This Project Manual pertains to site improvements at Sharshon Park in Connecticut and provides the technical specifications and requirements for construction contractors bidding on the project. The project encompasses regrading of turf fields, installation of drainage structures, construction of bituminous basketball courts, development of accessible paths compliant with accessibility standards, and restriping of the parking lot to incorporate accessible parking spaces. The manual serves as the governing document for design standards, material specifications, workmanship requirements, and technical performance criteria that all bidders must follow in preparing their proposals and that the selected contractor must adhere to during project execution.
The Project Manual establishes the technical framework and construction standards for all work to be performed at the site. Contractors should reference this document in conjunction with the bid solicitation documents for information regarding contract pricing, payment terms, project timeline, bonding requirements, insurance coverage, and other administrative aspects of the procurement. The manual provides detailed specifications for materials, methods, and quality standards to ensure consistent project delivery and compliance with applicable building codes and accessibility regulations in Connecticut.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TOWN OF WINDSOR
ENGINEERING
CONTRACT DOCUMENTS
FOR
SHARSHON PARK SITE IMPROVEMENTS
WINDSOR, CT
E2026-08
Bids will be received until 2:00 P. M. on December 15, 2026, in the Finance Office, Town Hall, Windsor, Connecticut. Bids will be opened and read in the Rose Room on the 3rd Floor of the Windsor Town Hall immediately following the deadline.
48 Skitchewaug St, Windsor, CT
E2026-08
Table of Contents
Section 1 – Bidding and Contract Requirements Invitation to Bid Information for Bidders Sample Agreement Special Conditions General Conditions
Section 2 – Construction Contract Requirements Prevailing Wage Bid Package
Section 3 – Technical Specifications Special Provisions
Appendices:
Appendix A – Executive Order Number 3 Appendix B – Executive Order Number 17 Appendix C – Executive Order Number 16 Appendix D – Standard Bid Bond Appendix E – Form of Non-Collusive Affidavit Appendix F – Bid Form Appendix G – Add Alternate No. 1 Appendix H – IWWC Permit
Section 1 – Bidding and Contract Requirements
FINANCE DEPARTMENT
TOWN HALL
275 BROAD STREET
WINDSOR, CONNECTICUT 06095
Notice to Contractors - Invitation to Bid
E2026-08
In accordance with provisions of the Town Charter, bids will be received until 2:00 P.M. on December 15, 2026 in the Finance Office, Town Hall, Windsor, Connecticut. Bids for furnishing of materials, equipment, and labor for SHARSHON PARK SITE IMPROVEMENTS will be opened and read in the Rose Room of the Town Hall immediately following the deadline.
Bids must be executed in accordance with and subject to instructions contained in the Information for Bidders.
It is the responsibility of the Bidder to ensure the sealed bid or proposal is delivered prior to the deadline above.
The SHARSHON PARK SITE IMPROVEMENTS project will consist of regrading turf fields, the installation of drainage structures, the construction of bituminous basketball courts, and accessible paths as well as the restriping of the parking lot to accommodate accessible parking spaces.
Bidders may obtain complete sets of Bidding Documents online from the Town of Windsor website:
https://www.windsorct.gov/bids.aspx. Bidding documents will be made available for viewing an after 12:00 pm local time on November 10, 2026.
The right is reserved to reject any or all bids or to waive defects in same if it is deemed in the best interest of the Town of Windsor.
For further information please send questions to Julie Wilson, Engineering Assistant, via email at jwilson@windsorct.gov. Pertinent questions will be answered via Addendum by close of business on December 10, 2026. Addenda will be issued through the Town of Windsor website:
https://www.windsorct.gov/bids.aspx.
The Town of Windsor is an equal opportunity/affirmative action employer. Disadvantaged, minority, small, and women’s Business Enterprises are encouraged to respond.
https://www.windsorct.gov/bids.aspx mailto:zinky@townofwindsorct.com https://www.windsorct.gov/bids.aspx
E2026-08 I-1 Information for Bidders
INFORMATION FOR BIDDERS
Sharshon Park Site Improvements
Table of Contents
NO. TITLE PAGE
1. RECEIPT & OPENING OF BIDS 2
2. PREPARATION OF BID 2
3. COMPETENCY OF BIDDERS 2
4. REJECTION OF BIDS 3
5. MODIFICATION BY E-MAIL OR FACSIMILE 3
6. ERRORS OR OMISSIONS 3
8. QUALIFICATIONS OF BIDDER 3
9. DISQUALIFICATION OF BIDDERS 4
10. BID SECURITY 4
12. ADDENDA & INTERPRETATIONS 4
13. EXECUTION OF CONTRACT & NOTICE TO PROCEED 4
14. TIME OF COMPLETION AND LIQUIDATED DAMAGES 5
15. CONDITIONS OF WORK 5
16. SECURITY AND FAITHFUL PERFORMANCE 5
17. METHOD OF AWARD 5
18. LAWS AND REGULATIONS 6
19. SALES TAX 6
20. INSURANCE 6
21. RIGHTS-OF-WAY 6
22. LIMIT OF CONSTRUCTION 6
23. COMPLIANCE WITH THE TOWN OF WINDSOR CODE OF ETHICS 7
E2026-08 I-2 Information for Bidders
INFORMATION FOR BIDDERS
1. Receipt & Opening of Bids Sealed bids or proposals for performing the work hereinafter described will be received at the Office of the Purchasing Agent, Finance Department, Town Hall, 275 Broad Street, Windsor, Connecticut, until the time and date as shown on the title page of this proposal.
2. Preparation of Bid Bids must be made on the form furnished by the Town of Windsor and attached hereto.
Bidders will state, both in numerals and in words, the proposed price for the work. If any price is omitted, the blank may be filled with the highest price proposed by any other bidder for such omitted item or the entire proposal may be rejected.
The unit price and/or lump sum for each of the several items in the proposal of each bidder shall include its pro rata share of overhead so that the sum of the products obtained by multiplying the quantity shown for each item by the unit price and/or lump sum bid represents the total bid. Any bid not conforming to this requirement may be rejected as informal. The special attention of all bidders is called to this provision, for should conditions make it necessary to revise the quantities, no limit will be fixed for such increased or decreased quantities nor compensation allowed.
The following documents shall be submitted with bids. Bids not including all forms shall be considered incomplete and will be rejected.
1. Bid Proposal Form
2. Bid Bond
3. Non-Collusive Affidavit
4. Copy of Contractor’s current “Contractor Prequalification Certificate” issued by the
State of CT Department of Administrative Services or Copy of Contractor’s current “Contractor Prequalification” issued by the State of CT Department of Transportation (CON-16)
3. Competency of Bidders The Town reserves the right to select bidders and may refuse to consider a bid form from any individual, firm or corporation based upon, but not limited to, one or more of the following facts:
(1) For having defaulted on previous contracts or is currently in litigation or arbitration with the Town of Windsor.
(2) For having failed to complete contracts within the time required without acceptable reasons.
(3) For having performed similar work in an unsatisfactory manner.
E2026-08 I-3 Information for Bidders
(4) For having failed to prosecute work continuously, diligently and cooperatively in an orderly sequence.
(5) When in the Town's judgment the bidder does not have the required experience in the class of work to be bid on, fails to have proper labor and equipment to prosecute the work within the time allowed, or fails to have sufficient capital and quick assets to finance the work.
4. Rejection of Bids Bids may be rejected if they show any irregularities, omissions, alteration of form or additions not called for, or do not comply with instructions to bidders, or contain conditional or alternate bids, unless bids on alternate materials are specifically called for in the bid form.
5. Modification by E-mail or Facsimile Any bidder may modify his bid by e-mail or facsimile at any time prior to the scheduled closing time for receipt of bids, provided such communication is received by the Town prior to the closing time, and provided further that the Town is satisfied that a written confirmation of the modification with the signature of the bidder was mailed prior to the closing time. The communication should not reveal the bid price but should provide the addition or subtraction or other modification so that the final prices or terms will not be known by the Town until the sealed bid is opened. If written confirmation is not received within two (2) days from the closing time, no consideration will be given to the modification.
6. Errors or Omissions The Contractor shall be and is required to check all dimensions and quantities on the Contract Drawings and all statements in the Information for Bidders and Specifications before undertaking any portion of the work, and shall notify the Engineer of all errors or omissions therein, which he may discover by such examination and checking. The Contractor will not be allowed to take advantage of any error or omission in these Specifications or in the Contract Drawings or in the Information for Bidders. Full instructions will be issued by the Engineer should such error or omission be discovered and the Contractor shall carry out such instructions as if originally specified.
7. Subcontracts The bidder is advised that any person, firm or other party to whom it is proposed to award a subcontract under this contract must be acceptable to and approved by the Town.
8. Qualifications of Bidder The Town of Windsor may make such investigation as deemed necessary to determine the ability of the bidder to discharge his contract. The bidder shall furnish the town with all such information and data as may be required for that purpose. The town reserves the right to reject any bid if the bidder fails to satisfactorily convince the town that he is properly qualified by experience and facilities to carry out the obligation of the contract and to satisfactorily complete the work called for herein. Conditional bids will not be accepted.
E2026-08 I-4 Information for Bidders
9. Disqualification of Bidders Any or all bids will be rejected if there is reason to believe that collusion exists among the bidders, and no participants in such collusion will be considered in future proposals for the same work. Bids in which the prices obviously are unbalanced may be rejected. Unbalanced prices shall be interpreted to mean that the unit price for any item is such that it is unreasonable for that particular item when considered by itself and not considered in connection with the bid submitted on any other item or items. No contract will be awarded except to competent bidders capable of performing the class of work contemplated.
10. Bid Security The bid must be accompanied by a bid bond which shall be not less than ten (10) percent of the amount of the bid, including the base bid and any and all alternates. The bid bond shall be duly executed by the bidder as principal and having a surety thereon which shall be acceptable to the town. Certified checks or bank drafts will not be accepted.
No bidder may withdraw his bid within ninety (90) calendar days after the actual date of bid opening.
11. Damages for Failure to Enter into Contract
The party to whom the contract is awarded will be required to execute the agreement and obtain the performance and payment bond within ten (10) calendar days from the date when notice of award is delivered to the bidder. In case of failure of the bidder to execute the agreement and submit bond forms, the town may, at its option, consider the bidder in default, in which case the bid security accompanying the proposal shall be called.
12. Addenda & Interpretations Any request from prospective bidder for interpretation of meaning of contract drawings, specifications or other contract documents shall be made in writing to Julie Wilson:
Engineering Assistant at jwilson@windsorct.gov or 275 Broad Street, Windsor, CT 06095. All questions must be received at least ten (10) days prior to date fixed for opening of bids in order to be considered.
Interpretations will be made in form of written addenda to contract documents, which addenda shall become a part of contract. Addenda will be posted to Town website at least five (5) days prior to date for opening of bids. Faxes, mailings, or emails of Addenda will not be provided by the Engineer or Town. Failure of any bidder to receive any such addenda shall not relieve bidder from any obligation under his proposal as submitted.
13. Execution of Contract & Notice to Proceed Upon receipt of acceptable performance bond, labor and materials payment bond, insurance certificates and signed agreement, the town will, within ten (10) days, enter into and sign the Agreement unless it deems it not to be in the best interest of the Town.
E2026-08 I-5 Information for Bidders
The notice to proceed shall be issued within ten (10) days of the execution of the agreement by the town. Should there be reasons why the notice to proceed cannot be issued within such period, the time may be extended by mutual agreement.
It is the intent for the Contractor to commence construction immediately, but in no case exceed ten (10) days from the date on the notice to proceed.
14. Time of Completion and Liquidated Damages The bidder must agree to commence work within ten (10) days after the date specified in the Notice to Proceed from the Town Engineer and to faithfully complete the project within the number of consecutive calendar days of the date of the Notice to Proceed, as stated in the Sample Agreement.
The bidder’s attention is directed to Article 31 of the General Conditions. The bidder must agree to pay as liquidated damages in the amount of Eight Hundred and Fifty Dollars and Zero Cents ($850.00) for each consecutive calendar day in excess of the completion date in accordance with the General Conditions.
15. Conditions of Work At the date fixed for opening of bids, it will be presumed that each bidder has made an examination of location and site work to be done under contract; has satisfied himself as to actual conditions, requirements and quantities or work; and has read and become thoroughly familiar with Contract Documents, including contract drawings, specifications and addenda.
16. Security and Faithful Performance In addition to the agreement, the successful bidder shall also provide, within the time stipulated above, a Performance Bond by a company satisfactory to the Town in an amount equal to one hundred (100) percent of estimate total contract price recorded in proposal of contract as executed. A Labor and Materials Payment Bond in like amount, will be required from successful bidder for faithful performance of contract.
Subcontractors selected to complete any work in excess of $100,000.00 must also provide both a Performance Bond and Labor and Materials Bond, in accordance with the above stipulations, in an amount equal to one hundred (100) percent of the estimated work.
17. Method of Award The contract will be awarded to the responsible bidder submitting the lowest bid complying with the conditions of these contract documents. The bidder to whom the award is made will be notified at the earliest possible date. The successful bidder shall execute and deliver to the Town, within ten (10) days after notification of the award, an agreement in the form included in the contract documents, in such number as the Town shall require.
The Town also reserves the right to reject any or all bids, for any reason the Town deems advisable, and to award contract or contracts to any of contractors bidding on work
E2026-08 I-6 Information for Bidders regardless of amount of bid. It is intended that contract or contracts will be awarded to lowest responsible and eligible bidder (or bidders) possessing skill, ability, and integrity necessary to faithfully perform the work.
Any bid in which the prices obviously are unbalanced is a cause for the bid to be rejected.
Unbalanced prices shall be interpreted to mean that the unit price for any item is such that it is unreasonable for the particular item when considered by itself and not considered in connection with the bid submitted on any other item or items.
The Town shall have the right to accept Alternates in any order or combination, unless otherwise specifically provided in the Bidding Documents, and to determine the low bidder on the basis of the sum of the Total Base Bid and Alternates accepted.
18. Laws and Regulations The bidder's attention is directed to the fact that all applicable federal and state laws, municipal ordinances, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout, and they will be deemed to be included in the contract the same as though herein written out in full.
19. Sales Tax Under the terms of the regulations referring to CONTRACTORS and SUBCONTRACTORS issued by the State Tax Commission in administration of the State Sales and Use Tax, to which the bidder is referred, the contractor may purchase materials or supplies to be consumed in the performance of this contract without payment of tax and shall not include in his bid nor charge any use or sales tax thereon.
Any non-resident Contractor shall obtain and provide to the Town of Windsor a certificate from the Connecticut Commissioner of Revenue Services of compliance with Connecticut General Statutes Section 12-430(7) or the Town will be required to deduct five percent (5%) of all amounts payable to such non-resident Contractor and pay it over to the Commissioner of Revenue Services.
20. Insurance The Contractor shall provide all insurance documents as specified in Article 33 of the General Conditions, including insurance documents for all proposed Subcontractors, within the time specified above.
21. Rights-of-Way The Town shall provide, upon request, any information which is pertinent to and delineates and describes the land owned and rights-of-way acquired or to be acquired.
22. Limit of Construction The bidder is advised that the limit of construction lines shown on the plans have been established based on funding allocation and the Engineer's construction estimate. The bid
E2026-08 I-7 Information for Bidders will be based upon the limit lines established. However, the bidder is advised that the town may elect to extend or delete portions of the contract to maximize funding allocations.
23. Compliance with The Town of Windsor Code of Ethics No former town employee in administrative pay grade 3 or above and no former board of education employee in a cabinet level position or above shall work for a private firm who has a contract with the town any time within six months after terminating service with the town.
If this occurs, the vendor could be subject to penalties up to and including contract termination. (Chapter 2, Article IV, Section 11. Sec. 2-30.)
E2026-08 - 1 - Sample Agreement
SAMPLE - AGREEMENT
THIS AGREEMENT made the {DAY} day of {MONTH}, in the year Two Thousand {YEAR};
BY AND BETWEEN the TOWN OF WINDSOR, a municipal corporation in the County of
Hartford and State of Connecticut, hereinafter called the "Owner" and {CONTRACTOR}, hereinafter called the “Contractor”.
W I T N E S S E T H:
That the Owner and the Contractor, for the consideration hereinafter named agree as follows:
ARTICLE 1. CONTRACT DOCUMENTS
This Contract shall consist of and shall include this Agreement, "CONTRACT DOCUMENTS FOR
SHARSHON PARK SITE IMPROVEMENTS, WINDSOR, CT", Information for Bidders, Bid
Proposal, Drawings, Maps, Technical Specifications, Special Conditions, General Conditions, Addenda, Modifications (whether issued prior to or after opening of bids or execution of this
Agreement).
All of the foregoing underlined items are herein referred to as the "CONTRACT" for purpose of convenience. Wherever a particular document in said "CONTRACT" requires a signature, the execution of this Agreement shall constitute the execution or signature on said document.
The Contractor represents that it (he or she) is familiar with the "CONTRACT" and shall initial front page of the "CONTRACT" for which it (he or she) shall be responsible.
In addition to the "CONTRACT", Contractor agrees to all federal, state, and local laws, rules and regulations as they may be applicable.
E2026-08 - 2 - Sample Agreement
ARTICLE 2. SCOPE OF WORK
The Contractor shall furnish all of the labor, materials, supplies, tools, equipment and other facilities and things necessary or proper for and incidental to, and perform all of the work for the construction of improvements as more fully described in the "CONTRACT." The Contractor has informed himself fully in regard to all conditions pertaining to the place where the work is to be done and other circumstances affecting the work.
ARTICLE 3. RESPONSIBILITY
The Contractor shall be responsible for the care and protection of all materials and equipment at the job site and shall be responsible for any loss from whatever cause. The Contractor shall be responsible for and agrees to hold harmless the Town of Windsor from any claims made as a result of unstable conditions created by the method used in excavation. For the scope of indemnification and for a more specific description of the responsibility of the Contractor and the Town, reference is made to Article 25 Indemnification found in the General Conditions of the document
"CONTRACT DOCUMENTS FOR SHARSHON PARK SITE IMPROVEMENTS, WINDSOR, CT”,
Exhibit A.
Appropriate insurance coverage as specified in said Exhibit A shall be provided at the time of execution to secure the Contractor's obligations herein specified.
ARTICLE 4. TIME OF COMMENCEMENT
The Contractor will commence work within ten (10) days after the date specified in the Notice to
Proceed from the Town Engineer notifying him to commence work and agrees to faithfully complete the project within Ninety (90) consecutive calendar days of the date of the Notice to
Proceed.
E2026-08 - 3 - Sample Agreement
ARTICLE 5. CONTRACT SUM
The Owner shall pay the Contractor for the performance of the "CONTRACT", subject to the additions and deductions provided in the "CONTRACT" in current funds not to exceed the sum of
{ZERO} Dollars and {ZERO} Cents ({$0,000.00}). All payments shall be made in accordance with the provisions of the "CONTRACT". The Contractor has obtained all the information he needs to enable him to estimate fully and fairly the costs of the work herein contemplated.
ARTICLE 6. MEDIATION
All claims, disputes or other matters in question between the parties to this Contract arising out of or relating to this Contract or breach thereof shall be submitted to non-binding mediation. On the written notice of either party to the other of the election to submit any dispute under this Contract to mediation, each party shall designate its representative and shall meet at the Windsor Town
Hall within ten (10) days after the service of notice. The parties themselves shall then attempt to resolve the dispute within ten (10) days of meeting.
Should the parties themselves be unable to agree on a resolution of this dispute, then the parties shall appoint a third party, who shall be a competent and impartial party and who shall be acceptable to each party, to mediate the dispute. Each party shall pay the fees and expenses of the party mediator and such costs shall be borne equally by both parties. Upon agreement of the parties, either party may waive the first step in the mediation process and appoint a mutually acceptable mediator.
Any third-party mediator designated to serve in accordance with the provisions of the Contract shall be disinterested and shall be qualified to evaluate the performance of both parties.
This process shall be considered as a condition precedent to moving to court. During the mediation process, the Contractor shall continue the work.
E2026-08 - 4 - Sample Agreement
ARTICLE 7. COURT LITIGATION AND WAIVER OF JURY TRIAL
Notwithstanding the existence of any provision for arbitration of disputes in the Contract or any legislation providing for arbitration, any dispute arising under this Contract shall not be submitted to arbitration and the parties shall be left to their remedies at law. It is further expressly agreed that both parties waive and relinquish their right to a trial by jury of any dispute arising out of this
Contract. The intent of the parties is not to have a jury decide any aspect of any dispute which may arise under this Contract.
ARTICLE 8. EQUITABLE RELIEF
Nothing herein shall prevent either party from obtaining a court order enforcing the mediation process or such other temporary or equitable relief until such time that the dispute is settled or finally adjudicated.
ARTICLE 9. SUCCESSORS
This Agreement shall be binding upon the heirs, successors, and assigns of the parties. The
Contractor has no right to assign its obligations under this Agreement without written approval of the Owner.
E2026-08 - 5 - Sample Agreement
IN WITNESS WHEREOF, the parties hereto executed this Agreement, the day and year first above written.
Signed, Sealed and Delivered in the presence of:
_____________________________________ By ______________________________
_____________________________________ Peter Souza
Its Town Manager
_____________________________________ Duly Authorized
{CONTRACTOR}
_____________________________________ By ______________________________
_____________________________________ {NAME}
Its {TITLE}
_____________________________________ Duly Authorized
E2026-08 - 6 - Sample Agreement
STATE OF CONNECTICUT)
: ss. Windsor
COUNTY OF HARTFORD)
Personally appeared PETER SOUZA, Town Manager of the TOWN OF WINDSOR, hereunto duly authorized Signer and Sealer of the foregoing instrument and acknowledged the same to be his free act and deed and the free act and deed of said TOWN OF WINDSOR, before me.
In Witness Whereof, I hereunto set my hand and seal.
Notary Public
My Commission Expires:
STATE OF )
: ss. ___________________________
COUNTY OF )
Personally appeared ___________ , and acknowledged the same to be his free act and deed as such _______________________________, and the free act and deed of said corporation before me.
In Witness Whereof, I hereunto set my hand and seal.
Notary Public
My Commission Expires:
E2026-08 SC-i Special Conditions
SPECIAL CONDITIONS
Table of Contents
NO. TITLE PAGE
1. INSPECTION 1
2. LABOR STANDARDS/WAGE RATES 1
3. PERMITS 1
4. PROTECTION AND COORDINATION OF UTILITIES 1
5. PUBLIC UTILITY PLANS AND UTILITY SPECIFICATIONS 2
6. EMERGENCY VEHICLE ACCESS 2
7. SAFETY SIGNS AND TRAFFIC CONTROL 3
8. DAILY CLEANUP 3
9. DUST CONTROL 3
10. SIGNS 4
11. SURVEYS 4
12. VERIFICATION OF PLAN DIMENSIONS AND FIELD MEASUREMENTS 4
13. METRIC UNITS 5
14. MATERIALS TESTING 5
15. REPORTS, RECORDS, AND DATA 5
16. RIGHT TO ELIMINATE WORK 5
17. CONDITIONS OF THE SITE AND CONSTRAINTS 5
18. SANITARY PROVISIONS 6
19. USE OF RECLAIMED MATERIALS 6
20. SUBMITTALS FOR IMPORTED AGGREGATES 6
21. PROJECT SCHEDULE AND EXECUTION 6
22. SUBMISSIONS REQUIRED AFTER BID OPENING 6
E2026-08 SC-1 Special Conditions
SPECIAL CONDITIONS
1. Inspection Authorized representatives and agents of the Town of Windsor shall have access and be permitted to inspect all work, materials, payrolls, contract records, invoices of materials and other relevant data in the development and progress of the project.
2. Labor Standards/Wage Rates State prevailing occupational wage rates and labor standards in accordance with the Connecticut Department of Labor (CT DOL) Wage and Workplace Standards SHALL apply.
3. Permits
The Town has secured an IWWC permit for the proposed work. The contractor will be provided with a copy of the approved permit. The Contractor shall review the permit information and follow all provisions of the permit.
The Town is in the process of securing a CT DEEP General Permit for Construction. The
Contractor shall review the permit information and follow all provisions of the permit and the Stormwater Pollution Control Plan.
Permits required by the Town or other agencies shall be the sole responsibility of the
Contractor unless provided for under this contract. All permits normally issued by the Town of Windsor Engineering Department will be required for the contract. The Town portion of any applicable fees will be waived.
4. Protection and Coordination of Utilities Existing utilities shall be maintained during construction except as specifically stated herein and/or noted on the plans and as coordinated with the utilities. The Contractor shall verify the location of underground, structure mounted and overhead utilities. Construction work within the vicinity of utilities shall be performed in accordance with current safety regulations.
The Contractor shall notify "Call Before You Dig", dial 811 or go to CBYD.com for the location of public utility, in accordance with Section 16-345 of the Regulations of the Department of Utility Control.
Representatives of the various utility companies shall be provided access to the work, by the
Contractor.
Contractors are cautioned that it is their responsibility to verify locations, conditions, and field dimensions of all existing features, as actual conditions may differ from the information shown on the plans or contained elsewhere in the specifications.
E2026-08 SC-2 Special Conditions
The Contractor shall notify the Engineer prior to the start of work and shall be responsible for all coordination with the Engineer. The Contractor shall allow the Engineer complete access to the work.
The Contractor shall be liable for all damages or claims received or sustained by any persons, corporations or property in consequence of damage to the existing utilities, their appurtenances, or other facilities caused directly or indirectly by the operations of the Contractor.
Any damage to any existing private and public utility, as a result of the Contractors operations, shall be repaired to the utility’s and Engineer's satisfaction at no cost to the Town or the Utilities, including all materials, labor, etc., required to complete the repairs.
The Contractor's attention is directed to the requirements of CT DOT Form 819 Section 1.07.13
– "Contractor’s Responsibility for Adjacent Property, Facilities and Services".
Prior to opening an excavation, effort shall be made by the Contractor to determine whether underground installations, i.e., water, sanitary, gas, electric ducts, communication ducts, etc., will be encountered and, if so, where such underground installations are located. When the excavation approaches the estimated location of such an installation, the exact location shall be determined by the Contractor through careful probing or hand digging, and when it is uncovered, proper supports shall be provided by the Contractor for the existing installation.
Utility companies shall be contacted and advised of proposed work prior to the start of actual excavation, as noted above.
The Contractor shall notify appropriate utility companies two weeks in advance of the required valve box, handholes, or other utility box adjustments as shown on the plans. The Contractor will be responsible for making these adjustments, unless directed otherwise by the Engineer.
5. Public Utility Plans and Utility Specifications It is the Contractor’s responsibility to coordinate all utility relocations and there will be no reimbursement for any delays caused by utility relocations. The contractor’s stage construction must accommodate the required utility relocations.
The contractor is hereby notified that all utility specifications contained elsewhere herein shall be made a part of this contract, and that the contractor shall be bound to comply with all requirements of such specifications. The requirements and conditions set forth in the subject specifications shall be binding on the contractor just as any other specification would be.
6. Emergency Vehicle Access The Contractor is hereby notified that emergency vehicle access through the project during construction shall be maintained at all times and shall be considered a priority in terms of
E2026-08 SC-3 Special Conditions public safety. The Town will not consider delay or other claims associated with temporary work stoppage due to emergency responses.
Contact information for the Windsor Volunteer Fire Department and Police Department shall be:
Windsor Volunteer Fire Department Chief William Lewis 275 Broad Street Windsor, CT 06095 Phone: 860-285-1983 Emergency Calls: 911
Windsor Police Department Chief Don Melanson 110 Addison Road Windsor, CT 06095 Phone: 860-688-5273 Emergency Calls: 911
7. Safety Signs and Traffic Control The Contractor shall furnish all warning signs, barricades, detour signs, including appropriate illumination, to ensure the safety of local traffic, cyclists, pedestrians, workmen, or any person in the vicinity of the construction area and establish such warning and traffic signs as directed. All signs shall be in accordance with the Manual on Uniform Traffic Control Devices for Streets and Highways, as published by the U.S. Department of Transportation, Federal Highway Administration, latest issue.
8. Daily Cleanup Before the completion of each day's work, the Contractor shall be responsible for cleaning up and removing or relocating all excavated material, debris, equipment and the like and for temporarily backfilling or filling excavations as necessary to ensure the continuous flow of traffic in roadways where work is progressing, including access to private property during non-working hours.
9. Dust Control The Contractor is responsible for controlling air pollution at all times during work of this contract, 24 hours a day, 7 days per week, including non-working hours, weekends and holidays.
The Contractor shall comply with all State and Federal regulations pertaining to dust control.
Particular attention shall be made to the Regulations of Connecticut State Agencies Section 22a-174-18a,b "Control of Particulate Emissions."
E2026-08 SC-4 Special Conditions
The Contractor shall submit a dust control plan to the Engineer within 30 days after the Award of the Contract. The dust control plan shall include contact information for the responsible individual(s) from the contractor (24-hour availability) who have authority to implement necessary controls. The plan should detail dust control procedures for anticipated activities that may typically generate dust (ex. Jack hammering, saw-cutting pavement, haul roads, material storage sites, etc.)
10. Signs Any signs disturbed or removed by the Contractor, whether shown on the plans or not, shall be reset or replaced at the Contractor's expense as directed by the Engineer. Any traffic control devices damaged due to negligence shall be replaced by the contractor at his expense.
11. Surveys The Contractor will furnish all lines, grades and measurements in laying out the work. Such stakes or marks as the Contractor may set shall be preserved by the Contractor. If such stakes are moved or destroyed by any party, they shall be replaced by the Contractor at the Contractor’s expense.
If any existing Windsor Highway bounds, CT Department of Transportation bounds, or any other public or private property bounds are disturbed during construction, they will be carefully and exactly replaced under the supervision of the Engineer. This work shall be at the expense of the Contractor.
12. Verification of Plan Dimensions and Field Measurements The Contractor is responsible for verifying all dimensions before any work is begun.
Dimensions of the existing structures shown on the plans are for general reference only; they are not guaranteed. The Contractor shall take all field measurements necessary to assure proper fit of the finished work and shall assume full responsibility for their accuracy. When shop drawings and/or working drawings based on field measurements are submitted for approval and/or review, the field measurements shall also be submitted for reference by the reviewer.
In the field, the Contractor shall examine and verify all existing and given conditions and dimensions with those shown on the plans. If field conditions and dimensions differ from those shown on the plans, the Contractor shall use the field conditions and dimensions and make the appropriate changes to those shown on the plans as approved by the Engineer. All field conditions and dimensions shall be so noted on the as-built drawings submitted for approval.
There shall be no claim made against the Town by the Contractor for work pertaining to modifications required by any difference between actual field conditions and those shown by the details and dimensions on the contract plans. The Contractor will be paid at the unit price bid for the actual quantities of materials used or for the work performed, as indicated by the various items in the contract.
E2026-08 SC-5 Special Conditions
13. Metric Units The Contractor is hereby notified that a number of the CT State standard details list English units and the equivalent metric units in parentheses. It should be noted that this is an English unit project and any references to metric units should be disregarded.
14. Materials Testing All testing of products and materials utilized on this project shall be in conformance with the Connecticut Department of Transportation Standard Specifications for Roads, Bridges, Facilities, and Incidental Construction, Form 819 and the project’s supplemental specifications.
15. Reports, Records, and Data The Contractor and each of his subcontractors shall submit to the Town, schedules of quantities and costs, progress schedules, payroll reports, estimates, records and other data as the Town may request concerning the work performed or to be performed under this contract.
16. Right to Eliminate Work The Town of Windsor reserves the right to eliminate from the Contract any of the items of work. This includes limiting the scope of work, in the event it deems it to be in the best interest of the Town.
17. Conditions of the Site and Constraints The Contractor shall furnish all warning signs, barricades, and other temporary traffic control devices to ensure the safety of local traffic, bicyclists, pedestrians, and transit users in the vicinity of the construction area. The work site will be maintained in an orderly manner and protected to ensure that no possibility exists where people may wander onto the construction site, fall into an open excavation or be injured due to the site conditions. If in the opinion of the Engineer or the Inspector, the site is not protected against such possibilities, the Contractor may be directed to provide temporary fencing or other protective measures to ensure the safety of the work area. Any such measures so ordered will be at the expense of the Contractor. No additional compensation will be granted.
Required precautions shall be taken concerning noise, clean up, safety, security, etc.
All excavation, trench cuts or other temporary disturbances of the travel surface shall be filled, leveled, and compacted in order to maintain vehicle passage. Gravel, stone, temporary bituminous, or other methods used to stabilize an area for safe passage will be the responsibility of the Contractor. If directed by the Engineer to make the parking area passable, the Contractor will immediately correct the deficiency at no additional cost to the Town.
The Contractor must submit to the Engineer for review and approval any areas he intends to use for staging and laydown. In addition to review and approval by the Engineer, potential
E2026-08 SC-6 Special Conditions sites to be obtained by the Contractor from private owners must be submitted to the Town of Windsor for approval. The Contractor must submit verification of approval to the Engineer prior to use.
18. Sanitary Provisions The Contractor shall provide and maintain in a neat and sanitary condition such accommodations for the use of his employees as may be necessary to comply with the requirements and regulations of the State Department of Health or of other bodies or tribunals having jurisdiction therewith.
19. Use of Reclaimed Materials Notwithstanding any language to the contrary in the Contract Documents, including the
Technical Specifications, Form 819, etc. the Contractor shall not use any reclaimed materials on this project from sources outside the project limits. This prohibition does not apply to any reclaimed product used to produce Superpave, subject to DOT specifications.
20. Submittals for Imported Aggregates In addition to the requirements of CT DOT Form 819, the Contractor is hereby notified of the requirement to provide product data submittals which include, but may not be limited to, test results on the gradation, abrasion and soundness of the aggregate materials proposed for use on this project. The tests must be current and based on a specific source location/pile. No material shall be imported until the Engineer issues a written approval.
21. Project Schedule and Execution The Contractor shall prepare and submit a construction schedule at the preconstruction meeting. The Town will review and approve the schedule before issuing a Notice to Proceed.
This sequencing shall include the following parameters:
Work hours are restricted to Monday through Friday between 7:00 AM and 3:30 PM unless otherwise approved and coordinated with the Engineer
The Contractor shall be responsible for coordinating the resetting of facilities with their respective utility company, which shall be incorporated into the overall project schedule.
Delay claims for resetting of utilities beyond the projected schedule will not be reviewed or accepted. It is the Contractor responsibility to ensure resetting of facilities and the overall project be completed within the allotted calendar days.
22. Submissions Required After Bid Opening After the Bid Opening, upon request of the Town, the low bidder shall submit the following documents within 5 business days of the Town’s request:
• Contractor’s Proposed Progress Chart
• List of proposed subcontractors
• List of references
E2026-08 SC-7 Special Conditions
• List of active projects as well as other projects the Contractor has committed to complete within the outlined Contract Duration
E2026-08 GC-1 General Conditions
GENERAL CONDITIONS
TABLE OF CONTENTS
No. Title Page
ARTICLE 1. DEFINITIONS 3
ARTICLE 2. PROGRESS AND SUBMISSION; PRECONSTRUCTION CONFERENCE; TIME
OF STARTING THE WORK 6
ARTICLE 3. CORRELATION, INTERPRETATION AND INTENT OF CONTRACT
DOCUMENTS 7
ARTICLE 4. COPIES OF DOCUMENTS AND RECORD DOCUMENTS 7
ARTICLE 5. SEPARATE CONTRACTS 8
ARTICLE 6. SUBCONTRACTS 8
ARTICLE 7. MATERIALS, EQUIPMENT AND LABOR; OR EQUAL CLAUSE 9
ARTICLE 8. PATENT FEES AND ROYALTIES 9
ARTICLE 9. PERMITS, LAWS AND REGULATIONS 9
ARTICLE 10. AVAILABILITY OF LANDS; PHYSICAL AND SUBSURFACE CONDITIONS 10
ARTICLE 11. PROJECT MANAGER'S CONTROL 10
ARTICLE 12. AUTHORITY AND DUTIES OF INSPECTORS 10
ARTICLE 13. TESTS AND INSPECTIONS 11
ARTICLE 14. SHOP DRAWINGS AND SAMPLES 11
ARTICLE 15. CONTRACTOR'S SUPERVISION AND SUPERINTENDENCE 12
ARTICLE 16. SAFETY AND PROTECTION; EMERGENCIES 13
ARTICLE 17. ACCESS TO THE WORK; UNCOVERING FINISHED WORK 14
ARTICLE 18. CHANGE IN THE WORK 14
ARTICLE 19. CHANGE ORDERS 15
ARTICLE 20. CHANGE OF THE CONTRACT TIME 15
ARTICLE 21. WARRANTY AND GUARANTEE: CORRECTION, REMOVAL OR
ACCEPTANCE OF DEFECTIVE WORK 16
ARTICLE 22. APPLICATIONS FOR PROGRESS PAYMENTS 17
E2026-08 GC-2 General Conditions
ARTICLE 23. CERTIFICATES OF COMPLETION AND FINAL PAYMENT 18
ARTICLE 24. WAIVERS OF CLAIMS AND CONTINUING OBLIGATIONS 19
ARTICLE 25. INDEMNIFICATION 19
ARTICLE 26. CLEANING UP 20
ARTICLE 27. TOWN'S RIGHT TO STOP OR SUSPEND 20
ARTICLE 28. TOWN'S RIGHT TO TERMINATE 20
ARTICLE 29. CONTRACTOR'S RIGHT TO STOP WORK OR TERMINATE 21
ARTICLE 30. CONTRACT SURETY 22
ARTICLE 31. TIME FOR COMPLETION AND LIQUIDATED DAMAGES 22
ARTICLE 32. NO DAMAGE FOR DELAY 23
ARTICLE 33. CONTRACTOR'S AND SUBCONTRACTOR'S INSURANCE 23
ARTICLE 34. WAGE RATES 25
ARTICLE 35. REMOVAL OF ROCK 25
ARTICLE 36. ASSIGNMENT OF CAUSES OF ACTION 25
ARTICLE 37. SANITARY PROVISIONS 25
ARTICLE 38. PROVISIONS REQUIRED BY LAW DEEMED INSERTED 26
ARTICLE 39. COMPLIANCE WITH EXECUTIVE ORDER NO. THREE 26
ARTICLE 40. COMPLIANCE WITH EXECUTIVE ORDER NO. SEVENTEEN 26
ARTICLE 41. COMPLIANCE WITH EXECUTIVE ORDER NO. SIXTEEN 26
ARTICLE 42. ENFORCEMENT OF PAYMENT TO GENERAL CONTRACTOR TO
SUBCONTRACTOR AND BY SUBCONTRACTOR TO HIS
SUBCONTRACTORS 27
ARTICLE 43. LABOR PROVISIONS IN CONSTRUCTION CONTRACTS 27
ARTICLE 44. RESIDENTS’ PREFERENCE IN WORK ON OTHER PUBLIC FACILITIES 27
ARTICLE 45. NON-RESIDENT CONTRACTOR 27
ARTICLE 46. COMPLIANCE WITH THE TOWN OF WINDSOR CODE OF ETHICS 27
E2026-08 GC-3 General Conditions
GENERAL CONDITIONS
ARTICLE 1. Definitions
Whenever used in these General Conditions or in the other Contract Documents, the following terms shall have the meanings which shall be applicable to both the singular and plural thereof:
Agreement The written agreement between the Town of Windsor and the Contractor covering the work to be performed, including the Contractor's bid and the bonds. The written agreement is intended to be the complete and exclusive agreement between the above parties covering the work to be performed, including the Contractor's bid and the bonds.
Architect Whenever in the Contract Documents the word "Architect" is used it shall be understood as referring to the Architect designated by the Town Manager as the primary contact related to building design and specifications.
A.A.S.H.T.O.
American Association of State Highway and Transportation Officials.
Bid The offer or proposal of the Bidder submitted on the prescribed form setting forth the price for the Work to be performed.
Bidder Any person, firm or corporation submitting a Bid for the Work.
Bonds Bid, performance and payment bonds and other instruments of security, furnished by the Contractor and his surety in accordance with the Contract Documents.
Change Order A written order to the Contractor signed by the Town Manager authorizing an addition, deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Time issued after execution of the Agreement.
Commission on Human Rights and Opportunities (CHRO) The State of Connecticut’s Commission on Human Rights and Opportunities, statutory authorization under C.G.S. Chapter 814c.
Contract Documents
E2026-08 GC-4 General Conditions
The Agreement, Invitation to Bid, Information for Bidders, Bid Sheet, Specifications, Drawings, Maps, Technical Specifications, Special Conditions, General Conditions, Addenda (whether issued prior to opening of Bids or execution of the Agreement) and Modifications.
Contract Price The total monies payable to the Contractor under the Contract Documents.
Contract Time The numbers of days or the dates stated in the Agreement to complete the Work so that it is ready for final payment as evidenced by Town Manager or his designee’s written recommendation of final payment.
Contractor The person, firm or corporation with whom the Town of Windsor has executed the Agreement.
Drawings The drawings and plans which show the character and scope of the Work to be performed and which have been prepared or approved by the Architect or Engineer and are referred to in the Contract Documents.
Engineer Whenever in the Contract Documents the word "Engineer" is used it shall be understood as referring to the Town Engineer of the Town of Windsor or an Engineer as designated by the Town Manager.
Form 819 Shall refer to the State of Connecticut Department of Transportation Standard Specifications for Roads, Bridges, Facilities, and Incidental Construction Form 819 dated 2024 and any and all approved changes to the Form.
Gender identity or expression A person’s gender-related identity, appearance or behavior, whether or not that gender-related identity, appearance or behavior is different from that traditionally associated with the person’s physiology or assigned sex at birth, which gender-related identity can be shown by providing evidence including, but not limited to, medical history, care or treatment of the gender-related identity, consistent and uniform assertion of the gender-related identity or any other evidence that the gender-related identity is sincerely held, part of a person’s core identity or not being asserted for an improper purpose.
Good faith That degree of diligence which a reasonable person would exercise in the performance of legal duties and obligations;
Good faith efforts
E2026-08 GC-5 General Conditions
“Good faith efforts” shall include, but not be limited to, those reasonable initial efforts necessary to comply with statutory or regulatory requirements and additional or substituted efforts when it is determined that such initial efforts will not be sufficient to comply with such requirements.
Inspector The authorized representative of the Town of Windsor who is assigned to the Project or any parts thereof.
Intellectual disability A significant limitation in intellectual functioning and deficits in adaptive behavior that originated during the developmental period before eighteen years of age;
Liens Liens, charges, security interests or encumbrances upon real property or personal property.
Marital status Being single, married as recognized by the State of Connecticut, widowed, separated or divorced.
Mental disability One or more mental disorders, as defined in the most recent edition of the American Psychiatric Association’s “Diagnostic and Statistical Manual of Mental Disorders”, or a record of or regarding a person as having one or more such disorders.
M.D.C. Specifications Shall refer to the Bureau of Public Works of the Metropolitan District of Hartford, Connecticut specifications for the construction of sewers and drains and similar structures reprinted December 1, 1963, and the sewer standards plans printed July, 1972 and any revisions or supplements thereto.
Minority business enterprise Any small contractor or supplier of materials fifty-one percent or more of the capital stock, if any, or assets of which is owned by a person or persons: (1) who are active in the daily affairs of the enterprise, (2) who have the power to direct the management and policies of the enterprise, and (3) who are members of a minority, as such term is defined in subsection (a) of Connecticut General Statutes section 32-9n.
Minority Minority groups are defined in Section 32-9n of the Connecticut General Statutes as (1) Black Americans,
(2) Hispanic Americans, (3) persons who have origins in the Iberian Peninsula, (4) Women, (5) Asian Pacific Americans and Pacific Islanders (6) American Indians.
Modification
(a) A written amendment of the Contract Document signed by both parties, (b) a Change Order, (c) a written clarification or interpretation issued by the Architect or Engineer or (d) a written order for a minor change or alteration in the work issued by the Architect or Engineer. A modification may only be issued after execution of the Agreement.
Project
E2026-08 GC-6 General Conditions
The entire construction to be performed as provided in the Contract Documents.
Project Manager The licensed Architect or licensed Engineer designated by the Town Manager as the primary contact for all project correspondence.
Shop Drawings All drawings, diagrams,…