This is a Statement of Work (SOW) for a Basic Ordering Agreement (BOA) in FY26 supporting the Columbia Program and Strategic Systems Programs under the Department of the Navy. The SOW encompasses five Contract Line Items (CLINs) addressing system integration testing, installation, and repair capabilities for submarine fire control systems.

CLIN 0001 requires on-site System Integration Testing (SIT) for the Strategic Weapon Interface Simulator (SWIS) at Kings Bay Trident Training Facility, including on-site personnel to conduct testing per approved schedules, supporting headquarters personnel for coordination and troubleshooting, and delivery of a final SIT report. CLIN 0002 mandates deployment and installation support for the Columbia program at Kings Bay Trident Training Facility in Georgia, including pre-deployment planning, on-site engineering support, and delivery of an Installation Final Report. CLIN 0003 (base) requires the contractor to establish repair capability for SSBN-R Fire Control Hardware Configuration Items by reviewing and updating cross-reference indexes, operational documents, quality technical instructions, production test and inspection plans, repair routing and procedures, and delivery of a final report on expanded repair capabilities. CLINs 0004 and 0005 are optional efforts running through September 30, 2028, requiring repair and recertification services for nine Columbia and five Dreadnought (United Kingdom-owned) components respectively, with monthly financial status reports, weekly program status reports, quarterly trouble and failure reports using SSP Form 3100.1, and monthly repair completion notices. All work must comply with specified T9001 checklists (modified March 24, 2025), operational documents, and Strategic Systems Programs procedures and standards.

View the file

Other files

File Type Posted
Sources Sought Notice (SSN) FY26 Consolidated-R3.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

CLIN 0001 – SWIS KBTTF On-Site SIT – (Completion)

The Contractor shall provide On-Site System Integration Testing for the Columbia Program Strategic Weapon Interface Simulator (SWIS) in accordance with OD 71877 v2 – Program Plan for SWIS 2.0 R2 and SWIS 2.1. This development effort for SWIS will be in accordance with the T9001B checklist as modified 24 March 2025, for Auxiliary Equipment Type, Development Phase. In support of these efforts, the Contractor shall provide the following as part of the basic ordering agreement:

In support of these efforts, the Contractor shall:

1. Provide personnel On-Site to perform the System Integration Testing (SIT).

2. Provide supporting personnel at Headquarters (HQ) to facilitate Test Program Coordination, Troubleshooting and Software updates as necessary.

3. Conduct the KB-TTF On-Site SIT per approved schedules.

4. Deliver a SWIS KBTTF On-Site SIT report.

CLIN 0002 – CLB KBTTF Installation and Checkout – (Completion)

The Contractor shall provide Deployment and Installation Support to the Kings Bay Trident Training Facility in support of the COLUMBIA program as defined in OD 68538, Program Plan for SSBN Replacement Fire Control System and Shipboard Data System.

In support of these efforts, the Contractor shall provide the following:

A. Installation Support The Contractor shall provide installation support including pre-deployment planning, on-site engineering support, headquarter support, and logistics services for the planning and execution of SPALT 30365 for Strategic Weapon Training Systems in Kings Bay, Georgia. Additionally, the Contractor shall provide technical and engineering support services to support Installation and Checkout at the Kings Bay Trident Training Facility.

1. Conduct CLB KBTTF Installation and Checkout in Kings Bay, Georgia.

2. Prepare and Deliver the Installation Final Report.

CLIN 0003 – SERF Repair Capability – (Completion)

The Contractor shall deliver repair capability for the SSBN-R FC Hardware Configuration Items in accordance with the T9001 Checklist dated March 24, 2025, Fire Control Type, R&R Phase.

In support of this effort the Contractor shall:

1. Review and update the Cross Reference Index (OD 58791).

2. Review and update OD’s, QTI’s and QCAP.

3. Update and deliver the Production Test and Inspection Plan (PTIP) (OD 57861 Volume 3) and the Strategic Systems Programs (SSP) Shipboard Electronics Repair Facility (SERF) Program Plan (OD 65000).

4. Create and update SERF Repair Routing and Procedures.

5. Deliver a Final Report detailing the expanded SERF repair capabilities.

CLIN 0004 – COLUMBIA Repair & Support – (Completion)(Option)

For components inducted from the date of option award through 30 September 2027, the Contractor shall provide the supplies and services as required to inspect, evaluate, repair, and recertify 9 components for COLUMBIA. Components shall be inducted no later than 30 September 2027 and the repair period for inducted assets shall not exceed 30 September 2028. All efforts shall be performed in accordance with:

· T9001C checklist dated March 24, 2025, Fire Control Type, R&R Phase

· R&R SSPINST 4423.39J

· PTIP, including OD 57861 for Weapon Control System Volume 3

· The SSP SERF Program Plan OD 65000

· Inspection Guide and Standard Repair Procedures (SRP) for the SSP SERF OD 65001

Only items inducted for repair shall be counted toward the number of components defined above. The Contractor shall manage the 4th level piece parts to perform the repair obligation. SPS shall act as the Management Control Activity and validate Contractor requests for purchase of 4th level piece parts. These services may include providing Non-Stocked Items (NSI) and Reactive Maintenance Program (RMP) material required. The Contractor shall also conduct all necessary tests, perform evaluations, and maintain test capability for Repair and Return of US SSBN-R FC components.

In support of this effort the Contractor shall:

1. Deliver a Monthly financial status report.

2. Deliver a Weekly Program Status Report.

3. Deliver a Quarterly Trouble and Failure Repair and Return (TFRR) Report SSP Form 3100.1 Series.

4. Deliver a Monthly Repair in Progress Report Completion Notice.

CLIN 0005 – DREADNOUGHT Repair & Support – (Completion)(Option)

For components inducted from the date of option award through 30 September 2027, the Contractor shall provide the supplies and services as required to inspect, evaluate, repair, and recertify 5 components for DREADNOUGHT. Components shall be inducted no later than 30 September 2027 and the repair period for inducted assets shall not exceed 30 September 2028. All efforts shall be performed in accordance with:

· T9001C checklist dated March 24, 2025, Fire Control Type, R&R Phase

· Repair of United Kingdom owned Strategic Weapon System material in the United States – SSPINST 4408.H

· PTIP, including OD 57861 for Weapon Control System Volume 3

· The SSP SERF Program Plan OD 65000

· Inspection Guide and SRP for the SSP SERF OD 65001

Only items inducted for repair shall be counted toward the number of components defined above. The Contractor shall manage the 4th level piece parts to perform the repair obligation. SPS shall act as the Management Control Activity and validate Contractor requests for purchase of 4th level piece parts. These services may include providing NSI and RMP material required. The Contractor shall also conduct all necessary tests, perform evaluations, and maintain test capability for Repair and Return of UK SSBN-R FC components.

In support of this effort the Contractor shall:

5. Deliver a Monthly financial status report.

6. Deliver a Weekly Program Status Report.

7. Deliver a Quarterly TFRR Report SSP Form 3100.1 Series.

8. Deliver a Monthly Repair in Progress Report Completion Notice.