AK USFS 2060(1), Naukati Road Reconstruction, Prince-of Wales-Hyder Census Area, Alaska

The work consists of grading, drainage, sub-excavation and other small items of work.

Project length: 2.4 Miles

Tentative Fixed Completion Date: Summer 2017 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $7 million to $10 million

Location: 29 Miles NE of Coffman Cove, Alaska

DESCRIPTION OF WORK in US CUSTOMARY

UNITS

FP-03

O ne S ch ed ul e

Sc h

N am e

A

DIVISION 150 – Project Requirements 152 Construction Survey & Staking (yes/no) Yes 153 Contractor Quality Control and Assurance

(yes/no) Yes 154 Contractor Sampling & Testing (yes/no) Yes 155 Schedules for Construction Contracts (construction schedules) (yes/no) Yes 157 Soil Erosion Control Devices (erosion control devices)

Temporary Diversion Channel

LPSM

Sediment Wattle

42,000 LNFT

Temporary Turf Establishment

55 SLRY

158 Watering for Dust Control 2,250 MGAL

DIVISION 200 – Earthwork 201 Clearing & Grubbing 24 ACRE 203 Removal of Structures & Obstructions (structures, demolition) Removal of Pipe Culvert

31 EACH

204 Excavation & Embankment Roadway Excavation

129,000 CUYD

Subexcavation

2,400 CUYD

Select Borrow

50,600 TON

Borrow, Rock

34,000 CUYD

S ch ed ul e

Sc h

N

207 Earthwork Geotextiles (geotextiles) Geotextile, II-A

36,700 SQYD

Geotextile, IV-A

34,000 SQYD

Geogrid, Biaxial

36,700 SQYD

211 Roadway Obliteration 3,400 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap Placed, Class 2

400 CUYD

Ditch, Class 2

3,700 LNFT

271 Reinforced Soil Slope, Geogrid 7,000 SQFT

DIVISION 300 – Aggregate Courses 301 Untreated Aggregate Courses (crushed aggregate)

Aggregate Base

15,500 SQFT

309 Emulsified Asphalt Treated Base Course (crushed aggregate) 12,000 TON

DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Hot Asphalt Concrete Pavement (asphalt concrete pavement) 240 TON 409 Asphalt Surface Treatment Surface Treatment, Designation 2C

52,400 SQYD

Emulsified Asphalt, Grade CRS-2P

220 TON

DIVISION 600 – Incidental Construction 602 Culverts & Drains (indicate one or both) 24-Inch Culvert

1,900 LNFT

36-Inch Culvert

600 LNFT

60-inch Culvert

100 LNFT

72-Inch Culvert

74 LNFT

84-Inch Culvert

62 LNFT

108-Inch Culvert

88 LNFT

S ch ed ul e

Sc h

N

617 Guardrail Guardrail G4, Type 2, Class A, Wood Posts

3,925 LNFT

Terminal Section Type Tangent

14 EACH

621 Monuments & Markers (construction survey & staking) Settlement Plate Assembly

6 EACH

622 Rental Equipment (yes/no) Yes 624 Topsoil (landscaping & related items) 4-Inch Depth

19,900 SQYD

625 Turf Establishment (indicate seeding or mulching separately) 54 SLRY 633 Permanent Traffic Control Devices (traffic control devices) Sign System

59 SQFT

635 Temporary Traffic Control – Flagger 7,000 FXHR 646 Buildings and Fixtures (use pay item description) Roadside Development

(Biofiltration Swale)

1,875 LNFT

647 Mitigation (use pay item description) Fish Passage Boulder

46 EACH

Stream Bed Material

355 CUYD