T.S. State of Michigan 2014 Fall Repair Package
1 6/11/2014
GENERAL CONDITIONS
AND
SPECIFICATIONS
FOR REPAIRS AND RENEWALS
FOR THE
TRAINING SHIP “STATE OF MICHIGAN”
THESE SPECIFICATIONS are for the repairs and renewals to the Training Ship “STATE OF
MICHIGAN”.
It is understood by the Contractor that the work herein specified is to be carried out expeditiously in a good and workmanlike manner and completed in all respects, leaving the vessel ready for sea; that material and workmanship used must be of the best marine quality throughout; that Contractor furnished material must generally conform in size, quality and details to those originally in the vessel; that repairs must, in every respect, be made under the supervision and entire satisfaction of the attending MARAD Surveyor (or his Designated Representative) and the Representatives of the Regulatory Bodies.
It is further understood by the Contractor that all materials requiring tests shall be tested in accordance with United States Coast Guard Regulations, The American Bureau of Shipping, Rules, and other applicable Regulatory Bodies, and must meet their requirements and that all costs for tests and inspections must be borne by the Contractor.
If any dispute or difference shall arise relating to or concerning these Specifications or the meaning thereof, the Contractor shall perform the disputed work in accordance with the written directions of the MARAD Surveyor without prejudice to the rights of the parties and specifically without prejudice to the rights of the Contractor for reimbursement.
T.S. State of Michigan 2014 Fall Repair Package
2 6/11/2014
The Contractor will adhere to all Safety Rules and Regulations as set forth by OSHA, MARAD and the Great Lakes Maritime Academy, Shipboard requirements.
The Contractor will be responsible for taking measurements of all sizes, lengths, weights, types, styles and all other pertinent specifications of the work item to ascertain that they conform to actual specifications. Any discrepancies or differences are to be brought to the attention of the COR so that changes may be made prior to completion of the ship check and submitting of the bid.
The Contractor is to provide an estimate for the time required to complete the work item.
Additional costs such as staging, man lifts, crane service, transportation, portable fire extinguishers, fire watches, removal and replacement of interferences, and daily removal of all debris caused by the work, etc. required to complete any work as described herein, shall be included in the item quotations forwarded in response to this specification.
The Contractor will perform all work during normal shipboard work hours. Normal shipboard work hours are defined as Monday thru Friday, 0800 – 1700. The contractor is to advise if they intend to work aboard the vessel on weekends, holidays, or hours outside of 0800 thru 1700. No work will be permitted outside of normal working hours unless agreed to in advance with the COR and Chief Engineer.
Should the Contractor require the removal of any parts of the vessel or fittings, engines, fuel oil, stores, outfit, etc., the cost of such removal is to be borne by the Contractor. All such removals must be subsequently replaced, and any damage resulting there from, is to be made good by the Contractor at his expense. Should the Contractor require the removal of dirt, debris, etc., the Contractor shall remove same from the vessel at his expense.
All scrap and Contractor furnished surplus material occasioned by the repairs shall become the property of the Contractor unless it is to be retained for disposition by the Great Lakes Maritime Academy and otherwise specified herewith. Any value the Contractor anticipates receiving as a result of disposal of scrap or surplus materials shall inure to the benefit of the vessel’s owner through reduced pricing for the respective item(s). Such value shall be considered reflected in the pricing originally submitted by the Contractor in response to this solicitation. Notwithstanding the foregoing, pumps, motors and other machinery are to remain the sole property of the Government.
Any internal parts specified to be renewed which can be restored to their original condition by fairing, etc., also any parts specified to be removed for fairing which can be faired in place to the satisfaction of the MARAD Surveyor and the Regulatory Bodies will be accepted; on the other hand, any parts broken in removal, or fairing shall be renewed by the Contractor at his expense.
T.S. State of Michigan 2014 Fall Repair Package
3 6/11/2014
The Contractor will be responsible for taking measurements of all sizes, lengths, weights, types, styles and all other pertinent specifications of the work item to ascertain that they conform to actual specifications. Any discrepancies or differences are to be brought to the attention of the COR so that changes may be made prior to completion of the ship check and submitting of the bid.
Any particulars in the Specification for the work involved are given for the guidance of the Contractor, who is however, to take his own particulars and dimensions, and to be responsible for same, as the intent of these Specifications are to renew and restore the vessel generally and specifically insofar as damage is concerned; and to repair the vessel in accordance with the attached Specification.
Each day, at a mutually agreed time, the representative of the Contractor shall meet with the MARAD Designated Representative and his staff on board, or as otherwise agreed, to present a status report and a working plan for the next 24 hours.
The Contractor shall have one MARAD Designated Representative in charge of all work and this Representative is only to attend this unit.
No tanks, machinery, or equipment, opened up for repair or other purposes are to be boxed up or closed until inspection and acceptance by the MARAD Surveyor or his delegate.
All work specified hereafter shall be inspected and approved by the MARAD Surveyor or the person he authorizes. Work is not considered complete until the job has been inspected / tested by the MARAD Surveyor or Chief Engineer. The Service and/or Test Reports will be turned over in hard copy and electronic format to the COR or Chief Engineer, prior to payment of invoice.
The MARAD Surveyor may add, cancel, or modify individual Specification items in writing as may be required. Any changes to bid prices and time to do the work shall be pursued expeditiously and presented to the MARAD designated representative within 8 hours of notification of change. Such changes shall be agreed in writing by the Contractor and MARAD designated representative prior to undertaking the modification. Such agreement shall specifically set forth the change, if any, in the completion of the hereunder.
MARAD reserves the right to perform normal overhauls, repairs, and maintenance throughout the vessel by using their own crews, while the vessel is at the Great Lakes Maritime Academy facility located in Traverse City, Michigan.
T.S. State of Michigan 2014 Fall Repair Package
4 6/11/2014
MARAD reserves the right to engage sub‐contractors to perform work, furnish services and/or materials not covered by the specifications. The Contractor shall permit employees of such sub‐contractors access to the vessel for such purpose. All service personnel attending the vessel will be required to present the following information to the gangway watch:
Name (First, MI, Last);
Company;
Driver’s license number & state of issue
Should MARAD advise the Contractor in writing of any failure to conform to the standards of the trade and all applicable Regulatory Bodies or defective material or workmanship provided by the Contractor in performance of the work required by the Specification, such defects shall be corrected by the Contractor at his expense.
All quotations must include Contractor’s time line schedule (Gantt chart) of production and repair activities stating number of days required to complete all items as listed in the proposed work specification. A work planning chart including the number of planned shifts per day as well as the daily manning per specification item to accomplish this work must be supplied.
SPECIAL NOTE: The Contractor must furnish individual costs in the tender for each work item contained in the attached specification. Additionally, the Contractor must advise of any anticipated Holidays occurring during the expected contract period.
Invoicing and Payments: Any goods or services provided as a result of a contract resulting from this solicitation are subject to acceptance by the MARAD Surveyor or his Designated Representative. As a condition of payment the Contractor must provide proof of receipt and acceptance of the goods, or services provided. Such proof shall be in the form of the MARAD Surveyor’s (or his Designated Representative’s) signature affixed to the original invoice, acknowledging receipt and acceptance, as well as the agreed amount payable. No invoice shall be considered proper, until such acceptance is received, and the original invoice is forwarded by the Contractor to the address indicated on the purchase order. All invoices must provide line item detail in order to be considered proper supports.
Ten percent (10%) retainage shall be withheld from all invoices paid under this contract until such time as the contract is considered complete and closed, at which time the Contractor as part of his final invoice can invoice for the retained balance. A contract shall not be considered complete and closed until all goods and services have been received and accepted, all deliverables and reports required by the contract have been received and accepted, and any/all disputes arising out of this contract have been resolved and agreed.
T.S. State of Michigan 2014 Fall Repair Package
5 6/11/2014
Notice of General Precaution
Contractor shall provide continuously adequate protection of the work, Government property, and adjacent property, and take all necessary precautions to free the work place from recognized hazards which are likely to cause death, illness, or injury to persons or damage to the property.
The Contractor shall cause all its employees, subcontractors, agents, and others under the contractor's control entering the vessel to perform the work in connection therewith, to comply with all applicable health, safety, labor and environmental laws, ordinances, rules and regulations. This shall include, but not be limited to, applicable standards of United States, the United States Coast Guard, Local and Municipal Authorities and The U.S.
Department of Transportation. It should be noted that the vessel in question is a Public Vessel, therefore in addition to normal commercial practices, the Contractor must attest to its compliance with the Federal Acquisition Regulations Flow‐Down Clauses.
The Contractor will be responsible for supplying, and having his crew wear PPE (Personal Protective Equipment) that will include but not be limited to the following: safety helmet, safety glasses, safety shoes, protective clothing and hearing protection. The Maritime Administration shall not be required to police contractors to comply with any of the fire, health, safety, labor or environmental rules, laws, regulations, or orders generally referred to herein and shall not establish or confirm any regulations or orders. The Maritime Administration does, however reserve the right to bring to the attention of the contractor issues related to apparent failure to comply with any such fire, health, safety, labor or environmental rules, laws, regulations, or orders generally referred to herein, and the contractor must take immediate action to correct, or respond to such issues as appropriate.
The safe, proper, and lawful handling, storage, removal and disposal of hazardous material and asbestos, as well as hazardous, regulated or special waste is the responsibility of the Contractor. The Contractor is responsible to test material for asbestos and dispose of same, in accordance with (IAW) all applicable Federal, State, and Local Regulations. The Contractor must determine for itself whether work specified in this specification requires the removing, storage, handling, or disposal of hazardous material, special, regulated or hazardous waste and include the price in the proposal. The Contractor shall be considered the generator and shall provide the Surveyor (COTR) all documentation pertaining to the sampling, analysis, and disposal of all wastes generated during this contract.
The initial Gas Free Certificate(s) for Hot Work Permit(s) must be issued by a Marine Chemist, and is the responsibility of the Contractor. Subsequent daily maintenance of the Gas Free Certificate(s) to support the Hot Work Permit(s) will be maintained by the Contractor’s Competent Person through the Chief Engineer or Chief Mate, provided pre‐ approval from the Marine Chemist. All confined spaces, tanks, vessels, strainers, etc., with limited natural ventilation are to be provided with forced ventilation prior to entry. Hot
T.S. State of Michigan 2014 Fall Repair Package
6 6/11/2014
Work Permits will be issued for all operations requiring welding, burning or grinding. The Contractor is responsible to provide fire watches, as covered elsewhere in this specification to the contractors account.
The Contractor will be required to ensure that all potential energy sources have been locked out and tagged out by the ship’s force prior to the commencement of work. The Contractor is to coordinate this with the Chief Engineer.
Contractor shall furnish and maintain sufficient temporary lights to ensure the affected spaces are adequately lit providing a safe effective working environment.
All work required to be accomplished in this contract shall be completed at the current location of the vessel. The current location of the vessel is at the Great Lakes Maritime Academy, in Traverse City, Michigan. The physical address of the campus is 715 East Front Street, Traverse City, MI 49686. The contractor’s employees and sub‐contractors shall have with them, at all times while working onboard the vessel, a government issued identification card (TWIC), or state issued driver’s license. The contractor shall follow all policies and procedures set forth by the University and Marad concerning safety and security. The contractor and his sub‐contractors will be required to check in with crew personnel upon arriving and departing the vessel daily. The Contractor will notify the COR, Chief Engineer, and/or Master/PIC of the individual vessel of their intentions to attend. The contractor’s Service Technicians are to report to the Chief Engineer, without these notifications the Contractor will not be allowed on board.
T.S. State of Michigan 2014 Fall Repair Package
7 6/11/2014
DEFINITIONS:
The following terms shall have meanings as listed below throughout the General
Conditions and the Specifications for activation, repairs, and renewals to the Training Ship
“State of Michigan”;
"ADMINISTRATIVE CONTRACTING OFFICER" ‐ identifies the official authorized to perform any post award contractual actions assigned by the contracting officer.
"ARTICLE" ‐ means a separate lettered part of a work item of the Work Package.
Articles in different items may bear the same number; hence, to identify an article completely, the work item of which it is a part must be specified.
“AS ORIGINAL” means a condition meeting the original system and manufacturer’s design.
“AS APPROVED” or “TO THE APPROVAL” or “FOR APPROVAL” or “AS DIRECTED” or “AS REQUIRED” are used without further qualification, indicating the decision of the MARAD Surveyor is required. Where an item is required to be submitted for approval, work shall not proceed until notification of approval is received. In the event the item is not approved, rationale will be provided and work shall not proceed until a satisfactory and mutually agreeable resolution has been resubmitted and approved.
“CFE” and “CFM” identify Contractor Furnished Equipment and Material and are used interchangeably.
"CHECKPOINT" ‐ In a Work Item, the phrase “Checkpoint” establishes a point in the sequence of work at which time the COTR shall be notified to observe a specific test or inspection. The COTR will be notified no less than 24 hours prior to the starting of any test or inspection. If tests are scheduled for the weekend, COTR must be notified no later than noon of the Thursday before.
"CLIN" ‐ Contract Line Item. An individually priced work item, within the specification package.
"CONTRACT" ‐ The agreement entered into between the Owner and the Contractor for the accomplishment of the work specified in the Specifications.
"CONTRACTING OFFICER" ‐ The person in charge of the contract.
“CONTRACTOR” identifies the shipyard or topside repair company holding the prime contract for the work supplied in this Specification.
"COTR" ‐ Contracting Officer's Technical Representative managing the repair availability. This individual will be a MARAD employee.
“DETACH” or “DISCONNECT” mean to disconnect all attachments to the unit to enable the unit to be moved. All attachment points shall be tagged, identified, blanked, and protected to facilitate reinstallation. Work items do not necessary identify interferences and the Contractor is responsible for the identification
T.S. State of Michigan 2014 Fall Repair Package
8 6/11/2014 and resolution of interferences affecting a detachment and subsequent movement.
"Equivalent" ("Or Equal") Equipment ‐ Where equipment is specified by manufacturer's name, make, and model number, the Contractor may request, in writing, equivalents to the COTR for approval. The approval request must delineate the design and performance data on both the specified and recommended substitute pieces of equipment. Approval will be based on, but not be limited to the following criteria:
a. Data presented that demonstrates that it meets the specified performance requirements.
b. Possess appropriate Regulatory Body approval or other pertinent design standards where required.
c. Possess similar and functionally equivalent dimensions; weight; power;
HVAC; cooling water, or other required services; capacity; material; marine service characteristics; maintenance features and requirements, maintenance manpower requirements; time in service; suitability for marine service; population in commercial service; life cycle cost and maintenance cost; structure borne and airborne noise characteristics;
vendor‐furnished training, worldwide service and support; warranty provisions; spare parts availability and provisioning; consumption and performance data; and compatibility with interrelated systems and arrangements.
d. Exceptions to these criteria will be considered if they are demonstrable to be superior to those specified and are to the advantage of the vessel's mission and the Government.
e. If approved, the Contractor shall take full contractual and technical responsibility from a cost and performance standpoint for installing the components, equipment, or systems and ensuring their compatibility with interrelated components, equipment, or systems.
“GFE” or “GFM” identify Government Furnished Equipment and Material and are used interchangeably.
“GOVERNMENT” or “MARAD” means the U. S. Government, including the U. S.
Maritime Administration or its authorized representative.
“INSTALL” or “EXTEND” or “MODIFY” mean that the Contractor shall provide the piece of equipment, material or system to be installed and shall provide the materials, structural supports and labor to attach, connect and test the equipment or systems to effect a finished fully operational installation complete in all aspects.
T.S. State of Michigan 2014 Fall Repair Package
9 6/11/2014
a. When new material or equipment is not specified by type, the material or equipment shall be identical to the existing. When “install” is used with reference to GFE, all conditions of the above definition except the requirement to provide the specific piece of equipment are applicable.
b. Work items do not necessarily identify interferences and the Contractor is responsible for the identification and resolution of interferences affecting the installation by temporarily removing, reinstalling, or relocating interferences.
The Contractor shall temporarily remove, permanently relocate, alter, and reroute all interferences, including but not limited to ductwork, piping, wire ways, fixtures, insulation, joiner linings, equipment, furniture, etc. to facilitate fully operational installations and modifications covered by this Specification.
In the event that piping, ductwork, equipment, joiner linings, etc., must be temporarily removed to facilitate new or modified work, the Contractor shall subsequently reinstall same in an “as original” condition.
“INTERFERENCE” means that a pipe system, ductwork, equipment, joiner bulkhead or lining, wire way, structural member, access opening, or other object(s), equipment, system, or components that must be removed and reinstalled, relocated, modified, or designed around to facilitate the repair, or installation of new or modified equipment or systems.
“LABOR AND MATERIALS” means labor, material, plant facilities, supervision, services, equipment, and all other resources required to accomplish the specified work.
“MANIFESTS” are the official shipping document forms originated and signed by the generators, transporters, and operators of the hazardous waste disposal facility as required by Federal, State, and Local Authorities.
"MARAD" ‐ Identifies the United States Department of Transportation, Maritime Administration.
"MARAD Approval" indicated only that the general method of construction and detailing is satisfactory and will not relieve the Contractor of the responsibility of any error.
"MARAD COTR" identifies the MARAD Contracting Officer's Technical Representative
"MARAD Representative" identifies the Technical Representative of the Maritime Administration at the Contracting Facility.
“MODIFY” means to provide materials, services, and labor to change or alter the item or system resulting in a finished and fully operational modified installation complete in all respects. The term “MODIFY” implicitly includes all requirements of “REMOVE AND INSTALL”.
“OFE” or “OFM” identify Government Furnished Equipment and Material and are used interchangeably with “GFE” or “GFM”.
“OR EQUAL” means that components or equipment shall be equivalent in terms of performance, services required, compatibility with interrelated systems and arrangements and supportability over the service life of the components or equipment. In the case of component or equipment substitution for those
T.S. State of Michigan 2014 Fall Repair Package
10 6/11/2014 components or equipment noted on the Contract Guidance Drawings or Specification, the Contractor shall submit a written request delineating the design and the performance data on both the specified and substituted piece of equipment for MARAD Surveyor approval and if approved, the Contractor shall take full contractual and technical responsibility for ensuring installation of components or equipment, or both, and compatibility with interrelated systems.
"OWNER" ‐ The U.S. Department of Transportation, Maritime Administration
(MARAD).
"Provide" ‐ To furnish and install all services, materials, equipment and systems to accomplish the specified requirements.
“REFURBISH” means to detach, temporarily remove, disassemble, clean reassemble the unit, equipment, or system using new screws, bolts, gaskets, and replacement parts and to reinstall and test the unit, equipment, or system to demonstrate proper function to the manufacturer’s tolerances. The reinstalled refurbished unit, equipment, or system shall be fully operational and complete in all aspects.
“REGULATORY BODY” or “REGULATORY BODY REQUIREMENTS” mean the American Bureau of Shipping or a Federal or International Regulatory Agency or an organization which is authorized by the agency to perform delegated regulatory functions on its own behalf.
“REINSTALL” means that the Contractor shall provide all material and labor to install a piece of equipment, material or system after the equipment, material or system was temporarily removed, relocated, modified, or refurbished.
“RELOCATE” means to provide all labor, material to detach the unit equipment, or system and to reinstall the same unit, equipment, or system at a new or modified location.
“REMOVE” or “RIP OUT” means to provide all labor and materials to disconnect, detach, and transfer the unit, equipment, materials, and system in its entirety off the ship. All removed materials shall be disposed of in accordance with the MARAD Surveyor’s directions. Part of removal process is to blank openings, remove brackets, hangers, foundations, etc. and to restore all removed items including re‐insulation and paint touch up to “as original” condition.
“REMOVE AND REPLACE INTERFERENCES” shall be construed to mean that the Contractor shall provide all labor, material and equipment necessary to remove, modify if required, material and equipment that cause interference in the way of intended installation, or removal path of an equipment, and replace or reinstall in the “as original” condition. Individual Specification items do not necessarily identify interferences to be resolved. The Contractor shall be totally responsible in the performance of the Specification for the identification and resolution of interferences necessary to complete the work required by this Specification. All open ends left as a result of these removals shall be suitably
T.S. State of Michigan 2014 Fall Repair Package
11 6/11/2014 protected to prevent any and all contaminants from entering the system or piece of equipment.
“RENEW” mean to remove the existing unit, equipment, or systems, including all interferences and to install a new unit, equipment or system which is either identical to or equal to that which was removed; the installation shall include at a minimum all hook‐up, supports, and adapters which are required to effect a fully operational installation complete in all respects.
"Repair" ‐ To fix the existing, thereby restoring it to its original capabilities.
“Retain” ‐ Means to keep and store in a safe environment (on or off the vessel) any material that is to be reused or turned in to the COTR.
“TAG OUT” means a procedure to both notify personnel that tagged‐out equipment, components, or systems are either isolated or not in a normal operating condition, and is done as a means to prevent injury to personnel, improper operation, or damage to a tagged‐out equipment, components or systems.
“TEMPORARY REMOVAL” or “TEMPORARILY MOVE” means to provide all labor and materials to disconnect and remove the unit, equipment or system from its initial location and to reinstall the same unit, equipment, or system whether in the same location or elsewhere on the ship as described in the Specification.
“UPGRADE” means to increase the capability of the item to the current state of practice at the time the work is accomplished.
"Work Item" or "Item" ‐ Means a separately numbered part of the Contract Work Package describing a discrete portion of the work to be accomplished.
"Work Package" ‐ Means the entire written portion of the contract including the contract provisions, and all work items.
T.S. State of Michigan 2014 Fall Repair Package
12 6/11/2014
VESSEL PARTICULARS
NAME: T. S. State of Michigan (ex USNS Persistent)
TYPE: Twin screw diesel‐electric ‐ Training Vessel.
OWNERS: U. S. Government / U.S.DOT Maritime Administration
Official Number: CG003458
USCG Certification: Public Nautical School Ship
Radio Call Sign: NFSJ
ABS Classification A1-E, Ice Strengthened Class "C", AMS, ACCU
ABS I.D. No. 8502561
IMO No. 8835451
Builder: Tacoma Boat Building Co., Tacoma WA.
Keel Laid: October 1984
Commissioned: August 1985
Port of Registry: NORFOLK, VA
Length Overall 224' 00"
Beam: 43' 00"
Design Draft: 15' 01"
Vertical Clearance: 71' 00" (Air Draft)
Deadweight : 2,250 tons
USCG Gross Tonnage: 1,914 tons
USCG Net Tonnage: 574 tons
Cruising Speed: 10 knots
Complement: 47 Officers and Midshipmen
Main Engines: Four (4) Caterpillar D398TA; 970 HP
Main Generators: Four (4) Kato 600 kW, 600 VAC, 3 Phase
T.S. State of Michigan 2014 Fall Repair Package
13 6/11/2014
Propulsion Motors: Two (2) General Electric, 800HP, 750 VDC
Bow Thrusters: Harbormaster 48" tunnel, 550 HP
Diesel Fuel Capacity: 228,615 gallons
Salt Water Ballast Capacity: 146, 642 gallons
Fresh Water Capacity: 5,099 gallons
Radars: 10-cm JRC 3-cm JRC
Gyroscope: Sperry Model – MK-227
Global Position System: Trimble NavTrac GPS
T.S. State of Michigan 2014 Fall Repair Package
14 6/11/2014
Work Item Page Description
Base Items:
01 15‐20 HAZARDOUS WASTE MANAGEMENT
02 18‐20 ENTRY &WORK IN CONFINED, ENCLOSED, & HAZARDOUS
SPACES
03 21‐22 HOUSE KEEPING AND HABITABILITY
04 23‐28 ABS SPECIAL CONTINUOUS MACHINERY SURVEY NO. 6
LABOR
05 29‐33 GENERATOR ENGINE NO. 3 TOP END OVERHAUL
06 34‐35 PROCURE FLEXIBLE STAINLESS STEEL JACKET WATER HOSES FOR
MDG ENGINES #1, 2, AND 3
07 36‐37 SUPPLEMENTAL LABOR
08 38‐39 SUPPLEMENTAL MATERIAL
Optional Items (in order of priority):
09 40‐44 KATO GENERATOR NO. 1 MAINTENANCE AND SERVICE
10 45‐47 A/C UNIT NO. 1 REMOVE ENTIRE UNIT
11 48‐50 REFRIGERATION PACKAGE RELOCATE CHILLERS
12 51‐53 STORES CRANE REPAIR
T.S. State of Michigan 2014 Fall Repair Package
15 6/11/2014
Work Item Number: 01
Title: HAZARDOUS WASTE MANAGEMENT
1.0 ABSTRACT
1.1 This item describes the requirements for the Contractor to handle and/or remove any hazardous wastes generated during the performance of this
Work Package.
2.0 REFERENCES/ENCLOSURES
2.1 Resource Conservation and Recovery Act (RCRA)
2.2 Applicable Hazardous Waste Manifest Form
2.3 Contractor Hazardous Waste Management Plan
3.0 ITEM LOCATION/DESCRIPTION
3.1 Throughout the vessel.
4.0 OWNER FURNISHED EQUIPMENT/MATERIAL/SERVICE
4.1 None.
5.0 STATEMENT OF WORK REQUIRED
5.1 For the purposes of this contract, any chemicals or other hazardous materials removed from the vessel for disposal or requiring clean‐up shall be considered generated by the Contractor. Contractor shall make any necessary allowance for same in the quoted fixed price for each respective item(s), as well as any additional item(s) released as a result of delivery orders. All hazardous material manifests shall show the Contractor as the generator of any such hazardous material being manifested.
5.2 The Contractor shall provide all Safety Data Sheets (SDS) as required for products needed to carry out specified items. Safety Data Sheets are to be made available for inspection by interested parties upon request and one (1) clear copy of each shall be submitted by the Contractor to the MARAD representative at the conclusion of the repair period.
5.3 Identify hazardous waste by methods described in section 5.8 below.
Submit a Hazardous Waste removal report to the MARAD representative
T.S. State of Michigan 2014 Fall Repair Package
16 6/11/2014 no later than twenty‐four (24) hours prior to the removal of hazardous waste. As a minimum, the report shall include the following:
5.3.1 Type of hazardous waste, including sufficient documentation to certify its Status as a hazardous waste.
5.3.2 Quantity of hazardous waste to be removed under this report.
5.3.3 Identification of subcontractors or shipyard departments responsible for removal, transportation, and disposal of the hazardous waste covered under this report.
5.4 Remove, handle, store, transport and dispose of all hazardous waste identified in accordance with all applicable federal, state, and local laws, codes, ordinances and regulations and in accordance with reference 2.3.
5.4.1 Ensure that only haulers registered to perform such
transportation with cognizant Federal, State, and Local Agencies accomplish transportation of hazardous waste.
5.4.2 Transport hazardous waste to a site permitted by cognizant Federal, State, and Local Agencies to accept the identified waste.
5.5 Submit a final hazardous waste report and completed disposal manifest no later than five (5) days after contract completion. The report shall include a summary of the quantity of hazardous waste removed from the vessel during performance of the contract, including breakdown by type and generator assignment. The Contractor shall provide an assignment of his performance with regards to the shipyard's Hazardous Waste Management Plan.
5.6 The Contractor shall be required to submit a Hazardous Waste Management Plan within one (1) week after the award of the contract.
5.6.1 Identify key shipyard personnel and subcontractors associated with removal, handling, and disposal of hazardous wastes. This should include personnel associated with employee training, hazardous waste identification, and manifest documentation and personnel and subcontractors responsible for removing, storing, transporting, recycling, reclaiming, or otherwise disposing of hazardous waste. All permits or other applicable credentials associated with safe and proper disposal of hazardous waste should be included. If a hazardous waste subcontractor is
T.S. State of Michigan 2014 Fall Repair Package
17 6/11/2014 changed for any reason, the Hazardous Waste Management Plan must be amended prior to the commencement of work on the vessel by the new subcontractor.
5.6.2 Identify all local, state, and federal agencies associated with the disposal of hazardous waste.
5.6.3 Outline procedures used by the facility to accomplish removals, handling, segregation, storage, and disposal of hazardous wastes in accordance with local, state, and federal requirements.
5.6.4 Describe all steps to be taken to reduce the volume and toxicity of hazardous waste generated during the performance of this contract.
5.7 Nothing contained in this work item shall relieve the Contractor from complying with applicable Federal, State and Local Laws, Codes, Ordinances and Regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.
5.8 Material is to be determined to be hazardous by: Chemical Analysis; or Reference to the Applicable Material Safety Data Sheet (MSDS); or
Application of inherent knowledge of the hazardous characteristics of the waste in light of the materials or the process used.
6.0 Notes: None
7.0 Deliverables:
7.1 The contractor shall provide the MSDS at the conclusion of repair period.
7.2 The contractor shall provide the Hazardous Waste report no later than 24 hours prior to waste removal.
7.3 The contractor shall provide a copy of the Hazardous Waste Plan within 1 week of award of the contract.
T.S. State of Michigan 2014 Fall Repair Package
18 6/11/2014
7.4 The contractor shall provide a copy of the of the final hazardous waste report and completed disposal manifest no later than five (5) days after contract completion.
7.5 Identify key shipyard personnel and subcontractors associated with removal, handling, and disposal of hazardous wastes.
T.S. State of Michigan 2014 Fall Repair Package
19 6/11/2014
Work Item Number: 02
Title: ENTRY AND WORK IN CONFINED, ENCLOSED, AND HAZARDOUS SPACES
1.0 ABSTRACT
1.1 This item describes requirements for entry and work in confined, enclosed, and hazardous spaces. The contractor shall to obtain required gas free certificates for "safe for workers" and "safe for hot work" from a certified Marine Chemist for all confined, enclosed, and hazardous spaces where entry and/or hot work shall be required. A competent person shall maintain the certificates daily until such entry and hot work is completed.
2.0 REFERENCES/ENCLOSURES:
2.1 NFPA 306, Standard for the Control of Gas Hazards on Vessels.
2.2 NFPA 312, Standard for the Protection of Vessels during
Construction, Repair, and Lay‐up.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Various Locations through‐out the Vessel.
4.0 OWNER FURNISHED EQUIPMENT/MATERIAL/SERVICES
5.1 Contractor shall provide the services of a Certified Marine Chemist to provide all gas free certificates in accordance with the above references.
5.2 Certificates shall be issued only by a Certified Marine Chemist and shall be maintained, on a daily basis, by a "Competent Person" as defined by the OSHA Regulations 29 CFR 1915.14 or NFPA 306.
5.3 Copies of the daily the Marine Chemist, Gas Free Certificate ‘Competent
Person Log to be distributed as follows:
5.3.1 One copy to the MARAD representative.
5.3.2 One copy to the Vessel’s Master
T.S. State of Michigan 2014 Fall Repair Package
20 6/11/2014
5.3.3 One copy to the shipyard’s safety person.
5.3.4 Additional copy(s) to be displayed on the top of the gangway(s) as well as in the vicinity of the gas freed space(s).
5.4 Contractor shall provide and maintain ventilation to confined spaces as required by the Marine Chemist, Gas Free Certificate ‘Competent Person Log to ensure the safety of personnel during work and inspections of confined spaces.
6.0 NOTES: None
7.0 DELIVERABLES:
7.1 One copy of Marine Chemist, Gas Free Certificate ‘Competent Person Log to be provided daily to the MARAD Representative and an additional copy to the vessel’s Master.
T.S. State of Michigan 2014 Fall Repair Package
Work Item Number: 03
Title: HOUSEKEEPING & HABITABILITY
1.0 ABSTRACT
1.1 This item describes housekeeping requirements to maintain cleanliness of the vessel throughout the availability.
2.0 REFERENCES/ENCLOSURES
2.1 None.
3.0 ITEM LOCATION/DESCRIPTION
3.1 Various Locations through‐out the Vessel.
4.0 OWNER FURNISHED EQUIPMENT/MATERIAL/SERVICES
5.1 Housekeeping
5.1.1.1 Vessel is currently in a clean and orderly condition in way of living spaces, machinery spaces and cargo holds. A joint inspection of all spaces will be carried out upon commencement of the repair period at the Texas A&M University Maritime Academy Dock Facility with the Contractor and the MARAD representative. The contractor shall note the condition of the vessel in writing. It will be the Contractor's responsibility to maintain cleanliness of all areas on a daily basis throughout the repair period, conducting cleaning as well as the removal and disposal of all debris generated as a result of work contained herein. Upon completion of all work under this contract a final joint inspection of all spaces will be carried out to ensure the cleanliness of the vessel at the time of Contractor completion. Any discrepancies noted in this final survey are to be corrected by Contractor at the Contractor's expense.
5.1.1.2 The Contractor shall place trash containers in strategic areas on board the vessel to receive and retain all waste material generated by Contractor and Owner's activities throughout the contract period.
Containers are to be checked on a daily basis and emptied as necessary so trash does not accumulate.
T.S. State of Michigan 2014 Fall Repair Package
5.2 Deck Protection
5.2.1.1 It shall be understood that all accommodation spaces, including but not limited to, the passageways, staterooms, lounges and dining rooms, are off limits to Contractor personnel unless access is necessary to conduct business or work.
5.2.1.2 Contractor is to provide and install protective floor coverings to areas subject to heavy traffic during the course of the contract. Covering shall be New Pig Corporation MAT607 or equal. The contractor shall repair all damage to flooring resulting from the contractor’s work prior to delivery of the vessel.
5.3 Sanitary Facilities
5.3.1 It shall be understood that all shipboard toilet and shower spaces are off limits to Contractor personnel. The Contractor shall provide and install signs to this effect.
5.3.2 Any contamination of shipboard facilities by Contractor personnel shall be cleaned and restored at the Contractor's expense.
5.3.3 The Contractor shall provide portable toilet facilities adjacent to the ship for use by Contractor personnel. The Contractor shall provide janitorial services to maintain cleanliness of toilet facilities on a daily basis.
5.4 Bilges: The Contractor shall maintain the bilges in a clean, dry, and safe condition at all times during the contract. The contractor shall dispose of all bilge waste generated by the contractor as part of this contract to the contractors account.
The Contractor shall not use the vessel systems to pump or clean the bilges.
6.0 Notes: None
7.0 DELIVERABLES:
7.1 Contractor to provide the MARAD Representative copies of all disposal manifests and record of total gallons of bilge/slop waste removed from the vessel.
T.S. State of Michigan 2014 Fall Repair Package
Work Item Number: 04
Title: ABS Special Continuous Machinery Survey #6 ‐Labor
1.0. ABSTRACT:
The intent of this item is to define the requirements for the contractor to perform the
‘ABS Special Continuous Machinery Survey #6 required’ inspections, servicing, testing, and renewal of expired items required, to prove functional operation, reliability, satisfactory material condition and summit Service Reports for supporting documentation for presentation to the attending ABS Surveyor.
2.0. REFERENCES / ENCLOSURES:
2.1. Manufacturers’ Installation, Operation, and Maintenance Manual(s)
2.2. ABS Classification Certificate
2.3. ABS Rules for Survey after Construction 2014, Part 7, Chapter 6, Section 2‐ 3
‘Special Periodical Surveys – Machinery’
2.4. CFR PARTS 110, 111, 112, Subchapter J (Electrical)
2.5. IEEE Standard 45 (Guide to Electrical Installations on Shipboard)
2.6. ABS Survey Manager Survey Status Report
3.0 ITEM LOCATION / DESCRIPTION:
3.1. Location: Thru‐out the vessel, primarily in the Main Diesel Generator Room
3.2. Access / Interference: As encountered
3.3. Quantity: Sixteen (16) Separate Systems
4.0. GOVERNMENT FURNISHED EQUIPMENT / MATERIAL:
4.1. None
5.0. CONTRACTOR FURNISHED EQUIPMENT / MATERIAL:
5.1. Contractor will furnish all labor, materials and consumables to complete the scope of work required in this specification.
6.0. STATEMENT OF WORK:
T.S. State of Michigan 2014 Fall Repair Package
Note:
OEM or OEM Certified Technical Representatives
6.1. In Accordance with ABS Rules for Survey after Construction 2014, Part 7, Chapter
6, Section 2‐ 3 ‘Special Periodical Surveys – Machinery’, the OEM or OEM
Certified Technical Representatives are, to open as required all equipment by the
ABS Surveyor, for inspections. OEM or OEM Certified Technical Representatives are to perform all servicing, testing, and renewal of expired items as required, to prove functional operation, reliability, and satisfactory material condition, for each of the following Systems and/or Equipment, and summit Service Reports for supporting documentation for presentation to the attending ABS Surveyor.
6.2. Prior to any work, contractor will electrically disconnect affected circuit(s), using lock out / tag out procedures to secure electrical power on any piece of equipment or system listed under this scope of work. To be coordinated with vessel’s Chief Engineer.
6.3. Contractor to follow OEM Maintenance / Overhaul Guidelines, Procedures and
Specifications and use OEM supplied renewal parts.
6.4. Prior to disassembly of the generators, megger readings shall be taken and recorded. Provide a typewritten report to MARAD COTR.
6.5. Upon completion of all work and testing, contractor shall clean all work sites to as original condition.
6.6. The contractor will maintain a clean and safe work environment at all times.
Care shall be taken not to allow any debris to fall into open Generators.
6.7 Contractor shall provide services of factory authorized Kato Engineering
Technical Representative.
6.8. The Contractor shall provide all labor, materials, and tools to accomplish all work as delineated by this specification item.
A. Compressed Air System‐ (page 12 of 23 (ABS Survey Manager Survey
Status).
T.S. State of Michigan 2014 Fall Repair Package
Compressed Air piping
Service Air Tank(s) ‐02 Deck Fwd & Motor Room ‐ (2 each with);
Tank relief valve
Tank relief valve – operational test
B. Cooling System – (page 12 of 23 (ABS Survey Manager Survey Status).
Jacket water Cooling Pump No. 1, Stbd Inbd
Jacket water Cooling Pump No.2, Port Inbd
Jacket water Cooling Pump No.3, Stbd Otbd
Jacket water Cooling Pump No.4, Port Otbd
C. Electric Propulsion System ‐ (page 12 & 13 of 23 (ABS Survey Manager
Survey Status).
Prior to operation of any electrical unit/circuit, contractor will perform a contact resistance test with a Low‐Resistance Ohmmeter, prior to operation. Proper contact resistance should be about 50 Micro‐Ohms.
DO NOT OPERATE IF OHMS ARE OUT OF RANGE!!!
Section ‘C’ Main Propulsion ‘Generator’ No. 1, Stbd Inboard
Maintenance & Service to be completed under S.R. # 0700491
(Megger Readings)
Main Propulsion Generator No. 1, Stbd Inboard
Main Propulsion Generator No. 2, Port Inboard
Main Propulsion Generator No. 3, Stbd Outboard
Main Propulsion Generator No. 4, Stbd Outboard
(Operational Test)
Main Propulsion Generator No. 1, Stbd Inboard
Main Propulsion Generator No. 2, Port Inboard
Main Propulsion Generator No. 3, Stbd Outboard
Main Propulsion Generator No. 4, Stbd Outboard
Electric Cables
(Reverse Power Protection)
Generator Trip – Port Inbd
Generator Trip – Port Otbd
T.S. State of Michigan 2014 Fall Repair Package
Generator Trip – Stbd Inbd
Generator Trip – Stbd Otbd
(Under Voltage Protection)
Generator Trip – Port Inbd
Generator Trip – Port Otbd
Generator Trip – Stbd Inbd
Generator Trip – Stbd Otbd
D. Emergency Power Distribution System ‐ (page 15 of 23 (ABS Survey
Manager Survey Status).
Emergency Generator – Megger Reading
Emergency Generator – Operational Test
Emergency Generator – Engine With attachments
E. Fire Main System ‐ (page 15 of 23 (ABS Survey Manager Survey Status).
Fire Main Piping
F. Fresh Water Cooling System ‐ (page 15 of 23 (ABS Survey Manager
Main Fresh Water Circulating Pump No.1, Stbd Inbd
Main Fresh Water Circulating Pump No.2, Port Inbd
Main Fresh Water Circulating Pump No.3, Stbd Otbd
Main Fresh Water Circulating Pump No.4, Port Otbd
G. Fuel Oil Service System ‐ (page 15 of 23 (ABS Survey Manager Survey
Fuel Oil Service Piping
H. Fuel Oil Service System ‐ (page 16 of 23 (ABS Survey Manager Survey
I. Fuel Oil Storage & Transfer System ‐ (page 16 of 23 (ABS Survey Manager
Fuel Oil Storage & Transfer Piping
Fuel Oil Transfer Pump
Fuel Oil Purifier
T.S. State of Michigan 2014 Fall Repair Package
J. Lubricating Oil Service System ‐ (page 16 of 23 (ABS Survey Manager
Lube Oil Pump Port Inbd
Lube Oil Pump Port Otbd
Lube Oil Pump Stbd Inbd
Lube Oil Pump Stbd Otbd
Lube Oil Service Pump No.1‐Propulsion Motor
Lube Oil Service Pump No.2‐Propulsion Motor
Lube Oil Service Piping
Main Lube Oil Cooler Port Inbd
Main Lube Oil Cooler Port Otbd
Main Lube Oil Cooler Stbd Inbd
Main Lube Oil Cooler Stbd Otbd
K. Lubricating Oil Storage & Transfer System ‐ (page 16 of 23 (ABS Survey
Manager Survey Status).
Lube Oil Transfer Pump
Lubricating Oil Storage & Transfer Piping
L. Main Propulsion System ‐ (page 16 of 23 (ABS Survey Manager Survey
Line Shaft Bearings Port
Line Shaft Bearings Stbd
Line Shafting Port
Line Shafting Stbd
Main Motor No.1 – Port
Main Motor No.2 – Stbd
Main Thrust Bearing ‐ Port
Main Thrust Bearing‐Stbd
Main Thrust Shaft‐Port
Main Thrust Shaft‐Stbd
M. Mooring System ‐ (page 16 of 23 (ABS Survey Manager Survey Status).
Mooring System – Operational Test
Anchor Windlass (And Auxiliaries)
N. Sanitary Water System ‐ (page 16 of 23 (ABS Survey Manager Survey
T.S. State of Michigan 2014 Fall Repair Package
Sea Water Cooling System
Air Coolers Circulating Pump‐ Main Motors
Sea Water Piping
O. Starting Air System ‐ (page 16 & 17 of 23 (ABS Survey Manager Survey
Staring Air Piping
Starting Air Tank No. 1‐Stbd
Starting Air Tank‐Relief Valve No. 1
Starting Air Tank‐Relief Valve No. 1
Operational Test
Starting Air Tank No. 2‐Stbd
Starting Air Tank‐Relief Valve No. 2
Starting Air Tank‐Relief Valve No. 2
Operational Test
7.0. QUALITY ASSURANCE:
7.1. All material procedures and/or items used or renewed are to be type approved by the ABS or USCG and in compliance with ABS Rules and USCG Regulations.
T.S. State of Michigan 2014 Fall Repair Package
Work Item Number: 05
Title: Generator Engine No.3 Top End Overhaul
The intent of this item is to define the requirements for the contractor to perform the
Generator Engine No.3, (S/N 035Z00950), Top End Overhaul’ in conjunction with the
‘ABS Special Continuous Machinery Survey #6, required’ inspections, servicing, testing, and renewal of expired items required, to prove functional operation, reliability, satisfactory material condition, and summit Service Reports for supporting documentation for presentation to the attending ABS Surveyor.
2.1. Caterpillar Tech Manual T6270‐AB‐MMC‐010, Model D‐398 TAABS
2.2. ABS Rules for Survey after Construction 2014, Part 7,
2.3. ABS Survey Manager Survey Status Report
3.1. Location: Main Diesel Generator Room
3.3. Quantity: One (1) Caterpillar Engine: Model ‐D398, Serial #035Z00950
5.1. Contractor will furnish all labor, materials, tools, and consumables to complete the scope of work required in this specification.
OEM or OEM Certified Technical Representatives, (Caterpillar Factory Authorized
RepairFacility)
T.S. State of Michigan 2014 Fall Repair Package
6.1. OEM or OEM Certified Technical Representatives, to perform the Generator
Engine No.3, (S/N 035Z00950), Top End Overhaul’ in conjunction with the ‘ABS
Special Continuous Machinery Survey #6, testing, and renewal of expired items as required, to prove functional operation, reliability, and satisfactory material condition, and summit Service Reports for supporting documentation for presentation to the attending ABS Surveyor.
6.2. Prior to any work, contractor will electrically disconnect affected Generator
Engine No.3 circuit(s), using lock out / tag out procedures to secure electrical power. To be coordinated with vessel’s Chief Engineer.
6.2.1. Generator overhaul shall be worked in conjunction with engine overhaul
6.2.2. GLMA will make arrangements for ABS inspection. Generators will not be closed until the units have been inspected by ABS and Chief Engineer.
Contractor shall provide a 48‐hour notice to GLMA so that arrangements can be made with ABS to attend the vessel.
6.2.3. Any and all new work, not addressed by…