This is a Design Build Project Advertisement issued by the Michigan Department of Technology, Management and Budget, State Facilities Administration, Design & Construction Division, in coordination with the Department of Corrections. The project involves propane plant replacement and repair of the back-up fuel system blender at E.C. Brooks Correctional Facility in Muskegon Heights, Michigan. The scope of work includes restoration of the existing propane plant to full functionality, installation of one propane blender system with a new propane air Venturi mixing system supplying 30 MM Btu per hour at 8 pounds of pressure, propane flow pumps with bypass valves, and a propane water bath vaporization unit at 30MM Btu per hour at -20 degrees Fahrenheit and 200 PSIG, along with all associated gas piping and electrical connections. The advertisement was released on June 19, 2018, with bids due July 11, 2018, at 2:00 p.m. local time. A mandatory walk-through inspection is scheduled for Thursday, June 28, 2018, at 11:00 a.m. at the Maintenance Building of the facility. Questions will be accepted until July 5, 2018, at noon EDT. The project requires 5% bid security and compliance with all applicable codes and standards administered by federal agencies (EPA, OSHA, DOT) and state agencies (DCH, DEQ, DNR, MIOSHA).
The project is a design/build delivery method, requiring submitted proposals to include design recommendations for restoring the system to full operation. No specific pricing terms, set-aside requirements, or incumbent information is detailed in the advertisement. All applicable permits and approvals must be obtained from the Michigan Bureau of Construction Codes and Bureau of Fire Services. Project documentation and bid results are available through the Michigan SIGMA system at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService. The Project Director is Todd Cordill, NCARB, reachable at (517) 897-7017 or cordillt1@michigan.gov, with questions directed to Tracy Falor at FalorT@michigan.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| EC Br Propane 2.JPG | JPG image | |
| Addendum 1.pdf | ||
| EC Br Propane 4.JPG | JPG image | |
| EC Br Propane 1.JPG | JPG image | |
| EC Br Propane 3.JPG | JPG image | |
| LEIN Request 16402.pdf | ||
| Design Build Master (10-27-17).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0415 (R 10/17)
DESIGN BUILD PROJECT ADVERTISEMENT
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN & CONSTRUCTION DIVISION
This form is required for the advertisement of all construction projects. (1984 PA 431)
TO:
DESIGN & CONSTRUCTION DIVISION
DATE
June 15, 2018
FROM:
Department of Corrections
PROJECT MANAGER
Todd Cordill, NCARB
DTMB FILE NUMBER
472/16402.TYC
INDEX NUMBER
37180
ADVERTISEMENT DATE
June 19, 2018
BID DUE DATE
July 11, 2018 @ 2:00 p.m. local time
PROJECT NAME AND LOCATION (INCLUDE STREET ADDRESS)
Propane Plant Replacement/ Replace & Repair the back-up fuel system blender E.C. Brooks Correctional Facility, 2500 S. Sheridan Drive, Muskegon Heights, MI 49444
WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION
Thursday, June 28, 2018 at 11:00 am at the Maintenance Building of the
E. C. Brooks Correctional Facility, 2500 S. Sheridan Drive, Muskegon Heights, MI 49444
Mandatory Yes No
LEIN CHECK (Dept. of Corrections ONLY) All contractor/vender representatives attending a Pre-Bid Walk Through Meeting must submit a Vendor/Contractor LEIN Request five business days prior to the meeting date, (See the attached Vendor/Contractor LEIN Request form). Send the LEIN Request form, filled out and signed, by email to Tracy Falor at email address: FalorT@michigan.gov. The email “Subject” must include (Facility Name, Project Name, Date & Time of Pre-Bid Walk Through Meeting).
NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.
DESCRIPTION OF WORK:
To restore the existing propane plant to be fully functional, that will include replacement/ installation of one Propane blender system consisting of: new propane air Venturi mixing system supplying 30 MM Btu per hour of mixed gas at 8 pounds of pressure; Propane flow pumps to the existing propane tank (includes bypass valves); Propane water bath vaporization unit at 30MM Btu per hour @-20 deg F and 200 PSIG. This will include all associated gas piping and electrical connections, grounding to be modified or replaced as required for a safe, operational system. All applicable codes shall be complied with including permits and approvals from the State of Michigan, Bureau of Construction Codes, and Bureau of Fire Services. Since this is a design/build project, the submitted proposal shall include design recommendations to restore the existing system to full operation in good repair.
5% Bid Security:
Required
Not Required
NIGP CODES: 90692 92595 91356 91389 90977 90924 91036
ACCEPTING QUESTIONS UNTIL: July 5, 2018 at noon (12:00 pm EDT)
REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers’ safety rules that are administered by federal agencies (EPA, OSHA and DOT), state agencies (DCH, DEQ, DNR, and MIOSHA), and any other local regulations and standards that may apply.
Documents & Bid Results may be obtained from:
https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
Project Director: Todd Cordill, NCARB
Address:
Phone: (517) 897-7017 Email: cordillt1@michigan.gov
Fax:
Approved by:
mailto:FalorT@michigan.gov https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
File details come from the government source that posted it. Updated .