This is an Advertisement for Bid issued by the City of St. Charles, Missouri for the Duchesne Drive Reconstruction project (Project No. STP-5414(643), Bid #4806). The project encompasses full depth pavement replacement of deteriorated concrete pavement on Duchesne Drive between West Clay Street and Droste Road, including 9 inches of asphalt pavement on a 6-inch aggregate base. The scope includes drainage improvements with additional grate inlets and storm sewers to address localized ponding between West Clay Street and Raymond Drive, sidewalk reconstruction on the west side, an 8-foot-wide shared use path on the east side connecting to existing paths, curb ramp reconstruction, storm sewer improvements, rapid rectangular flashing beacons, striping, signage, new driveway entrances and approaches, curb and gutter work, and street lighting. Sealed proposals must be submitted to City Hall, Engineering Office, 200 North Second Street, St. Charles, Missouri 63301 by 2:00 p.m. local time on July 29, 2026. Plans and specifications are available for download or order at http://planroom.drexeltech.com.
Bidders must submit a bid bond, certified check, or cashier's check in an amount not less than 5 percent of the bid amount. All bidders must be listed on MoDOT's Qualified Contractor List and submit a completed Contractor Questionnaire at least 7 days prior to bid opening. The DBE goal for this project is 0 percent. Missouri Law 292.675 RSMO requires awarded contractors and subcontractors to provide ten-hour OSHA Construction Safety Program training for applicable on-site employees, with non-compliance penalties of $2,500 plus $100 per employee per calendar day. The successful bidder must sign the contract and performance bond in triplicate within 15 days of receipt, and the City reserves the right to reject any or all bids and to defer contract acceptance for up to 120 days after bid opening. The City of St. Charles is an equal opportunity employer and will afford full opportunity to businesses owned and controlled by socially and economically disadvantaged individuals.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF ST. CHARLES DUCHESNE DRIVE RECONSTRUCTION
PROJECT NO. STP-5414(643)
August 2025 BCL – 1
ADVERTISEMENT FOR BID #4806
Notice is hereby given that the City of St. Charles will receive sealed proposals at City Hall, Engineering Office, 200
North Second Street, St. Charles, Missouri 63301 until 2:00 p.m. local time, on July 229, 2026 , at which time all bids for the Duchesne Drive Reconstruction will be publicly opened and read.
The Duchesne Drive Reconstruction project replaces pavement between West Clay Street and Droste Road. The existing concrete pavement has deteriorated and requires a full depth pavement replacement with 9-inches of asphalt pavement constructed on 6-inches of aggregate base. Duchesne Drive between West Clay Street and Raymond Drive experiences localized ponding during heavy rain events, therefore the project provides additional grate inlets and storm sewers to improve drainage. The project provides sidewalk reconstruction to complete a continuous sidewalk on the west side and an 8-foot-wide shared use path on the east side. The shared use path will connect to other existing shared use paths along
West Clay Street and Droste Road. Additional improvements include rapid rectangular flashing beacons, curb ramp reconstruction, storm sewer improvements, striping, signage, new driveway entrances, approaches, curb and gutter and street lighting.
The bid proposal shall be made on a form of proposal, provided in the specifications and delivered in a sealed envelope clearly marked on the outside Bid No. 4806 to the Engineering Office on or before the time specified above. No facsimiles will be accepted. The proposal shall be accompanied by a bid bond, certified check or cashier's check of a bank or trust company in St. Charles County, City of St. Charles, St. Louis County, or in the City of St. Louis for an amount not less than five (5%) percent of the bid amount. The amount of the check shall be forfeited to the City if the bidder neglects or refuses to enter into a contract or to furnish bond after their proposal has been accepted.
The City reserves the right to reject any and all bids, offers, or proposals submitted, or to advertise for new bids with the
MoDOT’s concurrence. The City reserves the right to defer the acceptance of any proposal and the execution of a contract for a period not exceeding one hundred twenty (120) days after the date of opening of the bids. The successful bidder to whom the contract has been awarded shall sign the contract and performance bond and other required certificates in triplicate and return the signed documents within fifteen (15) days after the date of their receipt.
The City of St. Charles hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, businesses owned and controlled by socially and economically disadvantaged individuals will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, religion, creed, sex, age, ancestry, or national origin in consideration for an award.
The City of St. Charles is an equal opportunity employer. The City does not discriminate against any person because of race, color, religion, sex, handicap, familial status, or national origin.
All bidders must be on MoDOT’s Qualified Contractor List per Section 102.2 of the Missouri
Standard Specifications for Highway Construction, 2011 Edition including all revisions. The contractor questionnaire must be on file 7 days prior to bid opening.
The DBE goal for this project is 0%
Plans and specifications are now on file at http://planroom.drexeltech.com. Plans and specifications can be downloaded or ordered from this site for the fee listed online.
Missouri Law, 292.675 RSMO, requires any awarded contractor and its subcontractor(s) to provide a ten-hour
Occupational Safety and Health Administration (OSHA) Construction Safety Program (or a similar program approved by the Missouri Department of Labor and Industrial Relations as a qualified substitute) for their on-site employees (laborers, workmen, drivers, equipment operators, and craftsmen) who have not previously completed such a program and are directly engaged in actual construction of the improvement (or working at a nearby or adjacent facility used for construction of the improvement). The awarded contractor and its subcontractor(s) shall require all such employees to complete this ten-hour program, pursuant to 292.675 RSMO, unless they hold documentation on their prior completion of said program.
Penalties, for Non-Compliance include contractor forfeiture to the Contracting Authority in the amount of $2,500, plus
$100 per contractor and subcontractor employee for each calendar day such employee is employed beyond the elapsed time period for required program completion under 292.675 RSMO.
The successful bidder and contractor will be furnished, without cost, not more than three (3) sets of plans and specifications for the project. If more are requested, additional sets will be furnished at a nominal charge. Any plans and specifications required for permits by a municipality or other public agency will be furnished by the City.
CITY OF ST. CHARLES DUCHESNE DRIVE RECONSTRUCTION
PROJECT NO. STP-5414(643)
August 2025 BCL – 2
BIDDER CHECKLIST
FINAL CHECKLIST BEFORE SUBMITTING BID
1. Submit completed Contractor Questionnaire and/or Contractor Prequalification Questionnaire with attachments not later than seven (7) days prior to the date and hour of the bid opening. See Secs 101-103 of the Standard Specifications, and
Rule 7 CSR 10-15.900, "Prequalifications to Bid of Certain Contractors". Questionnaire and Contact information are provided on MoDOT’s website.
2. For submittal of paper bids, the complete set of bidding documents includes all information through the DBE forms (for
DBE forms see #8). The Technical Specifications/Job Special Provisions are for the bidder’s information only and is not to be returned with the bid.
3. If submitting the bid by mail, it is to be completed, executed, and submitted in a sealed envelope addressed to City Hall
Public Works Office, 200 North Second Street, St. Charles, Missouri 63301. Provide the vendor name, vendor address, vendor number, county, route and federal project number on the outside of the envelope.
4. Please read all items in the bidding document carefully. For paper bids, complete all items in ink or by typing in the information.
5. Sign this bidding document properly. If submitted in the name of a firm or corporation, the legal name of the firm or corporation should appear in the space designated, and be signed for by one or more persons legally qualified to execute papers in the name of said firm or corporation. Affix Corporate Seal if the Bidder is a Corporation.
6. For paper bids submit a bid bond executed by bidder and surety, or attach cashier's check to the bid bond form.
7. Submit the Bidder’s List Quote Summary form with the bid.
8. Submit the DBE Submittal Forms within 3 business days of the Bid Opening. The DBE Identification Submittal Form
(Page 2 of this document) must be submitted for each DBE to be utilized on the project. Any DBE’s submitted as regular dealers/distributors must have an accompanying DBE Regular Dealer/Distributor Affirmation Form.
9. For paper bids, staple addenda to the bid in the appropriate part of the bid. The letter accompanying the addenda should be stapled to the inside of the back cover of the bid and returned. The bidder should retain a duplicate copy.
Below is a list of common mistakes made by bidders leading to non-responsive bids. Please refer to the Standard
Specifications for the appropriate procedures for completing and submitting a bid.
a) Not signing the bid
b) Not incorporating the addendum into the bidding documents, including attaching the letter to the bid
c) Not providing a bid bond
d) Using pencil to fill out the bid
e) Using white out to make corrections to the itemized bid sheets
f) Not initialing changes made
All questions concerning the bidding and project can be directed to the City of St. Charles Project Manager, Jonathan
Silver at 636-949-3241.
Special Needs: If you have special needs addressed by the Americans with Disabilities Act, please notify the Project
Manager, Jonathan Silver at 636-949-3241 or through Missouri Relay System, TDD 1-800-735-2966, at least five (5) working days prior to the bid opening.