Addressing the Challenges and Return on Investment (ROI) for Paperless Project Delivery (e-Construction)
Interim Report (Task 4)
January 2016
Updated: March 2016
FHWA Contract DTFH61-14-C-00045 Addressing Challenges and Return on Investment (ROI) for Paperless Project Delivery (e-Construction)
Note: The Federal Highway Administration, State Highway
Agencies listed in the report, and the authors do not endorse any of the products or manufacturers/vendors listed in this report.
Trademarks or vendors/manufacturers appear in this report only because they are considered essential to the objective of the document.
i | P a g e
Table of Contents
Introduction e-Construction Definition
Phase I Approach
Summary of Findings
State of Practice
Common Tools Used for e-Construction
Summary of State Agency Maturity
AASHTO Survey Findings
Respondents
Summary of Findings
Contractor Survey Findings
Summary of Findings
Interview Findings
Documented Benefits and Costs
Implementation Challenges and Lessons Learned
Implementation Challenges
Lessons Learned
Conclusion
Next Steps
Appendix A: AASHTO Survey Findings
Appendix B: Contractor Survey Findings
Table of Exhibits
Exhibit 1: Research Approach
Exhibit 2: e-Construction Findings Summary
Exhibit 3: e-Construction Maturity Overview
Exhibit 4: Overview of Software Used in e-Construction
Exhibit 5: Summary of State DOTs’ e-Construction Practices and Maturity
Exhibit 6: Summary of AASHTO Survey Findings
Exhibit 7: Summary of Contractor Findings
Exhibit 8: Agencies Selected for Detailed Follow-Up and Rational for Selection
Exhibit 9: Summary of Interview Findings
Exhibit 10: Oregon Estimated Categories of Savings
Exhibit 11: Documented Benefits of e-Construction file:///C:/Users/leed1/Desktop/FHWA%20e-Construction/4%20-%20Synthesis%20Report/FHWA%20e-Construction%20-%20Task%204%20Report_Final_March%202016_tracked%20changes.docx%23_Toc446321631 ii | P a g e
This Page Intentionally Blank
1 | P a g e
Introduction
The third round of the Every Day Counts (EDC) Initiative focuses on “efficiency through technology and collaboration” through a set of innovations targeted at shortening project development and delivery, enhancing roadway safety, reducing congestion, and improving environmental sustainability. Technical teams have developed implementation plans for each innovation and are managing the deployment effort over a two-year cycle during 2015-2016.
Among the innovations identified for the third round of the EDC initiative is e-Construction; the initiative aims to employ established technologies readily available to the transportation community, including digital electronic signatures, electronic communication, secure file sharing, version control, mobile devices, and web-hosted data archival and retrieval systems, to improve construction documentation management.1
The WSP| Parsons Brinckerhoff team has been retained by the Federal Highway Administration (FHWA) to assess how transportation agencies are transitioning to a more electronic/paperless project delivery system (e-Construction) and document the costs, benefits, and challenges during the transition. This activity provides the necessary return-on-investment (ROI) data to those agencies that are contemplating e-Construction. The scope of e-Construction covers the time from when a project is advertised to when the final project is accepted, and includes the processes used in the central office, field offices, and on the jobsite.
This document synthesizes all of the information gathered from Phase I and presents the best practices currently being used for paperless or electronic project delivery, primarily in the highway construction realm (e-Construction), and the challenges, lessons learned, and opportunities identified along the way.
This document includes findings from our literature search on e-Construction practices in Task 2 and the preliminary findings from the interviews we conducted in Task 3.
e-Construction Definition
This project follows the FHWA Every Day Counts Initiative Round 3 (EDC-3) definition of e-Construction:
A paperless construction administration delivery process, including: electronic submission of all construction documentation by all stakeholders, electronic document routing and approvals
(e-signature), and digital management of all construction documentation in a secure environment allowing distribution to all project stakeholders through mobile devices. The e-Construction process includes the following:2
Electronic capture of construction data.
Electronic submission of construction documentation.
Increased use of mobile devices.
Federal Highway Administration. (2013, November 7). e-Construction. Retrieved from EDC-3 Initiatives:
http://www.fhwa.dot.gov/everydaycounts/edc-3/econstruction.cfm (2014). FHWA Division Office EDC-3: e-Construction Webinar.
2 | P a g e
Increased automation of document review and approval.
Use of electronic signatures throughout the construction process by all parties involved.
Secure document and workflow management accessible on any device.
e-Construction can be used through all steps of the project delivery process, from project advertisement to final project acceptance, including the following:
Bidding and contractor selection/contract award.
Electronic plan documents.
Project construction and management (including utilization, transfer, and approval of electronic plan sets, contractor payroll submittals, claims, and change orders).
Project inspection and data collection.
Project acceptance (including punch lists, as-built submittal, and entering warranty phase).
Project close-out (including retainage release and entering warranty phase).
Project communications (e.g., public information management and internal communications).
Resource tracking (e.g., equipment, personnel, fleet, etc.).
3 | P a g e
Phase I Approach
This research project is divided into two phases: Phase I and Phase II, as illustrated in Exhibit 1.
Exhibit 1: Research Approach
The tasks in Phase 1 primarily involved collecting available information on agency practices in e-Construction, including documenting successes, challenges, and opportunities, as follows:
Task 2: Research Current and Evolving Practice involved conducting a comprehensive literature review for information on past and ongoing efforts of agencies for paperless or electronic project delivery, mainly in the highway construction realm (e-Construction), and identifying the leading agencies that use these practices.
Task 3: Document Successes, Challenges, and Opportunities included three components:
analyzing results of a web-based survey administered by the American Association of State
Highway and Transportation Officials (AASHTO) Subcommittee on Construction, surveying contractors, and conducting more detailed interviews with a subset of state highway agencies and airports with more progressive e-Construction practices. The AASHTO Subcommittee on
Construction survey aims to understand the use of e-Construction technology in project delivery with a specific emphasis on understanding the processes, tools, and systems used and the associated implementation costs and benefits. Based on the results of the web-based survey, the project team identified a subset of lead agencies to interview and obtain more information about their e-Construction practices. Two state agencies, the Michigan Department of
Transportation (Michigan DOT) and the Florida Department of Transportation (Florida DOT), were selected to be interviewed in advance of the release of the AASHTO survey results since both agencies were already recognized as national leaders in e-Construction. The project team also administered a survey to a list of contractors that was provided by state highway agencies to identify their construction practices and determine how they compare to those of state DOTs.
Task 4: Prepare Interim Report consolidates the information from prior tasks.
The second phase of the project will focus on detailing the scope of implementation (e.g., project size, contracting method), opportunities for automation, assessing the feasibility of these opportunities, and preparing implementation guidance for agencies.
4 | P a g e
Summary of Findings
State of Practice
There is an active national interest in implementing e-Construction, including electronic bidding and contract award, project collaboration tools, mobile tools, and electronic project document management. Many agencies have begun implementing pieces of e-Construction. However, some agencies are holding off because of a lack of clarity on where to begin and the uncertainty of the cost and feasibility of implementing e-Construction. Exhibit 2 summarizes the findings in this report.
Exhibit 2: e-Construction Findings Summary
Exhibit 3, which was included as a part of the FHWA EDC-3 Implementation Plan for e-Construction, summarizes the status of implementation of e-Construction by state DOTs across the nation, based on polling during regional summits. State highway agencies identified as “National Leaders” have adopted and implemented e-Construction technology and have constructed two or more projects using e-Construction technology. State highway agencies identified as “Potential Leads” have made strides in advancing e-Construction and may be national leaders, but further investigation is required. State highway agencies that have investigated or piloted some aspects of the e-Construction technology are labeled “Exploring.” Finally, agencies that are labeled as “Discussing” are not taking part in the national
EDC-3 technology initiative but are discussing potential e-Construction implementing. As of February
2016, 30 percent of agencies have adopted e-Construction, 64 percent of agencies are exploring e-
Construction technologies, and 6 percent of agencies have not yet used e-Construction. Based on the
EDC-3 regional summits and the results of target audience polling, the goal for the end of 2016 is that 40
5 | P a g e percent of states will have adopted e-Construction and at least 66 percent of states will have piloted e-
Construction.3
Exhibit 3: e-Construction Maturity Overview
The state of practice of e-Construction varies widely between agencies; state DOTs use different levels of automation for steps in the project-delivery process, from using paper documentation for most project delivery steps, to going completely paperless for the entire construction process. The Michigan
DOT, for example, has moved toward becoming completely paperless and is having all state highway system projects use e-Construction (as of the 2015 construction season). The Florida DOT is completing an e-Construction pilot project at the time of this report preparation. The Iowa DOT is working toward becoming completely paperless for highway projects from the design phase through construction.
However, some agencies are holding off on implementing e-Construction because of the lack of clarity on where to begin and the uncertainty of the cost and feasibility.
Common Tools Used for e-Construction
The most commonly used element of e-Construction is electronic bidding; 39 state departments of transportation have implemented electronic bidding through the use of Bid Express, a web-based electronic bidding software. In addition, the Connecticut DOT and the Wisconsin DOT use a digital review process for construction plan documents.
FHWA, Every Day Counts 3: e-Construction Implementation Plan, Available:
http://www.fhwa.dot.gov/construction/econstruction/implementation_plan.pdf http://www.fhwa.dot.gov/construction/econstruction/implementation_plan.pdf
6 | P a g e
Project collaboration tools, such as Bluebeam for as-built markups, and information management systems, such as ProjectWise to manage construction documentation, help agencies streamline the construction process by expediting document distribution, submission, review, and approval. Bluebeam enables multiple people to review a document simultaneously, in-real time, and mark it up electronically. ProjectWise enables staff to access documents, regardless of whether they are in the office or out in the field, and has workflow capabilities to streamline the approval process.
Multiple agencies reported using mobile devices, which enables inspectors and surveyors to access the latest construction documents wherever they are, take notes and photos in the field and attach them to files, and collaborate with office staff in real-time (e.g., ask specific design/construction field questions) through video conferencing. Mobile devices also enable staff to be more efficient; inspectors are able to perform their duties without having to sacrifice time for recordkeeping and are able to enter data quickly and minimize data entry redundancies.
Exhibit 4 provides an overview of the common types of applications, services, and software used for e-Construction; the key project elements of the construction administration delivery process that the applications, services, and software are applicable to; and the state DOTs that use the e-Construction solution. Many of these technologies are not specific to the construction industry, but rather, broader collaboration tools used across an array of other industries (e.g., PDF, Bluebeam, SharePoint, ProjectSolve, Facetime, etc.).
Exhibit 4: Overview of Software Used in e-Construction
Category Application/Service/Software Project Elements State DOT/
Project Users
Plans, Specification, and Estimates
(PS&E)
Adobe
PDF solution for creating, editing, and managing documents; used for plan set review and signing and sealing plan sets
PS&E Michigan DOT
Texas DOT
VTrans
MicroStation
CAD software used for project design
PS&E Florida DOT
North Carolina
DOT
Oregon DOT
Texas DOT
Note: The Federal Highway Administration, State Highway Agencies listed in the report, and the authors do not endorse any of the products or manufacturers/vendors listed in this report.
Trademarks or vendors/manufacturers appear in this report only because they are considered essential to the objective of the document.
7 | P a g e
Exhibit 4: e-Construction Software Overview (Cont’d)
Category Application/Service/Software Project Elements State DOT/
Project Users
Electronic Bidding Bid Express
Internet bidding service that enables an agency and contractors to communicate with each other; it is used to submit the bid, view and download project information, and access plans and bid data online;
this service is often used in conjunction with the Expedite Bid software.
PS&E
Bidding and Contractor Selection/Contract Award
Caltrans
Florida DOT
Iowa DOT
Kentucky Transportation Cabinet
Michigan DOT
Minnesota DOT
New Jersey DOT
North Carolina
DOT
Oregon DOT
VTrans
Expedite Bid Software
Software used to prepare, validate, and analyze an electronic bid and is often used in conjunction with the
Bid Express service
PS&E
Bidding and Contractor Selection/Contract Award
Caltrans
ExeVision integrated Project
Development (iPD)
Comprehensive project development system that integrates all functional aspects of construction, including cost estimating and electronic bidding through final contractor payment
PS&E
Bidding and Contractor Selection/Contract Award
Texas DOT
Project
Collaboration
Bluebeam Revu
Software used to edit and markup digital plans collaboratively
Project Construction and Management
Project Acceptance
Connecticut DOT
Florida DOT
Digital InterPlot
Server used to create, store, and share construction plans
PS&E Utah DOT
8 | P a g e
Exhibit 4: e-Construction Software Overview (Cont’d)
Category Application/Service/Software Project Elements State DOT/
Project Users
Project
Collaboration
(con’t)
Doc Express
Paperless contracting service that enables document exchange during construction projects; also allows for electronic signatures
PS&E
Project Construction and Management
Alaska DOT&PF (piloting)
Iowa DOT
SharePoint
Web application framework used for collaboration to centralize access to project information
Project Construction and Management
Denver International Airport
Florida DOT
North Carolina
DOT
Utah DOT
ProjectSolve
Internet-based collaboration tool that allows project teams to communicate and collaborate with each other
Project Construction and Management
Florida DOT
Data Storage HybridCloud Server
Storage solution that provides the ability for secure and controlled access to data from any device with internet access; includes a local storage component that can be a network-attached storage device
Project Construction and Management
Dallas/Fort Worth International Airport
Document
Management
Electronic Document Management
System
Software that manages the creation, storage, tracking, and control of documents electronically
Project Construction and Management
Florida DOT
Michigan DOT
Texas DOT
ProjectWise
Suite of software used for information management to manage, share, and distribute project materials in a single platform
Project Construction and Management
Michigan DOT
Oregon DOT
Texas DOT
Utah DOT
9 | P a g e
Exhibit 4: e-Construction Software Overview (Cont’d)
Category Application/Service/Software Project Elements State DOT/
Project Users
Project
Management
Primavera P6
Project management software to assist with planning, scheduling, and controlling project resources
Project Construction and Management
Denver International Airport
Minnesota DOT
Texas DOT
AASHTOWare Project SiteManager
Enterprise software suite that includes modules used to manage contract administration, contract records, daily work reports, contractor payments, materials management, and laboratory inventory management
PS&E
Bidding and Contractor Selection/Contra ct Award
Alaska DOT&PF
Florida DOT
Texas DOT
VTrans
West Virginia
DOT
Payment Electronic Project Record System
Online program that allows contractors to submit \ payrolls over the internet
Project Construction and Management
Texas DOT
Field Manager/FieldBook
Software suite used to manage construction projects; used for contractor payments
Project Construction and Management
Iowa DOT
Michigan DOT
Mobile FaceTime
Video chat application that enables collaboration between field staff and office staff
Project Construction and Management
Florida DOT
Michigan DOT
North Carolina
DOT
Texas DOT
Although a majority of agencies use commercial off-the-shelf software tools, a number of custom developed systems that agencies use include the following:
California Department of Transportation (Caltrans) o Two mainframe systems to initiate the project process:
A mainframe system to feed some basic project information.
Bid analysis system to determine the lowest bidder.
10 | P a g e o Internet Extra Work Bill (iEWB) system enables the verification and validation of electronic extra work bills for accuracy, which results in greater efficiency in processing of bills.
North Carolina DOT o Highway Construction and Materials System (HiCAMS) was developed in house in 1999 to track all inspections, materials, and test results, as well as for contractor payments.
Texas DOT o Bid Proposal Request System is a custom application that checks for contractors’ available bidding capacity.
o Electronic Project Record System (EPRS) is a custom-developed software that acts as a portal to collect payroll information from contractors.
VTrans o Construction Contract Finals is a cloud-based business process management software
(BPMS) used for construction close-out when field staff package all of their field records and turn them over to the Finals unit.
Summary of State Agency Maturity
A summary of agency practices, as identified through the literature review in Task 2 and the findings from the AASHTO survey and detailed interviews from Task 3, are presented in Exhibit 5 using a maturity framework to show where agencies fit on a maturity scale (ranging from nascent to mature).
Appropriate annotations regarding what the scale means for each category are also provided in the table. The practices are divided into the following key elements of the construction administration delivery process:
1. Transfer/Sharing of PS&E, which includes:
o Plans and specification documents in Computer Aided Design and Drafting (CADD) or ED
(geospatial) format.
o Tie-in of 3D plans to automated machine guidance (AMG) equipment.
2. Bidding and Contractor Selection/Contract Award, which includes:
o Electronic bidding through automated software.
o Electronic signatures.
3. Project Construction and Management, which includes:
o Electronic review and approval process (digital signatures/reviews).
o Collaborative sharing sites.
o Material testing and quality assurance records (including Quality Control, independent verification, inspection, and acceptance testing).
o Contractor payroll submittals.
o Claims and change orders.
o Mobile technologies for data collection.
11 | P a g e
4. Project Inspection and Testing, which includes:
o Tracking of inspection activities and material testing results.
o Survey instruments.
5. Project Acceptance, which includes:
o Providing documentation (e.g., punch lists, as-builts submittal, entering warranty phase) in the form of CAAD files or 3D as-built models.
6. Project Close-Out, which includes:
o Tracking of warranty items.
o Payment release.
7. Data Sharing between Steps/Phases, which includes:
o Electronic transfer of data between systems (e.g., contractor payment approvals to financial and accounting systems).
o Use of Civil Integrated Management practices.
12 | P a g e
13 | P a g e
Exhibit 5: Summary of State DOTs’ e-Construction Practices and Maturity
Process Step | Maturity Level Level 1
Nascent
Level 2
Intermediate
Level 3
Mature Transfer/Sharing of Plans, Specifications and Estimates (PS&E)
Alabama DOT
Alaska DOT&PF
Arkansas SHTD
Colorado DOT
New Hampshire DOT
Ohio DOT
Pennsylvania DOT
Virginia DOT
Washington DOT
Caltrans
Connecticut DOT
Florida DOT
Kansas DOT
Kentucky Transportation
Cabinet
Louisiana DOT
Massachusetts DOT
Michigan DOT
Minnesota DOT
Nebraska DOR
New Jersey DOT
North Carolina DOT
North Dakota DOT
VTrans
West Virginia DOT
Iowa DOT
Oregon DOT
Texas DOT
Paper PS&E packet, may be scanned to be converted to electronic files, and paper plan review
Electronic files in CADD software format and electronic plan review
3D plans (geospatial) that allow quantity take-offs, tie-in to AMG equipment
Bidding and Contractor Selection/Contract
Award
Alaska DOT&PF
New Hampshire DOT
Alabama DOT
Florida DOT
Minnesota DOT
Nebraska DOR
North Carolina DOT
Oregon DOT
Texas DOT
Arkansas SHTD
Caltrans
Colorado DOT
Connecticut DOT
Iowa DOT
Kansas DOT
Kentucky Transportation Cabinet
Louisiana DOT
Massachusetts DOT
Michigan DOT
Missouri DOT
New Jersey DOT
North Dakota DOT
Ohio DOT
Pennsylvania DOT
Tennessee DOT
Utah DOT
VTrans
Virginia DOT
Washington DOT
West Virginia DOT
Paper bidding and selection Online bidding as well as offline/paper bids Mandatory electronic bidding through Bid Express or other automated software, including electronic signatures
Project Construction and Management
(including digital review, contractor payroll submittals, claims, and change orders)
None identified Alabama DOT
Alaska DOT&PF
Caltrans
Connecticut DOT
Florida DOT
Iowa DOT
Kansas DOT
Louisiana DOT
North Dakota DOT
Oregon DOT
Utah DOT
Washington DOT
Wisconsin DOT
Arkansas SHTD
Colorado DOT
Connecticut DOT
Florida DOT
Iowa DOT
Kentucky Transportation Cabinet
Michigan DOT
Nebraska DOR
New Hampshire DOT
North Carolina DOT
Ohio DOT
Pennsylvania DOT
Texas DOT
VTrans
Virginia DOT
West Virginia DOT
Paper documentation (contractor and owner) Combination of paper and semi-electronic systems (e.g., Microsoft Word to track daily reports stored on a computer)
Electronic construction management systems (e.g., SiteManager) to track daily reports, progress percentage, change orders, payments, and other information
14 | P a g e
Exhibit 5: Summary of State DOTs’ e-Construction Practices and Maturity (Cont’d)
Process Step | Maturity Level Level 1
Nascent
Level 2
Intermediate
Level 3
Mature
Project Inspection and Testing Caltrans
Massachusetts DOT
Oregon DOT
Alabama DOT
Alaska DOT&PF
Arkansas SHTD
Colorado DOT
Connecticut DOT
Florida DOT
Iowa DOT
Kansas DOT
Louisiana DOT
Nebraska DOR
New Hampshire DOT
Nevada DOT
North Carolina DOT
North Dakota DOT
Ohio DOT
Texas DOT
VTrans
Virginia DOT
West Virginia DOT
Washington DOT
Wisconsin DOT
Michigan DOT
Pennsylvania DOT
Manual, paper-based tracking of inspection activities and materials testing. Analog tools (straight edges, measuring wheels) in use
Mix of manual and electronic systems (e.g., SiteManager) to track inspections and material test results
Electronic systems (e.g., SiteManager) to track all inspections and materials test results.
Capability to geo-code data (e.g., indicate location of test cores). Survey instruments to check tolerance against design (geospatial rovers) – pay plan quantities
Project Acceptance (including punch lists, as-builts submittal and entering warranty phase)
Alabama DOT
Alaska DOT&PF
Arkansas SHTD
Florida DOT
Massachusetts DOT
Nebraska DOR
New Hampshire
North Carolina DOT
North Dakota DOT
Oregon DOT
Pennsylvania DOT
VTrans
Virginia DOT
Washington DOT
Caltrans
Connecticut DOT
Iowa DOT
Louisiana DOT
Kansas DOT
Ohio DOT
Washington DOT
West Virginia DOT
Wisconsin DOT
Michigan DOT
North Carolina DOT
Paper as-built documentation provided to owner
CADD files provided to owner 3D as-built models provided to owner
Project Close-Out Alabama DOT
Alaska DOT&PF
Caltrans
Connecticut DOT
New Hampshire DOT
Oregon DOT
Virginia DOT
Arkansas SHTD
Iowa DOT
Kansas DOT
Louisiana DOT
Massachusetts DOT
Michigan DOT
Nebraska DOR
North Carolina DOT
Pennsylvania DOT
West Virginia DOT
Florida DOT
Manual tracking of most warranty items Some automated tracking of warranty items through spreadsheets
Release retainage amount to contractor automatically, ability to show all project warranty items and details on a map
Data Sharing between Steps/Phases Louisiana DOT
Massachusetts DOT
Oregon DOT
Connecticut DOT
Iowa DOT
Kentucky
Transportation Cabinet
Nebraska DOR
New Hampshire DOT
North Dakota DOT
Texas DOT
VTrans
Alabama DOT
Arkansas SHTD
Colorado DOT
Florida DOT
Kansas DOT
Michigan DOT
North Carolina DOT
Ohio DOT
Pennsylvania DOT
West Virginia DOT
Washington DOT
Virginia DOT
Mostly paper systems, no data sharing between systems
Stand-alone electronic systems, including spreadsheets and other electronic records
Electronic transfer of data between steps/phases, eliminating duplication. Ability to share data electronically between systems (e.g., contractor payment approvals to financial and accounting systems). Use of Civil Integrated Management practices.
15 | P a g e
AASHTO Survey Findings
Respondents
AASHTO sent the survey to its Subcommittee on Construction. A total of 23 individuals representing 21 agencies responded. These agencies were as follows:
Alabama Department of Transportation
(Alabama DOT)
Arkansas State Highway and
Transportation Department (Arkansas
SHTD)
California Department of
Transportation (Caltrans)
Colorado Department of Transportation
(Colorado DOT)
Connecticut Department of
Transportation (Connecticut DOT)
Florida Department of Transportation
(Florida DOT)
Kansas Department of Transportation
(Kansas DOT)
Kentucky Transportation Cabinet (KYTC)
Louisiana Department of Transportation
(Louisiana DOT)
Massachusetts Department of
Transportation (Massachusetts DOT)
Michigan Department of Transportation
(Michigan DOT)
Nebraska Department of Roads
(Nebraska DOR)
New Hampshire Department of
Transportation (New Hampshire DOT)
North Dakota Department of
Transportation (North Dakota DOT)
Ohio Department of Transportation
(Ohio DOT)
Oregon Department of Transportation
(Oregon DOT)
Pennsylvania Department of
Transportation (Pennsylvania DOT)
Vermont Agency of Transportation
(VTrans)
Virginia Department of Transportation
(Virginia DOT)
Washington Department of
Transportation (Washington DOT)
West Virginia Department of
Transportation (West Virginia DOT)
16 | P a g e
Summary of Findings
Exhibit 6 provides a high-level summary of the AASHTO survey findings for e-Construction practices used for each of the project delivery phases for three different contracting methods: Design-Bid-Build (D-B-B), Design-Build (D-B), and Construction Manager/General Contractor (CM/GC). For a more detailed summary of AASHTO survey findings, see Appendix A.
17 | P a g e
Exhibit 6: Summary of AASHTO Survey Findings
Project Delivery Phase Most Common Practices System/Tools Type Length of Time Level of Satisfaction
Plans, Specifications, and Estimates
Most states reported using electronic files in CADD software format for all contracting methods
Only two states (Oregon DOT and Michigan DOT) reported using 3D plans between all contracting methods
Several agencies cited that they are exploring 3D deliverables, including Florida DOT and West Virginia DOT
The majority of the primary systems/tools are commercial off-the-shelf
Only one agency reported using a paper-based system
More than half of agencies’ primary systems/tools have been in use for more than 10 years, while less than one-third of agencies’ primary systems/tools have been in use for 5 to 10 years
Most agencies reported that they are either satisfied (35 percent) or neither satisfied nor dissatisfied (45 percent) with their primary systems/tools
Bidding and Contractor Selection
The majority of agencies require electronic bidding using Bid Express or other software for D-B-B projects
For D-B and CM/GC, agencies use both online bidding and offline/paper bids
The majority of the primary systems/tools are commercial off-the-shelf
Most agencies responded that their primary systems/tools have been in use for more than 10 years, while one-third of agencies’ primary systems/tools have been in use for one to five years
Most agencies reported that they are very satisfied or satisfied with their primary systems/tools
Project Construction and Management
For D-B-B and D-B projects, most agencies reported using electronic construction management systems
More than half of the primary systems/tools used for Inspection and Testing are commercial off-the-shelf
The majority of agencies reported that their primary systems/tools have been in use for more than 10 years
More than half of agencies (55 percent) reported that they are satisfied with their primary systems/tools.
The second-most
18 | P a g e
Exhibit 6: Summary of AASHTO Survey Findings (Cont’d).
Project Delivery Phase Most Common Practices System/Tools Type Length of Time Level of Satisfaction
Project Construction and Management (Cont’d)
None of the agencies surveyed reported using paper documentation for this phase
No agencies reported using a system for less than one year frequent response was neither satisfied nor dissatisfied (20 percent)
Project Inspection and Testing
For all contracting methods, the majority of agencies use a mix of manual and electronic systems for project inspection and testing
Only one agency (Pennsylvania DOT) reported using electronic equipment for inspections for D-B-B and D-B projects
More than half of the primary systems/tools used for Inspection and Testing are commercial off-the-shelf
The majority of systems have been in use for more than 10 years, while one-quarter of systems have been in use for one to five years
Half of agencies that responded are satisfied
Project Acceptance
For all contracting methods, the majority of agencies use paper as-built documentation that is provided to the owner
While several agencies reported providing CADD files to the owner, none of the agencies reported using 3D as-built models for Project Acceptance
The majority of the primary systems/tools are commercial off-the-shelf
More than two-thirds of responding agencies reported that their current Project Acceptance systems/tools have been implemented for over 10 years
None of the agencies are using a system that is less than one year old
Level of satisfaction with Project Acceptance systems/tools varies widely
19 | P a g e
Exhibit 6: Summary of AASHTO Survey Findings (Cont’d).
Project Delivery Phase Most Common Practices System/Tools Type Length of Time Level of Satisfaction
Project Close-Out
For D-B-B projects, most agencies reported using some combination of electronic and paper practices for Project- Close-Out, while one-third of agencies reported having manual tracking of warranty items
For D-B projects, agencies use both manual and automated tracking for most warranty items
Only one agency (Florida DOT) reported having fully automated tracking of warranty items for both D-B-B and D-B projects
About one-third of primary systems/tools are commercial off-the-shelf and about one-third are paper-based
About one-quarter of systems/tools are custom-designed
Almost two-thirds of responding agencies reported that their primary systems/tools have been implemented for over 10 years
Only one agency reported using a system that is less than one year old
Most agencies are either satisfied or neither satisfied nor dissatisfied with their systems/tools
Data Sharing
For D-B-B projects, nearly half of responding agencies use stand-alone electronic systems
For D-B projects, most agencies use electronic transfer of data between phases
The majority of primary systems used for Data Sharing are custom designed
The majority of responding agencies reported that their current Data Sharing systems/tools have been implemented for over 10 years
Most agencies are satisfied with their Data Sharing systems/tools, while one-quarter are dissatisfied
20 | P a g e
Contractor Survey Findings
The project team administered a survey to a list of contractors, independent of the AASHTO survey. The names of contractors were provided by state highway agencies during initial interviews. This contractor survey focused on identifying the tools that contractors use for each step of the project delivery process
(and comparing these tools to those of state highway agencies), as well as the benefits and challenges associated with implementation. Four contractors responded, and their responses were analyzed to determine their construction practices and how they compare to those of state DOTs.
These firms have construction programs ranging from $50 million to $160 million in size, with the number of projects ranging from 20 to 50 projects to as many as 600 to 700 projects. These firms have collectively worked with the following state highway agencies:
Alabama DOT
Florida DOT
Georgia DOT
Indiana DOT
Iowa DOT
Kansas DOT
Michigan DOT
Missouri DOT
Minnesota DOT
Nebraska DOR
North Carolina DOT
North Dakota DOT
South Dakota DOT
Tennessee DOT
Texas DOT
Virginia DOT
Wisconsin DOT
Summary of Findings
Exhibit 7 summarizes findings from the contractor survey. For a more detailed summary of contractor findings, see Appendix B.
Exhibit 7: Summary of Contractor Findings
Project Delivery Phase Findings
Comparison to State Highway Agency Practices
Plans, Specifications, and Estimates
No one practice is used more frequently than others by the contractors surveyed
Most state agencies surveyed reported using electronic files in CADD software format
Bidding and Contractor Selection
Contractors use electronic bidding most frequently
Aligns with state highway agencies’ practices
21 | P a g e
Exhibit 7: Summary of Contractor Findings (Cont’d)
Project Delivery Phase Findings
Comparison to State Highway Agency Practices
Project Construction and Management
Two contractors reported that electronic construction management systems are used most frequently
One contractor reported that a combination of paper and semi-electronics systems is used most frequently
Three of the four contractors reported that paper documentation is rarely used, although one contractor reported that it is used commonly
Aligns with state agency practice
Agencies are either using a combination of paper and semi-electronic systems or electronic construction management systems; paper documentation is rarely used
Project Inspection and Testing
Three of the four contractors reported that manual, paper-based inspection activities and materials testing are rarely used, and one contractor reported that it is never used
Two contractors reported that survey instruments to as-built and CADD to compare to design and measure are used commonly, and two contractors reported that they are rarely/never used
Two contractors reported using electronic systems most frequently
Paper-based inspection activities was not common among state agencies—only 3 of the 21 agencies that responded reported using manual, paper-based systems
The majority of state agencies use a mix of manual and electronic systems for project inspection and testing; only one agency reported using electronic equipment for inspections
Project Acceptance Three of the four contractors reported that paper as-built documentation provided to the owner is used commonly/frequently
Two of the four contractors reported that providing CADD files to the owner is used commonly
3D as-built models provided to the owner are rarely/never used by the contractors surveyed
State highway agencies had similar responses
The majority of agencies use paper as-built documentation that is provided to the owner
No agencies reported using 3D as-built models for Project Acceptance
22 | P a g e
Interview Findings
Based on the web-based survey responses, the project team used the following selection criteria to select state highway agencies for follow-up:
At least one agency with nascent e-Construction practices.
At least three agencies that are national leaders in e-Construction.
Agencies that have documented e-Construction benefits.
Agencies that represent all regions of the country (West, Midwest, South, and East).
In some instances, agencies that did not respond to the AASHTO survey were selected for detailed follow-up. These agencies were either nascent in their implementation or had mature e-Construction practices. Exhibit 8 outlines the agencies selected for detailed follow-up and the rationale for selection.
Exhibit 8: Agencies Selected for Detailed Follow-Up and Rational for Selection
Agency Key Agency Properties/Criteria
Alaska DOT&PF Did not respond to AASHTO survey but selected based on recent implementation of SiteManager in Northern Region; maturity is nascent.
Caltrans Caltrans is looking to introduce mobile devices as a pilot for construction inspection—released survey to gather lessons learned from other state DOTs; has the largest construction program (in terms of dollars).
Florida DOT Mature e-Construction practices; considered national leader.
Iowa DOT Did not respond to AASHTO survey but selected based on mature e- Construction practices; considered national leader.
Massachusetts DOT Undertaking a department-wide look at how to implement a full electronic system for management of construction program. The agency has an in-house e-Construction team that is working on evaluating software options.
Michigan DOT Mature e-Construction practices; considered national leader.
North Carolina DOT Did not respond to AASHTO survey but selected based on its iPad pilot program launched in 2012, and iPads have now been rolled out in all field offices; also working on pilot project to give contractor access to project documents and test how agency can streamline submittal process of documentation from contractors.
Oregon DOT Uses 3D plans and digital signatures; is in the process of implementing ProjectWise.
Texas DOT Did not respond to AASHTO survey but selected based on mature e- Construction practices; considered national leader.
VTrans Smaller agency that faces challenges for advancing e-Construction;
developed a case for change for its project delivery improvement initiative.
23 | P a g e
In addition to the state highway agencies identified above, the project team interviewed Denver
International Airport. A summary of agency responses is provided in Exhibit 9. More detailed case studies for each agency are included in the Task 3 Report.
24 | P a g e
Exhibit 9: Summary of Interview Findings
Agency Size of Program e-Construction Practices Future Upgrades
Alaska
DOT&PF
(Northern Region)
Statewide: $700 million in Fiscal Year (FY) 2014, which includes $440 million in FHWA projects, $175 million in Federal Aviation Administration (FAA) projects, and $75 million in state-funded projects
Northern Region: $225 million in FY 2014, including $150 million in FHWA projects, $40 million in FAA projects, and $25 million in state-funded projects
PS&E: Provides 3D models of road alignments and existing ground surfaces as supplemental project information
Project Construction and Management: AASHTO SiteManager to store project documents
Project Acceptance: Testing Doc Express to submit documents electronically for Project Acceptance
Bidding and Contractor Selection/Contract Award: Bid Express for electronic bidding
Project Construction and Management: Implement AASHTOWare suite statewide
Caltrans
601 active construction projects worth $11.25 billion:
o D-B-B: 589 projects worth $8.6 billion o D-B: 6 contracts worth $1.7 billion o CM/GC: 6 contracts worth $950 million
Bidding and Contractor Selection/Contract Award: Bid Express and Expedite software
Project Construction and Management: Internet Extra Work Bill (iEWB) system for contractors to submit billing electronically; piloting mobile devices for contract administration
Project Inspection and Testing:
Record inspection results onsite with mobile devices
Denver International Airport
100 active projects
Capital Improvement Plan worth $850 million over the next 5 to 6 years
Undertaking $150 million in projects in 2015
PS&E: Ongoing initiative to get plans and specifications into BIM and Revit formats
Project Construction and Management: Implementing Oracle Unifier; Textura for contractor pay applications;
SharePoint for internal reporting; Primavera 6 for tracking contracts and budgets
Project Inspection and Testing: Piloting BIM 360 Field on iPads for electronic reporting
Data Sharing between Steps:
Identify synergies between systems
Exhibit 9: Summary of Interview Findings (Cont’d)
25 | P a g e
Agency Size of Program e-Construction Practices Future Upgrades
Florida DOT
535 active construction projects worth $11.5 billion:
o D-B-B: 434 projects o D-B: 77 contracts
PS&E: MicroStation, Autodesk Civil 3D; 3D design models used occasionally
Bidding and Contractor Selection/Contract Award: Bid Express for electronic bidding
Project Construction and Management: Hummingbird, ProjectSolve, SharePoint, mobile devices, digital signatures, form automation, electronic as-builts
Project Inspection and Testing: Mobile devices and SiteManager
PS&E: Advance 3D models initiative
Iowa DOT
650 D-B-B projects worth $700 million in FY 2014
PS&E: PDF, CAD, and 3D modeling files
Bidding and Contractor Selection/Contract Award: Bid Express for electronic bidding
Project Construction and Management: Doc Express, FieldManager/FieldBook, Electronic Reference Library, PDF Expert
Project Inspection and Testing: iPads
Project Acceptance: Develops own as-builts, exploring use of GIS tools for data collection for as-builts
Project Close-Out: Electronic document submission
Project Inspection and Testing:
Piloting electronic weight tickets
Explore how to tie construction with asset management
Massachusetts
DOT
406 active projects worth
1.6 billion:
o D-B-B: 400 projects worth $1.1 billion o D-B: 6 projects worth $500 million
PS&E: Plan sets converted to PDF for bid package but contractor can request CAD files for construction
Bidding and Contractor Selection/Contract Award: Bid Express for electronic bidding, which interfaces with the Contract Management System (CMS), a homegrown system that checks for prequalification
Project Construction and Management: Homegrown databases, Site Access Module (SAM), District Contract Database (DCD), and Construction Division System (CDS), which will eventually be merged with CMS; in the process of selecting a document management/ collaboration tool; SharePoint used to store documents on megaprojects
Project Construction and Management: Implement e- Signatures
Data Sharing between Steps:
Merge SAM, DCD, and CDS with CMS; interface CMS with selected document management/collaboration tool
Exhibit 9: Summary of Interview Findings (Cont’d)
26 | P a g e
Agency Size of Program e-Construction Practices Future Upgrades
Project Inspection and Testing: iPads used on megaprojects
Project Close-Out: Looking to implement a Laboratory Information Management System
Michigan DOT
Annual construction budget is $1.2 billion
Letting schedule includes about 800 contracts annually
PS&E: Exploring Bluebeam for digital markups
Bidding and Contractor Selection/Contract Award: Bid Express
Project Construction and Management: ProjectWise for document management; Adobe and Form Signed by Software 602 for digital signatures
Project Inspection and Testing: iPads in the field;
FieldManager for daily reports and pay estimates
Project Acceptance: Documents stored in ProjectWise
PS&E: Advancing 3D modeling
Bidding and Contractor Selection/Contract Award:
Boilerplate letting
Project Construction and Management: SharePoint site
North Carolina
DOT
Annual lettings amount to approximately $1.5 billion
At any one time, the agency has between 400 and 500 active D-B-B and D-B contracts
PS&E: All plans created in MicroStation and generated as PDF documents; Digital Terrain Modeling provided for all projects let centrally; 3D design files provided for projects designed through Corridor Modeling
Bidding and Contractor Selection/Contract Award: Bid Express
Project Construction and Management: SharePoint
Project Inspection and Testing: iPads; Highway Construction and Materials System (HiCAMS) to track inspections, materials, and test results, and for contractor payments
Project Acceptance: HiCAMS to track warranties
Project Construction and Management: DocuSign for digital signatures on plans and contracts
Oregon DOT
153 active construction projects worth $320 million:
o D-B-B: 150 projects worth $200 million o D-B: 2 contracts worth $100 million
PS&E: MicroStation; 3D models in use for over 10 years;
effective January 2015, the agency requires delivery of digital data bidding reference packages for most roadway construction projects
Bidding and Contractor Selection/Contract Award: Bid Express
Scheduled to go-live with e-Construction program in summer 2016
Exhibit 9: Summary of Interview Findings (Cont’d)
27 | P a g e
Agency Size of Program e-Construction Practices Future Upgrades o CM/GC: 1 contract worth $20 million
Project Construction and Management: ProjectWise;
CoSign ARX for digital signatures
Project Inspection and Testing: iPads
Texas DOT
As of January 2014, the agency had 1,405 active construction contracts and 1,739 active maintenance contracts valued at $13.3 billion
PS&E: MicroStation; 3D and 4D modeling
Bidding and Contractor Selection/Contract Award: Bid Proposal Request System to check contractor’s available bidding capacity; ExeVision’s integrated Project Development (iPD) solution for electronic bidding
Project Construction and Management: Electronic Document Management System and ProjectWise for document management; Electronic Project Record System to collect payroll information; SiteManager for construction administration; Primavera for scheduling
Project Inspection and Testing: iPads for mobile inspection
Project Construction and Management: Execute all contracts electronically with e-Signatures; explore use of QR codes to link to information in ProjectWise
Project Inspection and Testing:
Piloting HeadLight application for electronic data collection
VTrans
105 active construction projects worth $335 million:
o D-B-B: 100 projects worth $210 million o D-B: 3 contracts worth $100 million o CM/GC: 2 contracts worth $25 million
PS&E: Adobe to convert files to electronic format and review plans electronically
Bidding and Contractor Selection/Contract Award: Bid Express
Project Construction and Management: SiteManager
Project Close-Out: Construction Contract Finals, a cloud-based business process management software used for construction close-out
Bidding and Contractor Selection/Contract Award:
Explore the use of the Proposal and Estimates System and Letting and Award System
Project Construction and Management: Develop an electronic process for contract administration and manage contract submittal electronically
Project Inspection and Testing:
Implement mobile devices so inspectors can record findings electronically
28 | P a g e
Documented Benefits and Costs
This section presents the benefits and costs documented by various agencies and includes both qualitative and quantitative benefits. The costs of implementing e-Construction, which can include capital investment (hardware/software), training costs, annual IT maintenance costs, and proprietary products costs, are not as well documented as the benefits. Many agencies are still in the process of implementing e-Construction processes and do not yet have a final cost.
The quantitative benefits and costs are presented in Exhibit 11 and are grouped into four categories:
Direct costs/expense savings.
Collaboration.
Data access and reliability.
Productivity and process efficiencies.
Oregon DOT has started to consider the cost savings that have been realized by transitioning to a paperless process, but the agency has not yet quantified the savings. The agency anticipates major time savings (i.e., elimination of delays, expedition of certain processes, and faster turnaround times for public record requests) and has identified several other areas where e-Construction will reduce costs, as illustrated in Exhibit 10.
Reduced paper, printing, postage, envelopes, etc.
Reduced building storage space
Reduced travel to ship or transfer documents
Reduced overnight delivery, FedEx, UPS, etc.
Elimination of fax machines
Reduced number of copiers and toner Reduced labor
Reduced carbon footprint
A new multi-modal element – digital highway
Remote FHWA reviews
Reduced paper/analysis preparation
Lower risk of data loss
Ability to isolate sensitive files
Elimination of FTP site for file transfer
Exhibit 10: Oregon Estimated Categories of Savings
29 | P a g e
Exhibit 11: Documented Benefits of e-Construction
Benefit Stream/Benefits Qualitative/Quantitative Costs
Direct costs/Expense savings
Cost savings from the reduced use of paper, printing, and mailing
Dallas/Fort Worth International Airport estimates that the construction team saved $5.1 million in costs through electronic access of drawings
Florida DOT estimates saving $22 million each year and saving $125,000 in scanning costs annually
Kentucky Transportation Cabinet estimates it saves 200,000 pages of bid-related paper documents per year with its electronic bidding…