FFB Sewer Construction Scope of Work
U.S. GENERAL SERVICES ADMINISTRATION, NORTHWEST/ARCTIC REGION 10
Section 1:
Project Location & Building Number:
Fairbanks Federal Building (FFB) 101 12th Ave Fairbanks, AK 99701
Building Number: AK0029ZZ: RAK11316
Section 2:
Background:
The Fairbanks Federal Building (FFB) was constructed in 1979. The FFB has a steel and glass exterior, a steel and concrete interior, and has three floors as well as a partial basement level. The Fairbanks Annex Building (Annex), located across from the FFB, was also constructed in 1979.
The sewer line from the Annex building (see attached site plan) had been tied into an old wooden stave drain from the WWII Army base days. The sewer line/drainage does not drain properly into the manhole, freezes every year, and causes backups in the sewer. The heat trace does not go into the wooden stave pipe. When frozen, the effluent backs up into the oil sump in the garage of the Annex. This is the only indication that the line freezes - until then there is no indication. Once the lines freeze, the restrooms located in the Annex can no longer be used and the occupants must use the restrooms in the FFB.
There are no known sewer problems associated with the FFB.
The two sewer lines tie together and run off the site to the northwest corner of the property (see attached 1979 site plan).
The purpose of this project is to repair, replace, or rehabilitate the sewer/drainage condition of the structures from both the FFB and the Annex as indicated in the attached technical specifications and drawings.
SEE attached pdf “FFB Sewer Service Condition Report Memo” for additional background information.
Section 3:
Work Hours:
Section 4:
Parking/ Loading Dock/Storage
Section 5:
General Information
Access to the Fairbanks Federal Building must be during normal working hours of 8:00 AM to 5:00 PM weekdays, except Federal holidays.
Parking at the FFB is the responsibility of the Contractor. Access to the loading dock requires advanced coordination with the GSA Project Manager (PM). No storage is available.
1. All work shall comply with the latest versions of GSA’s PBS-P100, Facility
Standards for the Public Buildings Service http://www.gsa.gov/portal/content/104821, and GSA Region 10 Fire Alarm Design, Installation and Testing Policy http://www.gsa.gov/portal/content/104821
GENERAL SERVICE ADMINISTRATION Region 10
The PBS-P100 requires compliance with ICC Plumbing Code 2015 edition.
Contractor must also comply with Uniform Plumbing Code.
2. Specific attention should be given to PBS P-100 Chapter One requirements including Laws, Regulations, Codes and Standards, and Key Sustainable Product requirements for carpet, interior paint, gyp board, ceiling tiles, and concrete.
3. Contractor shall provide all supplies, equipment, materials, services, and labor to perform the work.
4. Contractor shall be responsible for obtaining all necessary local, state, and federal permits, licenses, and clearances.
5. Field Verification: All work dimensions, quantities, and locations shall be field verified by the contractor.
6. Contractor Use of Premises: The Contractor shall coordinate with the GSA PM to arrange a schedule for site access. The Contractor shall be authorized to use building restrooms.
7. Utilities: Contractor shall be authorized to use utilities during the course of this project. The contractor is responsible for making connections to the existing utility systems. Temporary electrical work shall meet the requirements of NFPA 70.
When temporary connections are removed, the Contractor is responsible for restoring existing utility services to their original condition.
8. Utility Outages and Locates: No utility outages will be approved without the written consent and approval of the GSA PM. Requests for utility outages shall be coordinated in writing at least 5 business days in advance with the GSA PM.
9. Protection of Public: The building site will continue to be used by tenants. The contractor shall fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
10. Housekeeping: The project site shall be kept in a neat, orderly, and safe condition at all times and all work areas shall be cleaned at the end of each work day. A final cleaning of the entire construction area will be required at substantial completion of the project. Final Cleaning to include (1) Removal of all tools, equipment, surplus material, and rubbish/debris; (2) Restore or refinish, to original condition, surfaces that are damaged due to the work of this contract; (3) Removal of grease, dirt, stains, foreign materials, and labels from finished surfaces; and (4) thoroughly clean building interiors.
11. Communications: Contractor project designee must be available to provide project status updates to GSA each work day.
Section 6:
Description:
Contractor shall execute the project as follows (see attached specifications and drawings):
Attached drawings and specifications shall prevail over scope of work.
1. See attached Traffic Pattern Map; this is the preferred traffic pattern flow to remain accessible during construction. If traffic pattern flow cannot be met, provide alternate routes for GSA approval.
2. Locate all underground utilities prior to excavation.
3. Document existing conditions.
4. Protect existing site improvements to remain from damage during construction.
5. Place detectable warning tape 3’ above all new sanitary sewer line.
6. Perform a video inspection of the sewer from the manhole in the northwest corner of the property to the City sewer line at 12th Ave. Evaluate and determine the condition of this portion of sewer. Provide a simple summary of the condition of the pipe by email to the GSA Project Manager and Contracting Officer; include recommendation if pipe is failing.
7. Rehabilitate the entire ~290-foot-long sewer from the FFB Main Building with a cured-in-place (CIPP) liner.
a. Prior to installation of CIPP liner, cut and remove minimum 20 linear feet of existing 6” diameter wood stave sanitary sewer line from the manhole that both the FFB Main Building and Annex sewer lines meet (northwest corner of the property), to the FFB Main Building and replace with new 6” diameter ductile iron pipe (minimum 20 linear feet),
b. From same manhole location to 12th Avenue, cut and remove minimum five
(5) linear feet existing 8” diameter ductile iron sewer main and replace 8” diameter new ductile iron pipe.
c. Remove and replace the existing manhole with a new modern 48” diameter precast manhole.
8. Remove and replace sewer from FFB Annex, as indicated in drawings. The new sewer pipe shall be 4” diameter HDPE sanitary sewer pipe, properly graded to a uniform slope and insulated and protected from freezing.
9. Remove cleanouts, as indicated on drawings, and replace with new ductile iron cleanouts.
10. Install heat trace, as indicated on drawings.
11. Restore all disturbed or damaged improvements to original condition.
All work shall conform to USA Standards, the 2015 International Plumbing Code and the project specifications, whichever is more stringent.
Section 7:
Submittals
Submittals: All documents shall be in electronic format with read/write capability using applications that are compatible with General Services Administration (GSA) Standard Software (Microsoft Office), Adobe Acrobat format, and CAD.
Submittals verify design intent; however, approved submittals DO NOT automatically constitute a waiver to the contract document requirements. If a waiver or deviation from the contract document requirements is required the Contractor must submit a Request for Information (RFI) to the Contracting Officer. The Contracting Officer will determine if a waiver is permitted and respond to the RFI.
Submittals required by this contract are the following:
1. See attached Excel “FFB Sewer Submittal Register” and pdf “FFB Sewer Pipe
Specifications” noting submittals required. The submittal register is a guide for submittal requirements. Submittals are required in accordance with the FFB Sewer Specifications.
Section 8:
Attachments
1.
1. FFB Sewer Service Condition Report Memo (pdf)
2. FFB Sewer Pipe Specifications (pdf)
3. SBU FFB Sewer Drawings (pdf)
4. SBU FFB Sewer Ownership Drawing (pdf)
5. AK0029ZZ GSA FFB Sewer Ownership Limits 180214 (pdf)
6. FFB Traffic Pattern Map (pdf)
7. FFB Sewer Submittal Register (Excel)
NOTE to obtain SBU drawings, Contractor must request SBU from the Contracting Officer.
End of Scope of Work