Amendment_0002_-_MWR_PMS_MI_(3).pdf
PDF 244 KB Posted
- Attached to
- Sleeping Bear Dunes National Lakeshore Federal contract opportunity
- Solicitation number
- DTFH71-15-B-00015
About this file
The Bid Opening date remains March 26 2015 at 2 00 p.m. EST.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0001_-_MWR_PMS_MI_(3).pdf | ||
| ADV_Bidder's_Qualifications_Form.doc | DOC document | |
| Plans_MWR_PMS_MI(3).pdf | ||
| FP03_Eng_.pdf | ||
| FP03_Errata.pdf | ||
| Subcontracting_plan.doc | DOC document | |
| IFB_Solicitation_Book_MWR_PMS_MI(3).pdf | ||
| Categorical_Exclusion_Form_(NEPA).pdf | ||
| VETS-100A-Form.pdf | ||
| Synopsis_-_MWR_PMS_MI(3).doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT CLAUSES INDEX
FEDERAL ACQUISITION REGULATION (FAR) TRANSPORTATION ACQUISITION REGULATION (TAR)
(Updated thru FAC 2005-80 on 03/02/2015)
FAR & TAR CLAUSES INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.202-1 DEFINITIONS Nov-13 52.203-3 GRATUITIES Apr-84 52.203-5 COVENANT AGAINST CONTINGENT FEES May-14 52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT Sep-06 52.203-7 ANTI-KICKBACK PROCEDURES May-14 52.203-8 CANCEL & RECOVER OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY May-14 52.203-11 CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACT Sep-07 52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS Oct-10 52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT Apr-10 52.203-14 DISPLAY OF HOTLINE POSTER(S) Dec-07 52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER May-11 52.204-7 SYSTEM FOR AWARD MANAGEMENT Jul-13 Contractor Mandatory Internet Data Input 52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS Jul-13 Contractor Mandatory Internet Data Input
52.209-6
PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS
DEBARRED, SUSPENDED OR PROPOSED FOR DEBARMENT Aug-13
52.214-5 SUBMISSION OF BIDS Mar-97 If applicable 52.214-19 CONTRACT AWARD -- SEALED BIDDING-CONSTRUCTION Aug-96 If applicable 52.214-26 ALT 1 AUDIT AND RECORDS -- SEALED BIDDING (ALT 1 - (MAR 09)) Oct-10 If applicable 52.214-27 PRICE REDUCTION FOR DEFECTIVE COST OR PRICING DATA - MODIFICATIONS - SEALED BIDDING Aug-11 52.214-28 SUBCONTRACTOR COST OR PRICE DATA -- MODIFICATIONS--SEALED BIDDING Oct-10 52.214-29 ORDER OF PRECEDENCE - SEALED BIDDING Jan-86 52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE Apr-91 52.214-35 SUBMISSION OF OFFERS IN THE U.S. CURRENCY Apr-91 52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS Oct-14 52.219-9 ALT 1 SMALL BUSINESS SUBCONTRACTING PLAN (ALT 1 - (Oct 01)) Oct-14 Large Business Mandatory Submittal Requirement 52.219-14 LIMITATIONS ON SUBCONTRACTING Nov-11 52.219-16 LIQUIDATED DAMAGES - SUBCONTRACTING PLAN Jan-99 52.222-3 CONVICT LABOR Jun-03 52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS -- OVERTIME COMPENSATION May-14 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS - SECONDARY SITE OF THE WORK May-14 52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS May-14 Contractor Mandatory Wage Rates Posting 52.222-7 WITHHOLDING OF FUNDS May-14 52.222-8 PAYROLLS AND BASIC RECORDS May-14 Contractor Weekly Payroll Submittals 52.222-9 APPRENTICES AND TRAINEES Jul-05 52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS Feb-88
52.252-2 Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. The full text of a clause may be accessed electronically at this address: www.arnet.gov/far/
(End of Clause)
(Updated thru FAC 2005-80 on 03/02/2015)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) May-14 52.222-12 CONTRACT TERMINATION -- DEBARMENT May-14 52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS May-14 52.222-14 DISPUTES CONCERNING LABOR STANDARDS Feb-88 52.222-15 CERTIFICATION OF ELIGIBILITY May-14 52.222-19 CHILD LABOR - COOPERATION WITH AUTHORITIES AND REMEDIES Jan-14 52.222-21 PROHIBITION OF SEGREGATED FACILITIES Feb-99 52.222-26 EQUAL OPPORTUNITY Mar-07 52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION Feb-99 52.222-35 EQUAL OPPORTUNITY FOR SPECIAL DISABLED VETERANS, VETERANS OF THE VIETNAM ERA, & OTHER EL Jul-14 52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES Jul-14 52.222-37 EMPLOYMENT REPORTS ON SPECIAL DISABLED VETS, VETS OF THE VIETNAM ERA, ET AL Jul-14 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Sep-10 Contractor Annual Mandatory Reporting Requirement 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT Mar-15 52.222-50 COMBATING TRAFFICKING IN PERSONS Feb-09 If applicable 52.222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 Dec-14 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACT Sep-13 http://www.biopreferred.gov 52.223-5 POLLUTION PREVENTION AND RIGHT TO KNOW INFORMATION May-11 52.223-6 DRUG-FREE WORKPLACE May-01 Contractor Annual Contractor Reporting Reqt 52.223-10 WASTE REDUCTION PROGRAM May-11 52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS May-08 Mandatory 52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING Aug-11 52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES Jun-08 52.227-1 AUTHORIZATION AND CONSENT Dec-07 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT Dec-07 52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS Dec-07 52.227-14 RIGHTS IN DATA - GENERAL May-14 52.227-17 RIGHTS IN DATA - SPECIAL WORKS Dec-07 52.228-1 BID GUARANTEE Sep-96 52.228-2 ADDITION BOND SECURITY Oct-97 Contractor Submittal Requirement 52.228-5 INSURANCE - WORK ON A GOVERNMENT INSTALLATION Jan-97 52.228-11 PLEDGES OF ASSETS Jan-12 52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS May-14 52.228-14 IRREVOCABLE LETTER OF CREDIT Nov-14 Contractor Submittal Requirement 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Oct-10 52.229-2 NORTH CAROLINA STATE AND LOCAL SALES AND USE TAX Apr-84 52.229-3 FEDERAL, STATE, AND LOCAL TAXES Feb-13 52.230-2 COST ACCOUNTING STANDARDS May-14 If applicable 52.230-3 DISCLOSURE AND CONSISTENCY OF COST ACCOUNTING PRACTICES May-14 If applicable 52.230-6 ADMINISTRATION OF COST ACCOUNTING STANDARDS Jun-10 Contractor Submittal Requirement 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS May-14 52.232-13 NOTICE OF PROGRESS PAYMENTS Apr-84 52.232-16 PROGRESS PAYMENT Apr-12 52.232-17 INTEREST May-14 52.232-18 AVAILABILITY OF FUNDS Apr-84 52.232-23 ASSIGNMENT OF CLAIMS May-14 52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS May-14 52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - SYSTEM FOR AWARD MANAGEMENT Jul-13 52.233-1 ALT 1 DISPUTES (ALT-1, DEC-91) May-14 52.233-3 PROTEST AFTER AWARD Aug-96 http://www.biopreferred.gov/
(Updated thru FAC 2005-80 on 03/02/2015)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM Oct-04 52.236-2 DIFFERING SITE CONDITIONS Apr-84 52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK Apr-84 52.236-5 MATERIAL AND WORKMANSHIP Apr-84 52.236-6 SUPERINTENDENCE BY THE CONTRACTOR Apr-84 52.236-7 PERMITS AND RESPONSIBILITIES Nov-91 52.236-8 OTHER CONTRACTS Apr-84 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES & IMPROVEMENTS Apr-84 52.236-10 OPERATIONS AND STORAGE AREAS Apr-84 52.236-11 USE AND POSSESSION PRIOR TO COMPLETION Apr-84 52.236-12 CLEANING UP Apr-84 52.236-13 ACCIDENT PREVENTION Nov-91 Contractor Submittal Requirement 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS Apr-84 52.236-17 LAYOUT OF WORK Apr-84 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION Feb-97 52.236-26 PRECONSTRUCTION CONFERENCE Feb-95 52.242-13 BANKRUPTCY Jul-95 52.242-14 SUSPENSION OF WORK Apr-84 52.243-4 CHANGES Jun-07 If applicable 52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS Mar-15 52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES Apr-12 52.246-12 INSPECTION OF CONSTRUCTION Aug-96 52.246-21 WARRANTY OF CONSTRUCTION Mar-94 52.248-3 ALT 1 VALUE ENGINEERING - CONSTRUCTION (ALT-1, APR-84) Oct-10 52.249-2 ALT 1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) (ALT-I, Sep-96) Apr-12 52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) Apr-84 52.253-1 COMPUTER GENERATED FORMS Jan-91
TAR CLAUSES INCORPORATED BY REFERENCE
1252.211-70 INDEX FOR SPECIFICATIONS Apr-05 1252.242-73 CONTRACTING OFFICERS TECHNICAL REPRESENTATIVE Oct-94
FAR & TAR PROVISIONS INCORPORATED BY REFERENCE
52.217-3 EVALUATION EXCLUSIVE OF OPTION Apr-84 52.217-4 EVALUATION OF OPTIONS EXERCISED AT TIME OF CONTRACT AWARD Jun-88 52.217-5 EVALUATION OF OPTIONS Jul-90 52-217-7 OPTION FOR INCREASED QUANTITY -- SEPARATELY PRICED LINE ITEM Mar-89
(Updated thru FAC 2005-80 on 03/02/2015)
FAR & TAR CLAUSES INCORPORATED BY FULL TEXT
CLAUSE TITLE DATE SECTION SECTION TYPE REMARKS
52.203-17
CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTELBLOWER RIGHTS Apr-14 G GEN'L CONTRACT REQS.
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS Jul-13 G GEN'L CONTRACT REQS. If Applicable 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.211-12 LIQUIDATED DAMAGES - CONSTRUCTION Sep-00 H CONSTR. CONTRACTS REQS Government Fill In 52.211-18 VARIATION IN ESTIMATED QUANTITY Apr-84 H CONSTR. CONTRACTS REQS 52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUB ZONE SB CONCERNS Oct-14 F SOCIOECON PROG REQS Contractor Fill In
52.222-23
NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT
OPPORTUNITY FOR CONSTRUCTION Feb-99 F SOCIOECON PROG REQS Contractor Reporting Reqs
52.223-3 ALT I HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (ALT-I, JUL-95) Jan-97 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.223-4 RECOVERED MATERIAL CERTIFICATION May-08 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA DESIGN ITEMS May-08 G GEN'L CONTRACT REQS. Contractor Reporting Reqs 52.225-9 BUY AMERICAN - CONSTRUCTION MATERIALS May-14 F SOCIOECON PROG REQS Govt & Contractor Fill In 52.228-15 PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION Oct-10 G GEN'L CONTRACT REQS. Contractor Submittal Reqs 52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.236-4 PHYSICAL DATA Apr-84 H CONSTR. CONTRACTS REQS Government Fill In 52.248-3 Alt 1 VALUE ENGINEERING - CONSTRUCTION (ALT -I APR-84) Oct-10 G GEN'L CONTRACT REQS. Contractor Submittal Reqs
TAR CLAUSES INCORPORATED BY FULL TEXT
FAR PT 22.9 NONDISCRIMINATION BECAUSE OF AGE POLICY Feb-64 F SOCIOECON PROG REQS Executive Order 11141-Not A Clause
(Updated thru FAC 2005-80 on 03/02/2015)
FAR & TAR PROVISIONS INCORPORATED BY REFERENCE
CLAUSE TITLE DATE REMARKS
52.211-6 BRAND NAME OR EQUAL Aug-99 52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS Dec-89 52.214-4 FALSE STATEMENTS IN BIDS Apr-84 52.214-5 SUBMISSION OF BIDS Mar-97 52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS Apr-84 52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS Nov-99 52.214-18 PREPARATION OF BIDS -- CONSTRUCTION Apr-84 52.214-19 CONTRACT AWARD -- SEALED BIDDING -- CONSTRUCTION Aug-96 52.223-1 BIOBASED PRODUCT CERTIFICATION May-12 52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN CERTAIN ACTIVITIES OR TRANSACTIONS RELATIN Dec-12
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by the paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision my be accessed electronically at this address: www.arnet.gov/far/ (End of Clause)
52.252-1 Solicitation Provisions Incorporated By Reference (Feb 1998)
(Updated thru FAC 2005-80 on 03/02/2015)
FAR PROVISIONS INCORPORATED BY FULL TEXT
PROVISION TITLE DATE SECTION SECTION TYPE REMARKS
52.203-11
CERTIFICATION AND DISCLOSURE REGARDING PAYMENTS TO INFLUENCE
CERTAIN FEDERAL TRANSACTIONS Sep-07 F
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS Dec-14 D REPS & CERTIFICATIONS Mandatory Contractor On-Line Input 52.209-5 CERTIFICATION REGARDING RESPONSIBILITY MATTERS Apr-10 K 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS Jul-13 K If Applicable
52.211-4 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN GSA INDEX
OF FEDERAL SPECIFICATION, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS
Jun-88 E INSTRUCTIONS TO BIDDERS Government Fill In
52.216-1 TYPE OF CONTRACT Apr-84 E INSTRUCTIONS TO BIDDERS Government Fill In 52.222-38 COMPLIANCE WITH VETERANS' EMPLOYMENT REPORTING REQUIREMENTS Sep-10 K
52.225-10 ALT
NOTICE OF BUY AMERICAN REQUIREMENT - CONSTRUCTION MATERIAL (ALT 1
MAY-14) May-14 F SOCIOECON PROG REQS
52.225-20
PROHIBITION ON CONDUCTING RESTRICTED BUSINESS OPERATIONS IN SUDAN -
CERTIFICATION Aug-09 K
52.228-1 BID GUARANTEE Sep-96 E INSTRUCTIONS TO BIDDERS Contractor Submittal Reqs 52.230-7 PROPOSAL DISCLOSURE - COST ACCOUNTING PRACTICE CHANGES Apr-05 K If Applicable 52.233-2 SERVICE OF PROTEST Sep-06 E INSTRUCTIONS TO BIDDERS Government Fill In 52.236-27 SITE VISIT (CONSTRUCTION) Feb-95 E CONSTR. CONTRACT REQS. Government Fill In
OTHER PROVISIONS INCORPORATED BY FULL TEXT
| IFB Index of FAR Clauses - FAC 80.pdf |
| FARTAR By Reference |
| FARTAR Full Text |
| Solicitation Provisions |
| FAR PROV Full Text |
File details come from the government source that posted it. Updated .