DESCRIPTION OF PROJECT:
WA FS ERFO 2007(1)-20(20) Project Number:
Evergreen Road Emergency Repairs Project Name:
Project Length: 0.111 MILES
Description & type of Work:
This work consists of emergency repairs, including debris removal, grading, reinforced soil slopes, drainage, riprap, and aggregate surfacing.
LOCATION:
FOREST, PARK, BLM DIST, etc. Mt. Baker-Snoqualmie National Forest
COUNTY Snohomish
STATE Washington
THIS PROJECT IS LOCATED AT:
Approx. 40 miles east of Monroe Washington
(City) (State)
PRICE RANGE:
X $500,000 to $1 million
CONTRACT TIME – The Government Estimate is based on:
SCHEDULE
FIXED COMPLETION
DATE
(indicate # of schedules)
One
One Schedule
(required information) October 15, 2009
DESCRIPTION OF WORK (check one):
X US CUSTOMARY UNITS
DIVISION 150 – Project Requirements
152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing X YES NO 155 Schedules for Construction Contracts (construction schedules) X YES NO 157 Diversion Channel Soil 175 LNFT 157 Erosion Control, Sediment Wattle 700 LNFT
DIVISION 200 – Earthwork
201 Clearing and Grubbing 1 LPSM 203 Removal of Pipe Culvert 3 EACH 204 Roadway Excavation 3,000 CUYD 204 Subexcavation 100 CUYD 204 Unclassified Borrow 15 CUYD 207 Earthwork Geotextile 725 SQYD
DIVISION 250 - Slope Reinforcement and Retaining Walls
251 Placed Riprap, Class 3 3,025 CUYD 251 Placed Riprap, Class 3 (with welded wire mats) 700 CUYD 251 Keyed Riprap 1,075 CUYD 255 Select Granular Backfill 100 CUYD 272 Reinforced Soil Slope, Geogrid 220 SQFT
DIVISION 300 – Aggregate Courses
308 Roadway Aggregate, Method 1 350 TON
DIVISION 600 – Incidental Construction
602 Government Furnished – 60 Inch Pipe Culvert 42 LNFT 602 78-Inch Equivalent Diameter Arch or Elliptical Pipe Culvert 46 LNFT 622 Dump Truck 36 HOUR 622 Hydraulic Excavator 36 HOUR 625 Turf Establishment 5 SLRY 629 Rolled Erosion Control Product 100 SQYD 635 Temporary Traffic Control, Barricade Type 3 2 EACH 635 Temporary Traffic Control, Warning Light Type A 4 EACH 635 Temporary Traffic Control, Construction Sign 10 SQFT