Statement_of_Work.docx
DOCX document 126 KB Posted
- Attached to
- T. S. KENNEDY ABS SPECIAL SURVEY- MACHINERY
- Solicitation number
- DTMA92Q1500043
About this file
STATEMENT OF WORK
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DTMA92Q1500043-0001.pdf | ||
| DTMA92Q1500043_Quote_Sheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF TRANSPORTATION
STATEMENT OF WORK (SOW)
U.S. DOT - MARITIME ADMINISTRATIONTRAINING SHIP “KENNEDY” ABS SPECIAL SURVEY- MACHINERY
7/27/2015
The purpose of the below Statement of work it for the contractor to provide all labor and materials necessary to accomplish a special survey of the main propulsion machinery to the satisfaction of the attending ABS surveyor.
Table of Contents
| GENERAL PROVISIONS | 4 | |
| ABBREVIATIONS/DEFINITIONS | 4 | |
| EXPANDED DEFINITIONS | 7 | |
| SOLE SOURCE/BID SUBSTITUTIONS | 8 | |
| CONFLICTS - SPECIFICATIONS/DRAWINGS | 8 | |
| INTENT AND GENERAL SPECIFICATION REQUIREMENTS | 8 | |
| GENERAL VESSEL DESCRIPTION | 9 | |
| DRAWING, CORRESPONDENCE, AND COMMUNICATION PROCEDURES | 11 | |
| LAWS, CLASSIFICATION, RULES, REGULATIONS, STANDARDS, CERTIFICATES | 11 | |
| PROGRESS MEETINGS AND PROGRESS REPORT | 12 | |
| CONTRACT AND GUIDANCE DRAWINGS | 12 | |
| HEADROOM | 13 | |
| ACCESS & MAINTENANCE REQUIREMENTS | 13 | |
| ASBESTOS /VENDORS /SUBCONTRACTORS | 13 | |
| ACCESS TO YARD/VESSEL/DOCUMENTS (IF APPLICABLE) | 13 | |
| INSPECTIONS | 14 | |
| PROSECUTION OF WORK | 15 | |
| GANTT CHART | 16 | |
| CRITICAL PATH METHOD (CPM) SCHEDULE | 16 | |
| PROGRESS REVIEW MEETINGS | 17 | |
| GUARANTEES | 17 | |
| MATERIALS AND WORKMANSHIP | 17 | |
| CONTRACTOR'S OBLIGATION | 18 | |
| HULL PROTECTION | 18 | |
| GENERAL INFORMATION | 18 | |
| CLIN000 1 | BILGE PUMP (ABS) | 20 |
| CLIN000 2 | #1 AND #2 MAIN FEED PUMPS (ABS) | 21 |
| CLIN000 3 | FEED HEATER FIRST STAGE (ABS) | 22 |
| CLIN000 4 | #1 & #2 AUXILIARY CONENSERS (ABS) | 23 |
| CLIN000 5 | GLAND EXHAUST CONDENSER (ABS) | 24 |
| CLIN000 6 | MAIN AIR EJECTOR (ABS) | 25 |
| CLIN000 7 | FUEL OIL SERVICE PUMP (ABS) | 26 |
| CLIN000 8 | FUEL OIL TRANSFER PUMP (ABS) | 27 |
| CLIN000 9 | LUBE OIL SERVICE PUMP (ABS) | 28 |
| CLIN00 10 | #1 and #2 MAIN CONDENSATE PUMPS (ABS) | 29 |
| CLIN00 11 | INSULATION RESISTANCE READINGS of MOTORS (ABS/USCG) | 30 |
| CLIN00 12 | H.P. & L.P. FLEXIBLE COUPLINGS (ABS) | 33 |
| CLIN00 13 | MAIN THRUST BEARING (ABS) | 34 |
| CLIN00 14 | MAIN UNIT LOW PRESSURE TURBINE (ABS) | 35 |
| CLIN00 15 | MAIN UNIT HIGH PRESSURE TURBINE (ABS) | 37 |
| CLIN00 16 | MAIN REDUCTION GEARS (ABS) | 38 |
| CLIN00 17 | MANEAUVERING VALVES (ABS) | 39 |
| CLIN00 18 | OPERATING GOVERNOR (ABS) | 40 |
| CLIN00 19 | MAIN LUBE OIL COOLERS (ABS) | 41 |
| CLIN00 20 | #1 & #2 GENERATOR ELECTRICAL END (ABS) | 42 |
| CLIN00 21 | #1 & #2 SSTG INSPECTION (ABS/USCG) | 43 |
| CLIN00 22 | STEERING GEAR | 44 |
| CLIN00 23 | SUPPLEMENTAL LABOR | 45 |
| CLIN00 24 | SUPPLEMENTAL MATERIAL | 45 |
GENERAL PROVISIONS
Note: This GENERAL section applies to all ITEMS within this SOW and therefore is Not Separately Priced. To the extent that efforts to comply with the requirements stated in this GENERAL section present a cost impact, the cost is to be allocated to the priced ITEMS
ABBREVIATIONS/DEFINITIONS
As used throughout this statement of work, the following terms and abbreviations shall have the meaning stated:
ABS American Bureau of Shipping
ANSI American National Standards Institute
ASME American Society of Mechanical Engineers
CFR Code of Federal Regulations substitute for (USCG Requirements)
CONTRACTOR Contractor (same as YARD or SHIPYARD if applicable)
CONTRACT Construction Contract between the Owner and the Contractor including these Specifications and the accompanying Contract Drawings. These Specifications are "senior" to Drawings in cases of potential conflict.
CRES Stainless steel (Grade should be specified)
COR Contracting Officer's Representative is responsible for monitoring the contractor's progress in fulfilling the technical requirements specified in the contract. The COR ensures that all required documentation and data are submitted in accordance with the procurement deliverable schedule. Should the contractor fail to fulfill the contractual requirements, the COR must inform the contractor of such failure. The COR informs the contracting officer of any technical or contractual problems or delays. The COR maintains administration records, approves invoices and performs final inspection and acceptance of work performed under the contract. The COR is not authorized to make any commitments or obligations on behalf of the government. The COR may not grant the contractor permission to deviate from the requirements stated in the contract, nor direct the contractor to perform any work outside that stated in the contract.
DWG or DWGS Contract Drawing or Drawings
EOS Engineer's Operating Station
GF Government Furnished
GFE Government Furnished Equipment
LT Long Ton (2240 LBS) All weights in this Specification are expressed in LT or pounds
MARAD Maritime Administration, U.S. Department of Transportation
MAY This word, or the adjective "OPTIONAL", mean that an item is truly optional. One vendor may choose to include the item because a particular marketplace requires it or because the vendor feels that it enhances the product while another vendor may omit the same item.
MUST This word, or the terms "REQUIRED" or "SHALL", mean that the definition is an absolute requirement of the specification.
MUST NOT This phrase, or the phrase "SHALL NOT", mean that the definition is an absolute prohibition of the specification.
OWNER U.S. Department of Transportation Maritime Administration West Building 1200 New Jersey Avenue, SE Washington, DC 20590
QA Quality Assurance
SEAL WELD Structure which is double continuously welded.
SHOULD This word, or the adjective "RECOMMENDED", mean that there may exist valid reasons in particular circumstances to ignore a particular item, but the full implications must be understood and carefully weighed before choosing a different course.
SHOULD NOT This phrase, or the phrase "NOT RECOMMENDED" mean that there may exist valid reasons in particular circumstances when the particular behavior is acceptable or even useful, but the full implications should be understood and the case carefully weighed before implementing any behavior described with this label.
SPECIFICATION The specification is an explicit set of requirements to be satisfied by a material, product, or service.
STATEMENT OF WORK (SOW)
A statement of work (SOW) is a formal document that captures and defines the work activities, deliverables and timeline a Contractor will execute against in performance of specified work for the OWNER. In this document the Specification is generally synonymous with the words statement of work (SOW)
USCG (CG) United States Coast Guard
VESSEL T/S Kennedy
YARD Contracting Shipyard as applicable (same as CONTRACTOR)
EXPANDED DEFINITIONS
GOVERNMENT FURNISHED
All equipment herein specified as GOVERNMENT FURNISHED (GF) or GOVERNMENT FURNISHED EQUIPMENT (GFE) is to be installed by the CONTRACTOR in such condition that it is completely serviceable under normal conditions of vessel operations. Such installations are to adhere to all applicable specifications of Regulatory Agencies and are to be to the satisfaction of the COR. This includes, but is not limited to, the following:
| 1. | Time and materials for assembly. |
| 2. | Time and materials for positioning and proper securing |
| 3. | Time and materials for connections of piping, wiring, etc. |
| 4. | Time and materials for operational testing |
All equipment, which is not herein, specified as either GOVERMENR FURNISHED (GF) or EXISTING shall be provided and installed as detailed above by the CONTRACTOR (CONTRACTOR).
CONTRACTING OFFICER'S REPRESENTATIVE (COR)
Contracting Officer's Technical Representative is responsible for monitoring the contractor's progress in fulfilling the technical requirements specified in the contract. The COR ensures that all required documentation and data are submitted in accordance with the procurement deliverable schedule. Should the contractor fail to fulfill the contractual requirements, the COR must inform the contractor of such failure. The COR informs the contracting officer of any technical or contractual problems or delays. The COR maintains administration records, approves invoices and performs final inspection and acceptance of work performed under the contract. The COR is not authorized to make any commitments or obligations on behalf of the government. The COR may not grant the contractor permission to deviate from the requirements stated in the contract, nor direct the contractor to perform any work outside that stated in the contract.
GOOD SHIPBUILDING PRACTICE
The term "good shipbuilding practice" means construction practices, which are in accordance with soundly engineered and approved processes. These processes are to meet the requirements contained within this document of SPECIFICATIONS. Construction and testing shall conform to regulatory agency and industry accepted standards so as to ensure that the vessel will meet the general and particular design requirements.
QUALITY ASSURANCE
Inspections by the COR are for the purpose of verifying the CONTRACTOR’s Quality Assurance Program. COR inspections are not to be used as a substitute for in-process control of quality by the CONTRACTOR.
SOLE SOURCE/BID SUBSTITUTIONS
It is not necessary to offer all material and equipment as "sole source" unless expressly stated in these Specifications. The CONTRACTOR will be permitted to submit bids containing substitutions as long as such substitutions are clearly stated and detailed. Any bid substitution must be equal to the specified model, must be sufficiently documented to prove equality, and must meet the performance requirements of the vessel.
The CONTRACTOR is responsible for all additional costs associated with proposed substitutions including, but not limited to, required engineering expenses. In this regard, the specifications herein are guidelines for minimum performance requirements. If those specifications are not offered by a particular manufacturer, product, or model, the CONTRACTOR will be expected to include a separate list of all discrepancies. Substituted manufacturers, products, or models will not be considered unless they have been demonstrated to be equal to or exceeding the quality, durability and design and the minimum performance functions of the specified equipment. Any proposed substitution must conform substantially to the specified requirements for the machinery and/or equipment.
CONFLICTS - SPECIFICATIONS/DRAWINGS
Where Specifications and Drawings are not in agreement, it is the responsibility of the CONTRACTOR to notify the COR in writing that such a disagreement does exist and request resolution of same. Generally, the Specifications are to be considered senior to the Contract Drawings; however, there may be instances where, by mutual agreement, this priority may be reversed. Written notification, therefore, is essential and required.
INTENT AND GENERAL SPECIFICATION REQUIREMENTS
GENERAL
The primary purpose of this Statement of Work (SOW) is to accomplish the following:
· For the contractor to provide all labor and materials necessary to accomplish a special survey of the main propulsion machinery to the satisfaction of the attending ABS surveyor.
· An ABS Special Periodical Survey #9-Machinery for a Non-ESP Cargo Ship (non-tanker, which is greater than 15 years of age)
ERRORS/OMISSIONS
In the event that there are found to be errors or omissions in these Specifications or in the accompanying Drawings that would have an adverse effect upon the completion of this contract and/or delivery to the OWNER of a product that is complete, functional, and seaworthy, the CONTRACTOR shall call attention to such errors or omissions in his bid package.
Minor design errors or omissions shall be properly addressed by the CONTRACTOR in the normal course of the contract performance. Major design errors or omissions shall be resolved by Change Orders.
SPECIFICATIONS IN EXCESS
Although the Drawings & Specifications contemplate a project, which will be completed in accordance with the requirements of the several regulatory bodies referred to herein, in certain respects the Contract Drawings and Specifications may be in excess of such requirements and must not be changed except on written approval of the OWNER.
If the CONTRACTOR is of the opinion that any aspect of the Contract Drawings and Specifications are so stringent, that his Company is unwilling or incapable of completing the Project within those parameters; it is the CONTRACTOR's obligation to provide written notification of such a conflict to the OWNER in his bid package. If such notification is not included with the bid package, it is held that the CONTRACTOR agrees with and will complete the project in compliance with the specifications as set forth.
MANUFACTURER'S REPS
Whether or not it is specifically stated in these Specifications, when it is required by the equipment manufacturer or by the specialized technical nature of the installation, and/or when work is outside the normal scope of the CONTRACTOR work force, the CONTRACTOR is to provide the services of Manufacturers' Reps for such assistance and expertise as is required for the proper installation, on-line testing, calibration, adjustments, etc. of CONTRACTOR Furnished and GF equipment.
CERTIFICATION/DOCUMENTATION
The CONTRACTOR shall, in a timely manner, provide the OWNER with information and certifications as may be required for the re-documentation and re-certification of the vessel.
The latest amendments to all laws, regulations, rules and conventions, which are in force at the time of Bid Closing, are to be considered as part of the CONTRACT. Any amendment to such requirements or any new laws, regulations, rules or conventions that come into force after Bid Closing, shall be treated as a change to the CONTRACT if not otherwise covered by these Specifications and Drawings.
GENERAL VESSEL DESCRIPTION
The TS Kennedy is a U.S. Government owned “Public Nautical School Ship” provided to the Massachusetts Maritime Academy for the purpose of training young men and women for a career in the U.S. Maritime Industry.
Name/ KENNEDY Primary VIN/ 509652 Call/ KVMU Flag/ US
| Alt VIN's |
| Type |
| 509652 |
| Official Number (U.S.) |
| 6621662 |
| IMO Number |
| 6704200 |
| ABS Number |
| 1069 |
| Hull Number |
| 338919000 |
| MMSI Number |
| 11270 |
| GMDSS |
| a. Length overall | 536 ft-11 in | |||
| b. Breadth, molded | 76 ft 0 in | |||
| c. Depth, molded | 42 ft-6 in | |||
| d. Full Load Draft | 28 ft-6 in | |||
| e. Propulsion Plant | Steam Geared Turbines | |||
| f. Propulsion Rated BHP, Normal | 12,500 | |||
| g. Propulsion Rated BHP, Maximum | 15,500 | |||
| h. Fuel Consumption, Max Power | 594 Bbl/Day | |||
| i. Fuel Consumption, Normal Power | 490 Bbl/Day | |||
| j. Fuel Consumption, In Port | 40 Bbl/Day | |||
| k. Trial Speed, Normal HP @ 29’0” Draft | 20 Kts | |||
| l. Cruising Radius @ 20 Kts | 10,000 N. M. | |||
| m. Light Ship Weight: | 12,891.54 LT | |||
| n. With fixed ballast | 12,891.54 LT | |||
| o. Without fixed ballast | 8,540.29 LT | |||
| p. U.S. Gross Tonnage | 13,886 LT | |||
| q. U.S. Net Tonnage | 4,165 LT | |||
| r. Displacement, Full Load | 18,550.49 LT | |||
| s. Deadweight | 1,431 LT | |||
| t. Classification | ABS/USCG (Subchapter R) IMO & |
SOLAS
u. Class notation Unrestricted service, A1 E, AMS, and applicable Passenger Vessel Rules
| v. Fuel Oil Storage Capacity, 98% Full | 11793.95 Bbls | |||
| w. Fuel Oil Settling Capacity, 98% Full | 1472.72 Bbls | |||
| x. Diesel Oil – Emergency Generator Tank | 896 Gallons | |||
| y. Fresh Water, 100% Full | 31731 Gallons | |||
| z. Distilled Water, 100% Full | 5730 Gallons | |||
| aa. Reserve Feed Water | 38896 Gallons | |||
| ab. Lube Oil – Gravity, 100% | 1234 Gallons | |||
| ac. Lube Oil – Storage, 100% | 1314 Gallons | |||
| ad. SW Clean Ballast, 100% Full | 998.36 Tons | |||
| ae. Permanent Fixed Ballast | 3546 LT | |||
| af. Liquid Mud Fixed Ballast, 100% Full | 873.3 LT | |||
| ag. Heavy Fuel Oil (for Aux Diesel Gen) | 4036 Gallons | |||
| ah. Diesel Oil (for Aux Diesel Gen) | 971 Gallons | |||
| ai. Clean Lube Oil (for Aux Diesel Gen) | 207 Gallons | |||
| aj. Sludge/Dirty Oil (for Aux Diesel Gen) | 412 Gallons |
DRAWING, CORRESPONDENCE, AND COMMUNICATION PROCEDURES
The CONTRACTOR shall provide the COR with a copy of all correspondence relating to this vessel conversion, which the CONTRACTOR has with Regulatory Bodies, in particular, the ABS or USCG (MSC) Washington and the Local OCMI.
The CONTRACTOR shall invite the COR to be present during all discussions relating to this vessel, which he may have with the Representatives of Regulatory Bodies, in particular, with the Local ABS representative, OCMI or representatives of those offices.
These documents and discussions may include, but are not limited to, the design, construction of modules, ripouts, and relocations, installation of equipment and machinery, testing, sea trials, delivery, and operation of the vessel.
LAWS, CLASSIFICATION, RULES, REGULATIONS, STANDARDS, CERTIFICATES
COMPLIANCE
The vessel, as delivered, shall comply with the requirements of relevant State and Federal Regulatory Agencies. These shall include:
· USCG: 46 CFR Subchapter “R” PART 167—PUBLIC NAUTICAL SCHOOL SHIPS.
· USPHS: Publication No.393, "Handbook on Sanitation of Vessel Construction"
· USCG: "International Rules of the Road"
· Institute of Electrical & Electronics Engineers Standards #45
· Federal Communications Commission
· Classification: ABS/USCG (Subchapter R) IMO & SOLAS
· Class notation: Unrestricted service, A1 E, AMS, and applicable Passenger Vessel
DOCUMENTATION
All necessary certifications and/or documents covering the approval of and indicating compliance with subject regulations shall be obtained by the CONTRACTOR and supplied to the OWNER.
SUBSEQUENT REGULATORY CHANGES
| IF: | CONTRACT changes are required by modifications or additions to the Laws or Regulations of the Commonwealth of Massachusetts, the United States, the Regulatory Agencies listed in 1.9.1, or any governmental body or board thereafter organized or created; |
| AND: | Such changes require an increase or decrease in the cost of the vessel, and occur within a period of 30 days following the Bid Opening; |
| THEN: | It is agreed by the CONTRACTOR and OWNER to re-negotiate the CONTRACT PRICE and/or DELIVERY DATE in light of such changes. |
PROGRESS MEETINGS AND PROGRESS REPORT
A weekly progress meeting shall be attended by the Contractor, COR and the ship’s Captain/Chief Engineer/Chief Mate to discuss individual ITEM and Delivery Order progress. A Progress Report shall be delivered to the COR one day prior to the progress meeting. This report shall list each contract ITEM and Delivery Order, their awarded dollar value, the Contractor’s estimate of their percent completion, and the resulting earned value (which will be the awarded amount x the percent completion). This Progress Report shall be examined by the COR along with the Contractor’s Production Chart. A percent completion shall be negotiated and the report signed for by both parties. This document shall be the ONLY document requiring signature of the COR. In order to avoid conflicting and/or erroneous information, NO OTHER document delivered to the COR (such as a condition report) which makes a statement regarding ITEM and/or Delivery Order progress and/or percent completion shall be signed as being agreed to by the COR.
CONTRACT AND GUIDANCE DRAWINGS
GENERAL
The Contractor shall submit DWGS, permits or other correspondence required by regulation for review and approval. Submittals will commence upon signing a Contract with the successful bidder. The Contractor is tasked to keep the Owner and the operator apprised of the status of such submittals.
EXISTING VESSEL INFORMATIONAL DRAWINGS
Existing vessel informational drawings are available from the Chief Engineer, and should be requested in writing if required. It should be understood that the vessel has been in service for a number of years and had a number of conversions; therefore, interested bidders should be cautioned that the accuracy of the existing vessel drawings cannot be verified, and bidders should be specific about what information they are seeking from the existing drawings. Requested drawings will be forward to all interested bidders upon request. Drawings will be provided in electronic format when available. The OWNER does not warrant the accuracy of these plans and requires the CONTRACTOR to verify by physical ship check any and all of the existing plans prior to submitting their bid.
INTERFERENCES/ACCESS
The elimination of all equipment interferences; and the location or relocation of machinery, pumps, piping, wiring, ductwork and misc. equipment so that proper access for operation and maintenance can be readily achieved is the CONTRACTOR responsibility. It is essential that the CONTRACTOR is aware of his obligation in this regard. The CONTRACTOR is responsible to see that ALL INSTALLATIONS are arranged, constructed, and/or relocated in "good shipbuilding practice" and that they adhere to the requirements of the CFR. The CONTRACTOR and the COR are mutually responsible for the maintenance of ongoing communications, inspections, and approvals as construction progresses.
HEADROOM
Clear headroom in accommodations, working spaces, public spaces, passageways, and toilet and shower spaces shall be as high as possible but shall not be less than 7 feet 0 inches. Clear headroom under local points such as ducts, piping, lights, girders, etc. shall not be less than 6 feet 8 inches in the above spaces and will be the subject of individual, case by case, written approval from the COR. In way of double berths, clear headroom (ceiling height) shall be not less than 7 feet 0 inches above the finished deck.
ACCESS & MAINTENANCE REQUIREMENTS
GENERAL
The structure and layout of any added machinery and equipment shall be designed and constructed to permit ready access to all parts for operation, inspection, maintenance and repair without removal or disturbance of other structure or equipment. Ladders, doors, manholes, scuttles, bolted plates, etc. shall be provided as required for access. If conversion structure or installations affect access to existing machinery and equipment, satisfactory steps shall be taken to re-route reasonable access.
ASBESTOS /VENDORS /SUBCONTRACTORS
ASBESTOS ABATEMENT
The CONTRACTOR shall, as part of this Contract, remove and dispose of all asbestos removed or disturbed for the performance of this contract. In addition, CONTRACTOR shall comply with the most current edition of all federal, state, county, and city codes and ordinances as they apply to the location(s) in which the work is performed.
Note: The OWNER hereby informs the CONTRACTOR that the existing vessel does contain asbestos and that the CONTRACTOR is specifically required to provide certification that the CONTRACTOR is a certified asbestos abatement contractor or that the CONTRACTOR has engaged a certified asbestos abatement subcontractor.
VENDOR LISTING
The CONTRACTOR shall provide the COR with a listing of major Vendors and Subcontractors being employed on the contract. The list shall include name; address; telephone and fax numbers; e-mail address; purchase order or contract number; and an equipment or service description. This list will give a baseline for the entry of the vessel as converted into the OWNER electronic contact system.
An initial Vendor/Contractor List shall be provided not more than 10 days after contract signing and shall be updated, as required, every 10 days thereafter over the course of the contract.
ACCESS TO YARD/VESSEL/DOCUMENTS (IF APPLICABLE)
ACCESS TO YARD/VESSEL
The Government Representatives (COR) shall be afforded access to the CONTRACTOR Shipyard, the COR’s offices, and the vessel 24 hours a day for the duration of the Contract and for a reasonable time after delivery or until such time as the vessel departs the CONTRACTOR facility for her home port (if applicable) .
ACCESS TO DOCUMENTS
The OWNER and/or COR shall have ready access during normal working hours to all documentation concerning the vessel including but not necessarily limited to: Drawings; Specifications; Technical Information; Engineering Calculations; Schedules; Test & Inspection Reports; Relevant Subcontractor Documents; Regulatory Body Reports; Approvals; Recommendations; and the Contractor’s Detailed Contract Estimate.
INSPECTIONS
GENERAL
All materials and workmanship shall be subject to inspection by the COR, ABS, the USCG and other regulatory bodies having jurisdiction. All inspection and observation of tests by the COR will be performed in such a manner as not to unnecessarily delay the contract work.
The COR shall promptly approve all work and material conforming to the requirements of this Specification and shall promptly reject all work and materials, which do not conform. Such rejected work or material shall be satisfactorily corrected.
SCHEDULING & ATTENDANCE
The CONTRACTOR is responsible for scheduling and presenting all completed work for Acceptance Inspections and for giving written ADEQUATE NOTICE of 24 HOURS to the COR and other required inspection agencies that such work is complete, has been passed by the CONTRACTOR QA, and is ready for such inspection. Inspections shall, when possible, be scheduled and accomplished during normal workdays on the CONTRACTOR day shift.
The COR will make every effort to maintain communications with the parties involved and to report to the inspection site per agreed schedule. If the COR is unable to keep the schedule, he shall notify the CONTRACTOR as soon as possible and reschedule for a mutually agreeable time. Failure of the COR to attend an inspection does not constitute an acceptance of the work. Inspections by ABS, the Coast Guard or other agency do not eliminate these requirements for inspection and acceptance by the COR.
PREPARATIONS
Work presented for inspection shall be complete in all respects, clean, free of debris, scrap, lines, welding wire ends and all temporary gear. Reasonable accommodations shall have been made for access, lighting, and fresh air supply in advance of the inspection party.
COVERINGS
Prior to the application/installation of paint, deck covering, insulation, sheathing, joiner work, ceilings, etc., all structure and weld that is to be covered will be given final inspection and will be signed off on by the COR. It must be clearly understood by the CONTRACTOR that the COR has the right and option to require removal of any or all coverings for inspection in areas that have not been previously inspected and passed. This requirement makes it essential that weekend and night shift foremen, for both CONTRACTOR and Subcontractors, be in close communication with the QA Department and Project Manager.
RE-INSPECTIONS
Any welding, burning, heat shrinking, etc. which is performed as rework, repair, or on change orders after an inspection has been completed, may require (at the COR's option) the removal of any or all coverings for re-inspection of plate, welds, etc. This requirement will further emphasize the necessity of a formal QA Inspection process and the necessity for close communications between CONTRACTOR and COR. An initial inspection in no way negates the requirement for re-inspection if an area is reworked in any manner.
COMPARTMENT COMPLETIONS
Living spaces, workspaces and control/machinery spaces shall be inspected and certified complete by the COR and the CONTRACTOR representative. A compartment shall not be considered accepted until the inspection is complete, deficiencies are corrected, and the COR and CONTRACTOR have signed off on the space. At this time, so far as is possible, the compartment shall be secured and no further work shall be conducted within the space unless approved by the mutual consent of the COR and CONTRACTOR.
The intent of the foregoing paragraph is to guarantee that the OWNER will receive, at delivery, a fully operational vessel which is immediately capable of entering service. Any pre-existing deficiencies not covered in these Specifications or Drawings will be subject to correction at the OWNER expense.
PROSECUTION OF WORK
STARTING DATE FOR PROJECTS
The Notification of Award will stipulate the date on which it is expected the Contractor will begin contract work and from which date contract time will be charged. No work shall begin on the project until the contract has been fully executed.
SCHEDULE REQUIREMENTS
Unless otherwise specified in the contract, the Contractor is required to furnish the COR with the following schedules at or before the pre-work conference: Gantt chart (Bar Chart) and CPM Schedule.
The COR will independently review the initial schedule, and then meet with the Contractor for a joint review and make necessary corrections and adjustments. These specifications require this meeting take place within 5 calendar days of the contract award. After this meeting, but within 5 calendar days, the Contractor shall make the necessary changes, and then resubmit the schedule to the COR. If necessary, this process shall be repeated. However, the schedule must be finalized within 7 calendar days of the scheduled completion.
The schedule shall show contract milestones, intermediate contract completion dates, and the contract completion date. The schedule shall show the Contractor’s scheduled completion date and the substantial completion date when applicable.
Should the prosecution of the work be discontinued or changed for any reason, these specifications require the Contractor to notify the COR at least two days in advance of changing or resuming operations. Through the life of the project, the COR should verify that activities, durations, start and finish dates, etc. shown on the schedule represent the actual status of work.
The COR may request in writing a supplemental schedule if the actual prosecution of work differs significantly from that represented on the schedule. The Contractor must provide the requested supplemental schedule within 3 calendar days of the request and at no cost to the Government.
Jobsite progress meetings shall be held weekly or as specified for the purpose of updating the schedule. Progress will be reviewed to verify actual start and finish dates of completed activities, remaining duration and percent complete of uncompleted activities, and any proposed revisions to the schedule. It is the Contractor's responsibility to provide the COR with the status of activities at the progress meetings and prepare schedule updates based on this information once it has been verified and agreed upon. A written narrative describing the schedule status, the critical path and any revisions to the schedule shall be included with the updated schedule. The updated schedule will be resubmitted should it not contain the agreed upon information.
The COR must have a schedule that accurately represents the prosecution of work and activities at all times. A current schedule is essential for evaluating requests for adjustments and determining how delays, extra work, interruptions, suspensions, etc. will impact the contract completion date or the Contractor’s scheduled completion date. These specifications allow the COR to withhold progress payments if the Contractor fails to provide the schedules and updates as required.
GANTT CHART
A Gantt chart is another name for a bar chart. The Gantt chart provides a graphical representation of the project plan that includes the activities that make up the project, the estimated duration of each activity, and the planned sequence of activity performance. The critical path must be identified on the Gantt chart. Total float must be identified on Gantt charts developed from CPM schedules. Total float is not required to be identified on Gantt charts developed without CPM schedules. The Gantt chart must conform to the specifications as set forth in the contract.
CRITICAL PATH METHOD (CPM) SCHEDULE
A CPM schedule is one that forecasts the amount of time required from project start to finish by arranging all project activities in their logical sequence and calculating all possible path lengths through the project. CPM schedules are used to ensure adequate project planning and provide a tool to quickly and accurately evaluate project changes. The CPM schedule may also be used to determine when and what activities need to be accelerated to meet contract milestones, completion dates, etc.
Two copies of the Time-Scaled Logic Diagram, Network Report, and Schedule Report must be submitted by the Contractor.
The Network Report shall completely define the schedule logic. It will clearly indicate all logical relationships and constraints.
The Schedule Report shall be sorted by activity number and shall provide the following information for each activity: activity number, activity description, activity calendar, original duration, remaining duration, percent complete, scheduled or actual start and finish dates, late start and finish dates, free float and total float.
PROGRESS REVIEW MEETINGS
The CONTRACTOR and COR shall hold progress review meetings every (1) week to be held at the CONTRACTOR facility or such other location as approved by both parties beginning (1) week after the delivery of the vessel to the CONTRACTOR facility. The purpose of the meetings is to discuss, report, and resolve problems relative to progress, anticipated delays, cost experience in relation to budget and projected end costs, staffing, schedules, receipt of GFE (if any), CONTRACTOR furnished material, production problems (including Subcontractor problems), and other related matters.
GUARANTEES
All guarantees or warrantees shall begin at the completion of final acceptance the completed work detailed in the specification by the COR.
MATERIALS AND WORKMANSHIP
MATERIAL GENERAL
All material unless otherwise specified herein, shall be of commercial quality; suitable for marine environment; and shall conform to ASTM, Federal, Military, SAE, ABS, and USCG (CFR) requirements. This material shall be so designated on Bills of Material and on Construction Drawings. All materials shall be free from imperfections of manufacture and from defects, which adversely affect appearance or serviceability.
WORKMANSHIP GENERAL
All workmanship shall be first-class in all respects. All material, machinery, equipment, pieces and/or parts specified herein and installed in the converted vessel shall be suitable for the marine service intended.
MATERIAL MILITARY SPECS
Where Military or Federal Specifications are referred to herein, they are referenced solely to indicate the degree of quality of material required. The furnishing of material or items in strict compliance with the detailed requirements of these Military/Federal Specs is not intended.
STORAGE/PROTECTION
All material and equipment intended for the vessel in any form, whether CONTRACTOR or GF, shall be adequately stored and protected from the elements and shall be given appropriate security by the CONTRACTOR. Due consideration shall be given to the nature of particular equipment or material with storage and security mutually agreed upon by COR and CONTRACTOR. Inside storage shall be required for all equipment and material that will be located on the interior of the vessel.
The CONTRACTOR shall be responsible during construction and prior to vessel delivery for the protection of all items installed with finished surfaces such as joiner panels, door frames, deck coverings, joiner ceilings, countertops, furniture, etc.
CONTRACTOR'S OBLIGATION
The CONTRACTOR is to provide all plant infrastructure, labor, and transportation for employees, supplies as required, fuel for vehicles and machinery, water, power, lighting, air, steam, crane and forklift services, CONTRACTOR communications, line handling, wharfage, towing and shifting services.
HULL PROTECTION
WELDING
Rigid control of welding and grounding shall be maintained for the protection of hull and hull appendages. Care shall be taken that the welding polarity and ground connections of welding machines used on this vessel, other vessels in the immediate vicinity, or on the dock to which the vessel is moored shall be such as not to damage any parts of the vessel. The CONTRACTOR shall adequately protect, in all respects, the underwater part of the hull prior to delivery.
GENERAL INFORMATION
Note: This GENERAL section applies to all ITEMS within this SOW and therefore is Not Separately Priced. To the extent that efforts to comply with the requirements stated in this GENERAL section present a cost impact, the cost is to be allocated to the priced ITEMS
SITE VISIT
The following Shipbuilder's Drawings (Avondale Shipyard) and conversion drawings (Bender Shipyard) are included with this Request for Proposal, and will be available on board at the Site Visit and Pre-Proposal Conference on 09:00, Tuesday, August 18 2015 at the Massachusetts Maritime Academy, 101 Academy Drive, Buzzards Bay, MA 02532. Point of Contact: COR, Jeffrey Brown at (757) 694-5505.
AVAILABILITY AND PERFORMANCE PERIOD
The ship shall be available for work performance on or about September 15, 2015 with a stop work date of November 15, 2015 for CLIN’s 1, 2, and 3 all other CLINS will start after the ship returns from the annual training cruise. Work shall resume no later than March 7, 2016 and ALL work shall be completed by May 20, 2015 .
Machinery Particulars:
Main Engine: The Vessel is equipped with a complete propulsion unit of De Laval design and manufacture, comprising a high pressure ahead turbine, a low pressure ahead turbine including astern elements, and double-helical, double speed reduction gear. The turbines are connected to the reduction gear through flexible, mechanical, dental type couplings.
Manufacturer: De Laval Turbine Inc. Instruction Book No. 1611 Maximum Rating (BHP) 15,500 hp HP Cover w/ diaphragm (wt - lbs.) 6,000 lbs.. HP Rotor w/o Lifting gear (wt - lbs.) 2,282 lbs. LP Cover w/ diaphragm (wt - lbs.) 20,300 lbs. LP Rotor w/o Lifting gear (wt - lbs.) 11,510 lbs.
Turbo - Generator
| Manufacturer: | De Laval Turbine Inc. Type: | GJ | ||||||
| Rating | 750 KW Rated Speed (turbine): | 10,012 rpm Rated Speed (generator): | 1,200 rpm Turbine covers - Complete (wt - lbs): | 1900 lbs Turbine Rotor (wt - lbs): | 610 lbs Gear (wt - lbs): | 2770 lbs Generator Rotor (wt - lbs):: | 2930 lbs Generator Complete (wt - lbs) | 7590 lbs |
Main Propulsion Boilers - (2) Manufacturer Foster Wheeler Corp.
Type Contract No. 3-37-4538 Contract No. 3-37-4564 Contract No. 3-37-4606
Design Pressure 700 lbs @ 850 deg. F.
Test Pressure 1050 PSI (150% of design)
MACHINERY INSPECTION ITEMS
Note: The Contractor must provide rigging equipment appropriate for the estimated weights, installed lifting points are available but the status of certifications in unknown, therefore it is the contractor’s responsibility to ensure the safety of all rigging equipment including padeyes, trolleys and lifting beams.
BILGE PUMP (ABS)
1. Scope of Work:
1.1 Intent. Contractor to supply labor, material and equipment to open up for inspection by Regulatory Bodies, bilge pump.
1.2 Location. Lower level engine room, port side, forward
1.3 Identification. Fairbanks Morse Inc. Horizontal 5", Fig. 5811, centrifugal pump.
2. Work Description:
2.1 Contractor to remove upper pump casing half and put on floor plates next to pump.
2.2 Both casing halves to be thoroughly cleaned before inspection. All packing to be removed and packing glands thoroughly cleaned.
2.3 All studs, nuts and bolts to be thoroughly cleaned before inspection.
2.4 Pump motor end, end bell to be removed for motor inspection.
2.5 After unit is properly cleaned, unit to be inspected by concerned parties and regulatory bodies.
2.6 After completion of inspection, pump and motor to be reassembled in good order as original.
3. Performance Criteria/Deliverables:
3.1 Contractor to supply all new gasketing and packing of the proper type for salt-water service for reassembly.
3.2 As necessary contractor to supply new bearings for pump end and motor end of unit.
3.3 Contractor responsible for returning all interferences removed in the way of repair to original condition.
3.4 At completion of repair and when feasible pump unit to be test run under operating conditions to the satisfaction of concerned parties and Regulatory Bodies.
3.5 If in the course of inspection additional repairs are deemed necessary they will be the subject of a separate delivery order.
4. References:
4.1 Vessel to supply Technical Manual as necessary
#1 AND #2 MAIN FEED PUMPS (ABS)
1. Scope of Work:
1.1 Intent. Open up for inspection by Regulatory Bodies #1 & #2 main feed pumps.
1.2 Location. Lower level engine room, starboard side forward.
1.3 Identification. Coffin Turbo Pump, Type DE.
2. Work Description:
2.1 Contractor to remove turbine end and pump suction heads as per manufacturer’s instructions.
2.2 Contractor to follow manufacturer’s instructions for removal of turbine end and pump internals.
2.3 Contractor to perform all manufacturer recommended alignments and checks.
2.4 Contractor to remove hand trip and over-speed units from pumps for inspection.
2.5 After inspection by concerned parties and Regulatory Bodies, pumps to be reassembled in good order. Contractor to follow manufacturer’s instructions when reassembling pumps.
3. Performance Criteria/Deliverables:
3.1 A certified Coffin Technical Representative to be in attendance for all items involved with this repair item.
3.2 Contractor to supply and install new bearings for units.
3.3 Pump turbine combination to be balanced before final assembly.
3.4 Contractor responsible for removing all interferences in way of repair and returning same to original condition at finalization of repair.
3.5 Contractor responsible for supplying new fasteners. Contractor responsible for renewing all gasketing and packing associated with repair, with an approved type for this repair.
3.6 All mating surfaces, gasketed and non-gasketed, including studs, nuts and bolts to be thoroughly cleaned before inspection.
3.7 For a final test and when feasible pumps to be run under operating conditions to the satisfaction of concerned parties and Regulatory bodies.
3.7.1 Coffin Technical Representative to be in attendance for all operational testing of pump units.
3.8 Any additional repairs associated with this item to be the subject of a supplemental delivery order.
4.1 Vessel to supply Coffin Feed pump technical Manual as necessary
FEED HEATER FIRST STAGE (ABS)
1.1 Intent. Contractor to supply labor, material and equipment to open up for inspection by Regulatory Bodies, the first stage feed heater.
1.2 Location. Upper-tween deck level engine room, port side.
1.3 Identification. Acqua-Chem Inc., Paracoil 6-2V-96D, low pressure feed heater and drain cooler.
2. Work Description:
2.1 Contractor to remove insulation in way of water box heads.
2.2 Contractor to drain water from condensate side of first stage heater.
2.3 Contractor to remove interferences in way of removal of water box heads.
2.4 Contractor to remove top and bottom water box heads for inspection of tubes by Regulatory Bodes.
2.5 All tubes to be thoroughly mechanically cleaned before inspection by Regulatory Bodies.
2.6 Both tube sheets, nuts and bolts and gasketed surfaces to be cleaned before inspection.
2.7 After inspection by concerned parties and Regulatory Bodies unit to be reassembled in good order as original.
3. Performance Criteria/Deliverables:
3.1 Contractor responsible for supplying proper material to fabricate new gaskets for water box heads and interferences removed in way of repair.
3.2 All nuts and bolts associated with item to be liberally coated with anti-seize compound upon reassembly of unit.
3.3 Depending on condition of tubes they may have to be cleaned by circulating safe acid or equivalent.
3.4 At finalization of repair unit to be pressurized and tested via the use of the main condensate system to the satisfaction of concerned parties and Regulatory Bodies.
4. References:
Vessel to supply Technical Manual as necessary.
#1 & #2 AUXILIARY CONENSERS (ABS)
1. Scope of Work:
1.1 Intent. Contractor to provide labor, material and equipment to open up for inspection by Regulatory Bodies, #1 and #2 auxiliary condensers saltwater side.
1.2 Location. Lower level engine room, starboard side, aft.
1.3 Identification. De Laval, horizontal surface, two pass.
2. Work Description:
2.1 Contractor to secure all inlet and outlet seawater valves by mechanical means. Valves to be tied off and tagged. Drain condensers.
2.2 Open condenser fore and aft inspection plates.
2.3 All inspection plate gasketed surfaces, nuts and bolts to be thoroughly cleaned.
2.4 Tube sheets to be cleaned, all debris to be removed from condenser access area.
2.5 All tubes to be thoroughly mechanically cleaned by power brushing before inspection by Regulatory Bodies.
2.6 After inspection by concerned parties and Regulatory Bodies condensers to be closed up in good order as original.
3. Performance Criteria/Deliverables:
3.1 Contractor to provide new gasketing of appropriate type for seawater service.
3.2 Contractor to provide an original report and three copies of plugged tubes, if any, and their location to concerned parties.
3.3 Contractor to remove zinc anodes and replace with contractor furnished new zinc anodes. Contractor to furnish new monel fasteners.
3.4 All cover plate's nuts and bolts to be liberally coated with anti-seize compound upon reassembly.
3.5 At finalization of repair and when directed auxiliary circulators to be lined up and started. Seawater to be run through condensers so that inspection cover gaskets can be checked for tightness.
4. References:
Vessel to supply Technical Manual as necessary.
GLAND EXHAUST CONDENSER (ABS)
1. Scope of Work:
1.1 Intent. Contractor to supply labor, material and equipment to open up for inspection by Regulatory Bodies, the gland exhaust condenser.
1.2 Location. Upper-tween deck level engine room, starboard side.
1.3 Identification. Acqua-Chem Inc., Paracoil 2-K-108D, gland exhaust condenser.
2. Work Description:
2.1 Contractor to remove insulation in way of water box heads.
2.2 Contractor to drain water from condensate side of first stage heater.
2.3 Contractor to remove interferences in way of removal of water box heads.
2.4 Contractor to remove top and bottom water box heads for inspection of tubes by Regulatory Bodies.
2.5 All tubes to be thoroughly mechanically cleaned before inspection by Regulatory Bodies.
2.6 Both tube sheets, nuts and bolts and gasketed surfaces to be cleaned before inspection.
2.7 After inspection by concerned parties and Regulatory Bodies unit to be reassembled in good order as original.
3. Performance Criteria/Deliverables:
3.1 Contractor responsible for supplying proper material to fabricate new gaskets for water box heads and interferences removed in way of repair.
3.2 All nuts and bolts associated with item to be liberally coated with anti-seize compound upon reassembly of unit.
3.3 Before inspection tubes to be cleaned by circulating safe acid or equivalent.
3.4 At finalization of repair and when feasible unit to be pressurized and tested via the use of the main condensate system to the satisfaction of concerned parties and Regulatory Bodies.
4. References:
5.1 Vessel to supply Technical Manual as necessary.
MAIN AIR EJECTOR (ABS)
1. Scope of Work:
1.1 Intent. Contractor to open up for inspection by Regulatory bodies #1 and #2 auxiliary air ejectors inter and after condensers.
1.2 Location. Operating level engine room starboard side under ladder coming down from upper level.
1.3 Identification. Foster Wheeler Corporation. Twin element, two-stage unit, size No. 4 with combined surface type inter and after condenser.
2. Work Description:
2.1 Contractor to remove inlet and outlet water heads of air ejector condensers.
2.1.1 After removal of heads contractor to thoroughly clean tube sheets and gasketed surfaces. Contractor to clean tubes via a non-abrasive method.
2.2 Contractor to fabricate new head gaskets from contractor supplied material approved for this service.
2.3 Contractor to provide equipment to hydraulically test water boxes, to manufacturers specification, to test for tube leaks.
2.4 Contractor to remove 1st and 2nd stage nozzles for inspection and comparison to original size.
2.5 After inspection by Regulatory Bodies air ejector units to be reassembled as original.
2.6 Contractor to check packed tube ends for tightness and condition of ferrules and foil packing.
3. Performance Criteria/Deliverables:
3.1 All associated fasteners to be properly cleaned before reassembly.
3.2 Tubes are rolled at one end and packed at the other end.
3.3 Contractor responsible for all blanks, piping, etc. necessary for testing.
3.4 A final test, after closing, to be done via the use of the auxiliary condensate pump to test heads.
4. References:
4.1 Vessel to supply Technical Manual as necessary
FUEL OIL SERVICE PUMP (ABS)
1. Scope of Work:
1.1 Intent. Contractor to supply labor, material and equipment to open up for inspection by Regulatory Bodies, main fuel oil service pump.
1.2 Location. Engine room lower level, starboard side, forward.
1.3 Identification. De Laval. IMO Type 3EF-218, rotary screw type pump.
2. Work Description:
2.1 Contractor to uncouple pump from driving unit.
2.2 Disconnect suction and discharge piping.
2.3 Remove bolts from mounting bracket and remove pump to bench for disassembly.
2.4 Remove coupling hub from shaft and disconnect external piping.
2.5 Remove packing box end cover, packing gland and packing as a unit.
2.6 Remove end cover and remove rotors as a unit from outboard end of pump case.
2.7 Remove holding bolts and thrust plate to separate rotors.
2.8 After disassembly of parts inspection to be done by concerned parties and Regulatory Bodies.
2.9 After inspection and as directed pump unit to be reassembled as original.
3. Performance Criteria/Deliverables:
3.1 Contractor responsible for all oil spilled during pump disassembly.
3.2 Rotors and housing to be thoroughly cleaned before inspection by Regulatory Bodies.
3.3 Contractor to follow manufacturers specifications for disassembly and reassembly of pump unit.
3.4 Contractor responsible for returning all interferences removed in way of repair to original condition.
3.5 Contractor responsible for renewing all gasketing, packing, nuts and bolts as required for this service.
3.6 After reinstallation of pump, couplings to be realigned to the satisfaction of concerned parties and to manufacturers specifications.
3.7 At the completion of repair and when feasible pump unit to be test run under operating conditions to the satisfaction of concerned parties and Regulatory Bodies.
3.8 If in the course of inspection additional repairs are deemed necessary they will be the subject of a separate delivery order.
4. References:
4.1 Vessel to supply Technical Manual as necessary.
FUEL OIL TRANSFER PUMP (ABS)
1. Scope of Work:
1.1 Intent. Contractor to supply labor, material and equipment to open up…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .