RESTORE Science Program milestone Gantt chart template (OMB Control No. 0648-0384) (3).xlsx
XLSX spreadsheet 144 KB Posted
- Attached to
- NOAA RESTORE Science Program 2021
- Opportunity number
- NOAA-NOS-NCCOS-2021-2006590
- Issued by
-
Department of Commerce
About this file
Restore Science Program Milestone
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NOAA-NOS-NCCOS-2021-2006590 NOFO Report (1) (a).pdf | ||
| PKG00262954-instructions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| Instructions |
| Please follow instructions below to fill out a milestone Gantt chart ("Gantt Chart" tab) per the requirement in the funding announcement. Refer to the "Example" tab as needed. |
| For FFO-2021 - Planning for Actionable Science, the anticipated project start date is September 1, 2021. Please align your milestones and tasks in this Gantt chart using the start date proposed in your application |
| 1. Fill out Columns A-E as follows (See example Gantt chart under "Example" tab): |
| a. Each task (column B) should fit under a project milestone (in bold, column A). Please add additional milestones in column A as needed and add the associated tasks for each milestone in separate rows in column B. |
| b. Please provide a category of your choosing for each task in column C. Suggestions include (but are not limited to): Data collection, Data Analyses, Data Management, Meeting, Meeting Preparation, Workshop, Outreach, Writing, Reporting/Publications. You may have different task categories under a single milestone (e.g., see milestone 2 in “Example” tab). |
| c. Please add the start date and completion date for each task in columns D and E, respectively. |
| Note: Although the template only contains 3 milestones with 3 tasks each, there is no limit to the number of milestones or tasks associated with each milestone. |
2. Using the timeline provided in rows 1 through 3, please fill in the appropriate cells for each task using blue that corresponds to the start and completion date provided in columns D and E, respectively. Blue cells can be continuous (e.g., from 9/1/2021-1/31/2022) or on a frequency of your choosing (e.g., bi-monthly or quarterly meetings). Note - years are in fiscal years (FY2021, FY2022).
3. Using the timeline provided in rows 1 through 3, please fill in the appropriate cells for each milestone using green that corresponds to the start and completion date of all of the tasks associated with that milestone. Note - years are in federal fiscal years (FY2021, FY2022).
4. Please save the spreadsheet as "[PI Last Name- Project title keyword- Gantt chart]" and submit the file along with your full application to Grants.gov ahead of the deadline for this funding opportunity
Gantt Chart
| Milestone | Task | Task Category | Task Start Date | Task Completion Date | 2021 | 2022 | ||||||||||
| Q1 | Q2 | Q3 | Q4 | |||||||||||||
| S | O | N | D | J | F | M | A | M | J | J | A | |||||
| Milestone 1: [Enter name of milestone] | - | - | - | - | - | - | - | - | - | - | - | - | ||||
| 1.1 | [Enter first task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| 1.2 | [Enter second task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| 1.3 | [Enter third task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| Milestone 2: [Enter name of milestone] | - | - | - | - | - | - | - | - | - | - | - | - | ||||
| 2.1 | [Enter first task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| 2.2 | [Enter second task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| 2.3 | [Enter third task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| Milestone 3: [Enter name of milestone] | - | - | - | - | - | - | - | - | - | - | - | - | ||||
| 3.1 | [Enter first task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| 3.2 | [Enter second task] | [Enter category] | [Enter start date] | [Enter due date] | ||||||||||||
| 3.3 | [Enter third task] | [Enter category] | [Enter start date] | [Enter due date] |
Etc.
Example - Planning Project
| This Gantt chart is based on an example project focused on reducing the scientific uncertainities around a state agency decision to set nutrient reduction targets and where to place continuous nutrient monitoring stations. | ||||||||||||||||
| Task | Task Category | Task Start Date | Task Completion Date | 2021 | 2022 | |||||||||||
| Q4 | Q1 | Q2 | Q3 | Q4 | ||||||||||||
| S | O | N | D | J | F | M | A | M | J | J | A | |||||
| Milestone 1: Scoping Activities* | - | - | - | - | X | - | - | - | - | - | - | - | ||||
| 1.1 | Design survey to query nutrient management community on current practices | Meeting Preparation | 9/1/21 | 9/30/21 | ||||||||||||
| 1.2 | Conduct nutrient management practices survey | Meeting Preparation | 10/1/21 | 10/31/21 | ||||||||||||
| 1.3 | Design first scoping workshop (virtual) with facilitator | Meeting Preparation | 10/1/21 | 10/31/21 | ||||||||||||
| 1.4 | Generate initial project scope based on nutrient managment reduction decision and identified uncertainties | Writing | 11/1/21 | 12/31/21 | ||||||||||||
| 1.5 | Gather feedback on project scope from project team | Data Collection | 12/1/21 | 12/31/21 | ||||||||||||
| 1.6 | Revise project scope to include feedback and finalize scope | Writing | 1/1/22 | 1/31/22 | ||||||||||||
| Milestone 2: Data Collection | - | - | - | - | - | - | X | - | - | - | - | - | ||||
| 2.1 | Nutrient reduction options literature review | Data Collection | 9/1/21 | 2/28/22 | ||||||||||||
| 2.2 | Review of current nutrient reduction Decision Support Tools | Data Collection | 9/1/21 | 2/28/22 | ||||||||||||
| 2.3 | Individual watershed characterizations | Data Collection | 9/1/21 | 1/31/21 | ||||||||||||
| 2.4 | Design nutrient reduction targets and goals survey to query nutrient management community | Data Analysis | 1/1/22 | 1/31/22 | ||||||||||||
| 2.5 | Conduct nutrient targets and goals survey | Data Collection | 2/1/22 | 2/28/22 | ||||||||||||
| 2.6 | Design continuous monitoring station location prioritization excercise | Data Analysis | 2/1/22 | 3/31/21 | ||||||||||||
| 2.6 | Synthesis of literature review and survey results | Data Processing | 2/1/22 | 3/31/21 | ||||||||||||
| Milestone 3: Research and Development Plan and Application Plan | - | - | - | - | - | - | - | - | - | - | - | X | ||||
| 3.1 | Draft Research and Development (R&D) Plan | Writing | 4/1/22 | 5/31/22 | ||||||||||||
| 3.2 | Draft Application Plan | Writing | 4/1/22 | 5/31/22 | ||||||||||||
| 3.3 | Gather feedback from project team and others on R&D and Application plans | Data Collection | 6/1/22 | 6/30/22 | ||||||||||||
| 3.4 | Revise R&D Plan and Application Plan | Writing | 7/1/22 | 7/31/22 | ||||||||||||
| 3.5 | Finalize R&D Plan and Application Plan | Writing | 8/1/22 | 8/31/22 | ||||||||||||
| Milestone 4: Meetings and Workshops | - | - | - | - | - | - | - | - | - | - | X | - | ||||
| 4.1 | Initial project meeting | Meetings | 9/1/21 | 9/30/21 | ||||||||||||
| 4.2 | First scoping workshop (virtual) | Workshop | 11/1/21 | 11/30/21 | ||||||||||||
| 4.3 | Final scoping meeting - review data synthesis and execute nutrient monitoring station prioritization excercize (virtual) | meetings | 2/1/22 | 3/1/22 | ||||||||||||
| 4.4 | Meet for drafting R&D Plan and Application Plan | meetings | 3/1/22 | 4/1/22 | ||||||||||||
| 4.5 | Meeting for final review and updates to R&D Plan and Application Plan (virtual) | meetings | 7/1/22 | 8/1/22 | ||||||||||||
| Milestone 5: Reporting | - | - | - | - | - | - | - | - | - | - | - | X | ||||
| 5.1 | Progress reports | Reporting | 2/1/21 | 8/31/22 | ||||||||||||
| 5.2 | Science Program check ins (60 min web meeting) | Reporting | 12/1/21 | 6/30/22 | ||||||||||||
| 5.3 | Prepare final report** | Reporting/ Data Management | 8/1/22 | 8/31/22 |
| * These activities should build upon the initial scoping activities described in your proposal |
| ** Final report is due 90 days after the end of the period of performance |