Price Form 02A-02D
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 30 Amendment 001 Final.pdf | ||
| Aerial Photo with Project Overlay.pdf | ||
| EPG ROW_10June2008_Demo Notes.pdf | ||
| PreBidMeetingMinutes 3June08.pdf | ||
| Form PP03A-03D.pdf | ||
| Form PP02A-02D.pdf | ||
| ACOE_Permit_05-4015-15.pdf | ||
| EPG_ROW_LTM_Oct07.pdf | ||
| SB I-95 Signing.pdf | ||
| FHWA_BD_TRAFFIC VOLUMES 2030_FNL.pdf | ||
| FHWA_BD_TRAFFIC VOLUMES 2011_FNL.pdf | ||
| SF 30 Amendment 002.pdf | ||
| DEQ_Permit___05-4015.pdf | ||
| FCPPhasingPlan.pdf | ||
| Plans_VDOT.zip | ZIP file | |
| FinalFCPRFQ.doc | DOC document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5A-72
Price Form 02B Lump Sum Bid Item Price Proposal Form
Option 1 Offeror:
Bid Item Number
Bid Item Description
Unit
Price
0107-1
Hazardous/Special Waste Removal/Clean Up/Disposal2 (On EPG)
LS
$ 100,000
0107-3
Investigative Work Plan and Site Investigation (on EPG)
Design
Mobilization
Contractor QA/QC & Testing
Clearing and Grubbing, Removal of Structures and Obstructions
Earthwork
Aggregate Base
Superpave, SACP
Bridge
Drainage
Temporary and Permanent Erosion Control, Landscaping
Temporary and Permanent Traffic Control
Form Subtotal =
Notes:
1. With the exception of Item 0151 and 0154, breakdown each Lump Sum Bid Item shown. Additional Lump Sum Items not already shown may be added at the Contractor’s option.
2. The bid item 0107-1, Hazardous/Special Waste Removal/Clean Up/Disposal (On EPG) Cost (to include MEC) is set up as a Lump Sum Pay Item but will be paid out on a negotiated basis, based on the agreed upon cost for removal, clean up and disposal of any encountered hazardous waste. These costs will vary based on the extent of hazardous waste in the soil, type of contamination, area of impact, the costs for delays to the schedule, and the extent of the required clean up limits. The total Hazardous/Special Waste Removal/Clean Up/Disposal Costs may be less than or more than the amount estimated. Although this is a lump sum pay item, only the actual removal/clean up/disposal costs will be paid for under the contract.
5A-73
Price Form 02C Lump Sum Bid Item Price Proposal Form
Option 2
Up/Disposal (On EPG)2
Bridge
1. With the exception of Item 0151 and 0154, breakdown each Lump Sum Bid Item shown. Additional Lump Sum Items not already shown may be added at the Contractor’s option.
2. The bid item 0107-1, Hazardous/Special Waste Removal/Clean Up/Disposal (On EPG) Cost (to include MEC) is set up as a Lump Sum Pay Item but will be paid out on a negotiated basis, based on the agreed upon cost for removal, clean up and disposal of any encountered hazardous waste. These costs will vary based on the extent of hazardous waste in the soil, type of contamination, area of impact, the costs for delays to the schedule, and the extent of the required clean up limits. The total Hazardous/Special Waste Removal/Clean Up/Disposal Costs may be less than or more than the amount estimated. Although this is a lump sum pay item, only the actual removal/clean up/disposal costs will be paid for under the contract.
5A-74
Price Form 02D Lump Sum Bid Item Price Proposal Form
Option 3
Up/Disposal2 (On EPG)
0107-2
Hazardous Waste Removal/Clean Up/Disposal2 (Off EPG)
$ 500,000
1. With the exception of Item 0151 and 0154, breakdown each Lump Sum Bid Item shown. Additional Lump Sum Items not already shown may be added at the Contractor’s option.
2. The bid items, 0107-1 Hazardous/Special Waste Removal/Clean Up/Disposal (On EPG) and bid item 0107-2, Hazardous Waste Removal/Clean Up/Disposal (Off EPG) Cost (to include MEC disposal) is set up as a Lump Sum Pay Item but will be paid out on a negotiated basis, based on the agreed upon cost for removal, clean up and disposal of any encountered hazardous waste. These costs will vary based on the extent of hazardous waste in the soil, type of contamination, area of impact, the costs for delays to the schedule, and the extent of the required clean up limits.
The total Hazardous/Special Waste Removal/Clean Up/Disposal Costs may be less than or more than the amount estimated. Although this is a lump sum pay item, only the actual removal/clean up/disposal costs will be paid for under the contract.
5A-75
109.07 Request for Progress Payment Forms
File details come from the government source that posted it. Updated .