Solicitation Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP_Attachments_1-4.pdf | ||
| RFP_STIPDG_7-15.pdf | ||
| RFP_Attachment_5.pdf | ||
| RFP_Attachment_7.doc | DOC document | |
| RFP_Attachment_6.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers 8‐7
1. Is the budget increased if FHWA selects greater than 80 but not more than 150 interns?
‐Your proposed budget for CLIN 0001, 0101, 0201, 0301, and 0401 should be for a maximum of 100 interns.
‐Your proposed budget for CLIN 0002, 0102, 0202, 0302, and 0402 should be for a maximum of 50 interns
2. Since the acquisition of talent is highly competitive, would FHWA approve a higher stipend rate for the selected interns?
‐No
3. Will FHWA provide a copy of the existing mentor guidelines?
‐No, not before contract award.
4. The contractor shall arrange housing for the interns. Does FHWA reimburse the contractor for housing or the intern?
‐The Contractor
5. Does Federal Highway have possession of all current data and other pertinent material to effectuate an orderly transfer to a new contractor?
‐Yes
6. Will FHWA consider the submission of electronic proposals in lieu of hard copies?
‐No, see Section L for submission requirements.