Scope of Work (SOW) Alcan Border Station Boiler Replacement
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GENERAL SERVICE ADMINISTRATION Region 10
ALCAN LPOE Boiler Replacement
U.S. GENERAL SERVICES ADMINISTRATION, NORTHWEST/ARCTIC REGION 10
SCOPE OF WORK
Section 1:
Project Location & Building Number
Section 2:
Background
Section 3:
Work Hours
Section 4:
Parking/ Loading Dock
Section 5:
General Information
Service Building Alcan LPOE, Mile 1221.8 Alcan Hwy Tok, Alaska 99780
AK0507AH
The United States General Services Administration requires the demolition/removal of
(2) each fuel oil fired Burnham 3-pass cast iron boilers and replacement with modern higher efficiency units. The antiquated system presently in operation is not capable of adequately heating the entire facility during extreme cold weather cycles. Each of the new boilers must be individually capable of carrying the entire facility BTU heat load during the coldest winter months when outside ambient air temperatures can reach -50’F and colder.
This project shall be accomplished between the hours of 6:00 AM and 8:00 PM and may take place any day of the week to include weekends and Federal holidays. Contractor shall schedule the work in writing with the GSA Project Manager (PM).
Contractor parking at the Service Building is available. Access to the facility requires coordination with the GSA Project Manager in advance.
1. All work shall comply with the latest versions of GSA’s PBS-P100, Facility Standards for the Public Buildings Service http://www.gsa.gov/portal/content/104821, and GSA Region 10 Fire Alarm Design, Installation and Testing Policy
2. Specific attention should be given to PBS P-100 Chapter One requirements including Laws, Regulations, Codes and Standards, and Key Sustainable Product requirements for carpet, interior paint, gyp board, ceiling tiles, and concrete.
3. Contractor shall provide all supplies, equipment, materials, services, and labor to perform the work.
4. Contractor shall be responsible for obtaining all necessary local, state, and federal permits, licenses, and clearances.
5. Field Verification: All work dimensions, quantities, and locations shall be field http://www.gsa.gov/portal/content/104821
Section 6:
Description verified by the contractor.
6. Contractor Use of Premises: The Contractor shall coordinate with the GSA PM to arrange a schedule for site access during construction. Construction processes disruptive to normal facility operations shall be coordinated with the GSA PM in writing at least 5 business days in advance. The Contractor shall be authorized to use building restrooms.
7. Utilities: Contractor shall be authorized to use utilities during the course of this project. The contractor is responsible for making connections to the existing utility systems. Temporary electrical work shall meet the requirements of NFPA 70. When temporary connections are removed, the Contractor is responsible for restoring existing utility services to their original condition.
8. Utility Outages and Locates: No utility outages will be approved without the written consent and approval of the GSA PM. Requests for utility outages shall be coordinated in writing at least 5 business days in advance with the GSA PM.
9. Protection of Public: The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
10. Housekeeping: The project site shall be kept in a neat, orderly, and safe condition at all times and all work areas shall be cleaned at the end of each work day. A final cleaning of the entire construction area will be required at substantial completion of the project. Final Cleaning to include (1) Removal of all tools, equipment, surplus material, and rubbish/debris; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Removal of grease, dirt, stains, foreign materials, and labels from finished surfaces; and (4) thoroughly clean building interiors.
11. Disposal: Ensure all waste materials and debris is disposed at an Alaska
Department of Environmental Conservation (DEC) approved disposal site, in accordance with applicable environmental regulations. Unless otherwise specified, all material(s) removed becomes the property of the Contractor.
12. Communications: Contractor project designee must be available to provide project status updates to GSA each work day. Contractor is required to work in close collaboration with the GSA O&M representative on site.
As indicated, execute the project as follows:
1. Proposal: Design plan will follow and comply with NFPA 72, NFPA 101, IBC, IECC, IMC, IFGC, IFC, UPC, GSA R10 and GSA PBS P-100 standards. Based on the attached 2014 ALCAN Site Visit 2014 Report, develop a bid plan and submit design as outlined in the following paragraphs. A separate NTP for construction will be issued by the GSA CO.
2. Design Development and Submission: Contractor shall submit each design phase (65%, 95% and 100%) to GSA Project Manager and Contracting Officer for approval. All drawings shall be submitted electronically in PDF format. Contractor receipt of approved comments will begin next phase. All approved comments and corrections will be included on next phase submission. 100% drawings showing all final corrections and comments must be submitted within fourteen (7) calendar days of 95% approval.
a. Upon NTP for Design, Contractor and Government will adhere to following design and review timeline:
65% Design Submittal 21 Calendar Days
Government Review 7 Calendar Days
Incorporate Review Comments 7 Calendar Days
95% Design Submittal and Specs 14 Calendar Days
Government Review 7 Calendar Days
Incorporate Review Comments 7 Calendar Days
b. Design details must provide at a minimum:
Proposed boiler type and specifications.
Proposed engineering system Drawings.
Proposed BAS integration drawings.
3. Government Review: The Government may require up to seven (7) calendar days to complete reviews prior to providing comments on the 65% & 95% design.
4. Construction: Upon NTP for Construction, the Contractor shall provide labor, material, tools, transportation, supplies, supervision, and equipment necessary to complete the boiler replacement and ancillary requirements in accordance with approved design.
a. Prior to beginning work, the Contractor shall submit a construction schedule showing major milestones and significant site coordination events.
b. Installation of new system must be complete and fully operational NLT 1 October 2018.
c. Contractor shall demo and dispose of (2) existing oil fired Burnham 3-pass cast iron boilers.
d. Contractor shall replace the two existing boilers and associated equipment and piping with the highest efficiency boiler possible. Each boiler shall be sized by the Contractor to handle the full load of the facility under a design day appropriate for the area as defined by ASHRAE. System replacement shall include expansion tanks, chemical feeders, and a complete system flush and fill with the appropriate glycol solution.
e. Contractor shall remove old ancillary equipment piping, secondary pumps etc.) and dispose of as required.
f. Contractor shall modify existing piping with a traditional primary/secondary piping system (i.e. the system is decoupled with separate pumps, see attachment 1).
g. Contractor shall replace the constant volume distribution pumps to the system with variable speed pumps (2 minimum) controlled by differential pressure controls located in the distribution piping.
h. Contractor shall supply and install new ancillary equipment into the system in accordance with GSA approved design.
i. Contractor shall integrate the boiler controls with the existing facility JCI Building Automation System (BAS) controls. Boilers shall be setup for
Section 7:
Submittals automatic lead-lag control.
5. Operational Testing: Contractor shall coordinate complete 100% acceptance/commissioning test of new system, zones and controls with GSA Project Manager and/or designee in accordance with R10 and P100 standards.
Submittals: : Shop drawings, Manufacturer’s product data, product samples and MSDS data sheets must be submitted to the Project Manager and Contracting Officer in the form of a submittal. Submittals verify design intent; however, approved submittals DO NOT automatically constitute a waiver to the contract document requirements. If a waiver or deviation from the contract document requirements is required the Contractor must submit a Request for Information (RFI) to the Contracting Officer. The Contracting Officer will determine if a waiver is permitted and respond to the RFI.
Submittals required by this contract are the following:
1. Drawings:
a. Provide 65%, 95% and 100% CAD drawings in PDF format for approval in accordance with submission timeline depicted in Section 6.
Submit revised drawings in PDF format for approval.
Final drawings shall be provided to GSA in AutoCAD and PDF formats.
2. Work Schedule:
a. Submit a Construction Schedule for the contract period within seven (7) calendar days of contract award. Indicate lead time for materials submittal and delivery.
The schedule shall be in Gantt format.
The schedule shall provide project start and completion dates that will be used to coordinate the work of all project trades, and shall identify time required prior to construction for ordering/obtaining materials if necessary.
Contractor shall provide a revised Project Schedule when schedule changes are deemed as being significant by the COR.
3. Material specifications:
a. Boilers
b. Pumps
c. BAS components
d. Valve components
e. Other ancillary components and/or equipment
4. Substantial Completion and Final Inspection:
a. When project, or designated portion of project is complete, request a substantial completion inspection.
b. Upon receipt of request that project is substantially complete, the GSA PM will proceed with the inspection or will advise the contractor of items that prevent the project from being designated substantially complete.
5. Defects and Omissions:
a. Final inspection shall be coordinated and scheduled through the PM and CO.
Contractor shall submit Defects and Omissions List to COR at least five (5) working days prior to scheduled close out meeting/completion of project.
b. Upon receipt of the punch list, GSA will inspect the jobsite; based on the Contractor’s punch list and GSA’s inspection, GSA will provide the Contractor
Section 8:
Attachments with any additions or comments within two (2) days.
6. Close out Requirements:
a. Warranties - The contractor shall be responsible for installing all material and equipment in accordance with original manufacturer specifications and requirements. All warranty documents shall be provided to the COR in duplicates of three.
b. Contractor shall provide red-line copies of as-built drawings in CAD format prior to final payment request.
c. Contractor shall provide itemized equipment list and O&M materials.
d. Draft Invoice – to be reviewed/approved by the COR prior to submittal of final invoice.
e. Final Invoice – submit to contracting officer upon approval of draft invoice.
f. Submit Release of Claims per contract requirements.
Attachments:
1. Reports:
a. NMSI Field Report dated 9/18/14
b. AMES Heat Study report dated 12/30/14
c. Cinnovas Building Engineering Review (BER) report dated 9/28/16
END OF SCOPE