Section_B..pdf

PDF 18 KB Posted

Attached to
Drydock Repairs to NOAA Ship NANCY FOSTER
Solicitation number
EA-133M-15-RP-0119
Issued by

About this file

Section B. Replacement Pages

View the file

Other files

File Type Posted
SF_30 _Amend_0003.pdf PDF
SF_30 _Amend_0002.pdf PDF
NOAA_Ship_Nancy_Foster_Tank_Sounding_Tables_GSSP_2005_9-4-2009.pdf PDF
Drawing_NF-100-004_Starboard_Exhaust_Stack_Mod_Rev_03-19-2015.pdf PDF
Drawing_601130_Zinc_Anode_Installation.pdf PDF
NF-533-002_Potable_Water_Piping_System.pdf PDF
NFFY16DD_Repair_Index_and_Spec_Package_with_Forms_Rev_08-28-2015_for_Amend_0002.pdf PDF
Std_Spec_573-1C_Testing_of_Davits_and_Weight_Handling_Gear.pdf PDF
Std_Spec_533-1_Potable_Water_Tank_Disinfection.pdf PDF
Std_Spec_300-1_Overhaul_of_Electrical_Rotating_Machinery.pdf PDF
Std_Spec_510-1B_HVAC_Cleaning.pdf PDF
Std_Spec_581-1A_Inspection___Preservation_of_Ground_Tackle.pdf PDF
Technical_Manual_NF-243-01_Shaft_Seal_TM.pdf PDF
Std_Spec_000-2C_Temporary_Services_at_Contractor_Facilities.pdf PDF
Std_Spec_631-2D_Coating_Systems_for_Steel_Surfaces.pdf PDF
Photo_100_2119_DESH-5_Winch_as_installed_aboard_M2_08-17-2007.pdf PDF
Std_Spec_583-1b_General_Requirements_for_Liferaft_Inspections.pdf PDF
Std_Spec_635-1_Thermal_Insulation_for_Piping.pdf PDF
NF-555-6500975_Halon_1501_Fire_Suppression_System.pdf PDF
Std_Spec_997-1A_Drydocking_and_Routine_Drydock_Work.pdf PDF
Section_G..pdf PDF
Technical_Namual_for_GoodCrane_Model_40KSC10000_Crane.pdf PDF
NF-555-001-1I-SHT_1_Fire_Plan.pdf PDF
Photo_100_2120_DESH-5_Winch_as_installed_aboard_M2_08-17-2007.pdf PDF
Std_Spec_505-1B_Valve_Overhaul_and_Test.pdf PDF
Std_Spec_631-3B_Underwater_Ablative_Coating_System.PDF PDF
Std_Spec_573-2_Overhaul___Repair_of_Hydraulic_Cylinders.pdf PDF
Drawing_101-6500833_Model_E_ structural .pdf PDF
Std_Spec_505-2_Hydrostatic_Pressure_Tests.pdf PDF
NF-561-001_Rev._C. _Steering_System_Installations.pdf PDF
NF_512-003 _HVAC_System.pdf PDF
Std_Spec_635-2_Thermal_Insulation_for_Compartments.pdf PDF
Technical_Manual_NF-561-001_Rev._C_Steering_System_Installation.pdf PDF
SF_30 _Amend_0001.pdf PDF
NF-555-001-2I-SHT_2_Fire_Plan.pdf PDF
Photo_100_2118_DESH-5_Winch_as_installed_aboard_M2_08-17-2007.pdf PDF
Std_Spec_602-1_Weight_Test_Data_Plates.pdf PDF
Std_Spec_100-1A_ABS_Load_Line_Survey.pdf PDF
Std_Spec_240-1_Propulsion_Shafts_and_Propellers.pdf PDF
Drawing_101-6500837_Aft_Foc'sle_House_Module_(Module_J).pdf PDF
NFFY16DD_Repair_Index_and_Spec_Package_with_Forms_Rev_08-19-2015.pdf PDF
Std_Spec_300-3_General_Requirements_for_Electrcial_Electronic_Items.pdf PDF
NF-555-6500976_AFFF_System.pdf PDF
NF-243-001_Shafting_Arrangement_and_Details.pdf PDF
NF-461-002___EM710_-_Multibeam_Echo_Sounder__Installation_85767775.pdf PDF
NF-424-001___DSN-450_-_Doppler_Speed_Log_Installation_85770548.pdf PDF
Desh5_Winch_Addition_and_Operations.pdf PDF
Technical_Manual_YTT-243-034_Propeller_Removal-Installation_System.pdf PDF
Drawing_214-MS_Watertight_Spring_Assist_Raised_Hatch_with_Dogs.pdf PDF
Drawing_C34842_DESH-5_Turntable_-_19000OL_CERT.pdf PDF
Show 40 more

Latest 50 of 84 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION B

SUPPLIES OR SERVICES AND PRICES

EA-133M-15-RP-0119

Page - 2

B.1 SCHEDULE OF PRICES

BASE ITEMS

CLIN

SPECIFICATION

WORK ITEM SPECIFICATION WORK ITEM TITLE QTY UNIT

UNIT

PRICE

EXTENDED

PRICE

0001 001 GENERAL REQUIREMENTS 1 JOB $________ $___________

0002 002 TEMPORARY SERVICES

JOB $________ $___________

0003 003

DRY DOCKING & ROUTINE DRYDOCK

WORK 1

JOB $________ $___________

0004 004 UNDERWATER HULL MAINTENANCE COAT

JOB $________ $___________

0005 005 PROPELLER SHAFT INSPECTION 1 JOB $________ $___________

0006 006 Z-DRIVE PROPELER SHAFT RENEWALS 1 JOB $________ $___________

0007 007

BOW THRUSTER REPAIRS &

MODIFICATIONS 1

JOB $________ $___________

0008 008 SEA VALVE OVERHAULS 1 JOB $________ $___________

0009 009 MAIN ENGINE OVERHAUL 1 JOB $________ $________

0010 010 ABS SURVEYS 1 JOB $________ $________

0011 011 SHELL PLATE REPAIRS 1 JOB $________ $________

0012 012 STEEL REPAIRS & MODIFICATIONS 1 JOB $________ $________

0013 013 PIPE REPAIRS & MODIFICATIONS 1 JOB $________ $________

0014 014 AFT DECK CRANE OVERHAUL & TEST 1 JOB $________ $________

0015 015 VENT DUCT CLEANING 1 JOB $________ $________

0016 016

ANCHOR CHAIN INSPECTION &

PRESERVATION & WINDLASS REPAIR

1 JOB $________ $________

0017 017

LIFERAFT ANNUAL INSPECTION &

CERTIFICATION

1 JOB $________ $________

0018 018 FIREFIGHTING SYSTEM CERTIFICATION 1 JOB $________ $________

SUBTOTAL CLINS 0001 – 0018: $______________

SECTION B

SUPPLIES OR SERVICES AND PRICES

EA-133M-15-RP-0119

Page - 3

ADDITIONAL ITEM REQUIREMENTS (AIRs): These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.

0019 400

AIRS/Growth (estimated)

**Provide breakdown, as follows:

AIRs/Growth Labor Rate Unit Price: $________; Quantity: 1,400; Unit of Issue: Hour; Extended Price: $____________

AIRs/Growth Material Markup/Handling Fee Unit Price: $100,000.00; Quantity: 1; Unit of Issue:

Percent ________%;

Extended Price: [$100,000.00 X percentage quoted]:

1 LT $_______ $__________

0020 N/A LAYDAYS (SEE CAR CLAUSE 1372.271-86)

EST.

DAY $________ $_________

0021 N/A ADDITIONAL TEMPORARY SERVICES (SEE

CAR CLAUSE 1372.271-89)

EST.

DAY $________ $_________

SUBTOTAL (CLINS 0019 – 0021): $______________

OPTION CLINS

CLIN

SPECIFICATION

WORK ITEM SPECIFICATION WORK ITEM TITLE QTY UNIT

UNIT

PRICE

EXTENDED

PRICE

0022 501 SEWAGE TANK COATING REPAIRS 1 JOB $_______ $__________

0023 502

TEMPORARY BERTHING & HOTEL

ACCOMODATIONS

1 JOB $_______ $__________

0024 503

STACK MODIFICATIONS FOR NEW FAST

RESCUE BOAT

1 JOB $_______ $__________

0025 504

OCEANOGRAPHIC WINCH INSTALLATION

& TEST

1 JOB $_______ $__________

0026 505

RUDDER STOCK INSPECTION & BEARING

RENEWAL

1 JOB $_______ $__________

0027 506 DELETED

0028 507 TRANSDUCER GASKET RENEWAL 1 JOB $_______ $_______

0029 508

FREEBOARD PRESERVATION,

MAINTENANCE COATING

1 JOB $_______ $_______

0030 509 SACRIFICIAL ANODE REPLACEMENTS 1 JOB $_______ $_______

0031 510

MISSION UPS WIRING & VSAT ATENNA

WIRING UPGRADES

1 JOB $_______ $_______

SUBTOTAL OPTION CLINS (CLINS 0022 – 0031): $______________

GRAND TOTAL ALL CLINS (BASE, AIRS, AND OPTION ITEMS): $______________

File details come from the government source that posted it. Updated .