REV: ENGINEERING DATA REQUIREMENTS

(ATTACHMENT “A”)

NOTE: MILITARY SPECIFICATIONS / STANDARDS WILL NOT BE FURNISHED IN THE BID SET.

1. THE FOLLOWING INSTRUCTIONS ARE FURNISHED FOR THE MANUFACTURE OF:

HOUSING ASSEMBLY, BEARING, TURBINE. F-15

2. PART NUMBER:

366820-4

3. NATIONAL STOCK NUMBER:

2835-01-474-8756RP

PREPARED BY:

TYRELL PHILPOTT

OFFICE SYMBOL:

419 SCMS/GUEA

DATE:

15 JUNE 2016

HILL AFB FORM 462 Page 1 of 1

4. THE FOLLOWING SPECIFICATIONS/STANDARDS, ETC., WILL BE USED IN LIEU OF THE DATA INDICATED. THE

SUPERSEDED DATA WILL NOT BE FURNISHED UNLESS SO INDICATED:

a. 419 SCMS/GUEA RETAINS ALL RIGHTS TO REVIEW AND ACCEPT MATERIAL REVIEW BOARD (MRB) DISPOSITIONS PRIOR TO SHIPMENT OF DISCREPANT ITEM. ALL DEVIATIONS, MINOR AND MAJOR, FROM THE ENGINEERING DRAWING

PACKAGE SHALL BE SUBMITTED FOR MRB DISPOSITION.

b. PRIOR TO CONTRACT AWARD, THE CONTRACTOR SHALL CERTIFY TO THE GOVERNMENT IN WRITING FULL COMPLIANCE WITH MANUALS, SPECIFICATIONS AND STANDARDS CALLED OUT AND REQUIRED FOR THE MANUFACTURE OF THIS CONTRACTED SECONDARY POWER COMPONENT/ASSEMBLY. CONTRACTOR IS RESPONSIBLE TO COMPLETELY SEARCH THESE MANUALS, SPECIFICATIONS AND/OR STANDARDS AND FULLY UNDERSTAND THE REQUIREMENTS NECESSARY TO

MANUFACTURE THIS COMPONENT. ANY QUESTIONS CAN BE FORWARDED TO 419 SCMS/GUEA.

c. ITEM UNIQUE IDENTIFICATION (IUID) IS REQUIRED, REFERENCE MIL-STD-130. SPECIFIC INSTRUCTIONS FOR MARKING METHODS, LOCATION, CONTENT, AND FORMAT SHALL BE SPECIFIED BY THE CONTRACTOR AND SUBMITTED TO THE GOVERNMENT FOR APPROVAL PRIOR TO CONTRACT DELIVERY. THE CONTRACTOR MUST DEMONSTRATE THAT THE MARKING DOES NOT ADVERSELY AFFECT ITEM INTEGRITY OR PERFORMANCE AND WILL REMAIN READABLE AND ATTACHED THROUGHOUT THE USEABLE LIFE OF THE ITEM. THE ITEM SHALL BE MARKED IN A HIGHLY VISIBLE AND EASILY ACCESSABLE AREA UNLESS IT INTERFERES WITH PART FUNCTIONALITY. THE CONTRACTOR SHALL OBTAIN WRITTEN APPROVAL OF THE PROPOSED MARKING METHOD PRIOR TO IUID APPLICATION AND CONTRACT DELIVERY.