OR PFH 102(4) Cody Road Wamic Market Grade Reconstruction; OR WASCO 104(1) Rail Hollow Overlay
Solicitation number
DTFH70-15-B-00004
Issued by

View the file

Other files

File Type Posted
A004_CodyRoad-Wamic.pdf PDF
A003_Cody.pdf PDF
A002_CodyRd.pdf PDF
A001_Cody.pdf PDF
http //www.wfl.fhwa.dot.gov/contracting/construction/plans/cody/ —
Physical_Data_Request_Form_CodyRd.pdf PDF
Plan_Request_CodyRd.pdf PDF
IFB_CodyRoad.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OR PFH 102(4), Cody Road – Wamic Market Grade Reconstruction, OR WASCO 104(1) Rail Hollow Overlay Wasco County, Oregon

The work consists of grading, drainage, base, paving, striping, signage and other small items of work.

Total Project length: 2.95 Miles

Tentative Fixed Completion Date: Mid-August 2015 (Once solicitation is issued, see FAR Clause 52.211-10 for exact date.)

Estimated Price Range: $2 million to $3 million

Location: Rail Hollow Overlay is just outside of Dufur, Oregon and Cody Road is

0.5 Miles SW of Tygh Valley, Oregon

DESCRIPTION OF WORK in US CUSTOMARY UNITS

FP-14

DIVISION 150 – Project Requirements 152 Construction Survey & Staking Yes 153 Contractor Quality Control and Assurance

Yes 154 Contractor Sampling & Testing Yes 155 Schedules for Construction Contracts (construction schedules) Yes 157 Soil Erosion & Sediment Control(soil stabilization) 6 ACRE 157 Soil Erosion & Sediment Control(Fiber Roll, Sediment Wattle) 4,100 LNFT 158 Watering for Dust Control 2 MGAL

DIVISION 200 – Earthwork 201 Clearing & Grubbing 6.0 ACRE 203 Removal of Structures & Obstructions (sign/marker) 5 EACH 203 Removal of Structures & Obstructions (guardrail) 2,122 LNFT 203 Removal of Structures & Obstructions (Pipe Culvert) 180 LNFT 204 Excavation & Embankment 39,550 CUYD 204 Unclassified Borrow 2,420 CUYD 211 Roadway Obliteration 3,510 SQYD

DIVISION 250 – Slope Reinforcement and Retaining Walls 251 Riprap 20 CUYD 253 Gabions 371 SQFT

DIVISION 300 – Aggregate and Base Courses 302 Crushed Aggregate, Method 2 12,000 TON

DIVISION 400 – Asphalt Pavements & Surface Treatments 403 Asphalt Concrete 3,000 TON 412 Asphalt Tack Coat (asphalt surface treatment) 12 TON

DIVISION 600 – Incidental Construction 601 Minor Concrete Structures(concrete-minor structures) 30 SQYD

OR PFH 102(4), Cody Road – Wamic Market Grade Reconstruction, OR WASCO 104(1) Rail Hollow Overlay Wasco County, Oregon

602 Culverts & Drains (24” culvert) 300 LNFT 604 Inlet (Ditch Inlet, Type D) 2 EACH 609 Curb (Concrete 16 Inch Depth) 80 LNFT 609 Curb (Asphalt 4 Inch Depth) 225 LNFT 617 Guardrail (System G4, Type 4, Wood Posts) 2,450 LNFT 617 Terminal Section (Type Tangent) 1 EACH 617 Terminal Section (Type LST) 5 EACH 622 Rental Equipment yes 623 General Labor yes 624 Topsoil (conserved-6” depth) 4 ACRE 625 Turf Establishment (indicate seeding or mulching separately) 6 ACRE 633 Permanent Traffic Control (sign system) 35 SQFT 633 Permanent Traffic Control (object marker-culvert) 8 EACH 634 Permanent Pavement Markings (type A solid white) 18,000 LNFT 634 Permanent Pavement Markings (type A solid yellow) 18,000 LNFT 635 Temporary Traffic Control –signal system 1 LPSM 635 Temporary Traffic Control – barricade type 3 7 EACH 635 Temporary Traffic Control-tubular marker 70 EACH 635 Temporary Traffic Control-warning light type A 7 EACH 635 Temporary Traffic Control-warning light type B 6 EACH 635 Temporary Traffic Control-Warning Light type C 80 EACH 635 Temporary Traffic Control-crash cusion marker 8 EACH 635 Temporary Traffic Control-concrete barrier 4000 LNFT 635 Temporary Traffic Control-construction sign 259 SQFT 635 Temporary Traffic Control-flagger 1,480 FXHR 635 Temporary Traffic Control-traffic control supervisor 74 DAY 646 Fixture (Bench) 2 EACH 646 Fixture (Kiosk) 1 EACH