RECOVERY - MT PRA-GLAC 10(23), GTSR Rehabilitation, Big Bend to Logan Pass, Phase VIII
Solicitation number
DTFH70-08-R-00032
Issued by

About this file

Preliminary quantities and elements of work

View the file

Other files

File Type Posted
A001 —
Physical Data Request Form for Internet.pdf PDF
FBO-RFP.pdf PDF
http //www.wfl.fhwa.dot.gov/edi/plans/bigbend/ —
PlanRequestforInternet.pdf PDF
http //www.wfl.fhwa.dot.gov/edi/plan-in-hand/bigbend/ —
Tech_Submit_Req.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DESCRIPTION OF PROJECT:

MT PRA-GLAC 10(23) Project Number:

Going to the Sun Road Rehabilitation, Big Bend to Logan Pass, Phase VIII Project Name:

Project Length: 2.84 Miles

Description & type of Work:

This work consists of Grading, base, pavement, drainage (including concrete box culverts), retaining walls and stone masonry guardwalls.

(e.g. grading, drainage, base, paving, structure, etc.)

LOCATION: Glacier National Park, Montana FOREST, PARK, BLM DIST, etc. Glacier National Park COUNTY Flathead

STATE

Montana

THIS PROJECT IS LOCATED APPROXIMATELY:

Miles

Northeast

Columbia Falls Montana of (City) (State)

PRICE RANGE:

X Over $20 million

CONTRACT TIME – The Government Estimate is based on:

SCHEDULE

FIXED COMPLETION

DATE

One Schedule October 20, 2011

DESCRIPTION OF WORK:

US CUSTOMARY UNITS

DIVISION 150 – Project Requirements 152 Construction Survey & Staking X YES NO 153 Contractor Quality Control and Assurance X YES NO 154 Contractor Sampling & Testing X YES NO 155 Schedules for Construction Contracts (construction schedules) X YES NO 157 Soil Erosion Control Devices (erosion control devices)

Sandbags Inlet Protection

250 Each 15 Each

158 Watering for Dust Control 2.2 MGAL

DIVISION 200 – Earthwork 201 Clearing & Grubbing 1,000 SQYD 204 Excavation & Embankment

Roadway Excavation Subexcavation Select Borrow

2,615 CUYD

4,100 CUYD

4,100 CUYD

207 Earthwork Geotextiles (geotextiles) Geogrid Other Geotextiles

17,150 SQYD

5,900 SQYD

DIVISION 250 - Slope Reinforcement and Retaining Walls 251 Riprap 1,500 CUYD 255 Mechanically Stabilized Earth Walls (retaining walls) 2,170 SQFT Other: Compaction Grouting Drilled Column (4” dia.)

Grout

5,500 LNFT

215 CUYD

DIVISION 300 – Aggregate Courses 310 Recycled Aggregate Course (asphalt pavement recycling) 38,500 SQYD

DIVISION 400 – Asphalt Pavements & Surface Treatments 401 Superpave Hot Asphalt Concrete Pavement 6,500 Ton 411 Asphalt Prime Coat (asphalt surface treatment) 48 Ton 412 Asphalt Tack Coat (asphalt surface treatment) 13 Ton

DIVISION 550 – Bridge Construction 566 Shotcrete

Guardwall Underpinning 40 CUYD

DIVISION 600 – Incidental Construction 602 Culverts & Drains (indicate one or both)

Pipe Culverts Concrete Box Culverts

1,300 LNFT

125 LNFT

609 Curb & Gutter (concrete – minor structures) (indicate which) Colored concrete curb and gutter 1,000 LNFT

619 Fences, Gates & Cattle Guards Fences, Log Rail

Stone Masonry Guardwall (Ashlar & Random Rubble) Stone Masonry Guardwall (Repair) Stone Masonry Guardwall (Veneer)

400 LNFT

2,500 LNFT

275 SQYD

834 SQYD

621 Monuments & Markers (construction survey & staking) X YES NO