[AUG 24, 2026] 2 of 3 Back to Top
1. PROJECT INFORMATION
This section provides an overview of the project.
1.1. PROJECT SUMMARY
U.S. Fish & Wildlife Service (FWS) requires the removal of the existing divider doors located inside the agency’s conference room. The current doors are no longer in use per the local fire inspector.
The Contractor shall coordinate work and gain approvals required in this Statement of Work (SOW) with the Contracting Officer (CO) and Contracting Officer’s Representative/Project Manager (COR/PM) as required.
1.2. CONTRACT TYPE
This contract is a firm-fixed price contract. The services required shall include, but shall not be limited to, the following:
● Contract Management
● Construction Services including Materials, Labor, and Supervision
1.3. DELIVERY TYPE
The project is a Construction Services delivery type.
2. SCOPE OF WORK
This section details the technical requirements and constraints for which the Contractor is responsible. The Contractor shall perform all services described in this Statement of Work (including work required under exercised options, if any). The Contracting Officer and the COR/PM must approve all proposed changes to the Scope of Work.
2.1. PROJECT REQUIREMENTS
1. Provide floor protection at the work site for existing carpet tile finishes.
2. Detach four (4) divider doors from the overhead ceiling track with care to prevent twisting or damage to existing track components.
3. Leave existing ceiling track fully intact, clean, and anchored in place.
4. Haul away door panels and properly dispose materials off site.
The Contractor shall perform all services described in all solicitation documents and Request for Proposal documents including this Statement of Work.
2.2. PROJECT SITE REQUIREMENTS
The Contractor shall visit the site prior to submitting a bid to examine conditions. Access to customer spaces shall be made upon request (and within reason) to review as-built situations, perform field measurements, calculate material requirements, review mechanical electrical and plumbing infrastructure, and identify finishes. It is the Contractor’s responsibility to thoroughly understand the specific conditions in the space to be constructed. The Contractor shall identify any discrepancies and site conditions prior to submission of a bid. The Contractor shall verify for accuracy, any information supplied by the
Construction Services Lite Statement of Work, V8.0 [FWS Conference Room Divider Door Removal, Tudor Business Center, AK3177ZZ]
[AUG 24, 2026] 3 of 3 Back to Top
Government. All work areas must be cleaned at the end of every work day. All corridors and hallways are to be kept clean and free of dirt and debris during the performance of this contract. Where applicable, the contractor must employ adequate dust control measures.
2.2.1. Working Hours
Perform all work during normal working hours. Normal working hours are 8:00 AM to 4:30 PM Monday through Friday.
If at any time work performance becomes disruptive to the tenant agency (due to noise, dust, fumes, etc.), property management may immediately stop work on this project and reschedule the task(s) for a more suitable time.
2.3. CONSTRUCTION SCHEDULE
The Contractor shall provide a work schedule after contract award. The schedule shall contain the start date, finish date, working hours, activities and durations.
2.4. CONSTRUCTION INSPECTIONS
Construction inspections shall be scheduled, coordinated and performed to ensure that all specified materials, means and methods are installed per code compliance and contract. At a minimum, inspections must be performed at the following intervals:
● Final inspection (after all construction is complete)
Key personnel from the Contractor shall be in attendance in-person at all inspections directly related to their discipline.
2.5. MODIFICATIONS / CHANGE ORDERS
A Contract Modification (Change Order) will only be approved if the CO agrees that additional work to be performed by the Contractor, as a result of resolution of an RFI, and is beyond the original scope of work. No work shall be performed until an executed contract modification has been awarded. Proposals from sub-contractors shall be included in any proposal requested by the Contracting Officer.
2.5.1. Permits and Responsibilities
The Contractor shall be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State, and municipal laws, codes, and regulations applicable to the performance of the work.
2.6. MEETINGS
The Contractor shall participate in pre-installation meeting(s) at the installation site, if required. This meeting may include the Government's COR/PM, the Building Manager (or representation) and others.
2.7. PROJECT CLOSEOUT
The Contractor shall complete all punch list items prior to the completion of project closeout.
| 1. PROJECT INFORMATION |
| 1.1. PROJECT SUMMARY |
| 1.2. CONTRACT TYPE |
| 1.3. DELIVERY TYPE |
| 2. SCOPE OF WORK |
| 2.1. PROJECT REQUIREMENTS |
| 2.2. PROJECT SITE REQUIREMENTS |
| 2.3. CONSTRUCTION SCHEDULE |
| 2.4. CONSTRUCTION INSPECTIONS |
| 2.5. MODIFICATIONS / CHANGE ORDERS |
| 2.6. MEETINGS |
| 2.7. PROJECT CLOSEOUT |
| 2026-08-24T09:05:32-0700 | |