ENN SOW Final.pdf
PDF 160 KB Posted
- Attached to
- VORTAC Vegetation Removal Nenana AK Federal contract opportunity
- Solicitation number
- 697DCK-20-R-00528
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Location.png | PNG image | |
| Aerial photo of ENNVOR 03-05-2020-233606 2.pdf | ||
| 697DCK-20-R-00528.pdf | ||
| Nenana RE dwg land.pdf | ||
| AK20210001 Wage Determination.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY OF WORK
Nenana VORTAC Vegetation Removal
March 8, 2021
1.0 GENERAL
FAA VORTAC equipment requirements include a ground level horizontal 1000 ft. radial clear zone. The Nenana VORTAC located on FAA property has had significant vegetation growth encroaching the 1000 ft. radial clear zone. As a mountaintop facility, there are trees located on the flat top and the sloped edges surrounding the antenna. Trees below the horizontal antenna base field of view do not affect signal radiation. Approximately 5 acres of trees and brush require removal. The remaining 1000 ft. zone is below line of site and does not affect the signal. The purpose of this project is to remove approximately 5 acres of vegetation from the areas designated on the attached map for the FAA VORTAC facility in Nenana, Alaska.
1.1 SCOPE
The scope of work includes, but is not limited to, the following:
The selected Contractor shall furnish all labor, (specialized) equipment, materials, transportation and supervision of the work associated to complete all of the work. This includes, but is not limited to; identify the limits of the radial zone, identify the vegetation/trees within the specific zone and proceed to remove the vegetation/trees. Prior to project implementation, all working concepts and/or methods shall be reviewed by the FAA’s Contracting Officer’s Representative (COR).
The following items are a summary of the project and are provided solely for the purpose of describing the general nature of the work. The Contractor is responsible for accomplishing all items of work identified in the applicable drawings, specifications, and provisions of the contract:
A. General
1. Prior to bidding on the contract, all potential contractors shall attend a pre-bid walk through of the site. A FAA representative will coordinate the exact day and time of the walk through. No Contractor shall be allowed on site without prior scheduling and approval from the FAA.
2. Contractor shall provide proof of certifications, licensing, bonding and/or insurance to cover possible damages.
3. The Nenana VORTAC is an active operational FAA facility 24 hours a day, 7 days a week.
Nenana Vegetation Removal SOW Page 2 Nenana, Alaska
4. All work shall be coordinated with the FAA and be accomplished on a “Not to interfere with FAA operations” basis. Access to the site is restricted and requires FAA escort at all times.
5. Equipment and personnel shall not enter the 1000 ft radial zone without FAA coordination and approval as this will affect the operation of the facility and could cause interference with aviation safety.
6. Construction material shall be stored only in FAA approved areas.
7. Construction staging shall be allowed only in FAA approved areas.
8. The Contractor shall ensure the 1000 ft radial zone is free of equipment, debris piles, or other matter at the end of the day unless approved by the COR.
9. Vegetation removal shall be done in a manner, which provides minimal impact to the ground to avoid excessive erosion or drainage.
10. There is no water or plumbed facilities on site. The Contractor shall provide temporary sanitation facilities (porta john) with hand sanitation on site for the duration of the work. An FAA representative will review and approve the location of these facilities before placement.
11. Electrical power will not be available to the Contractor at the site. If electrical power is required, the Contractor shall arrange for a temporary power source.
B. Site Specific Requirements
1. The location of the work is on a mountaintop with significant slopes.
2. The Contractor shall locate and be cognizant of all overhead power lines on the lot before beginning project.
3. The Contractor shall review all cut areas associated with this work on the Government provided VORTAC map with the COR.
4. Contractor shall plan work and coordinate with the COR at least 1 week prior to commencement of work for site access, location, and areas to be cleared.
5. All contractor personnel shall remain in the designated construction areas at the scheduled times and is not allowed access without FAA escort.
6. All tree cutting shall be accomplished by skilled personnel, experienced in this type of work and topography. All labor and logging shall be in strict conformance with rules, regulations and recommendations of the Occupational Safety and Health Administration (OSHA). All cut, dead, or downed tree/brush debris within the construction boundary must be removed from the site by the Contractor. Contractor must protect against debris travel down the hillside.
7. The Contractor shall not burn or chemically treat material/debris on site as a method of vegetation control.
Nenana Vegetation Removal SOW Page 3
8. The Contractor shall cut all vegetation at or below 4 inches from the ground.
9. Trees or brush removed from the designated area must be cut no more than 4” above ground level. Stumps in traffic areas must be removed.
10. The Contractor shall remove all cut material from the site or shred to a fine mulch in place. If shredded, clippings must be not be more than four inches in depth and level with the ground. The COR must approve final clipping method and locations.
11. Prior to any project activities, all environmental and safety reviews must be completed.
12. The Contractor shall conduct brush/tree removal operations in a manner that will protect the surrounds FAA facilities and equipment.
1.3 MEETINGS
The contractor shall attend all meetings scheduled by the CO or COR (in person or by phone) to discuss work objectives, scheduling and facility/property access.
1.4 CONSTRUCTION CONDITIONS
A. Meetings - The Contractor shall attend all meetings including a pre-construction conference at the time and location specified by the CO.
Requirements for material disposal, security and safety will be discussed. Use of facility restrooms, water, and power will also be discussed. Compliance with these procedures while on site is mandatory.
B. Conflict Resolution - The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings shall rule in all cases. Specifications shall govern over drawings. If any conflict should exist between site drawings (location-specific drawings) and standard drawings (drawings not referring to a particular location), the site drawings shall govern. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and notify the COR. No work shall be done until agreement has been made with the COR.
C. Inspection –
1. Access for Inspection - The Contractor shall allow the COR complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the COR before being obscured by the next operation of the Contractor. In all cases, the COR shall be informed accordingly and given access to the work. Work obscured before inspection and acceptance by the COR, may, at the option of the COR be opened for inspection at no additional cost to the Government.
The COR will inspect all work in progress up to completion and
Nenana Vegetation Removal SOW Page 4 final Contractor’s Acceptance Inspection (CAI) as related to the tree cutting activities. Such inspection may extend to all or a part of the work for the preparation. The COR will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.
2. Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The COR will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present. It may be held concurrently with the CAI.
D. Project Coordination - The Contractor shall be required to coordinate his/her construction activities with the FAA through the COR. All work which affects the facility shall be coordinated and approved by FAA personnel through the COR at least forty-eight (48) hours in advance of the scheduled work. Failure to notify and obtain the necessary approval may result in a rescheduling of the work. If weather conditions or aircraft operations preclude a scheduled shutdown of an existing FAA facility, the Contractor shall reschedule the work. The Contractor will be required to coordinate all power shutdowns of existing facilities with the FAA, through the COR, seventy-two (72) hours in advance.
Each shutdown shall be limited and off-peak hours shall be required for testing or power shutdowns, with the facility placed back in service at the end of the workday, or as stipulated by the FAA.
E. Layout of Work - The Contractor shall field verify measurements. The Contractor shall furnish, at his/her own expense, all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work from the base lines and bench marks previously established. The Contractor will be held responsible for the execution of the work as detailed in the plans and specifications. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them.
F. Compliance with Local and Other Codes - The Contractor shall comply with local and other codes and standards. Where the requirements of the specifications and drawings exceed those of the local or other codes, the Contractor shall comply with the requirements of the specifications and drawings.
G. Stop Work Orders - When the Contractor or subcontractors are notified by the COR of any non-compliance with the provisions of the contract and the action(s) to be taken, the Contractor shall correct the
Nenana Vegetation Removal SOW Page 5 unsafe or unhealthy condition. Life threatening or other serious violations shall be corrected immediately. Non-serious violations shall be corrected within 24 hours of the non-compliance notice. The COR may stop the work with a “stop work order” if the Contractor fails to comply promptly with all or any part of the work being performed.
When, in the opinion of the COR, satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, the Contractor may resume work. The Contractor shall not be allowed any extension of time or compensation for damages by reason of or in connection with such work stoppage.
H. Protection of Existing Vegetation, Improvements and Structures - The Contractor shall take all precautions necessary to protect the existing facilities, equipment, buildings, foundations, vegetation, etc., during construction. Any areas damaged by the Contractor or any subcontractors, shall be repaired or replaced to their original conditions by the Contractor at no additional cost to the government. Repairs shall be approved by the COR and shall match to original finish. The Contractor shall provide all temporary covers, enclosures, barricades, etc., required to protect the existing facilities.
I. Schedules
1. Project Schedule - The Contractor shall, within five (5) calendar days from date of award of contract, submit to the CO for approval a practical project schedule. The schedule shall show the order in which the Contractor proposes to carry out the work, the date on which he/she will start the several salient features (including procurement of materials, plant and equipment) and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time. The Contractor shall enter on the chart the actual progress at such intervals as directed by the CO. The project schedule shall include a milestone schedule for payments. The milestones should be stated with requested reimbursement for each milestone (based upon actual costs, overhead and profit).
2. Progress Schedule - The Contractor, if requested by the CO, shall submit a progress schedule at such intervals as directed by the CO. If the Contractor fails to submit a progress schedule within three (3) business days, the CO may withhold approval of progress payment estimates until the Contractor submits the required progress schedule.
3. Hours of Work – Shall be approved by the COR, all work shall be accomplished during normal business hours specified by the COR. No work is allowed on weekends and Federal holidays unless approved by the COR in writing.
Nenana Vegetation Removal SOW Page 6
4. Site Access - Access to the site will be via a pre-determined route identified and agreed upon at the pre-construction conference. No Contractor shall be allowed on site without FAA escort.
5. Special Permits - The Contractor shall obtain and submit evidence of all necessary permits for the work. The Contractor shall abide by all requirements dictated by the city, state, federal, airport authority or municipality for such permits without any additional cost to the government.
J. Waste Disposal - The Contractor shall provide on-site containers for the collection of construction waste materials, debris and rubbish and their daily removal from the site. Any spillage on access and haul routes shall be cleaned up immediately. All spoil, waste and debris removed from the work site and not specified for reuse or identified as salvageable items, or identified as contaminated contents shall be disposed of off site in areas authorized by the applicable County, State and/or Local agencies and in accordance with current rules and regulations governing the disposal of such waste. The Contractor, at no additional cost to the government, shall pay disposal fees and miscellaneous charges. Copies of all documentation of the disposal of any fuel or hazardous wastes will be submitted to the COR.
K. Cleanup - The work site shall be kept clean and orderly during the progress of work. After final inspection, but before final acceptance of the work, all exterior surfaces of the equipment shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.
1.5 SAFETY
OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall, at a minimum, provide:
A. Safety Plan - The Contractor shall have and submit a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site. The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.
B. COVID Safety Plan – The Contractor shall have and submit a COVID Safety Plan describing safety practices and plan for symptomatic personnel.
C. Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the
Nenana Vegetation Removal SOW Page 7
Contract. The COR may request documentation or other evidence of training at any time. Personnel without adequate training will be prohibited from using such equipment.
D. Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating, and properly inspected PPE`.
E. Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the COR may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The COR may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.
F. Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent contractor’s foreman is required at the job site. The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.
G. Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.
2.0 CONTRACTOR-FURNISHED MATERIAL AND EQUIPMENT
2.1 MATERIAL DELIVERIES - All material deliveries made under this contract shall be arranged for delivery to the Contractor's material staging area. This area shall be located as determined at the pre-construction conference.
2.2 STORAGE AND PROTECTION -The Contractor, through the COR, shall secure from FAA all necessary clearances for storage areas on site, including any time limitations upon the use of such areas. The storage and protection of Contractor material shall be the sole responsibility of the Contractor. The Contractor shall provide at his/her own expense all fencing, shelters and security personnel as may be necessary for the protection of the material and equipment.
2.3 PERTINENT INFORMATION - Any pertinent information listed about the contractor- furnished material and equipment shall be submitted to the
COR.
3.0 EXECUTION
3.1 CONTRACTOR USE OF PREMISES
A. Use of the Site - Do not disturb portions of the site beyond the areas in which work is required.
Nenana Vegetation Removal SOW Page 8
B. Driveways and Entrances - Keep driveways and entrances serving the premises clear and available to the Government, the Government’s employees, and emergency vehicles at all time. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. The Contractor shall schedule his activities to cause the least amount of interference with FAA operations and at the FAA’s discretion. Such operations shall take precedence over construction convenience.
1.6 SPECIAL SCHEDULING REQUIREMENTS
The Contractor shall coordinate all work with the COR prior to commencement. Work shall be conducted Monday through Friday 8:00 a.m. – 3:00 p.m. unless otherwise approved by the COR. All work shall be completed within 45 days from the start date of the project.
1.7 STORAGE OF MATERIAL AND EQUIPMENT
Staging area to store equipment may be available upon request. Liability of equipment security will be solely the responsibility of the contractor.
1.8 SUBMITTALS
Contractor is required to submit a safety work plan to include a COVID plan for review and approval before start of service. This plan shall also include required climbing/tree removal Personal Protective Equipment (PPE) training certifications and PPE inspections.
Contractor is required to submit all required Environmental Protection Agency National Pollutant Discharge Elimination System (NPDES) Storm water permits required for land disturbances greater than 5 acres for review and approval before start of service.
Contractor is required to submit proof of licensing, bonding and/or insurance for this project.
End of Section