Enclosure 1.pdf

PDF 212 KB Posted

Attached to
Sources Sought Notice for USS MICHAEL MONSOOR (DDG 1001) CNO Availability
Solicitation number
N00024-26-R-4443
Issued by

About this file

This document is an enclosure to a Sources Sought Notice (N00024-26-R-4443) for a DDG 1000 Class ship availability that includes repair/maintenance and modernization work.

The availability encompasses approximately 320,000 hours of repair and maintenance work and 1,000,000 hours of modernization work. The ship specifications include a length of 186 meters, beam of 24.6 meters, and draft of 7 meters, with a depth to the top of the lightning rod of 39.8 meters. The facility requirements include a pier length exceeding 610 feet, 800 amps of 4160-volt electrical service, potable water capacity of 10,000 gallons per day at 55 PSI, firefighting seawater of 1,250 GPM at 150 PSI, sewage/wastewater disposal of 20,000 gallons per day combined, a mean pier water depth exceeding 33 feet, and a dry dock capable of supporting the DDG 1000 Class ship. An LMVLS unit module measuring 44'7" long, 20'8" wide, 41'1" high, and weighing approximately 600 tons must be accommodated.

The modernization scope focuses on the Conventional Prompt Strike (CPS) weapon system installation, which includes removal of the MT 62 Advanced Gun System, installation of the LMVLS magazine and associated launch modules, relocation of Main Turbine Generator intakes, and modifications to the Propulsion Seawater system. Additional modernization work encompasses fuel endurance improvements, MTG intake pressure loss improvements, propulsion system enhancements, EO/IR system improvements, ECS network and hardPLC refresh, crew accommodation increases from 200 to 219 personnel, and various other system upgrades. The maintenance package includes extensive planned maintenance system accomplishments totaling 94,000 checks and 77,000 man-hours, along with numerous specialized maintenance tasks covering hull preservation, propulsion systems, seawater systems, ventilation, fire suppression, steering, anchoring, combat systems, and related equipment across multiple ship systems.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enclosure (1) to Sources Sought Notice N00024-26-R-4443

General Information and Availability Work Package

A. General

a. Rough Estimate:

i. Repair/Maintenance 320K hours

ii. Modernization: 1,000K hours

b. Ship Particulars:

i. Length: 186m (610 ft)

ii. LBP: 182.9m (600 ft)

iii. Beam, max: 24.6m (80.7 ft)

iv. Draft, DWL: 7m (23.0 ft)

v. Draft, Navigation: 8.4m (27.6 ft)

vi. Depth, Fwd/Aft: 16.5m / 13.5m (54.1 ft / 44.3 ft)

vii. Depth, top Deckhouse: 34.5m (113.2 ft)

viii. Depth, top Ltng Rod: 39.8m (130.6 ft)

c. Facility Particulars:

i. Pier Length: > 610 ft

ii. Electrical: 800 amps, 4160 volts, 60 hz, 3 ph (UFC 4-150-02 table C-7)

iii. Potable Water: 10,000 GPD, 55 PSI (UFC 4-150-02 Table C-4)

iv. Firefighting Sea Water: 1250 GPM (UFC 4-150-02 Table C-3), 150 PSI measured at the most remote outlet (UFC 4-150-02, Para 3-3.2.1)

v. Sewage: Ability to accommodate and dispose of 10,000 GPD of effluent and

10,000 GPD of waste water

vi. Mean Pier Water depth draft: >33 ft

vii. Dry Dock to support DDG1000 Class Ship

d. LMVLS Unit Module Dimensions

i. Length: 44’7”

ii. Width: 20’8”

iii. Height: 41’1”

iv. Weight: ~600 tons

B. The Availability’s modernization scope will largely be removal of the MT 61 Advanced Gun System (AGS) mount, installation of Conventional Prompt Strike capability, relocation of the Main Turbine Generator (MTG) intakes, and incorporation of changes to the Propulsion Seawater (PSW) system. The awarded contractor must be able to include and incorporate AIT integration, 3rd Party contractors, Government personnel, Long Lead Time Material (LLTM) procurement, etc. in their Integrated Production Schedule (IPS). Key trades & efforts include: Structural welding, cabling pulling, piping, electrical and ventilation work if needed. Both the MSR and AIT will execute the structural/Industrial work. A list of work specifications to be performed is provided in Enclosure (2).

C. The Availability’s maintenance package targets prioritized lifecycle and preventative maintenance activities outlined in Enclosure (2):

Enclosure (2)

CONVENTIONAL PROMPT STRIKE (CPS)

ALTERATION WORK SPEC # TITLE DESCRIPTION

SHIPALT-

97881- 711-90-006 MT62 AGS UPPER GUN MOUNT

REMOVAL

REMOVAL OF MT62 ADVANCED GUN SYSTEM (AGS). THIS

INCLUDES REMOVING THE LOWER GUN MOUNT ASSEMBLY,

ROTATING WEATHER SHIELD, AND CENTERLINE HOIST

ASSEMBLY. STRENGTHENING THE MAIN DECK TO SUPPORT

SLAMMING LOADS CAUSED BY REMOVAL OF MT62.

SHIPALT-

97505- 721-90-001 AGS MT 61 REMOVAL AND LMVLS

HM&E MODIFICATIONS

MODIFICATIONS NECESSARY TO SUPPORT INSTALLATION OF

THE CONVENTION PROMPT STRIKE (CPS) WEAPON SYSTEM

WITHIN THE 1400 STACK. INSTALLATION INCLUDES: THE

LMVLS MAGAZINE, APM LAUNCH MODULES, SHOCK

ISOLATION SYSTEM, WEATHER DECK HATCHES, AND ALL

HM&E MODIFICATIONS NECESSARY TO SUPPORT CPS

SHIPALT-

97869- 721-90-002 LMVLS WCS RIPOUT AND

INSTALLATION

INTEGRATION OF (CPS) WEAPONS CONTROL SYSTEM

COMPONENTS INCLUDE THE FOLLOWING: WEAPON CONSOLES,

WEAPONS INTERFACE BOXES, REMOTE DISPLAYS, AND

CS/C4I CABLING AND CONNECTIONS AS REQUIRED FOR CPS

OPERATION AND CONTROL. IN ADDITION, THIS

ALTERATION SUPPORTS RAYTHEON, LOCKHEED MARTIN, AND

NAVWAR AIT WORK SCOPE.

SHIPALT-

98380- 863-71-403 CPS TSCE ENTI CONVENTIONAL

PROMPT STRIKE

BASELINE CONFIGURATION CHANGES ARE NEEDED IN

SEVERAL TSCE HARDWARE CONFIGURATION ITEMS IN ORDER

TO INTEGRATE WITH THE CONVENTIONAL PROMPT STRIKE

WEAPON SYSTEM. PERIPHERALS AND CABLE CHANGES, CPS

EEME CHANGES TO HOUSE CPS RACKS, CPS 1PPS

EQUIPMENT ADDITION TO EME 1B

NON-CPS MODERNIZATION

ALTERATION WORK SPEC # TITLE DESCRIPTION

SHIPALT-

96881- 202-90-001 FUEL ENDURANCE AND RANGE

EXTENSION MODIFICATION

INCREASE THE NAUTICAL MILE RANGE OF THE DDG 1000

CLASS SHIPS. THIS IS ACCOMPLISHED BY INCREASING

THE FUEL OIL STORAGE CAPACITY AS A RESULT OF

CONVERTING EXISTING SALT WATER BALLAST (SWB) TANKS

TO FUEL OIL (FO) STORAGE TANKS.

SHIPALT-

97208- 251-90-001 MTG INTAKE RELOCATION

RELOCATION OF MAIN TURBINE GENERATOR INTAKE

LOCATIONS FROM TOP TO SIDE OF DECKHOUSE TO AVOID

EXHAUST INGESTION WHILE UNDERWAY.

SHIPALT-

97209- 251-90-003 MTG INTAKE PRESSURE LOSS

IMPROVEMENTS

THE EXISTING MTG 1 & MTG 2 INTAKE AND FOUNDATIONS,

FROM THE TOP OF THE INTAKE BOOT THROUGH 2ND DECK,

WILL BE REMOVED AND SCRAPPED. THE BERP PLATES AT

2ND DECK AROUND THE INTAKE WILL ALSO BE REMOVED

AND SCRAPPED. A NEWLY FABRICATED INTAKE SECTION,

WITH MODIFIED GEOMETRY, WILL BE INSTALLED. NEW

BERP PLATES WILL BE INSTALLED AROUND THE NEW

INTAKES.

SHIPALT-

96942- 256-90-001 PROPULSION SEA WATER (PSW)

REDESIGN

THIS MODIFICATION WILL ADD AUTOVENTS TO SEACHESTS

IN THE PSW SYSTEMS THAT ARE CURRENTLY NON-VENTED.

SHIPALT-

97760- 256-90-002

PROPULSION SEA WATER AND

AUXILIARY PUMP SEA WATER

CASING AUTOVENTS

THIS ALTERATION WILL ADD AUTOMATIC AIR RELEASE

VALVES TO (5) MAIN PSW PUMP CASINGS, AND (4) ASW

PUMP CASINGS TO PREVENT PUMP SEAL FAILURE, AND

REMOVE AIR FROM THE PSW/ASW PUMP CASINGS DURING

OPERATION.

SHIPALT-

96880- 261-90-001 FUEL OIL STANDPIPE

MODIFICATION

THIS ALTERATION WILL INCREASE THE REFUELING RATE

OF DDG 1000 CLASS SHIPS WHILE ALONGSIDE, REFUELING

AT SEA (RAS), BY INCREASING THE HEIGHT OF THE FWD

AND AFT FUEL OIL OVERFLOW STANDPIPES.

SHIPALT-

98337- 418-90-001 EO/IR SYSTEM IMPROVEMENTS

ADDITION OF TWO (2) FLIR 380HD CAMERAS, MOUNTED

PORT AND STARBOARD ON THE HOUSE SIDES, ON SPONSONS

SIMILAR TO EXISTING UHF, EHF, AND WHIP ANTENNAS.

INSTALLATION OF WASH SYSTEM FOR CAMERAS AND CESV

WINDOWS

SHIPALT-

97994- 436-90-005 DDG 1000 CLASS ECS HARDPLC

REFRESH

UPGRADING ENGINEERING CONTROL SYSTEM (ECS)

SOFTPLC'S TO HARDPLCS TO AVOID OBSOLESENCE AND

CYBER VULNERABILITIES

SHIPALT-

97995- 436-90-005 DDG 1000 CLASS ECS NETWORK

REFRESH

UPGRADING ECS NETWORK SWITCHES WITH NEW MODELS TO

ADDRESS CYBERSECURITY AND OBSOLESENCE ISSUES

SHIPALT-

98174- 536-90-001

PROPULSION FRESH WATER

(PFW) SYSTEM HIGH POINT

VENT

THIS ALTERATION WILL ADD HIGH POINT AUTO-VENTS

THROUGHOUT THE PFW SYSTEM TO REMOVE ENTRAINED AIR

AND IMPROVE PERFORMANCE OF THE PFW SYSTEM.

SHIPALT-

97983- 583-90-006

BOAT HANDLING SYSTEM

MODIFICATIONS V BUNK &

LOCKING PIN

MODIFICATION OF EXISTING BOAT HANDLING SYSTEM

(BHS) TO REMOVE EXISTING TRANSFER WHEELS, CAPTURE

WHEELS, BRIDGE FENDERS AND KEEL ROLLERS IN ORDER

TO INCOPROATE V-BUNK AND LOCKING MECHANISM

SHIPALT-

96878- 643-90-001 CREW ACCOMMODATION AND

BERTHING INCREASE

HABITIABILITY MODIFICATIONS (BERTHING, UNCLASS

NETWORK DROPS) TO STATEROOMS TO SUPPORT INCREASE

OR CREW SIZE FROM 200 TO 219. INSTALLATION OF

ADDITIONAL LIFTRAFT ATOP HANGAR.

MAINTENANCE WORK PACKAGE

WORK ITEM WORK SPEC # TITLE DESCRIPTION

AWI-1178- 897-11-001 PLANNED MAINTENANCE SYSTEM (PMS)

ACCOMPLISHMENT

94K CHECKS/77K MRC MAN HOURS

AWI-1237- 980-11-001 LIGHT OFF DISCREPANCY CORRECTION

ASSISTANCE

PROVIDE 500 MAN-DAYS OF LABOR AND

100,000 DOLLARS OF MATERIAL TOACCOMPLISH

WORK NOT PREVIOUSLY IDENTIFIED IN THE

WORK ITEM AS DIRECTED BY THE SUPERVISOR.

AWI-1239- 982-31-001

MACHINERY SPACE PRODUCTION

COMPLETION AND REQUIREMENT FOR NON

COMPLEX LIGHT OFF ASSESSMENT

PROVIDE 25 MAN-DAYS OF LABOR AND 50,000

DOLLARS OF MATERIAL TO CORRECT

GOVERNMENT RESPONSIBLE DEFICIENCIES THAT

ARE DISCOVERED DURING THE CONDUCT OF THE

LOA, WHICH PREVENT SAFE LIGHT-OFF OF

THE PLANT, AS DESIGNATED BY THE

SUPERVISOR.

AWI-1241- 982-31-003 DOCK TRIAL, SEA TRIAL DISCREPANCY

CORRECTION; ACCOMPLISH

PROVIDE 300 MANDAYS OF LABOR AND 100,000

DOLLARS OF MATERIAL FOR CORRECTION OF

MINOR GOVERNMENT DISCREPANCIES ARISING

FROM PRETRIAL MACHINERY OPERATIONAL

TESTING, DOCK TRIAL, AND SEA TRIAL AS

DIRECTED BY THE SUPERVISOR.

CNSP-0163 110-21-001 UNDERWATER HULL; INSPECT AND REPAIR

UNDERWATER HULL AND EACH APPENDAGE FROM

FLAT KEEL TO 6IN ABOVE EACH UPPER LIMIT

OF BOOT TOP, TO INCLUDE EACH ANCHOR

BOLSTER, BILGE KEEL, SKEG, STERN FLAP,

RUDDER STOOL, RUDDER, SUCTION AND

DISCHARGE FROM SHELL INBOARD 24IN, EACH

FAIRING, GRATING, ROPE GUARD, FAIRWATER,

INTERIOR AND EXTERIOR OF EACH STERN TUBE

BARREL, STRUT AND STRUT BARREL.

CNSP-0165 123-21-003 BALLAST TANK; PRESERVE

ACCOMPLISH BASE METAL WELD BUILD-UP OF A

TOTAL OF 108 SQUARE INCHES OF PLATE

DEFECTS IN THE TANK BOTTOM.

CNSP-0166 123-21-005 GRAY WATER TANK; INSPECT AND REPAIR

QUANTITY (6 EA), ANODE, CORROSION

PREVENTIVE, ZEP-5 STYLE B, CIRCULAR

SLAB, DISPOSAL

CNSP-0167 130-21-001 AIRCRAFT SECURING FITTING

REPLACEMENT; ACCOMPLISH

ACCOMPLISH A VISUAL INSPECTION OF EACH

AIRCRAFT SECURING FITTING

CNSP-0168 163-21-001 SEA CHEST; INSPECT AND REPAIR

ACCOMPLISH A VISUAL INSPECTION OF EACH

SEA CHEST LOCATED INCLUDING EACH

STRAINER PLATE, BUBBLE SHIELD, AND

STRUCTURAL MEMBER FOR STRUCTURAL

INTEGRITY, DETERIORATION, EACH PITTING,

CRACK AND AREA OF DAMAGE OR DISTORTION

CNSP-0169 163-21-002 SEA VALVE WASTER SLEEVE INSPECT,

REPAIR AND REPLACEMENT; ACCOMPLISH

REMOVE EACH PROTECTION SLEEVE, WASTER

SLEEVE, WASTER RING, INCLUDING EACH

ASSOCIATED FLANGE AND SPACER

CNSP-0170 235-21-001 PROPULSION MOTOR DRIVE (PMD)

ENCLOSURE CLEANING

ACCOMPLISH AN IN-PLACE CLEANING OF QTY

(4 EA) PMDS

CNSP-0171 235-21-002 ADVANCED INDUCTION MOTOR (AIM) WATER

COOLERS; REPLACE

REMOVE EACH EXISTING EQUIPMENT, REMOVE

EACH EXPANSION JOINT, QUANTITY (16 EA),

INSTALL EACH NEW GENERATION WATER

COOLER. INSTALL QUANTITY (16 EA)

EXPANSION JOINTS

CNSP-0172 243-21-001 PORT AND STARBOARD PROPULSION SHAFT

WATERBORNE BEARING CLEARANCE

ACCOMPLISH THE INSPECTION OF QTY (6 EA)

WATERBORNE BEARINGS

CNSP-0173 243-21-002 PORT AND STARBOARD STERN TUBE SHAFT

SEAL; OVERHAUL

ACCOMPLISH AN OVERHAUL OF THE PORT AND

STBD STERN TUBE SAFT SEALS

CNSP-0174 243-21-003 POST DRY-DOCK PORT AND STARBOARD

PROPULSION SHAFTING ALIGNMENT

ACCOMPLISH A WATERBORNE SHAFTING

ALIGNMENT EVALUATION CHECK

CNSP-0175 243-21-004 WATERBORNE PROPULSION SHAFTING

ACCOMPLISH THE MEASURING AND RECORDING

OF EACH AS-ARRIVED CLEARANCE BETWEEN THE

EQUIPMENT

CNSP-0176 243-21-005 UNSHIP INSPECT AND REPAIR PROPULSION

SHAFTING; ACCOMPLISH

ACCOMPLISH THE REMOVAL, INSPECTION AND

REPAIR OF THE PORT AND STARBOARD MAIN

PROPULSION WATERBORNE SHAFTING

CNSP-0177 256-21-001 HARMONIC FILTER GROOM, ACCOMPLISH

ACCOMPLISH A HARMONIC FILTER GROOM FOR

EQUIPMENT

CNSP-0178 256-21-002 AUXILIARY SEAWATER (ASW) STRAINER

REPLACEMENT; ACCOMPLISH

ACCOMPLISH THE REPLACEMENT OF QTY (8 EA)

ASW STRAINER SCREEN ASSEMBLIES

CNSP-0179 256-21-003 PROPULSION SEAWATER (PSW) STRAINER

SCREEN REPLACEMENT

ACCOMPLISH THE REPLACEMENT OF QTY (7 EA)

PSW STRAINER SCREEN ASSEMBLIES

CNSP-0180 256-21-004 PROPULSION SEAWATER (PSW) COOLING

PUMP; REPAIR

ACCOMPLISH PSW PUMP REPAIRS FOR

EQUIPMENT

CNSP-0181 256-21-005 MIDEL TO SW COOLER

ACCOMPLISH CLEANING AND FLUSHING OF QTY

(4 EA) AIR/SEAWATER COOLERS AND QTY (4

EA) MIDEL COOLERS

CNSP-0182 256-21-006 PROPULSION SEAWATER (PSW) PUMP

REPAIR; ACCOMPLISH

ACCOMPLISH THE REQUIREMENTS OF 009-90 TO

PROVIDE THE SERVICES OF AN AUTHORIZED

ORIGINAL EQUIPMENT MANUFACTURER (OEM)

SERVICE PROVIDER TO PROVIDE OVERSIGHT

AND TECHNICAL GUIDANCE FOR THE

DISASSEMBLY, INSPECTION, REPAIR,

REASSEMBLY, INSTALLATION, CALIBRATION,

ADJUSTMENT, AND TESTING FOR THE

EQUIPMENT.

CNSP-0183 301-21-002 PERSONNEL SAFETY BARRIER (PSB)

ACTUATORS; REPLACE

ACCOMPLISH THE REQUIREMENTS OF 009-90

FOR TECHNICAL DOCUMENTATION, OVERSIGHT,

SPECIAL TOOLS, OPERATIONAL TESTING AND A

TECHNICAL REPRESENTATIVE WHO WILL

DIRECTLY ASSIST THE GOVERNMENT

SUPERVISOR.

CNSP-0184 301-21-003 TELEROBOTIC FIREFIGHTING NOZZLE

(TFN) DEPLOY/STOW SERVOMOTORS

ACCOMPLISH THE REPLACEMENT OF THE

SERVOMOTORS FOR THE TELEROBOTIC FIRE

NOZZLES

CNSP-0185 304-21-001 EXTENDABLE RAMP INCLINOMETERS;

REPLACE

ACCOMPLISH THE INSTALLATION OF THE

EXTENDABLE RAMP INCLINOMETERS

CNSP-0186 311-21-001 MAIN TURBINE GENERATOR; MAINTAIN

ACCOMPLISH THE REQUIREMENTS OF 009-90

FOR A TECHNICAL REPRESENTATIVE TO

PROVIDE OVERSIGHT, TECHNICAL

DOCUMENTATION, OPERATIONAL TESTING,

SPECIAL TOOLS OR EQUIPMENT, AND DIRECT

ASSISTANCE TO THE SUPERVISOR. TECHNICAL

SERVICES OBTAINED BY THIS PARAGRAPH ARE

NOT TO BE USED TO PERFORM PRODUCTION

WORK.

CNSP-0187 312-21-002 EMERGENCY DIESEL ENGINE (EDG)

TECHNICAL SUPPORT; PROVIDE

ACCOMPLISH THE REQUIREMENTS OF 009-90

TO PROVIDE THE SERVICES OF AN ORIGINAL

EQUIPMENT MANUFACTURER (OEM) TO INSPECT

AND ACCOMPLISH A TOP END OVERHAUL FOR

THE EQUIPMENT

CNSP-0188 313-21-002 UNINTERRUPTIBLE POWER SUPPLY BATTERY

REPLACEMENT: ACCOMPLISH

PROCURE EACH NEW UNINTERRUPTIBLE POWER

SUPPLY PORTABLE BATTERY AND TURN OVER TO

THE SUPERVISOR FOR STORAGE AND BATTERY

HEALTH MAINTENANCE.

CNSP-0189 512-21-001 DRY ICE VENTILATION DUCTWORK

CLEANING; ACCOMPLISH

ACCOMPLISH CLEANING OF EACH VENTILATION

SYSTEM FROM EACH WEATHER OPENING TO

TERMINAL END, INCLUDING IN-PLACE

CLEANING OF EACH INSTALLED VENTILATION

SYSTEM HEAT EXCHANGER, TO INCLUDE EACH

AIR CONDITIONING CHILL WATER REFRIGERANT

COIL, STEAM, AND ELECTRIC MAIN AND

BOOSTER HEATER COIL

CNSP-0190 514-21-001 AUXILIARY SEAWATER (ASW) PUMP;

INSPECT AND REPAIR

ACCOMPLISH THE REQUIREMENTS OF 009-90

TO PROVIDE THE SERVICES OF AN AUTHORIZED

ORIGINAL EQUIPMENT MANUFACTURER (OEM)

SERVICE PROVIDER TO PROVIDE OVERSIGHT

AND TECHNICAL GUIDANCE FOR THE

DISASSEMBLY, INSPECTION, REPAIR,

REASSEMBLY, INSTALLATION, CALIBRATION,

ADJUSTMENT, AND TESTING FOR THE

EQUIPMENT.

CNSP-0191 520-21-001 SEA VALVE REPAIR AND REPLACEMENT;

ACCOMPLISH

ACCOMPLISH A PRE-REPAIR OPERATIONAL

TEST, BOTH LOCALLY AND REMOTELY, OF EACH

VALVE OPERATOR AND VALVE PRIOR TO EACH

REMOVAL TO DETERMINE ACTUAL OPERATING

CONDITION BY FULLY OPENING AND CLOSING

EACH VALVE THROUGH 4 COMPLETE CYCLES.

CNSP-0192 521-21-001 FIRE MAIN PUMP INSPECT AND REPAIR;

ACCOMPLISH

REMOVE AND DISPOSE OF SYSTEM FLUIDS IN

ACCORDANCE WITH FEDERAL, STATE AND LOCAL

ENVIRONMENTAL REQUIREMENTS

CNSP-0193 523-21-001 DISTRIBUTIVE SEAWATER (DSW) PUMP

REPAIR

ACCOMPLISH DSW PUMP REPAIRS FOR

EQUIPMENT

CNSP-0194 532-21-001

AIR CONDITIONING (AC) PLANT

CONDENSER MECHANICAL CLEAN AND

SEAWATER STRAINER

ACCOMPLISH THE MECHANICAL CLEANING OF

THE SEAWATER SIDE OF THE EQUIPMENT

CNSP-0195 532-21-002 PROPULSION HEAT EXCHANGER PLATE

CLEANING: ACCOMPLISH

ACCOMPLISH THE CLEANING OF PROPULSION

FRESH WATER HEAT EXCHANGERS PLATES

CNSP-0196 532-21-003 PROPULSION FRESHWATER (PFW) COOLING

PUMP; REPAIR

ACCOMPLISH THE REQUIREMENTS OF 009-90 TO

PROVIDE THE SERVICES OF AN AUTHORIZED

ORIGINAL EQUIPMENT MANUFACTURER (OEM)

SERVICE PROVIDER TO PROVIDE OVERSIGHT

AND TECHNICAL GUIDANCE FOR THE

DISASSEMBLY, INSPECTION, REPAIR,

REASSEMBLY, INSTALLATION,

CNSP-0197 532-21-004 AIR CONDITIONING PLANT CONDENSER

WATER CONTROL VALVE (CWCV); REPLACE

ACCOMPLISH THE REPLACEMENT OF THE AIR

CONDITIONING WATER CONTROL VALVES (CWCV)

CNSP-0198 532-21-005 PROPULSION FRESHWATER (PFW) COOLING

PUMP; REPAIR

ACCOMPLISH THE REQUIREMENTS OF 009-90 TO

PROVIDE THE SERVICES OF AN AUTHORIZED

ORIGINAL EQUIPMENT MANUFACTURER (OEM)

SERVICE PROVIDER TO PROVIDE OVERSIGHT

AND TECHNICAL GUIDANCE FOR THE

DISASSEMBLY, INSPECTION, REPAIR,

REASSEMBLY, INSTALLATION, CALIBRATION,

ADJUSTMENT, AND TESTING FOR THE

EQUIPMENT

CNSP-0199 551-21-001 LOW PRESSURE AIR COMPRESSOR (LPAC);

OVERHAUL

ACCOMPLISH THE REQUIREMENTS OF 009-90

FOR TECHNICAL DOCUMENTATION, OVERSIGHT,

TOOLS, OPERATIONAL TESTING AND A

TECHNICAL REPRESENTATIVE WHO WILL

DIRECTLY ASSIST THE GOVERNMENT

SUPERVISOR

CNSP-0200 555-31-001

HIGH PRESSURE WATER MIST

MECHANICALLY ATTACHED FITTINGS (MAF)

AND PIPE; INSPECT

ACCOMPLISH THE REQUIREMENTS OF 009-71

FOR A HYDROSTATIC TEST OF EACH HIGH

PRESSURE WATER MIST (HPWM) SYSTEM

INSTALLED .

CNSP-0201 561-21-001 STEERING GEAR ACTUATION SYSTEM

(SGAS)OIL INSPECTION

ACCOMPLISH THE REQUIREMENTS OF 009-90 TO

PROVIDE THE SERVICES OF BUREAU VERITAS

TO ACCOMPLISH TESTING OF THE GEARBOX OIL

IN EACH SGAS GEARBOX

CNSP-0202 562-21-001 RUDDER BEARING SEAL AND RUDDERSTOCK

SEAL; REPAIR

ACCOMPLISH PORT AND STBD RUDDER STOCK

REPAIRS

CNSP-0203 581-21-001 ANCHOR AND ANCHOR CHAIN INSPECTION

AND PRESERVATION; ACCOMPLISH

REMOVE THE EQUIPMENT, SEPARATE EACH

ANCHOR, OUTBOARD SWIVEL SHOT, CHAIN

STOPPER ASSEMBLY AND EACH SUCCEEDING 15

FATHOM SHOT, BY DISASSEMBLING THE

DETACHABLE LINKS AND BITTER END SHACKLES

CNSP-0204 588-21-001 PVLS BERM PRESERVATION; ACCOMPLISH

ACCOMPLISH THE PREPARATION OF A SKETCH

SHOWING EXISTING MARKINGS, LABEL PLATES

AND PLACARDS OF EACH BERM COVER

CNSP-0205 593-21-001

VACUUM, COLLECTION, HOLDING AND

TRANSFER (VCHT) SYSTEM; CHEMICAL

CLEANING

ACCOMPLISH VCHT TANK AND PIPE CLEANING

INSPECTION AND REPAIRS

CNSP-0206 624-21-001 CHILL AND FREEZE STOREROOM DOOR

INSPECT AND REPAIR; ACCOMPLISH

ACCOMPLISH THE REQUIREMENTS OF 009-90 TO

PROVIDE THE SERVICES OF A QUALIFIED OEM

REPRESENTATIVE TO INSPECT AND REALIGN

CHILL ROOM AND FREEZE ROOM DOORS

CNSP-0207 624-21-002 BALANCED JOINER DOOR

PROVIDE 25 MANDAYS OF LABOR AND 50,000

DOLLARS OF MATERIAL. INSPECT, TEST,

REMOVE, CRATE, STORE, AND RE-INSTALL ALL

BALANCED JOINER DOORS AND FRAMES.

CNSP-0208 631-21-001

UNDERWATER HULL PRESERVATION PAINT

COMPANY ORIGINAL EQUIPMENT

MANUFACTURERS'

ACCOMPLISH THE REQUIREMENTS OF DM 220-

020 SURF, UNDERWATER HULL: PRESERVE

UTILIZING OEM REPRESENTATIVE

CNSP-0209 631-21-002 FREEBOARD; PRESERVE

EXTERIOR HULL FROM UPPER LIMIT OF BOOT

TOPPING TO TOP OF 01 LEVEL WATERWAY BAR,

FROM BOW TO STERN, TO INCLUDE 12 INCHES

INTO EACH PENETRATION AND PIPE AND WORK

BOUNDARY, EXCLUDING RADAR ABSORBENT

MATERIAL (RAM) TILE AREA/SURFACE, TO

INCLUDE EACH DOOR

CNSP-0210 633-21-001 IMPRESSED CURRENT CATHODIC

PROTECTION (ICCP) REFERENCE CELL

ACCOMPLISH THE REQUIREMENTS OF 009-90

TO PROVIDE THE SERVICES OF AN AUTHORIZED

ORIGINAL EQUIPMENT MANUFACTURER (OEM)

SERVICE PROVIDER TO ACCOMPLISH A PRE-

DRYDOCK INSPECTION OF THE IMPRESSED

CURRENT CATHODIC PROTECTION SYSTEM

CNSP-0211 634-21-003 FLIGHT DECK NONSKID REPLACEMENT

ACCOMPLISH FLIGHT DECK NONSKID

REPLACEMENT UTILIZING SPRAYABLE DECK

COATING, AND ACCOMPANYING TESTS OF

DISTRIBUTED SEA WATER AND COUNTER

MEASURE WASHDOWN SYSTEM, AND DECK DRAINS

CNSP-0212 639-21-001 PASSIVE COUNTERMEASURE SYSTEM (PCMS)

REPAIR AND REPLACEMENT; ACCOMPLISH

ACCOMPLISH A JOINT VISUAL INSPECTION

WITH THE SUPERVISOR OF EACH PCMS RAM

TILE SHOWN TO DETERMINE LOCATIONS FOR

DAMAGED TILE, MISSING TILE, CORROSION

UNDER TILE, MISSING OR DETERIORATING

CAULK, AND ENVIRONMENTAL LAYER PEELING.

ACCOMPLISH REPAIR OF DAMAGED PCMS TILES

USING MATERIALS PROVIDED

CNSP-0213 864-21-001 AN/SPY-3 ANTENNA PROTECTIVE COVERS

FABRICATE AND INSTALL PROTECTIVE

COVERINGS FOR AN/SPY-3 ANTENNAS

CNSP-0214 865-21-001 STAGING AND SCAFFOLDING

PROVIDE 50 MAN-DAYS AND 50,000 DOLLARS

OF STAGING AND SCAFFOLDING SERVICES

CNSP-0215 867-21-001 COMBAT SYSTEM TESTING SUPPORT;

PROVIDE

PROVIDE 2,500 MANHOURS OF LABOR AND

25,000 DOLLARS OF MATERIAL, AS

DESIGNATED BY THE SUPERVISOR, FOR

SUPPORT OF COMBAT SYSTEMS WORK.

CNSP-0164- 123-21-

001R1

TANK AND VOID CLEANING AND PUMPING;

ACCOMPLISH

OPEN, VENTILATE, EMPTY, CLEAN, RENDER

DRY, AND MAINTAIN EACH TANK

CNSP-0216- 123-21-006 TANK GAS FREE, REPAIR AND PRESERVE;

ACCOMPLISH

OPEN, VENTILATE, EMPTY, CLEAN, RENDER

DRY, AND MAINTAIN EACH TANK

CNSP-0217- 711-11-001 GUN WEAPON SYSTEM, 30MM, MK 46 MOD

1/2 RACE RING; INSTALL

PREPARE, REMOVE, INSPECT, INSTALL QTY 2

MK 46 GWS