Price Form 02A-02D.pdf

PDF 24 KB Posted

Attached to
FAIRFAX COUNTY PARKWAY PROJECT NO. R000-029-249
Solicitation number
DTFH71-08-R-00007
Issued by

About this file

Price Form 02A-02D

View the file

Other files

File Type Posted
SF 30 Amendment 001 Final.pdf PDF
Aerial Photo with Project Overlay.pdf PDF
EPG ROW_10June2008_Demo Notes.pdf PDF
PreBidMeetingMinutes 3June08.pdf PDF
Form PP03A-03D.pdf PDF
Form PP02A-02D.pdf PDF
ACOE_Permit_05-4015-15.pdf PDF
EPG_ROW_LTM_Oct07.pdf PDF
SB I-95 Signing.pdf PDF
FHWA_BD_TRAFFIC VOLUMES 2030_FNL.pdf PDF
FHWA_BD_TRAFFIC VOLUMES 2011_FNL.pdf PDF
SF 30 Amendment 002.pdf PDF
DEQ_Permit___05-4015.pdf PDF
FCPPhasingPlan.pdf PDF
Plans_VDOT.zip ZIP file
FinalFCPRFQ.doc DOC document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5A-72

Price Form 02B Lump Sum Bid Item Price Proposal Form

Option 1 Offeror:

Bid Item Number

Bid Item Description

Unit

Price

0107-1

Hazardous/Special Waste Removal/Clean Up/Disposal2 (On EPG)

LS

$ 100,000

0107-3

Investigative Work Plan and Site Investigation (on EPG)

Design

Mobilization

Contractor QA/QC & Testing

Clearing and Grubbing, Removal of Structures and Obstructions

Earthwork

Aggregate Base

Superpave, SACP

Bridge

Drainage

Temporary and Permanent Erosion Control, Landscaping

Temporary and Permanent Traffic Control

Form Subtotal =

Notes:

1. With the exception of Item 0151 and 0154, breakdown each Lump Sum Bid Item shown. Additional Lump Sum Items not already shown may be added at the Contractor’s option.

2. The bid item 0107-1, Hazardous/Special Waste Removal/Clean Up/Disposal (On EPG) Cost (to include MEC) is set up as a Lump Sum Pay Item but will be paid out on a negotiated basis, based on the agreed upon cost for removal, clean up and disposal of any encountered hazardous waste. These costs will vary based on the extent of hazardous waste in the soil, type of contamination, area of impact, the costs for delays to the schedule, and the extent of the required clean up limits. The total Hazardous/Special Waste Removal/Clean Up/Disposal Costs may be less than or more than the amount estimated. Although this is a lump sum pay item, only the actual removal/clean up/disposal costs will be paid for under the contract.

5A-73

Price Form 02C Lump Sum Bid Item Price Proposal Form

Option 2

Up/Disposal (On EPG)2

Bridge

1. With the exception of Item 0151 and 0154, breakdown each Lump Sum Bid Item shown. Additional Lump Sum Items not already shown may be added at the Contractor’s option.

2. The bid item 0107-1, Hazardous/Special Waste Removal/Clean Up/Disposal (On EPG) Cost (to include MEC) is set up as a Lump Sum Pay Item but will be paid out on a negotiated basis, based on the agreed upon cost for removal, clean up and disposal of any encountered hazardous waste. These costs will vary based on the extent of hazardous waste in the soil, type of contamination, area of impact, the costs for delays to the schedule, and the extent of the required clean up limits. The total Hazardous/Special Waste Removal/Clean Up/Disposal Costs may be less than or more than the amount estimated. Although this is a lump sum pay item, only the actual removal/clean up/disposal costs will be paid for under the contract.

5A-74

Price Form 02D Lump Sum Bid Item Price Proposal Form

Option 3

Up/Disposal2 (On EPG)

0107-2

Hazardous Waste Removal/Clean Up/Disposal2 (Off EPG)

$ 500,000

1. With the exception of Item 0151 and 0154, breakdown each Lump Sum Bid Item shown. Additional Lump Sum Items not already shown may be added at the Contractor’s option.

2. The bid items, 0107-1 Hazardous/Special Waste Removal/Clean Up/Disposal (On EPG) and bid item 0107-2, Hazardous Waste Removal/Clean Up/Disposal (Off EPG) Cost (to include MEC disposal) is set up as a Lump Sum Pay Item but will be paid out on a negotiated basis, based on the agreed upon cost for removal, clean up and disposal of any encountered hazardous waste. These costs will vary based on the extent of hazardous waste in the soil, type of contamination, area of impact, the costs for delays to the schedule, and the extent of the required clean up limits.

The total Hazardous/Special Waste Removal/Clean Up/Disposal Costs may be less than or more than the amount estimated. Although this is a lump sum pay item, only the actual removal/clean up/disposal costs will be paid for under the contract.

5A-75

109.07 Request for Progress Payment Forms

File details come from the government source that posted it. Updated .