This document outlines a federal contract award notice for a research project on partitioning behaviors of per- and poly-fluoroalkyl substances. The Strategic Environmental Research and Development Program awarded Simon Fraser University a cost-plus-fixed-fee contract worth $963,108 on January 25, 2022. The contract number is W912HQ22C0024 and it was awarded under broad agency announcement W912HQ-19-S-0005. The work will involve research to support bioaccumulation modeling and risk assessment of per- and poly-fluoroalkyl substances in different biological media. The period of performance is January 25, 2022 through January 24, 2026. The Army Corps of Engineers is the contracting agency and will administer the contract.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AWARD/CONTRACT

2. CONTRACT

RATING PAGE OF PAGES

3. EFFECTIVE DATE

(Proc. Inst. Ident.)

W912HQ22C0024 25 Jan 2022

5. ISSUED BY CODE 6. ADMINISTERED BY (If other than Item 5) CODE

NO. 4. REQUISITION/PURCHASE REQUEST/PROJECT NO.

W74RDV10848930

USACE HUMPHREYS ENGR CTR SPT ACTIVITY

ATTN: CEHEC-CT,

7701 TELEGRAPH ROAD

ALEXANDRIA VA 22315-3860

7. NAME AND ADDRESS OF CONTRACTOR (No., street, city, county, state and zip code)

SIMON FRASER UNIVERSITY

SFU

8888 UNIVERSITY DR SUITE 1200

BURNABY V5A 1S6

CODE

11. SHIP TO/MARK FOR

L0515

SERDP PROGRAM OFFICE

PROGRAM MANAGER

4800 MARK CENTER DRIVE, SUITE 16F16

ALEXANDRIA VA 22350-3600

CODE

FACILITY CODE

W74RDV

13. AUTHORITY FOR USING OTHER THAN FULL AND OPEN

COMPETITION:

[ ] 10 U.S.C. 2304(c)( )

15A. ITEM NO.

[ ] 41 U.S.C. 253(c)( )

15B. SUPPLIES/ SERVICES

SEE SCHEDULE

(X)

PART I - THE SCHEDULE

SEC. DESCRIPTION

16. TABLE OF CONTENTS

PAGE(S)

X X

A SOLICITATION/ CONTRACT FORM 1

B C

SUPPLIES OR SERVICES AND PRICES/ COSTS

DESCRIPTION/ SPECS./ WORK STATEMENT

2 - 3

X D E

PACKAGING AND MARKING

X F

INSPECTION AND ACCEPTANCE

X G

DELIVERIES OR PERFORMANCE

CONTRACT ADMINISTRATION DATA

5 - 6

X H SPECIAL CONTRACT REQUIREMENTS

7 - 8

17. [ ] CONTRACTOR'S NEGOTIATED AGREEMENT X

CONTRACTING OFFICER WILL COMPLETE ITEM 17 (SEALED-BID OR NEGOTIATED PROCUREMENT) OR 18 (SEALED-BID PROCUREMENT) AS APPLICABLE document and return copies to issuing office.)1 Contractor is required to sign this items or perform all the services set forth or otherwise identified above and on any continuation Contractor agrees to furnish and deliver all sheets for the consideration stated herein. The rights and obligations of the parties to this contract shall be subject to and governed by the following documents: (a) this award/contract,

(b) the solicitation, if any , and (c) such provisions, representations, certifications, and specifications, as are attached or incorporated by reference herein.

(Attachments are listed herein.)

19A. NAME AND TITLE OF SIGNER (Type or print)

19B. NAME OF CONTRACTOR 19C. DATE SIGNED

BY

(Signature of person authorized to sign)

Previous edition is NOT usable

See Item 5

8. DELIVERY

[ ] FOB ORIGIN [ ] OTHER X (See below)

9. DISCOUNT FOR PROMPT PAYMENT

Net 30 Day s

10. SUBMIT INVOICES 1 ITEM

TO THE ADDRESS

SHOWN IN:

(4 copies unless otherwise specified)

12. PAYMENT WILL BE MADE BY

USA CORP ENG FINANCE CTR 40042

5722 INTEGRITY DRIVE

MILLINGTON TN 38054-5005

CODE W916TX

14. ACCOUNTING AND APPROPRIATION DATA

See Schedule

15C. QUANTITY 15D. UNIT 15E. UNIT PRICE 15F. AMOUNT

15G. TOTAL AMOUNT OF CONTRACT $963,108.00

(X)

PART II - CONTRACT CLAUSES

SEC. DESCRIPTION PAGE(S)

PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACH.

X I CONTRACT CLAUSES 10 - 12

X

PART IV - REPRESENTATIONS AND INSTRUCTIONS

J LIST OF ATTACHMENTS 13

K

L

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

INSTRS., CONDS., AND NOTICES TO OFFERORS

M EVALUATION FACTORS FOR AWARD

18. [ ] SEALED-BID AWARD (Contractor is not required to sign this document.)

20A. NAME OF CONTRACTING OFFICER

DOUGLAS E POHLMAN / ADDED BY UPASS

TEL: 703-428-6420 EMAIL: Douglas.E.Pohlman@usace.army.mil

20B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

20C. DATE SIGNED

25-Jan-2022

W912HQ

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

AUTHORIZED FOR LOCAL REPRODUCTION

Prescribed by GSA – FAR (48 CFR) 53.214(a)

STANDARD FORM 26 (REV. 5/2011)

document is necessary. (Block 18 should be checked only when awarding a sealed-bid contract.)

following documents: (a) the Government's solicitation and your bid, and (b) this award/contract. No further contractual to the terms listed above and on any continuation sheets. This award consummates the contract which consists of the including the additions or changes made by you which additions or changes are set forth in full above, is hereby accepted as

Your bid on Solicitation Number

W912HQ22C0024

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Project $963,108.00

ER18-1502 SIMON FRASER UNIVERSITY

COST

The Contractor, Simon Fraser University, shall furnish all management, facilities, supplies, personnel, and equipment and do all things necessary for the performance of the work required in response to a Statement of Need in BAA W912HQ-20-S-0006, Program Area: ER18-1502 “Partitioning Behavior of Per-and Poly-fluoroalkyl Substances in Different Biological Media to Support Bioaccumulation Modelling and Risk Assessment.”

The Initial Proposal is dated 19 May 2020 and the respective revision is dated as follows: 16 December 2020 Revision 1.

FOB: Destination

MILSTRIP: W74RDV10848930

PURCHASE REQUEST NUMBER: W74RDV10848930

PSC CD: AJ12

ESTIMATED COST $963,108.00

000101 $0.00

FOR FUNDING PURPOSES ONLY

FFP

MFR PART NR: 1

NET AMT $0.00

ACRN AA

$381,301.00

0002 NSP

DD1423 CDRLS

COST

Data is as specified in Exhibit A, Contract Data Requirements List, DD Form 1423. This CLIN is not separately priced. The cost for this CLIN has been included in CLIN 0001.

ESTIMATED COST $0.00

Section E - Inspection and Acceptance

INSPECTION AND ACCEPTANCE TERMS

Supplies/services will be inspected/accepted at:

CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

0001 N/A Government N/A Government 000101 N/A N/A N/A N/A 0002 N/A N/A N/A N/A

CLAUSES INCORPORATED BY FULL TEXT

52.246-9 INSPECTION OF RESEARCH AND DEVELOPMENT (SHORT FORM) (APR 1984)

The Government has the right to inspect and evaluate the work performed or being performed under the contract, and the premises where the work is being performed, at all reasonable times and in a manner that will not unduly delay the work. If the Government performs inspection or evaluation on the premises of the Contractor or a subcontractor, the Contractor shall furnish and shall require subcontractors to furnish all reasonable facilities and assistance for the safe and convenient performance of these duties.

(End of clause)

252.235-7010 Acknowledgment of Support and Disclaimer. (MAY 1995)

(a) The Contractor shall include an acknowledgment of the Government's support in the publication of any material based on or developed under this contract, stated in the following terms: This material is based upon work supported by The US Army Corps of Engineers and The Department of Defense Strategic Environmental Research and Development Program under Contract No.

W912HQ22C0024.

(b) All material, except scientific articles or papers published in scientific journals, must, in addition to any notices or disclaimers by the Contractor, also contain the following disclaimer: Any opinions, findings and conclusions or recommendations expressed in this material are those of the author(s) and do not necessarily reflect the views of The US Army Corps of Engineers and The Department of Defense Strategic Environmental Research and Development Program.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 POP 25-JAN-2022 TO

24-JAN-2026

N/A SERDP PROGRAM OFFICE

PROGRAM MANAGER

4800 MARK CENTER DRIVE, SUITE 16F16

ALEXANDRIA VA 22350-3600

571-372-6400 FOB: Destination

W74RDV

000101 N/A N/A N/A N/A

0002 N/A N/A N/A N/A

52.242-15 STOP-WORK ORDER (AUG 1989) - ALTERNATE I (APR 1984)

(a) The Contracting Officer may, at any time, by written order to the Contractor, require the Contractor to stop all, or any part, of the work called for by this contract for a period of 90 days after the order is delivered to the Contractor, and for any further period to which the parties may agree. The order shall be specifically identified as a stop-work order issued under this clause. Upon receipt of the order, the Contractor shall immediately comply with its terms and take all reasonable steps to minimize the incurrence of costs allocable to the work covered by the order during the period of work stoppage. Within a period of 90 days after a stop-work is delivered to the Contractor, or within any extension of that period to which the parties shall have agreed, the Contracting Officer shall either--

(1) Cancel the stop-work order; or

(2) Terminate the work covered by the order as provided in the Termination clause of this contract.

(b) If a stop-work order issued under this clause is canceled or the period of the order or any extension thereof expires, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule, the estimated cost, the fee, or a combination thereof, and in any other terms of the contract that may be affected, and the contract shall be modified, in writing, accordingly, if--

(1) The stop-work order results in an increase in the time required for, or in the Contractor's cost properly allocable to, the performance of any part of this contract; and

(2) The Contractor asserts its right to the adjustment within 30 days after the end of the period of work stoppage;

provided, that, if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon the claim submitted at any time before final payment under this contract.

(c) If a stop-work order is not canceled and the work covered by the order is terminated for the convenience of the Government, the Contracting Officer shall allow reasonable costs resulting from the stop-work order in arriving at the termination settlement.

(d) If a stop-work order is not canceled and the work covered by the order is terminated for default, the Contracting Officer shall allow, by equitable adjustment or otherwise, reasonable costs resulting from the stop-work order.

Section G - Contract Administration Data

SECTION G CLAUSES

G001 CONTRACTING OFFICER AUTHORITY

Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO) or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.

G002 PAYMENT SCHEDULE AND INVOICE SUBMISSION

The Contractor shall submit invoices pertaining to this contract action via e-mail.

The subject line shall include the contract number, project number, if known, and an invoice number.

CEFC-S0invoices@usace.army.mil

Additionally, the Contracting Officer’s Representative (COR) and SERDP/ESTCP Program Office shall be copied on all invoice submissions.

The COR’s email is provided in separate correspondence.

The SERDP/ESTCP Program Office email for invoices osd.mc-alex.ousd-atl.mbx.serdp-estcp-invoices@mail.mil The final invoice should be marked as such. If more than 30 days have passed since the invoice was submitted. Questions regarding status of payment should be directed to the USACE Finance Center at:

CEFC-Payments@usace.army.mil

Instructions for Final Invoices

1. Cost Contracts: The final invoice (public voucher) must be submitted directly to the Contracting Officer and is subject to review and acceptance the Program Manager and requires approval by the Contracting Officer prior to final payment being released.

- Universities: Final payments will be approved once the Contracting Officer verifies the cumulative amount invoiced matches the contract price. If the amount invoiced does not match the final contract price a modification to de-obligate unused funds may be necessary prior to paying the final invoice (public voucher).

- Businesses: The final invoice will not be approved for payment until after the Program Manager accepts all deliverables prior to payment, and the invoice is reviewed and approved by the Contracting Officer. Final payment will not be approved until the Contracting Officer receives an audit or receives a low-risk memorandum from DCAA or another cognizant Government authority.

In accordance with FAR 42.705: All final Indirect Cost rates are subject to review and approval by the Contracting Officer. Once the audit or low-risk memorandum is received, the Contracting Officer will verify the final invoice cumulative amounts matches the final contract price and complete a modification to de-obligate unused funds if necessary prior to approving payment for the final invoice.

Summary: For cost contracts, final Public Voucher's must always be reviewed/approved by a KO, and the P.M. must be involved - i.e. acceptance.

2. Firm Fixed-Price Contracts: The final invoice must be submitted directly to the Contracting

Officer and is subject to review and acceptance the Program Manager and requires approval by the Contracting Officer prior to payment being released.

- Final invoice that match the contract price: once the Program Manager accepts the final deliverables, the Contracting Officer will approve the final invoice for payment.

- Final invoices that do not match the contract price: once the Program Manager accepts the final deliverables, the invoice is subject to review and approval by the Contracting Officer. A modification to de-obligate unused funds may be necessary prior to paying the final invoice.

Summary: For firm-fixed-price contracts: All final invoices for FFP contracts could go to CT for KO review; however, anytime the invoice total does NOT match the contract price, CT needs the final invoice so that a de-obligation modification can be started, and a KO can approve the invoice.

ACCOUNTING AND APPROPRIATION DATA

AA: 97104001101 088000 255YJL98DH0603716D8Z0 NA 44213

AMOUNT: $381,301.00

ACRN CLIN/SLIN CIN AMOUNT

AA 000101 W74RDV10848930000101 $381,301.00

252.201-7000 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 1991)

(a) "Definition. Contracting officer's representative" means an individual designated in accordance with subsection 201.602-2 of the Defense Federal Acquisition Regulation Supplement and authorized in writing by the contracting officer to perform specific technical or administrative functions.

(b) If the Contracting Officer designates a contracting officer's representative (COR), the Contractor will receive a copy of the written designation. It will specify the extent of the COR's authority to act on behalf of the contracting officer. The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.

Section H - Special Contract Requirements

SECTION H CLAUSES

H002 GOVERNMENT RESERVED RIGHTS

The Government reserves the right to approve contractor recommended changes in technical personnel during the life of the contract.

H008 TRAVEL COSTS

Travel will be reimbursed at actual direct cost in accordance with the limitations set forth in FAR 31.205- 46 (Commercial Organizations), FAR 31.3 (Educational Institutions), or FAR 31.7 (Nonprofit Organizations). The appropriate Government Official, Quality Assurance Personnel or Contracting Officer shall approve travel. All invoices for travel shall be accompanied by supporting receipts

H010 REVIEW FOR CONTRACTORS RELEASE OF TECHNICAL REPORTS

The Contractor shall be free to use the results of the subject research for its own teaching, research, educational, clinical, and publication purposes. The Contractor shall not release any reports with the SERDP or ESTCP logo, in any form (interim, draft, and final reports), to any person or agency, including those within the Department of the Army, without the prior written approval of the SERDP/ESTCP program office.

All publications and deliverable reports prepared by the contractor under this contract shall conspicuously display the following disclaimer:

VIEWS, OPINIONS, AND/OR FINDINGS CONTAINED IN THIS REPORT ARE THOSE OF THE

AUTHOR(S) AND SHOULD NOT BE CONSTRUED AS AN OFFICIAL DEPARTMENT OF DEFENSE

POSITION OR DECISION UNLESS SO DESIGNATED BY OTHER OFFICIAL DOCUMENTATION.

H012 TECHNICAL DATA - WITHHOLDING OF PAYMENT

In accordance with DFARS 252.227-7030, entitled “Technical Data – Withholding of Payment”, the Government may withhold payment to the Contractor of ten percent (10%) unless a lesser withholding amount is specified in the contract. As such, the Government reserves the right to withhold $25,000.00 or 10% of the contract value, whichever is the smaller amount, pending receipt and acceptance of all required deliverables.

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government JUN 2020 52.203-7 Anti-Kickback Procedures JUN 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity

MAY 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

JUN 2020

52.203-17 Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights

JUN 2020

52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper

MAY 2011

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

JUN 2020

52.204-19 Incorporation by Reference of Representations and Certifications.

DEC 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.

JUL 2018

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

AUG 2020

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment

JUN 2020

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.215-2 Alt II Audit and Records--Negotiation (JUN 2020) - Alternate II AUG 2016 52.215-8 Order of Precedence--Uniform Contract Format OCT 1997 52.215-14 Integrity of Unit Prices JUN 2020 52.216-7 Alt II Allowable Cost and Payment (AUG 2018) - Alternate II AUG 2012 52.216-11 Alt I Cost Contract--No Fee (Apr 1984) Alternate I APR 1984 52.216-15 Predetermined Indirect Cost Rates APR 1998 52.222-2 Payment For Overtime Premiums JUL 1990 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-29 Notification Of Visa Denial APR 2015 52.222-50 Alt I Combating Trafficking in Persons (OCT 2020) Alternate I MAR 2015 52.223-18 Encouraging Contractor Policies To Ban Text Messaging

While Driving

JUN 2020

52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.227-1 Alt I Authorization And Consent (JUN 2020) - Alternate I APR 1984 52.227-2 Notice And Assistance Regarding Patent And Copyright

Infringement

JUN 2020

52.227-14 Alt IV Rights in Data--General (May 2014) - Alternate IV DEC 2007 52.227-16 Additional Data Requirements JUN 1987 52.228-7 Insurance--Liability To Third Persons MAR 1996 52.232-9 Limitation On Withholding Of Payments APR 1984 52.232-20 Limitation Of Cost APR 1984

52.232-22 Limitation Of Funds APR 1984 52.232-25 Alt I Prompt Payment (Jan 2017) Alternate I FEB 2002 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

OCT 2018

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.233-1 Disputes MAY 2014 52.233-3 Alt I Protest After Award (Aug 1996) - Alternate I JUN 1985 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.242-1 Notice of Intent to Disallow Costs APR 1984 52.242-3 Penalties for Unallowable Costs SEP 2021 52.242-13 Bankruptcy JUL 1995 52.243-2 Alt V Changes--Cost-Reimbursement (Aug 1987) - Alternate V APR 1984 52.243-6 Change Order Accounting APR 1984 52.244-6 Subcontracts for Commercial Items JUL 2021 52.245-1 Alt II Government Property (SEP 2021) Alternate II APR 2012 52.245-9 Use And Charges APR 2012 52.246-25 Limitation Of Liability--Services FEB 1997 52.249-5 Termination For Convenience Of The Government

(Educational And Other Nonprofit Institutions)

AUG 2016

52.249-14 Excusable Delays APR 1984 52.251-1 Government Supply Sources APR 2012 52.253-1 Computer Generated Forms JAN 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies

DEC 2008

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7006 Billing Instructions OCT 2005 252.204-7012 Safeguarding Covered Defense Information and Cyber

Incident Reporting

DEC 2019

252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support

MAY 2016

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services

JAN 2021

252.209-7004 Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism

MAY 2019

252.222-7002 Compliance With Local Labor Laws (Overseas) JUN 1997 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.225-7041 Correspondence in English JUN 1997 252.225-7048 Export-Controlled Items JUN 2013 252.227-7013 Rights in Technical Data--Noncommercial Items FEB 2014 252.227-7016 Rights in Bid or Proposal Information JAN 2011 252.227-7030 Technical Data--Withholding Of Payment MAR 2000 252.227-7037 Validation of Restrictive Markings on Technical Data SEP 2016 252.232-7008 Assignment of Claims (Overseas) JUN 1997 252.232-7010 Levies on Contract Payments DEC 2006 252.233-7001 Choice of Law (Overseas) JUN 1997 252.235-7011 Final Scientific or Technical Report DEC 2019 252.242-7006 Accounting System Administration FEB 2012 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.247-7023 Transportation of Supplies by Sea FEB 2019

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov/

52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation Supplement (48 CFR 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

Section J - List of Documents, Exhibits and Other Attachments

SECTION J CLAUSES

J001 ADDITIONAL DOCUMENTATION

The attached DD Form 1423, Contract Data Requirements List (CDRL) is part of Contract Line Item Number (CLIN) 0002.

File details come from the government source that posted it. Updated .