This document is an enclosure to a Sources Sought Notice (N00024-26-R-4443) for a DDG 1000 Class ship availability that includes repair/maintenance and modernization work.
The availability encompasses approximately 320,000 hours of repair and maintenance work and 1,000,000 hours of modernization work. The ship specifications include a length of 186 meters, beam of 24.6 meters, and draft of 7 meters, with a depth to the top of the lightning rod of 39.8 meters. The facility requirements include a pier length exceeding 610 feet, 800 amps of 4160-volt electrical service, potable water capacity of 10,000 gallons per day at 55 PSI, firefighting seawater of 1,250 GPM at 150 PSI, sewage/wastewater disposal of 20,000 gallons per day combined, a mean pier water depth exceeding 33 feet, and a dry dock capable of supporting the DDG 1000 Class ship. An LMVLS unit module measuring 44'7" long, 20'8" wide, 41'1" high, and weighing approximately 600 tons must be accommodated.
The modernization scope focuses on the Conventional Prompt Strike (CPS) weapon system installation, which includes removal of the MT 62 Advanced Gun System, installation of the LMVLS magazine and associated launch modules, relocation of Main Turbine Generator intakes, and modifications to the Propulsion Seawater system. Additional modernization work encompasses fuel endurance improvements, MTG intake pressure loss improvements, propulsion system enhancements, EO/IR system improvements, ECS network and hardPLC refresh, crew accommodation increases from 200 to 219 personnel, and various other system upgrades. The maintenance package includes extensive planned maintenance system accomplishments totaling 94,000 checks and 77,000 man-hours, along with numerous specialized maintenance tasks covering hull preservation, propulsion systems, seawater systems, ventilation, fire suppression, steering, anchoring, combat systems, and related equipment across multiple ship systems.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Enclosure (1) to Sources Sought Notice N00024-26-R-4443
General Information and Availability Work Package
A. General
a. Rough Estimate:
i. Repair/Maintenance 320K hours
ii. Modernization: 1,000K hours
b. Ship Particulars:
i. Length: 186m (610 ft)
ii. LBP: 182.9m (600 ft)
iii. Beam, max: 24.6m (80.7 ft)
iv. Draft, DWL: 7m (23.0 ft)
v. Draft, Navigation: 8.4m (27.6 ft)
vi. Depth, Fwd/Aft: 16.5m / 13.5m (54.1 ft / 44.3 ft)
vii. Depth, top Deckhouse: 34.5m (113.2 ft)
viii. Depth, top Ltng Rod: 39.8m (130.6 ft)
c. Facility Particulars:
i. Pier Length: > 610 ft
ii. Electrical: 800 amps, 4160 volts, 60 hz, 3 ph (UFC 4-150-02 table C-7)
iii. Potable Water: 10,000 GPD, 55 PSI (UFC 4-150-02 Table C-4)
iv. Firefighting Sea Water: 1250 GPM (UFC 4-150-02 Table C-3), 150 PSI measured at the most remote outlet (UFC 4-150-02, Para 3-3.2.1)
v. Sewage: Ability to accommodate and dispose of 10,000 GPD of effluent and
10,000 GPD of waste water
vi. Mean Pier Water depth draft: >33 ft
vii. Dry Dock to support DDG1000 Class Ship
d. LMVLS Unit Module Dimensions
i. Length: 44’7”
ii. Width: 20’8”
iii. Height: 41’1”
iv. Weight: ~600 tons
B. The Availability’s modernization scope will largely be removal of the MT 61 Advanced Gun System (AGS) mount, installation of Conventional Prompt Strike capability, relocation of the Main Turbine Generator (MTG) intakes, and incorporation of changes to the Propulsion Seawater (PSW) system. The awarded contractor must be able to include and incorporate AIT integration, 3rd Party contractors, Government personnel, Long Lead Time Material (LLTM) procurement, etc. in their Integrated Production Schedule (IPS). Key trades & efforts include: Structural welding, cabling pulling, piping, electrical and ventilation work if needed. Both the MSR and AIT will execute the structural/Industrial work. A list of work specifications to be performed is provided in Enclosure (2).
C. The Availability’s maintenance package targets prioritized lifecycle and preventative maintenance activities outlined in Enclosure (2):
Enclosure (2)
CONVENTIONAL PROMPT STRIKE (CPS)
ALTERATION WORK SPEC # TITLE DESCRIPTION
SHIPALT-
97881- 711-90-006 MT62 AGS UPPER GUN MOUNT
REMOVAL
REMOVAL OF MT62 ADVANCED GUN SYSTEM (AGS). THIS
INCLUDES REMOVING THE LOWER GUN MOUNT ASSEMBLY,
ROTATING WEATHER SHIELD, AND CENTERLINE HOIST
ASSEMBLY. STRENGTHENING THE MAIN DECK TO SUPPORT
SLAMMING LOADS CAUSED BY REMOVAL OF MT62.
SHIPALT-
97505- 721-90-001 AGS MT 61 REMOVAL AND LMVLS
HM&E MODIFICATIONS
MODIFICATIONS NECESSARY TO SUPPORT INSTALLATION OF
THE CONVENTION PROMPT STRIKE (CPS) WEAPON SYSTEM
WITHIN THE 1400 STACK. INSTALLATION INCLUDES: THE
LMVLS MAGAZINE, APM LAUNCH MODULES, SHOCK
ISOLATION SYSTEM, WEATHER DECK HATCHES, AND ALL
HM&E MODIFICATIONS NECESSARY TO SUPPORT CPS
SHIPALT-
97869- 721-90-002 LMVLS WCS RIPOUT AND
INSTALLATION
INTEGRATION OF (CPS) WEAPONS CONTROL SYSTEM
COMPONENTS INCLUDE THE FOLLOWING: WEAPON CONSOLES,
WEAPONS INTERFACE BOXES, REMOTE DISPLAYS, AND
CS/C4I CABLING AND CONNECTIONS AS REQUIRED FOR CPS
OPERATION AND CONTROL. IN ADDITION, THIS
ALTERATION SUPPORTS RAYTHEON, LOCKHEED MARTIN, AND
NAVWAR AIT WORK SCOPE.
SHIPALT-
98380- 863-71-403 CPS TSCE ENTI CONVENTIONAL
PROMPT STRIKE
BASELINE CONFIGURATION CHANGES ARE NEEDED IN
SEVERAL TSCE HARDWARE CONFIGURATION ITEMS IN ORDER
TO INTEGRATE WITH THE CONVENTIONAL PROMPT STRIKE
WEAPON SYSTEM. PERIPHERALS AND CABLE CHANGES, CPS
EEME CHANGES TO HOUSE CPS RACKS, CPS 1PPS
EQUIPMENT ADDITION TO EME 1B
NON-CPS MODERNIZATION
ALTERATION WORK SPEC # TITLE DESCRIPTION
SHIPALT-
96881- 202-90-001 FUEL ENDURANCE AND RANGE
EXTENSION MODIFICATION
INCREASE THE NAUTICAL MILE RANGE OF THE DDG 1000
CLASS SHIPS. THIS IS ACCOMPLISHED BY INCREASING
THE FUEL OIL STORAGE CAPACITY AS A RESULT OF
CONVERTING EXISTING SALT WATER BALLAST (SWB) TANKS
TO FUEL OIL (FO) STORAGE TANKS.
SHIPALT-
97208- 251-90-001 MTG INTAKE RELOCATION
RELOCATION OF MAIN TURBINE GENERATOR INTAKE
LOCATIONS FROM TOP TO SIDE OF DECKHOUSE TO AVOID
EXHAUST INGESTION WHILE UNDERWAY.
SHIPALT-
97209- 251-90-003 MTG INTAKE PRESSURE LOSS
IMPROVEMENTS
THE EXISTING MTG 1 & MTG 2 INTAKE AND FOUNDATIONS,
FROM THE TOP OF THE INTAKE BOOT THROUGH 2ND DECK,
WILL BE REMOVED AND SCRAPPED. THE BERP PLATES AT
2ND DECK AROUND THE INTAKE WILL ALSO BE REMOVED
AND SCRAPPED. A NEWLY FABRICATED INTAKE SECTION,
WITH MODIFIED GEOMETRY, WILL BE INSTALLED. NEW
BERP PLATES WILL BE INSTALLED AROUND THE NEW
INTAKES.
SHIPALT-
96942- 256-90-001 PROPULSION SEA WATER (PSW)
REDESIGN
THIS MODIFICATION WILL ADD AUTOVENTS TO SEACHESTS
IN THE PSW SYSTEMS THAT ARE CURRENTLY NON-VENTED.
SHIPALT-
97760- 256-90-002
PROPULSION SEA WATER AND
AUXILIARY PUMP SEA WATER
CASING AUTOVENTS
THIS ALTERATION WILL ADD AUTOMATIC AIR RELEASE
VALVES TO (5) MAIN PSW PUMP CASINGS, AND (4) ASW
PUMP CASINGS TO PREVENT PUMP SEAL FAILURE, AND
REMOVE AIR FROM THE PSW/ASW PUMP CASINGS DURING
OPERATION.
SHIPALT-
96880- 261-90-001 FUEL OIL STANDPIPE
MODIFICATION
THIS ALTERATION WILL INCREASE THE REFUELING RATE
OF DDG 1000 CLASS SHIPS WHILE ALONGSIDE, REFUELING
AT SEA (RAS), BY INCREASING THE HEIGHT OF THE FWD
AND AFT FUEL OIL OVERFLOW STANDPIPES.
SHIPALT-
98337- 418-90-001 EO/IR SYSTEM IMPROVEMENTS
ADDITION OF TWO (2) FLIR 380HD CAMERAS, MOUNTED
PORT AND STARBOARD ON THE HOUSE SIDES, ON SPONSONS
SIMILAR TO EXISTING UHF, EHF, AND WHIP ANTENNAS.
INSTALLATION OF WASH SYSTEM FOR CAMERAS AND CESV
WINDOWS
SHIPALT-
97994- 436-90-005 DDG 1000 CLASS ECS HARDPLC
REFRESH
UPGRADING ENGINEERING CONTROL SYSTEM (ECS)
SOFTPLC'S TO HARDPLCS TO AVOID OBSOLESENCE AND
CYBER VULNERABILITIES
SHIPALT-
97995- 436-90-005 DDG 1000 CLASS ECS NETWORK
REFRESH
UPGRADING ECS NETWORK SWITCHES WITH NEW MODELS TO
ADDRESS CYBERSECURITY AND OBSOLESENCE ISSUES
SHIPALT-
98174- 536-90-001
PROPULSION FRESH WATER
(PFW) SYSTEM HIGH POINT
VENT
THIS ALTERATION WILL ADD HIGH POINT AUTO-VENTS
THROUGHOUT THE PFW SYSTEM TO REMOVE ENTRAINED AIR
AND IMPROVE PERFORMANCE OF THE PFW SYSTEM.
SHIPALT-
97983- 583-90-006
BOAT HANDLING SYSTEM
MODIFICATIONS V BUNK &
LOCKING PIN
MODIFICATION OF EXISTING BOAT HANDLING SYSTEM
(BHS) TO REMOVE EXISTING TRANSFER WHEELS, CAPTURE
WHEELS, BRIDGE FENDERS AND KEEL ROLLERS IN ORDER
TO INCOPROATE V-BUNK AND LOCKING MECHANISM
SHIPALT-
96878- 643-90-001 CREW ACCOMMODATION AND
BERTHING INCREASE
HABITIABILITY MODIFICATIONS (BERTHING, UNCLASS
NETWORK DROPS) TO STATEROOMS TO SUPPORT INCREASE
OR CREW SIZE FROM 200 TO 219. INSTALLATION OF
ADDITIONAL LIFTRAFT ATOP HANGAR.
MAINTENANCE WORK PACKAGE
WORK ITEM WORK SPEC # TITLE DESCRIPTION
AWI-1178- 897-11-001 PLANNED MAINTENANCE SYSTEM (PMS)
ACCOMPLISHMENT
94K CHECKS/77K MRC MAN HOURS
AWI-1237- 980-11-001 LIGHT OFF DISCREPANCY CORRECTION
ASSISTANCE
PROVIDE 500 MAN-DAYS OF LABOR AND
100,000 DOLLARS OF MATERIAL TOACCOMPLISH
WORK NOT PREVIOUSLY IDENTIFIED IN THE
WORK ITEM AS DIRECTED BY THE SUPERVISOR.
AWI-1239- 982-31-001
MACHINERY SPACE PRODUCTION
COMPLETION AND REQUIREMENT FOR NON
COMPLEX LIGHT OFF ASSESSMENT
PROVIDE 25 MAN-DAYS OF LABOR AND 50,000
DOLLARS OF MATERIAL TO CORRECT
GOVERNMENT RESPONSIBLE DEFICIENCIES THAT
ARE DISCOVERED DURING THE CONDUCT OF THE
LOA, WHICH PREVENT SAFE LIGHT-OFF OF
THE PLANT, AS DESIGNATED BY THE
SUPERVISOR.
AWI-1241- 982-31-003 DOCK TRIAL, SEA TRIAL DISCREPANCY
CORRECTION; ACCOMPLISH
PROVIDE 300 MANDAYS OF LABOR AND 100,000
DOLLARS OF MATERIAL FOR CORRECTION OF
MINOR GOVERNMENT DISCREPANCIES ARISING
FROM PRETRIAL MACHINERY OPERATIONAL
TESTING, DOCK TRIAL, AND SEA TRIAL AS
DIRECTED BY THE SUPERVISOR.
CNSP-0163 110-21-001 UNDERWATER HULL; INSPECT AND REPAIR
UNDERWATER HULL AND EACH APPENDAGE FROM
FLAT KEEL TO 6IN ABOVE EACH UPPER LIMIT
OF BOOT TOP, TO INCLUDE EACH ANCHOR
BOLSTER, BILGE KEEL, SKEG, STERN FLAP,
RUDDER STOOL, RUDDER, SUCTION AND
DISCHARGE FROM SHELL INBOARD 24IN, EACH
FAIRING, GRATING, ROPE GUARD, FAIRWATER,
INTERIOR AND EXTERIOR OF EACH STERN TUBE
BARREL, STRUT AND STRUT BARREL.
CNSP-0165 123-21-003 BALLAST TANK; PRESERVE
ACCOMPLISH BASE METAL WELD BUILD-UP OF A
TOTAL OF 108 SQUARE INCHES OF PLATE
DEFECTS IN THE TANK BOTTOM.
CNSP-0166 123-21-005 GRAY WATER TANK; INSPECT AND REPAIR
QUANTITY (6 EA), ANODE, CORROSION
PREVENTIVE, ZEP-5 STYLE B, CIRCULAR
SLAB, DISPOSAL
CNSP-0167 130-21-001 AIRCRAFT SECURING FITTING
REPLACEMENT; ACCOMPLISH
ACCOMPLISH A VISUAL INSPECTION OF EACH
AIRCRAFT SECURING FITTING
CNSP-0168 163-21-001 SEA CHEST; INSPECT AND REPAIR
ACCOMPLISH A VISUAL INSPECTION OF EACH
SEA CHEST LOCATED INCLUDING EACH
STRAINER PLATE, BUBBLE SHIELD, AND
STRUCTURAL MEMBER FOR STRUCTURAL
INTEGRITY, DETERIORATION, EACH PITTING,
CRACK AND AREA OF DAMAGE OR DISTORTION
CNSP-0169 163-21-002 SEA VALVE WASTER SLEEVE INSPECT,
REPAIR AND REPLACEMENT; ACCOMPLISH
REMOVE EACH PROTECTION SLEEVE, WASTER
SLEEVE, WASTER RING, INCLUDING EACH
ASSOCIATED FLANGE AND SPACER
CNSP-0170 235-21-001 PROPULSION MOTOR DRIVE (PMD)
ENCLOSURE CLEANING
ACCOMPLISH AN IN-PLACE CLEANING OF QTY
(4 EA) PMDS
CNSP-0171 235-21-002 ADVANCED INDUCTION MOTOR (AIM) WATER
COOLERS; REPLACE
REMOVE EACH EXISTING EQUIPMENT, REMOVE
EACH EXPANSION JOINT, QUANTITY (16 EA),
INSTALL EACH NEW GENERATION WATER
COOLER. INSTALL QUANTITY (16 EA)
EXPANSION JOINTS
CNSP-0172 243-21-001 PORT AND STARBOARD PROPULSION SHAFT
WATERBORNE BEARING CLEARANCE
ACCOMPLISH THE INSPECTION OF QTY (6 EA)
WATERBORNE BEARINGS
CNSP-0173 243-21-002 PORT AND STARBOARD STERN TUBE SHAFT
SEAL; OVERHAUL
ACCOMPLISH AN OVERHAUL OF THE PORT AND
STBD STERN TUBE SAFT SEALS
CNSP-0174 243-21-003 POST DRY-DOCK PORT AND STARBOARD
PROPULSION SHAFTING ALIGNMENT
ACCOMPLISH A WATERBORNE SHAFTING
ALIGNMENT EVALUATION CHECK
CNSP-0175 243-21-004 WATERBORNE PROPULSION SHAFTING
ACCOMPLISH THE MEASURING AND RECORDING
OF EACH AS-ARRIVED CLEARANCE BETWEEN THE
EQUIPMENT
CNSP-0176 243-21-005 UNSHIP INSPECT AND REPAIR PROPULSION
SHAFTING; ACCOMPLISH
ACCOMPLISH THE REMOVAL, INSPECTION AND
REPAIR OF THE PORT AND STARBOARD MAIN
PROPULSION WATERBORNE SHAFTING
CNSP-0177 256-21-001 HARMONIC FILTER GROOM, ACCOMPLISH
ACCOMPLISH A HARMONIC FILTER GROOM FOR
EQUIPMENT
CNSP-0178 256-21-002 AUXILIARY SEAWATER (ASW) STRAINER
REPLACEMENT; ACCOMPLISH
ACCOMPLISH THE REPLACEMENT OF QTY (8 EA)
ASW STRAINER SCREEN ASSEMBLIES
CNSP-0179 256-21-003 PROPULSION SEAWATER (PSW) STRAINER
SCREEN REPLACEMENT
ACCOMPLISH THE REPLACEMENT OF QTY (7 EA)
PSW STRAINER SCREEN ASSEMBLIES
CNSP-0180 256-21-004 PROPULSION SEAWATER (PSW) COOLING
PUMP; REPAIR
ACCOMPLISH PSW PUMP REPAIRS FOR
EQUIPMENT
CNSP-0181 256-21-005 MIDEL TO SW COOLER
ACCOMPLISH CLEANING AND FLUSHING OF QTY
(4 EA) AIR/SEAWATER COOLERS AND QTY (4
EA) MIDEL COOLERS
CNSP-0182 256-21-006 PROPULSION SEAWATER (PSW) PUMP
REPAIR; ACCOMPLISH
ACCOMPLISH THE REQUIREMENTS OF 009-90 TO
PROVIDE THE SERVICES OF AN AUTHORIZED
ORIGINAL EQUIPMENT MANUFACTURER (OEM)
SERVICE PROVIDER TO PROVIDE OVERSIGHT
AND TECHNICAL GUIDANCE FOR THE
DISASSEMBLY, INSPECTION, REPAIR,
REASSEMBLY, INSTALLATION, CALIBRATION,
ADJUSTMENT, AND TESTING FOR THE
EQUIPMENT.
CNSP-0183 301-21-002 PERSONNEL SAFETY BARRIER (PSB)
ACTUATORS; REPLACE
ACCOMPLISH THE REQUIREMENTS OF 009-90
FOR TECHNICAL DOCUMENTATION, OVERSIGHT,
SPECIAL TOOLS, OPERATIONAL TESTING AND A
TECHNICAL REPRESENTATIVE WHO WILL
DIRECTLY ASSIST THE GOVERNMENT
SUPERVISOR.
CNSP-0184 301-21-003 TELEROBOTIC FIREFIGHTING NOZZLE
(TFN) DEPLOY/STOW SERVOMOTORS
ACCOMPLISH THE REPLACEMENT OF THE
SERVOMOTORS FOR THE TELEROBOTIC FIRE
NOZZLES
CNSP-0185 304-21-001 EXTENDABLE RAMP INCLINOMETERS;
REPLACE
ACCOMPLISH THE INSTALLATION OF THE
EXTENDABLE RAMP INCLINOMETERS
CNSP-0186 311-21-001 MAIN TURBINE GENERATOR; MAINTAIN
ACCOMPLISH THE REQUIREMENTS OF 009-90
FOR A TECHNICAL REPRESENTATIVE TO
PROVIDE OVERSIGHT, TECHNICAL
DOCUMENTATION, OPERATIONAL TESTING,
SPECIAL TOOLS OR EQUIPMENT, AND DIRECT
ASSISTANCE TO THE SUPERVISOR. TECHNICAL
SERVICES OBTAINED BY THIS PARAGRAPH ARE
NOT TO BE USED TO PERFORM PRODUCTION
WORK.
CNSP-0187 312-21-002 EMERGENCY DIESEL ENGINE (EDG)
TECHNICAL SUPPORT; PROVIDE
ACCOMPLISH THE REQUIREMENTS OF 009-90
TO PROVIDE THE SERVICES OF AN ORIGINAL
EQUIPMENT MANUFACTURER (OEM) TO INSPECT
AND ACCOMPLISH A TOP END OVERHAUL FOR
THE EQUIPMENT
CNSP-0188 313-21-002 UNINTERRUPTIBLE POWER SUPPLY BATTERY
REPLACEMENT: ACCOMPLISH
PROCURE EACH NEW UNINTERRUPTIBLE POWER
SUPPLY PORTABLE BATTERY AND TURN OVER TO
THE SUPERVISOR FOR STORAGE AND BATTERY
HEALTH MAINTENANCE.
CNSP-0189 512-21-001 DRY ICE VENTILATION DUCTWORK
CLEANING; ACCOMPLISH
ACCOMPLISH CLEANING OF EACH VENTILATION
SYSTEM FROM EACH WEATHER OPENING TO
TERMINAL END, INCLUDING IN-PLACE
CLEANING OF EACH INSTALLED VENTILATION
SYSTEM HEAT EXCHANGER, TO INCLUDE EACH
AIR CONDITIONING CHILL WATER REFRIGERANT
COIL, STEAM, AND ELECTRIC MAIN AND
BOOSTER HEATER COIL
CNSP-0190 514-21-001 AUXILIARY SEAWATER (ASW) PUMP;
INSPECT AND REPAIR
ACCOMPLISH THE REQUIREMENTS OF 009-90
TO PROVIDE THE SERVICES OF AN AUTHORIZED
ORIGINAL EQUIPMENT MANUFACTURER (OEM)
SERVICE PROVIDER TO PROVIDE OVERSIGHT
AND TECHNICAL GUIDANCE FOR THE
DISASSEMBLY, INSPECTION, REPAIR,
REASSEMBLY, INSTALLATION, CALIBRATION,
ADJUSTMENT, AND TESTING FOR THE
EQUIPMENT.
CNSP-0191 520-21-001 SEA VALVE REPAIR AND REPLACEMENT;
ACCOMPLISH
ACCOMPLISH A PRE-REPAIR OPERATIONAL
TEST, BOTH LOCALLY AND REMOTELY, OF EACH
VALVE OPERATOR AND VALVE PRIOR TO EACH
REMOVAL TO DETERMINE ACTUAL OPERATING
CONDITION BY FULLY OPENING AND CLOSING
EACH VALVE THROUGH 4 COMPLETE CYCLES.
CNSP-0192 521-21-001 FIRE MAIN PUMP INSPECT AND REPAIR;
ACCOMPLISH
REMOVE AND DISPOSE OF SYSTEM FLUIDS IN
ACCORDANCE WITH FEDERAL, STATE AND LOCAL
ENVIRONMENTAL REQUIREMENTS
CNSP-0193 523-21-001 DISTRIBUTIVE SEAWATER (DSW) PUMP
REPAIR
ACCOMPLISH DSW PUMP REPAIRS FOR
EQUIPMENT
CNSP-0194 532-21-001
AIR CONDITIONING (AC) PLANT
CONDENSER MECHANICAL CLEAN AND
SEAWATER STRAINER
ACCOMPLISH THE MECHANICAL CLEANING OF
THE SEAWATER SIDE OF THE EQUIPMENT
CNSP-0195 532-21-002 PROPULSION HEAT EXCHANGER PLATE
CLEANING: ACCOMPLISH
ACCOMPLISH THE CLEANING OF PROPULSION
FRESH WATER HEAT EXCHANGERS PLATES
CNSP-0196 532-21-003 PROPULSION FRESHWATER (PFW) COOLING
PUMP; REPAIR
ACCOMPLISH THE REQUIREMENTS OF 009-90 TO
PROVIDE THE SERVICES OF AN AUTHORIZED
ORIGINAL EQUIPMENT MANUFACTURER (OEM)
SERVICE PROVIDER TO PROVIDE OVERSIGHT
AND TECHNICAL GUIDANCE FOR THE
DISASSEMBLY, INSPECTION, REPAIR,
REASSEMBLY, INSTALLATION,
CNSP-0197 532-21-004 AIR CONDITIONING PLANT CONDENSER
WATER CONTROL VALVE (CWCV); REPLACE
ACCOMPLISH THE REPLACEMENT OF THE AIR
CONDITIONING WATER CONTROL VALVES (CWCV)
CNSP-0198 532-21-005 PROPULSION FRESHWATER (PFW) COOLING
PUMP; REPAIR
ACCOMPLISH THE REQUIREMENTS OF 009-90 TO
PROVIDE THE SERVICES OF AN AUTHORIZED
ORIGINAL EQUIPMENT MANUFACTURER (OEM)
SERVICE PROVIDER TO PROVIDE OVERSIGHT
AND TECHNICAL GUIDANCE FOR THE
DISASSEMBLY, INSPECTION, REPAIR,
REASSEMBLY, INSTALLATION, CALIBRATION,
ADJUSTMENT, AND TESTING FOR THE
EQUIPMENT
CNSP-0199 551-21-001 LOW PRESSURE AIR COMPRESSOR (LPAC);
OVERHAUL
ACCOMPLISH THE REQUIREMENTS OF 009-90
FOR TECHNICAL DOCUMENTATION, OVERSIGHT,
TOOLS, OPERATIONAL TESTING AND A
TECHNICAL REPRESENTATIVE WHO WILL
DIRECTLY ASSIST THE GOVERNMENT
SUPERVISOR
CNSP-0200 555-31-001
HIGH PRESSURE WATER MIST
MECHANICALLY ATTACHED FITTINGS (MAF)
AND PIPE; INSPECT
ACCOMPLISH THE REQUIREMENTS OF 009-71
FOR A HYDROSTATIC TEST OF EACH HIGH
PRESSURE WATER MIST (HPWM) SYSTEM
INSTALLED .
CNSP-0201 561-21-001 STEERING GEAR ACTUATION SYSTEM
(SGAS)OIL INSPECTION
ACCOMPLISH THE REQUIREMENTS OF 009-90 TO
PROVIDE THE SERVICES OF BUREAU VERITAS
TO ACCOMPLISH TESTING OF THE GEARBOX OIL
IN EACH SGAS GEARBOX
CNSP-0202 562-21-001 RUDDER BEARING SEAL AND RUDDERSTOCK
SEAL; REPAIR
ACCOMPLISH PORT AND STBD RUDDER STOCK
REPAIRS
CNSP-0203 581-21-001 ANCHOR AND ANCHOR CHAIN INSPECTION
AND PRESERVATION; ACCOMPLISH
REMOVE THE EQUIPMENT, SEPARATE EACH
ANCHOR, OUTBOARD SWIVEL SHOT, CHAIN
STOPPER ASSEMBLY AND EACH SUCCEEDING 15
FATHOM SHOT, BY DISASSEMBLING THE
DETACHABLE LINKS AND BITTER END SHACKLES
CNSP-0204 588-21-001 PVLS BERM PRESERVATION; ACCOMPLISH
ACCOMPLISH THE PREPARATION OF A SKETCH
SHOWING EXISTING MARKINGS, LABEL PLATES
AND PLACARDS OF EACH BERM COVER
CNSP-0205 593-21-001
VACUUM, COLLECTION, HOLDING AND
TRANSFER (VCHT) SYSTEM; CHEMICAL
CLEANING
ACCOMPLISH VCHT TANK AND PIPE CLEANING
INSPECTION AND REPAIRS
CNSP-0206 624-21-001 CHILL AND FREEZE STOREROOM DOOR
INSPECT AND REPAIR; ACCOMPLISH
ACCOMPLISH THE REQUIREMENTS OF 009-90 TO
PROVIDE THE SERVICES OF A QUALIFIED OEM
REPRESENTATIVE TO INSPECT AND REALIGN
CHILL ROOM AND FREEZE ROOM DOORS
CNSP-0207 624-21-002 BALANCED JOINER DOOR
PROVIDE 25 MANDAYS OF LABOR AND 50,000
DOLLARS OF MATERIAL. INSPECT, TEST,
REMOVE, CRATE, STORE, AND RE-INSTALL ALL
BALANCED JOINER DOORS AND FRAMES.
CNSP-0208 631-21-001
UNDERWATER HULL PRESERVATION PAINT
COMPANY ORIGINAL EQUIPMENT
MANUFACTURERS'
ACCOMPLISH THE REQUIREMENTS OF DM 220-
020 SURF, UNDERWATER HULL: PRESERVE
UTILIZING OEM REPRESENTATIVE
CNSP-0209 631-21-002 FREEBOARD; PRESERVE
EXTERIOR HULL FROM UPPER LIMIT OF BOOT
TOPPING TO TOP OF 01 LEVEL WATERWAY BAR,
FROM BOW TO STERN, TO INCLUDE 12 INCHES
INTO EACH PENETRATION AND PIPE AND WORK
BOUNDARY, EXCLUDING RADAR ABSORBENT
MATERIAL (RAM) TILE AREA/SURFACE, TO
INCLUDE EACH DOOR
CNSP-0210 633-21-001 IMPRESSED CURRENT CATHODIC
PROTECTION (ICCP) REFERENCE CELL
ACCOMPLISH THE REQUIREMENTS OF 009-90
TO PROVIDE THE SERVICES OF AN AUTHORIZED
ORIGINAL EQUIPMENT MANUFACTURER (OEM)
SERVICE PROVIDER TO ACCOMPLISH A PRE-
DRYDOCK INSPECTION OF THE IMPRESSED
CURRENT CATHODIC PROTECTION SYSTEM
CNSP-0211 634-21-003 FLIGHT DECK NONSKID REPLACEMENT
ACCOMPLISH FLIGHT DECK NONSKID
REPLACEMENT UTILIZING SPRAYABLE DECK
COATING, AND ACCOMPANYING TESTS OF
DISTRIBUTED SEA WATER AND COUNTER
MEASURE WASHDOWN SYSTEM, AND DECK DRAINS
CNSP-0212 639-21-001 PASSIVE COUNTERMEASURE SYSTEM (PCMS)
REPAIR AND REPLACEMENT; ACCOMPLISH
ACCOMPLISH A JOINT VISUAL INSPECTION
WITH THE SUPERVISOR OF EACH PCMS RAM
TILE SHOWN TO DETERMINE LOCATIONS FOR
DAMAGED TILE, MISSING TILE, CORROSION
UNDER TILE, MISSING OR DETERIORATING
CAULK, AND ENVIRONMENTAL LAYER PEELING.
ACCOMPLISH REPAIR OF DAMAGED PCMS TILES
USING MATERIALS PROVIDED
CNSP-0213 864-21-001 AN/SPY-3 ANTENNA PROTECTIVE COVERS
FABRICATE AND INSTALL PROTECTIVE
COVERINGS FOR AN/SPY-3 ANTENNAS
CNSP-0214 865-21-001 STAGING AND SCAFFOLDING
PROVIDE 50 MAN-DAYS AND 50,000 DOLLARS
OF STAGING AND SCAFFOLDING SERVICES
CNSP-0215 867-21-001 COMBAT SYSTEM TESTING SUPPORT;
PROVIDE
PROVIDE 2,500 MANHOURS OF LABOR AND
25,000 DOLLARS OF MATERIAL, AS
DESIGNATED BY THE SUPERVISOR, FOR
SUPPORT OF COMBAT SYSTEMS WORK.
CNSP-0164- 123-21-
001R1
TANK AND VOID CLEANING AND PUMPING;
ACCOMPLISH
OPEN, VENTILATE, EMPTY, CLEAN, RENDER
DRY, AND MAINTAIN EACH TANK
CNSP-0216- 123-21-006 TANK GAS FREE, REPAIR AND PRESERVE;
ACCOMPLISH
OPEN, VENTILATE, EMPTY, CLEAN, RENDER
DRY, AND MAINTAIN EACH TANK
CNSP-0217- 711-11-001 GUN WEAPON SYSTEM, 30MM, MK 46 MOD
1/2 RACE RING; INSTALL
PREPARE, REMOVE, INSPECT, INSTALL QTY 2
MK 46 GWS