Description of Work Elements

View the file

Other files

File Type Posted
Amendment A001 —
RFP —
http //www.wfl.fhwa.dot.gov/contracting/construction/idiq/wa-area-4.htm HTM file
http //www.wfl.fhwa.dot.gov/edi/plans/evergreen/ —
PlanRequest for Internet.pdf PDF
Physical Data request form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESCRIPTION OF PROJECT:

WA FS ERFO 2007(1)-20(20) Project Number:

Evergreen Road Emergency Repairs Project Name:

Project Length: 0.111 MILES

Description & type of Work:

This work consists of emergency repairs, including debris removal, grading, reinforced soil slopes, drainage, riprap, and aggregate surfacing.

LOCATION:

FOREST, PARK, BLM DIST, etc. Mt. Baker-Snoqualmie National Forest

COUNTY Snohomish

STATE Washington

THIS PROJECT IS LOCATED AT:

Approx. 40 miles east of Monroe Washington

(City) (State)

PRICE RANGE:

X $500,000 to $1 million

CONTRACT TIME – The Government Estimate is based on:

SCHEDULE

FIXED COMPLETION

DATE

(indicate # of schedules)

One

One Schedule

(required information) October 15, 2009

DESCRIPTION OF WORK (check one):

X US CUSTOMARY UNITS

DIVISION 150 – Project Requirements

152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing X YES NO 155 Schedules for Construction Contracts (construction schedules) X YES NO 157 Diversion Channel Soil 175 LNFT 157 Erosion Control, Sediment Wattle 700 LNFT

DIVISION 200 – Earthwork

201 Clearing and Grubbing 1 LPSM 203 Removal of Pipe Culvert 3 EACH 204 Roadway Excavation 3,000 CUYD 204 Subexcavation 100 CUYD 204 Unclassified Borrow 15 CUYD 207 Earthwork Geotextile 725 SQYD

DIVISION 250 - Slope Reinforcement and Retaining Walls

251 Placed Riprap, Class 3 3,025 CUYD 251 Placed Riprap, Class 3 (with welded wire mats) 700 CUYD 251 Keyed Riprap 1,075 CUYD 255 Select Granular Backfill 100 CUYD 272 Reinforced Soil Slope, Geogrid 220 SQFT

DIVISION 300 – Aggregate Courses

308 Roadway Aggregate, Method 1 350 TON

DIVISION 600 – Incidental Construction

602 Government Furnished – 60 Inch Pipe Culvert 42 LNFT 602 78-Inch Equivalent Diameter Arch or Elliptical Pipe Culvert 46 LNFT 622 Dump Truck 36 HOUR 622 Hydraulic Excavator 36 HOUR 625 Turf Establishment 5 SLRY 629 Rolled Erosion Control Product 100 SQYD 635 Temporary Traffic Control, Barricade Type 3 2 EACH 635 Temporary Traffic Control, Warning Light Type A 4 EACH 635 Temporary Traffic Control, Construction Sign 10 SQFT