E01.02 W913E522C0002_RELEASED.pdf
PDF 863 KB Posted
- Attached to
- Transcend Engineering BAA Proposal 20-C020 Federal contract opportunity
- Solicitation number
- W912HZ20BAA01
About this file
This document outlines a federal contract awarded to Transcend Engineering and Technology, LLC. The contract was awarded on November 30, 2021 for $500,000 by the Department of the Army Corps of Engineers to support research titled "Processing Data from Subsurface Sensing Infrastructure in the Arctic." Key details include the 18-month period of performance for the base award, deliverables due on a monthly, quarterly, and semi-annual basis, and requirements for progress reports, invoices, training certificates, review meetings, and technical briefings over the course of the work.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until local time
X
A X B X C
D
EX
X G F
H
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
30-Nov-2021
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
MELODIE Y FISHER
1 30
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
STEPHEN P. FARRINGTON, PE / PRINCIPAL
INVESTIGATOR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE
(802) 431-3456
15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
TRANSCEND ENGINEERING AND TECHNOLOGY, LL
TRANSCEND ENGINEERING
STEPHEN P. FARRINGTON, PE
768 S MAIN ST UNIT 2
BETHEL VT 05032-4472
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
W913E522C0002
W913E5 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT
PACKAGING AND MARKING
3 - 17 J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 20 - 23
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
Net 30 Days
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
5PFQ0 FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
melodie.y.fisher@usace.army.mil
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: 601-634-4687 (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
$500,000.00 See Schedule
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE W916TX
PR W1J5 USACE FIN CTR
5722 INTEGRITY DRIVE
BUILDING 787
MILLINGTON TN 38054-5005
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
24 - 30
PART II - CONTRACT CLAUSES
ERDC CONTRACTING OFFICE
HANOVER OFFICE
72 LYME ROAD
HANOVER NH 03755-1290 (217) 373-7297
(217) 373-6773FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.
W81EWF11347702
5. DATE ISSUED4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. SOLICITATION NO.
See Item 7
W913E522C0002
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job $500,000.00 $500,000.00 R&D Services
FFP
BAA Proposal 20-C020 titled, "Processing Data from Subsurface Sensing Infrastructure in the Arctic" FOB: Destination
PURCHASE REQUEST NUMBER: W81EWF11347702
PSC CD: AJ12
NET AMT $500,000.00
ACRN AA
CIN: W81EWF113477020001
$500,000.00
Section C - Descriptions and Specifications
PERFORMANCE WORK STATEMENT
C.1. INTRODUCTION: This contract is the result of a successful proposal received under the ERDC Broad Agency Announcement W912HZ-20-BAA-01 addressing the CRREL-1 Signature Physics Technical Area. The proposal (BAA-20-C020) is entitled “Processing Data from Subsurface Sensing Infrastructure in the Arctic” and was submitted by Transcend Engineering and Technology, LLC.
C.1.a. Scope of Contract Work. The overarching goal of this research effort is to recommend artificial intelligence (AI) and machine learning (ML) approaches and non-conventional signal processing techniques for acoustic/seismic source detection, classification, and tracking. Specifically, the proposed work will deliver recommendations for using AI or ML for automatic detection, classification, localization, and tracking tools for a Government provided dataset.
C.2. CONTRACTOR’S TECHNICAL PROPOSAL: The Contractor’s technical proposal referenced in Paragraph C.1 Introduction is incorporated herein by reference and made a part thereof. In the event of any discrepancies between the Contractor’s proposal and this Performance Work Statement, this Performance Work Statement shall govern.
C.3. PROPOSAL REVISIONS: See Paragraph C.5. “Government Furnished Support,” Paragraph C.8. “Schedule”, Paragraph C.9. “Meetings and Reviews”, Paragraph C.10. “Reports and Deliverables,” and Paragraph C.11 “Performance Requirements Summary”.
C.4. NON-PERSONAL SERVICES: The Government and the Contractor hereby understand and agree that the services to be delivered under this contract by the Contractor to the Government are non-personal services, and the parties recognize and agree that no employer-employee or master-servant relationships exist or will exist under this contract between the Government and the Contractor's employees.
C.5. GOVERNMENT-FURNISHED SUPPORT:
C.5.a. Government Laptops or IT: not required
C.5.b. CAC Cards: not required
C.5.c. Access to ERDC IT Systems: not required
C.5.d. Access to Government Installations: not required
C.5.e. Access to Government Information: CRREL will provide Transcend with an appropriately sanitized DAS dataset suitable to successfully accomplish the proposed work. CRREL may provide distribution limitations regarding use of the dataset and derivative products. CRREL will explain necessary aspects of the experimental design and findings. This initial dataset will not be from the Arctic, but will be sufficient for Transcend to execute this proposed scope of work leading to outcomes that will further CRREL’s research into the feasibility of employing a DAS system for airborne threat identification in the Arctic while advancing CRREL’s use of Artificial Intelligence (AI) and Machine Learning (ML). CRREL may share additional DAS datasets if an Arctic dataset becomes available. CRREL requires that all people working on this contract are citizens of Five Eyes Nations (US, UK, Canada, Australia, and New Zealand). Datasets provided to Transcend may be Unclassified // Five Eyes. Transcend may also be included in Unclassified // Five Eyes conversations with CRREL regarding operational applications of this work. As such, an OPSEC Plan shall be developed and updated as needed throughout this project (see Paragraph C.13).
C.5.f. Access to Federal or DOD Facilities / Lands: not required
C.6. CONTRACTING OFFICER'S REPRESENTATIVE (COR): The identification of duties and limitations of the COR are specified in the COR appointment letter, which will be provided to the contractor at or shortly after the time of award. No Government personnel, other than the Contracting Officer, shall have the authority to do other than clarify technical points or supply relevant information to the Contractor regarding this contract. Specifically, no requirement in these specifications may be altered through verbal clarification. Only a warranted Contracting Officer, acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer. The offeror is reminded that if this project coordinates with other governmental organizations or stakeholders regarding this contract, then the COR and TPOC should be made aware of such meetings. CRREL’s TPOC and COR may wish to participate. The offeror is also reminded that only CRREL’s Contracting Officer has the authority to modify the scope, schedule, deliverables, etc. of this contract.
Contracting Officer’s Representative (COR) Role
Sarah Kopczynski 603-646-4761 Sarah.E.Kopczynski@usace.army.mil
COR
C.7. TECHNICAL POINT OF CONTACT (TPOC): TPOCs offer technical backgrounds as subject matter experts (SMEs) in areas relevant to the contract. TPOCs provide value added technical feedback to the vendor and contractor performance feedback to the COR. TPOCs may coordinate with the contractor to consult, support execution, assist with access to necessary government data, hardware, or supplies, review monthly progress reports, review deliverables, and act as the government sponsor where engagement with other government entities is required (e.g., site access, product transition). The TPOC shall allocate necessary time and attention to this contract to fulfill all product review and acceptance responsibilities in a reasonable timeframe as determined by the COR (refer to Paragraph C.10). Recurring failures to execute TPOC responsibilities shall require the COR to inform the TPOC’s First and/or Second Level Supervisors as well as the KO. TPOCs shall always include the COR on correspondences, telecons, and communications with the contractor so the COR can document exchanges.
Likewise, the vendor shall always include the COR on correspondences, telecons, and communications with all government employees regarding this contract. Other TPOCs may engage as work evolves and will be formally introduced to the contractor by the COR and Lead TPOC. The offeror is reminded that if this project coordinates with other governmental organizations or stakeholders regarding this contract, then the COR and TPOC should be made aware of such meetings. CRREL’s TPOC and COR may wish to participate. The offeror is also reminded that only CRREL’s Contracting Officer has the authority to modify the scope, schedule, deliverables, etc. of this contract.
Technical Points of Contact (TPOCs) Role
Sergey N. Vecherin Sergey.N.Vecherin@erdc.dren.mil US Army ERDC-CRREL 72 Lyme Road, Hanover, NH 03755
(603) 646-4110 Desk
Lead TPOC
C.8 SCHEDULE AND TASKS. This contract includes a base award of 18 months with 5 tasks.
C.9. MEETINGS AND REVIEWS: The Contractor shall support the meetings listed below in the table. Section C.11 provides the Performance Requirements Summary (PRS) which lists the standards and expectations for meetings. Other adhoc meetings may be arranged as needed by either the contractor or the government to facilitate successful contractual performance. Meetings listed under this contract may be waived or rescheduled upon mutual agreement by the government and contractor; such changes will be recorded via an email including the COR, TPOCs, and Contractor PI.
Meeting Timeline Contract Kick Off Meeting Within 2 weeks of Contract Award Quarterly Meetings Once per quarter Final Contract Close-out Meeting No later than 1 week prior to end of POP
C.10. REPORTS AND DELIVERABLES: In addition to the deliverables listed in the Offeror’s proposal, the Contractor shall submit the following to the COR. A detailed description of each deliverable and associated performance standard is provided in Paragraph C.11.
Deliverable
ID
Description Task Due
A001 Contract Kick-off Meeting Brief 1 Within 2 weeks of award
A002 Progress Reports and Invoices 1 Monthly A003 Training Certificates 1 IAW Para 13 A004 Quarterly Review Meetings 1 Quarterly A005 Interim Progress Review (IPR) Briefs 1 Semi-Annually A006 Data Transfer Meeting with CRREL 2 Month 2 A007 Technical Briefing and Digital Products
Related to Signal Decomposition 2 Month 12
A008 Technical Briefing and Digital Products Related to ML Methods
4 Month 14
A009 Draft Final Report and Bundled Products 5 Month 15 A010 Final Report 5 NLT 2 weeks prior to
POP end A011 Final Contract Close-out Meeting 5 NLT 1 week before
POP end A012 DD Form 882 Patents – Reporting of Subject
Inventions 1 Per Contract Standard
Clause 252.227-7039
C.10.a. Technical Material Review and Release Process. Written material, presentations, abstracts, etc.
generated under this contract must be reviewed by CRREL prior to public release (i.e., public release includes sending drafts to a journal for review). Material generated under this contract submitted for publication or other public release after contract POP closes must also be reviewed by CRREL to ensure no OPSEC (Operational Security) concerns exist before public release. The following outlines the review process:
1. Contractor Submits Draft-Final Product: The Contractor submits material to CRREL for review via email (or other electronic means if files are too large)
2. CRREL Review: CRREL provides both Technical feedback and Security feedback.
a. Security feedback is provided via an official form signed by the COR and CRREL Security Office assigning a Distribution Statement for the subject material. This statement must be added to the product by the contractor.
b. Required Technical feedback from the COR and TPOC will: verify that the product fulfills the contract requirements, and if necessary, outline any technical deficiencies which prevent the product from being accepted (e.g., errors, or quality, quantity, scope issues, etc.)
c. Optional Technical feedback may be offered by CRREL scientists and engineers as helpful technical suggestions provided for consideration (i.e., these changes are not necessary to accept the product per the contract standards)
d. COR Superseding Review: The TPOC shall allocate necessary time and attention to this contract to fulfill all product review and acceptance responsibilities in a reasonable timeframe as determined by the COR. Should the TPOC fail to provide the COR with product review feedback and/or product approval within a reasonable timeframe, the COR shall omit the TPOC from the subject product technical review and/or product acceptance. In this case, the COR shall independently provide a final official technical review and/or acceptance.
3. Contractor Revises & Submits Final Product: The contractor revises and re-submits the product if any required technical changes are needed to resolve deficiencies preventing acceptance. Otherwise, if no technical changes are required, the contractor only adds the Distribution Statement to the product as instructed and submits the final version for CRREL’s acceptance.
C.10.b. Distribution Statements. Products generated under this contract (reports, manuscripts, abstracts, presentations, data, code, prototypes, etc.) require Security review to determine if the content is suitable for public distribution or must be restricted. It is anticipated that most products from this research will be DISTRIBUTION-A (Approved for public release - distribution unlimited). However, some aspects of this work may be restricted for various security reasons (Distribution B, C, D, E, or F). Public release of material generated under this contact must first be cleared through CRREL. Distribution Statement guidance will be issued in written document signed by the COR and Security Officer after review of each product by the CRREL COR, Security Office, and TPOCs. Refer to Paragraph C.13 for additional details.
C.10.c. Government Support and Disclaimer Statements. Technical products may need to include the acknowledgment of necessary support and disclaimer statements (IAW Clause 252.235-7010), as appropriate per the guidance below:
1. Acknowledgment. The Contractor shall include an acknowledgment of the Government's support in the publication of any material based on or developed under this contract, stated in the following terms: This material is based upon work supported by the Broad Agency Announcement Program and the Cold Regions Research and Engineering Laboratory (ERDC-CRREL) under Contract No.W913E522C0002.
2. Disclaimers. All material, except scientific articles or papers published in scientific journals, must, in addition to any notices or disclaimers by the Contractor, also contain the following disclaimer: Any opinions, findings and conclusions or recommendations expressed in this material are those of the author(s) and do not necessarily reflect the views of the Broad Agency Announcement Program and ERDC-CRREL
C.10.d. State and Federal Regulations. The contractor is advised that for all work conducted under this contract in pursuit of deliverables, the contractor’s research plans must obtain all the necessary land access permits to allow sampling, ad adhere to all State and US Federal regulations governing public domain and private area observation, analysis, and data release.
C.10.e. Data and Information Management. The contractor is advised that their quality control plan or OPSEC Plan shall include statements, as needed, regarding inclusion of appropriate data security and any information privacy protocols relevant to the any cyberinfrastructure platforms and resiliency platform software. All monitoring data and software development, platforms, and code shall also include readme, metadata, instruction documentation as appropriate. This applies as relevant to all products developed under this contract.
C.10.f. ERDC Contract Reports. Products generated under this contract become the property of the US Government. CRREL may choose to convert some contract products into ERDC Technical Report Publications to ensure longevity of and accessibility to the material.
C.11. PERFORMANCE REQUIREMENTS SUMMARY (PRS): The Government will track and monitor progress using a Quality Assurance Surveillance Plan (QASP) developed by the Government in conjunction with the below Performance Requirements Summary (PRS) and all content contained in the contractor’s proposal. The following list [A001, A002,…] comprises the PRS for the products under this contract with the standards outlined and surveillance processes for each deliverable. Threshold standards are the minimum acceptable standard that must be met. Objective standards are optional standard exceeding threshold which may be achievable within the available cost, schedule, and scope of the contract, assuming a higher risk approach by the vendor. Objective standards are optional / not required to meet contract requirements.
[A001] KICK-OFF: Contract Kick-off Meeting Brief. Standard: The contractor shall deliver and present a PowerPoint brief at the kickoff meeting. The purpose of this meeting is for the Government to review the contract and associated documentation with the Offeror, TPOCs, and any other personnel to ensure all parties understand the contract and the processes necessary to follow for proper execution of the contract IAW policies, procedures, and laws.
The meeting will be held via electronic means (telecon, webex, etc.) with representatives from the contractor’s office, government representatives, TPOCs, and other stakeholders as appropriate. It may be possible for members of the contractor’s office to attend CRREL in person if they desire, pending CRREL site access limitations.
This meeting should occur within 2 weeks of contract award, consistent with the delivery schedule established in Contract Performance Work Statement (PWS) Paragraph C.10. The COR will deliver a briefing on the contract, processes, and government’s performance expectations; the COR will open the floor to questions to ensure clear understanding by both the government and contractor on these matters. The Contractor will participate in the meeting and also present a PowerPoint overview of their project to include: team members with roles, technical approach, schedule – milestone – deliverable review covering the full contract POP, discussion of risks (schedule, cost, performance/product), and any other topics the contractor wishes to discuss. For the kickoff, the contractor is requested to present a list of all deliverables and meetings outlined in the contract baselined to calendar dates.
Delivery schedule is established in Paragraph C.10. When delivering a contract product, be sure that both the email subject line and the product minimally include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Attend the meeting, present on the topics as described in the standard above, deliver briefing materials as specified
Objective: COR notes that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection
Who: The COR will determine the final assessment of performance, with input from the others to include the TPOC(s) and other stakeholders as appropriate.
Incentive: Reschedule missed meeting at no additional cost to the government; invoices will not be paid until the Government’s kickoff meeting has taken place
Inspection: Inspection applies to all standards.
[A002] Progress Reports and Invoices. Standard: The contractor shall deliver by email to the COR and TPOCs progress reports describing contract work completed during the reporting period. The progress report shall be delivered between the 1st and the 10th calendar day following the reporting period and shall follow the format specified below (“Template for Progress Report”). Variances to stated delivery dates for invoices and progress reports may be approved by the COR upon request by the contractor; such agreements are concurred in writing via an email. The government may provide a word document version of this template upon request. The progress report shall be clearly organized and sufficiently convey descriptions of the progress completed.
The contractor shall also include a copy of the invoice for that reporting period with the progress report so the COR and TPOCs can review the invoice that the vendor intends to submit to the billing office for payment (see Official Billing Instructions in Section G and guidance under Paragraph 14).
Upon mutual concurrence of the TPOC, COR, and Contractor, the periodicity may be changed.
The below listed “Template for Progress Report” provides the framework of minimum required elements for a contractor’s progress report. The contractor is welcome to include additional material and/or to format of the report to align with styles preferred by their own organization, so long as the elements requested by the government remain included and easy to locate.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Error free and complete progress reports and invoices delivered on time and in accordance with (IAW) the standards described in this contract
Objective: COR observes evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance, with input from the others to include the TPOC(s) and other stakeholders as appropriate Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished at no additional cost to the government; invoices will not be paid unless progress reports and invoices are submitted IAW the contract
Inspection: Inspection applies to all standards.
------- Template for Progress Report (start) -------
PROGRESS REPORT
Contract Title: ________________________ Contract No. ________________________ Period Covered in this Report: day-month-yyyy to day-month-yyyy Progress Report Prepared By: Principle Investigator Name, Institution, Address, Email & Phone
RISK SUMMARY. The following are currently identified or anticipated risks that may impact project completion.
Schedule Risk Budget Risk
Technical / Product Risk Other Issues
OUTSTANDING ACTION ITEMS. The following actions items are still pending….
Example…We are still waiting for CRREL to confirm dates we can access the cold rooms for sensor testing in December
Example…We still waiting for feedback on the dates for the Q2 IPR.
CONTRACT DELIVERABLES STATUS. The table below lists the status of all contract deliverables.
Deliverable
ID
Description Month Due Status
A001 Contract Kick-off Meeting Brief
JUL 2020 Delivered JUL 2020
A002 Progress Reports and Invoices
OCT 2020 Late, Not yet delivered
A003 Observational Dataset DEC 2020 Delivered Dec 2020 A004 Technical Report APR 2021 Delivered Jan 2021 A005 Final Report JUL 2021
TASK UPDATE. The following discusses the status of each of the Tasks. Sufficient information is provided so the government can see measured progress and understand current or emerging problems.
Task 1. “Title of this Task.” The goal of this task is to _________. This task is approximately ___% technically completed. Provide your summary of progress here…
Task 2. “Title of this Task.” The goal of this task is to _________. This task is approximately ___% technically completed. Provide your summary of progress here…
OUT OF SCOPE WORK & PERSONAL SERVICES. Indicate whether any of the following occurred in this reporting period.
Yes or No. Have you conducted work, or are you planning work, that varies in any way from the scope outlined in your proposal or the government’s contract? If yes, please explain:
Yes or No. Did a government employee instruct you to perform work outside the scope of the current contract? If yes, please explain:
Yes or No. Did a government employee interfere with the management of your employees (e.g., ask you to hire or fire a particular employee, reassign or discipline an employee, grant or deny leave to an employee, change a contractor's personnel duty hours, or engage with a contractor in a manner suggestive of providing supervision or control)? If yes, please explain:
GOVERNMENT FURNISHED SUPPORT. In the space below please indicate a list of all Government Furnished Equipment, Property, Information or Data, and any persons on your team who have CAC cards issued to them through CRREL and need them for this contract. Please indicate n/a as appropriate.
Government Furnished Property: List item and bar code CAC Cards Status: List names, expiration, confirm the employees still employed
------- Template for Progress Report (end) -------
[A003] Training Certificates. Standard: The Contractor shall complete the training requested under Paragraph 13 and submit the necessary training documentation to the COR in accordance with the guidance provided under Paragraph 13.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Submit training certificates, absent errors or omissions, in accordance with the schedule and standards outlined in the contract Paragraph 13.
Objective: COR observes evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance by evaluation of material presented to the COR by the vendor.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished at no additional cost to the government Inspection: Inspection applies to all standards.
[A004] Quarterly Review Meetings. Standard: The contractor shall attend quarterly update meetings with the government to discuss technical progress. The meeting may be held via electronic means (telecon, WebEx, etc.)
with representatives from the contractor’s office, government representatives, TPOCs, and other stakeholders as appropriate. These meetings may be waived with concurrence of the government and the contractor; decisions to waive are recorded via emails which include the COR.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Attend meeting, discuss the topics and materials as specified
Objective: COR notes that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance, with input from the others to include the TPOC(s) and other stakeholders as appropriate.
Incentive: Reschedule missed meeting at no additional cost to the government; final invoice will not be paid until the meeting has taken place
[A005] Interim Progress Review (IPR) Briefs. Standard: The contractor shall present interim progress at one IPR per each 6 months during contract POP. The meeting will be scheduled jointly with the contractor and government to occur at an interim annual point when sufficient technical work has been accomplished and milestones met to be productive. This is meant to be an opportunity for azimuth checks and stakeholder review and feedback during the development process. The government may hold these meetings at CRREL or via electronic means (telecon, WebEx, etc.). These meetings may be waived with concurrence of the government and the contractor; decisions to waive are recorded via emails which include the COR.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Attend IPR and provide overview of project status. One IPR in year 1, a second IPR in year 2 (if applicable).
Objective: COR notes that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance, with input from the others to include the TPOC(s) and other stakeholders as appropriate.
Incentive: Reschedule missed meeting at no additional cost to the government; final invoice will not be
[A006] Data Transfer Meeting with CRREL. Standard: The contractor shall schedule a meeting with the CRRELTPOC and COR regarding this DAS work. The CRREL TPOC may include additional researchers studying DAS to support this meeting. The goal of this meeting will be to arrange transfer, as deemed appropriate by CRREL, elements of CRREL’s knowledge of their work to TE and for TE to ask initial questions of CRREL. TE will receive CRREL’s data at this meeting or before. This meeting will take place within the first two months of the project. The contractor shall take notes during the meeting to record the action items and products expected from CRREL, to include agreed delivery dates and any other pertinent details; these notes shall be emailed to all in attendance at this meeting (including the COR and TPOC).
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Satisfactory resolution of questions regarding contents, quantity, format, and delivery schedule for pertinent DAS data needed to support performance of technical investigatory aspects of the contract statement of work.
Objective: COR documents evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance with input from the TPOC(s) and other stakeholders.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished
[A007] Technical Briefing and Digital Products Related to Signal Decomposition. Standard: The contractor shall deliver organized code, data, and files produced or used by TE in execution of Task 3, and a technical briefing of the task outcomes and conclusions. As appropriate, a demonstration of findings is also requested.
Electronic copies of all final products (observational data sets, modeled data sets) along with metadata or appropriate documentation shall be made available to CRREL via a hard-drive or other electronic data exchange medium agreed by the TPOC.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Organized, error-free, and complete compilation of code, test data, and technical briefing delivered on time.
Objective: COR documents evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance with input from the TPOC(s) and other stakeholders.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished
[A008] Technical Briefing and Digital Products Related to ML Methods. Standard: The contractor will deliver organized code and files produced by TE in execution of Task 4, and a technical briefing of the task outcomes and conclusions. As appropriate, a demonstration of findings is also requested.
The outcomes of this product will deliver automatic detection, classification, localization, and tracking tool recommendations using AI or ML that can be tested at CRREL. A key part of assessing the usefulness of different ML techniques for this particular application is assessing accuracy of each approach. We will compare our estimates with ground truth and recommend ways to improve accuracy where possible. The vendor will show how they quantified the accuracy of their detection, tracking, and classifications via comparing their estimates with the known true data, and provide recommendations on how to improve the accuracy for the recommended approach.
Electronic copies of all products (observational data sets, modeled data sets) along with metadata or appropriate documentation shall be made available to CRREL via a hard-drive or other electronic data exchange medium agreed by the TPOC. This will enable the CRREL Signal Processing Team analyze Transcend's final products to test/verify the work completed by Transcend.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Organized, error-free, and complete compilation of code, test data, and technical briefing delivered on time.
Objective: COR documents evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance with input from the TPOC(s) and other stakeholders.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished
[A009] Draft Final Report and Bundled Products. Standard: The contractor shall deliver a Draft Final Technical Report to the COR and TPOC. The technical report shall holistically summarize all technical work conducted under this contract, to include the previously summarized material, Signal Decomposition Technical Briefing, the ML based DAS analysis methods Technical Briefing, and include a section outlining recommend next steps for DOD to enact an ML-based DAS analysis system. The report shall also discuss failures as well as research findings concluding that certain approaches or datasets will not work.
The report shall be prepared in the ERDC Technical Report format (a template will be provided by the COR). The “ERDC Technical Report Format” is only required for reports intended for CRREL (i.e., this format is not intended to influence journal manuscript formats which should align with the journal publication standards). Content shall minimally include the appropriate report headings and content as per the template provided and as appropriate.
Variances shall be agreed via email with the COR and TPOC.
The government will review and may provide feedback prior to accepting the deliverable. In addition to technical feedback CRREL will also review the product for Security / OPSEC issues in accordance with Paragraphs C.13 and C.10. CRREL TPOC, COR, and Security Office may request that some written material, datasets, and other products developed may be classified with limited distributions depending on content.
Final technical products shall be bundled and re-delivered along with this draft Final Report. This final bundling and re-delivery is requested because often minor but important refinements to interim digital technical products are made previous product delivery, thus the final version is requested prior to POP closure. Pending file sizes, delivery may need to be made via an external hard drive. In addition to the final report, final digital deliverables for this entire contract shall include: include the code used to arrive at conclusions and digital products that may have resulted from the code, such as the weights of a particular artificial neural network. These code files and digital products will provide details to those interested in the conclusions of our report. For clarity, creation of production level tools that can detect, classify, or track airborne threats is beyond the scope of this project as proposed. Rather, this project is the first step to developing those production level tools and intended to show that ML is a viable path forward for DAS-based monitoring of airborne threats.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Documentation, datasets, models, delivered error-free, omission free, on schedule, and addressing the requirements and intent of the product as outlined in the contract and proposal.
Objective: COR documents evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance with input from the TPOC(s) and other stakeholders.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished
[A010] Final Report. Standard: The contractor shall deliver the Final Technical Report to the COR and TPOC.
The contractor will develop this Final Draft by incorporating CRREL’s comments from the Draft Final Report review to issue a Final Report in which those comments are addressed.
The technical report shall holistically summarize all technical work conducted under this contract, to include the previously summarized material, Signal Decomposition Technical Briefing, the ML based DAS analysis methods Technical Briefing, and include a section outlining recommend next steps for DOD to enact an ML-based DAS analysis system. The report shall also discuss failures as well as research findings concluding that certain approaches or datasets will not work.
The report shall be prepared in the ERDC Technical Report format (a template will be provided by the COR). The “ERDC Technical Report Format” is only required for reports intended for CRREL (i.e., this format is not intended to influence journal manuscript formats which should align with the journal publication standards). Content shall minimally include the appropriate report headings and content as per the template provided and as appropriate.
Variances shall be agreed via email with the COR and TPOC.
The government will review and may provide feedback prior to accepting the deliverable. In addition to technical feedback CRREL will also review the product for Security / OPSEC issues in accordance with Paragraphs C.13 and
C.10. CRREL TPOC, COR, and Security Office may request that some written material, datasets, and other products developed may be classified with limited distributions depending on content.
Delivery schedule is established in Paragraph C.10. When delivering this contract product, be sure that both the email subject line and the product (as appropriate) include the Product Title, Contract Number, and Deliverable number (for example: Snow Report, W913E529C0005, A005).
Threshold: Documentation, datasets, models, delivered error-free, omission free, on schedule, and addressing the requirements and intent of the product as outlined in the contract and proposal.
Objective: COR documents evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance with input from the TPOC(s) and other stakeholders.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished
[A011] Final Contract Close-out Meeting. Standard: The contractor shall attend a final close out meeting with the government at the end of the contract before the POP end date. A technical demonstration of findings showing the examples evaluated with demonstrations supporting the reported conclusions shall be provided. The meeting may be held via electronic means (telecon, etc.). It may be possible for members of the contractor’s office to attend CRREL in person if they desire, pending site access limitations. The contractor and the government will review final deliverables, review the products developed, way ahead for future research, and discuss any other aspects of the contract as appropriate. Execution and delivery schedule are established in Contract PWS Paragraph C.10.
Threshold: Attend meeting, discuss the topics and materials as specified; satisfactory resolution of CRREL’s review comments in a complete and error-free report delivered on time
Objective: COR notes that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance, with input from the others to include the TPOC(s) and other stakeholders as appropriate.
Incentive: Reschedule missed meeting at no additional cost to the government; final invoice will not be
[A012] DD Form 882. Standard: The Contractor shall submit DD Form 882(s) in accordance with Section I, Clause No. 252.227-7039, and “Patents – Reporting of Subject Inventions”. Interim reports every twelve (12) months (or such longer period as may be specified by the Contracting Officer) from the date of the contract, listing subject inventions during that period and stating that all subject inventions have been disclosed or that there are no such inventions. If the period of service of this contract is not in excess of eighteen (18) months, an interim DD Form 882 is not required. A final report, within three (3) months after completion of the contracted work, listing all subject inventions or stating that there were no such inventions. The final invoice cannot be paid until the DD Form 882 has been submitted. Upon completion by the Contractor of the work to be performed under the contract, acceptance of such work by the Government, and receipt of DD Form 882 (reference Section I, Clause 252.227- 7039), the Government may pay the final invoice due for work performed.
Threshold: Comply with Patents – Reporting of Subject Inventions requirements
Objective: COR observes evidence that the Contractor has exceeded threshold requirements.
Surveillance & Inspection:
How: 100% inspection Who: The COR will determine the final assessment of performance by evaluation of material presented to the COR by the vendor.
Incentive: Rework/replacement required due to negligent mistakes or omissions will be accomplished
C.12. VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS: In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222- 38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S.
Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran employment information at http://www.fedshirevets.gov/index.aspx Department of Labor Veterans Employment Assistance http://www.dol.gov/vets/ Department of Veterans Affairs–VOW to Hire Heroes Act http://benefits.va.gov/vow/ Army Wounded Warrior Program – http://wtc.army.mil/modules/employers/index.html U.S. Chamber of Commerce Foundation–Hiring Our Heroes http://www.hiringourheroes.org/ Guide to Hiring Veterans – Reference Material http://www.whitehouse.gov/sites/default/files/docs/white_house_business_council_- _guide_to_hiring_veterans_0.pdf
C.13. ANTI-TERRORISM AND OPERATIONAL SECURITY REQUIREMENTS (AT/OPSEC):
C.13.a. Security or Distribution Release Classification of Contract Products. It is anticipated that most products generated under this research (reports, manuscripts, abstracts, presentations, data, code, prototypes, etc.) will be acceptable for DISTRIBUTION-A (Approved for public release: distribution unlimited). However, some aspects of this work may be restricted (DISTRIBUTION B-F) if the content is determined to potentially cause damage to National Security or contain content that should be protected for other reasons. Most commonly, CRREL limits or restricts public release of material that could assist adversaries to counter or defeat the US Government or threaten sensitive evolving Research and Development (R&D). Common categories requiring distribution limitations include material related to: Administrative or Operational Use; Contractor Performance Evaluation; Critical Technology; Direct Military Support; Export Controlled Topics; Foreign Government Information; Operations Security; Premature Dissemination; Proprietary Information; Test & Evaluation; Vulnerability Information; and Other Specific Authorities. Potential Operational Security (OPSEC) issues may exist regarding explicit research linkages made, for example, to the Next Generation Combat Vehicle, Future Vertical Lift, and mission planning and terrain characterization incorporated with the Network / Command, Control, Communications and Intelligence priority. Release of any material from this contact must first be cleared through CRREL’s Distribution Release Classification process wherein a Distribution Statement will be issued for each product via a written document signed by the COR and Security Officer after review of each product by the CRREL COR, Security Office, and TPOCs in accordance with Paragraph C.10 of this contract. This Distribution Statement must be obtained from CRREL before material is shared with any journal manuscript editors, conference abstract submissions, or other groups not included as subcontractors to the prime on this subject contract. It is often, though not always possible for CRREL to work with the Contractor to guide revision of a product to remove sensitive material so a version of a limited distribution product may be released as DISTRIBUTION-A (Approved for public release: distribution unlimited). The Contractor is encouraged to talk with the contract COR if further discussion of this security review process and Distribution Statements are desired.
C.13.b. Five-Eyes Nations. CRREL requires that all people working on this contract are citizens of Five Eyes Nations (US, UK, Canada, Australia, and New Zealand). Datasets provided to Transcend may be Unclassified // Five Eyes. Transcend may also be included in Unclassified // Five Eyes conversations with CRREL regarding operational applications of this work.
C.13.c. CRREL Site Access. Contractor personnel allowed on site shall follow all sign-in and security regulations as directed by the CRREL Security Office, COR, and TPOC, and as listed below:
i. Proof of Negative COVID-19 testing (coordinate details with CRREL) – if required.
ii. U.S. Citizens – Only U. S. Citizens are allowed on site.
iii. Personnel List – Contractor shall supply the COR & TPOC with a list of his employees who will be working on the CRREL site.
iv. Positive Picture ID – Contract personnel shall provide a positive picture ID prior to site access.
v. Identification Badges – Contractor personnel are required to sign in with Security and to obtain and wear security identification badges while on government site.
vi. Weapons – No weapons of any kind are allowed on site either in vehicles or on persons.
vii.…