This document is a Statement of Work (SOW) for an Advanced Fire Control System (FCS) development contract with the Department of the Navy Strategic Systems Programs. The SOW includes three Contract Line Item Numbers (CLINs) detailing specific development and production requirements: CLIN 2021 focuses on accelerated advanced FCS development through continuous development activities, prototyping, demonstrations, and backlog grooming; CLIN 2022 involves delivering equipment to support the SSBN Replacement Fire Control System, including building, inspecting, and testing various system components; and CLIN 2023 covers program protection activities involving software procurement, testing, system security engineering, and developing capabilities deployment roadmaps for controlled network environments.
The pre-solicitation opportunity (Solicitation Number N0003024C1005P0TBD5) is associated with advanced fire control system development, specifically targeting replacement systems for submarine-based platforms. The scope indicates a complex technical engagement requiring advanced engineering capabilities in fire control system design, production, and program protection, with a strong emphasis on systematic development approaches, technical program management practices, and comprehensive system security considerations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Final FY24 Advanced FCS Acceleration Sources Sought Notice (SSN) 20251103.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIN 2021 –Accelerated Advanced FCS Development – (Completion) The Contractor shall provide design and development efforts and necessary materials to accelerate development of the Advanced FCS and associated derisking activities. Activities shall be in alignment with scope approved by the Government during quarterly agile planning increments (PIs) toward the advancement of the SWS Program of Record (POR). Activities shall include, but not limited to continuous development activities, prototyping, demonstration of capabilities, interfaces, acceleration of backlog, trade studies and detailed analysis. All activities shall be performed in accordance with the applicable Technical Program Management practices and governing documents. The Contractor shall execute Continuous Development Backlog Grooming, PI planning and PI Closeout activities, perform Trade Studies and Analysis, Concept Exploration, prototyping, design and development activities, and execution of applicable demonstrations.
CLIN 2022 – Advanced FCS Production – (Completion) The Contractor shall deliver equipment to support program schedule dates for SPALT 30365 (FIRE CONTROL REPLACEMENT SYSTEM) – US Replacement as defined in OD 71981, Program Plan for the SSBN Replacement Fire Control System and Shipboard Data System, and the T9001C checklist. The contractor shall build, inspect, test, and deliver SPALT, Auxiliary, Mock-up, Repair, and Installation Kits as required in accordance with technical requirements and established regulations.
CLIN 2023 –Program Protection (Completion) The Contractor shall perform Program Protection in support of the Program Portfolio and shall support software, procure material, test, inspect, and deliver materials and or software as may be required to support each of the required networks, enclaves, and systems in support of the Program. Activities shall be in accordance with established regulations, guidance and policies. The contractor shall further assess technical guidance requirements, perform system security engineering, develop, maintain, prepare, and deliver a capabilities deployment roadmap for unique enclaves, expand access to controlled environment and enclaves in accordance with established regulations, directives, and instructions. Prepare and deliver planning factors, estimates, projections, plans and planning factors for program protection requirements and the design of a future software development environment.