This file is a Data Item Matrix for the T-ARC(X) Cable Repair Ship Functional Design phase, listing required deliverables and their completion levels for Phase I of the acquisition. The matrix contains approximately 120 required deliverables spanning various technical areas including hull design, machinery systems, electrical systems, piping systems, and ship arrangements.
The matrix indicates many deliverables are expected to be completed at 100% level during the Functional Design phase, while others range from 5% to 90% completion. Key deliverables include 3-D Product Models (30% completion), Design Review documentation (100%), various system reports and drawings for hull, mechanical, and electrical systems, and verification/testing documentation. The deliverables are categorized as either J-2a or J-2b items, with some new items added that weren't in previous versions. This matrix appears to support the Navy's revised acquisition strategy for the T-ARC(X) program to achieve greater design maturity before Detail Design and Construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Enclosure 1 Market Research Questionnaire - December 2025.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Functional Design DIs
| DRL Title | Origin | Level of Completion | Suggested Changes | Rationale |
| 3-D Product Model | J-2b | 30% | ||
| Regulatory Body Communications and Correspondence with Enclosures | J-2a | 100% | ||
| Design Maturity Assessment Report | J-2a | 100% | ||
| Design Summary Report | J-2a | 100% | ||
| Design Review Agendas, Presentations, and Minutes | J-2a | 100% | ||
| Preliminary Design Review Data Item Status Summary, Agenda, Presentation, and Minutes | J-2b | 100% | ||
| Functional Design Review Data Item Status Summary, Agenda, Presentation, and Minutes | New | 100% | ||
| Working Groups Meeting Agendas, Presentations, and Minutes | New | 100% | ||
| Special Study Report | J-2b | As Needed | ||
| Speed and Power Report | J-2a | 100% | ||
| Seakeeping Performance Report | J-2a | 100% | ||
| Maneuvering Performance Report | J-2a | 100% | ||
| Intact and Damage Stability Report | J-2a | 100% | ||
| Hull Lines Drawing | J-2a | 100% | ||
| Appendages Drawing | J-2a | 100% | ||
| Compartment Access Drawing | J-2b | 100% | ||
| Trim and Stability Calculations | J-2a | 100% | ||
| Weight Control Plan | J-2a | 100% | ||
| Preliminary Allocated Baseline Weight Estimate | J-2a | 100% | ||
| Model Test Program Plan | J-2a | 100% | ||
| Resistance, Appendage Alignment, Wake Survey, and Self-Propulsion (Stock Propeller) Model Test Report | J-2a | 100% | ||
| Maneuvering Model Test Report | J-2a | 100% | ||
| Model Test Data, Video, and Photographs | J-2a | 100% | ||
| Airborne Noise Analysis Report | J-2a | 50% | ||
| Vibration Analysis Report and FEA Files | J-2b | 100% | ||
| Airborne Noise and Structureborne Vibration Control Plan | J-2b | 100% | ||
| Structural Design Criteria Report | J-2a | 100% | ||
| Standard Structural Details | J-2b | 100% | ||
| Midship and Other Hull Sections Drawing | J-2a | 100% | ||
| Hull Scantling Plans and Profiles Drawing | J-2a | 100% | ||
| Superstructure Scantling Drawing | J-2a | 100% | ||
| Shell Expansion Drawing | J-2b | 100% | ||
| Mast Drawing | J-2b | 90% | ||
| Deck Loading Capacity Drawing | J-2b | 100% | ||
| Foundation Drawings, Analysis Reports, and FEA Files | J-2b | 5% | ||
| Hull Girder Longitudinal Strength Analysis (LSA) Report | J-2b | 100% | ||
| DLA and SFA Analysis Approach | New | 100% | ||
| DLA and SFA Analysis Report(s) | J-2b | 50% | ||
| DPS Performance Report | J-2a | 100% | ||
| Main Machinery System Report | J-2a | 100% | ||
| Machinery Arrangement Drawing | J-2a | 100% | ||
| Equipment Removal Plan | J-2a | 100% | ||
| Endurance Fuel Calculations | J-2a | 100% | ||
| Annual Fuel Consumption Calculations | J-2b | 100% | ||
| Power Management System Description of Operations | J-2b | 60% | ||
| Propulsion Control System Description of Operations | J-2b | 70% | ||
| MCCS Description of Operations | J-2b | 90% | ||
| MCCS Block Wiring and System Architecture Diagrams | J-2b | 70% | ||
| MCCS Input/Output Signal List | J-2b | 20% | ||
| Dynamic Positioning System Description of Operations | J-2b | 100% | ||
| Dynamic Positioning System Control System Description of Operations | J-2b | 80% | ||
| Engine Emissions Control Systems Report | J-2b | 100% | ||
| Combustion Air Intake and Exhaust System Diagram | J-2b | 20% | ||
| Combustion Air Intake and Exhaust System Analysis | J-2b | 50% | ||
| Documented Service Record Report | J-2b | 100% | ||
| ABS Design Assessment Letter | J-2b | 100% | ||
| Engine Low-Load Operation Report | J-2b | 100% | ||
| Propulsion SSV Configuration Management Plan | J-2b | 100% | ||
| Propulsion SSV Regulatory Body Communications and Correspondence with Enclosures | J-2b | 100% | ||
| Electrical System Fault Current Analysis | J-2b | 80% | ||
| Electrical System One-Line Diagram | J-2a | 100% | ||
| Master Equipment List | J-2a | 100% | ||
| Critical Equipment List | J-2b | 100% | ||
| Electrical Power Load Analysis | J-2a | 100% | ||
| System Harmonic Analysis and Report | J-2b | 30% | ||
| Subtransient Reactance Calculations | J-2b | 80% | ||
| Voltage Drop Calculations | J-2b | 100% | ||
| Electrical Power Quality Report | J-2b | 100% | ||
| Arc Flash Hazard Analysis Report | J-2b | 60% | ||
| Power Systems Wiring Deck Plan | J-2b | 100% | ||
| Lighting System One-Line Diagram | J-2b | 100% | ||
| Topside Arrangement Drawing | J-2a | 100% | ||
| Integrated Topside Design Plan | J-2b | 100% | ||
| 3-D Integrated Topside Design Model | J-2b | 30% | ||
| Communications Requirements Matrices | J-2a | 100% | ||
| CCTV Block Wiring and System Architecture Diagram | J-2b | 20% | ||
| Lighting System Design Report | J-2b | 80% | ||
| Ship Control, Integrated Bridge, and Navigation Systems Block and Elementary Wiring Diagram | J-2b | 80% | ||
| IBS Block Wiring and System Architecture Diagram | J-2b | 100% | ||
| IBS Input/Output Signal List | J-2b | 20% | ||
| Sea Plow System Report | J-2a | 100% | ||
| Sea Plow System Drawing | J-2a | 100% | ||
| ROV System Report | J-2a | 100% | ||
| ROV System Drawing | J-2a | 100% | ||
| Cable Stowage and Handling Report | J-2a | 100% | ||
| Cable Stowage and Handling Drawing | J-2a | 100% | ||
| Cable Gear Stowage and Handling Drawing | J-2a | 100% | ||
| Sonar Systems Arrangement Drawing | J-2a | 100% | ||
| CHE Description of Operations | J-2b | 100% | ||
| CHE Block Wiring and System Architecture Diagram | J-2b | 70% | ||
| CHE Control Systems Input/Output Signal List | J-2b | 20% | ||
| MSN Input/Output Signal List | J-2b | 20% | ||
| CS SSV Configuration Management Plan | J-2b | 100% | ||
| HVAC System Report | J-2a | 100% | ||
| Refrigeration System Report | J-2a | 100% | ||
| Refrigeration Plant Cooling Load Calculations | J-2b | 100% | ||
| HVAC Load Calculations | J-2b | 100% | ||
| HVAC System Equipment List and Diagram | J-2b | 100% | ||
| HVAC Design Criteria Manual | J-2b | 100% | ||
| Piping Systems Design Reports | J-2b | 90% | ||
| Fresh and Potable Water Service | J-2b | 100% | ||
| Freshwater Production and Technical Services Water | J-2b | 100% | ||
| Low Temperature Freshwater Cooling | J-2b | 100% | ||
| Firemain and Sprinkling | J-2b | 100% | ||
| AFFF Firefighting | J-2b | 100% | ||
| Fixed Fire Extinguishing (Clean Agent, Galley) | J-2b | 100% | ||
| Washdown Countermeasures | J-2b | 100% | ||
| Watermist | J-2b | 100% | ||
| Ballast/De-ballast and Ballast Water Treatment | J-2b | 100% | ||
| Main and Auxiliary Seawater Cooling Services | J-2b | 100% | ||
| Lube Oil Service, Fill, Transfer, and Purification | J-2b | 100% | ||
| Fuel Oil Service, Fill, Transfer, and Purification | J-2b | 100% | ||
| Sanitary Drain | J-2b | 100% | ||
| Air Escapes, Sounding Tubes, and Overflows | J-2b | 100% | ||
| Bilge and Oily Waste/Waste Oil Collection and Transfer | J-2b | 100% | ||
| HVAC and Chilled Water | J-2b | 100% | ||
| Machinery Combustion Exhaust | J-2b | 100% | ||
| Ship's Service Refrigeration | J-2b | 100% | ||
| EDG Auxiliaries | J-2b | 100% | ||
| Lifting Appliances Drawing | J-2a | 100% | ||
| Deck Systems Report | J-2a | 100% | ||
| Stores Handling and Stowage Arrangement Drawing | J-2b | 100% | ||
| Anchoring, Mooring and Fendering, and Towing Arrangement Drawing | J-2b | 50% | ||
| Boat Stowage and Handling Drawing | J-2b | 70% | ||
| Pollution Control Systems Report | J-2b | 90% | ||
| Airflow, Stack Gas Dispersion, and Stack Design Report | J-2b | 100% | ||
| Area/Volume Report | J-2a | 100% | ||
| General Arrangement Drawing | J-2a | 100% | ||
| Impressed Current Cathodic Protection System Block Wiring Diagram | J-2b | 20% | ||
| Food Service Space Drawing | J-2b | 75% | ||
| Pilot House, Naval Communications Center, and Navigational Equipment Spaces Drawing | J-2b | 75% | ||
| Berthing and Sanitary Space Drawing | J-2b | 75% | ||
| Leisure and Public Spaces Drawing | J-2b | 75% | ||
| Medical Facility Drawing | J-2b | 75% | ||
| Laundry Space Drawing | J-2b | 75% | ||
| Administrative Space Drawing | J-2b | 75% | ||
| Engineer's Operating Station Drawing | J-2b | 75% | ||
| Workshop and Maintenance Area Drawing | J-2b | 75% | ||
| Ship's Store, Storerooms, Lockers, and Special Stowage Drawing | J-2b | 75% | ||
| Mission Area Drawing | J-2b | 75% | ||
| Magazine and Ready Service Locker Arrangement Drawing and Outfit List | J-2b | 75% | ||
| Armory and Gun Mount Arrangement Drawing and Outfit List | J-2b | 75% | ||
| Post-Award Conference Agenda, Presentation, and Minutes | J-2a | 100% | ||
| Cost Estimates | J-2a | 100% | ||
| Phase I Master Schedule | J-2a | 100% | ||
| Notional Phase II Schedule | J-2a | 100% | ||
| Contract Problem Identification Reports | J-2b | As Needed | ||
| Requirements Verification Matrix | J-2a | 100% | ||
| Integrated Ship Verification Program Plan | J-2b | 50% |