Justification for Exception to Fair Opportunity Mod 0003 to DTFH6112D00026/0211
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Justification for an Exception to Fair Opportunity
Office of Acquisition and Grants Management 1200 New Jersey Ave. SE
Washington, D.C. 20590
Subject: Justification for an Exception to Fair Opportunity
Contract Number: DTFH61-12-D-00026
Task Order Number: 0211
Modification Number: 0003
Date: November 10, 2016
Authority: This is a justification for an exception to fair opportunity prepared pursuant to the requirement for documentation at Federal Acquisition Regulation (FAR) Part 16.505(b)(2)(ii).
JUSTIFICATION
A) Nature and/or description of the action being approved
This is a justification for an exception to fair opportunity, for a modification to raise the ceiling of the subject task order.
B) Description of the supplies or services required to meet the agency’s needs (including the estimated value)
The additional services required consist of legal services, specifically continuation of the “negotiation” tasking described in the task order. The estimated value of the additional services is $300,000. The contractor is Skadden, Arps, Slate, Meagher & Flom.
C) Identification of the exception to fair opportunity (see FAR 16.505(b)(2)) and the supporting rationale.
The exception to fair opportunity is that cited at FAR 16.505(b)(2)(i)(C): “The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.”
Rationale: This modification is a logical follow-on to the base task order, because it is to continue legal services connected to ongoing negotiations between the Government and other parties, in connection with the “Transbay Transit Center Loan Amendment and Lease Financing Review,” an ongoing project in the TIFIA/Build America Bureau portfolio. The scope of work remains identical to that of the base task order, however a ceiling increase is necessary because the extent and duration of the negotiations required to complete the work effort are at this point estimated to substantially exceed that initially anticipated under the task as described below. Additional unanticipated effort has arisen due to the following and includes and will continue to include:
1. The timing for closing has been adversely affected by delays in receiving revised drafts of key documents. In addition, the drafts of key documents (once received) have not reflected the terms previously discussed, resulting in delays and additional time expended on the matter by the contractor. In addition, certain financing documents have not yet been distributed to all relevant parties, thus we anticipate that it will take some time to negotiate finalize terms for those agreements.
2. The structure of the financing has changed in material ways, since the contractor originally proposed for the work originally understood to be required. This will require the contractor to make substantial unanticipated revisions to the TIFIA loan documents and re-analyze and mark up provisions of the financing documents.
3. The Government’s understanding is that despite delays to date, the borrower desires to achieve closing of the financing and the related amendments to the TIFIA loan documents on an expedited basis, which will require sustained intensive work activity (e.g., reviewing drafts, marking up drafts, conference calls) on the part of the contractor.
It is in the interest of economy and efficiency for the same contractor to complete the negotiations work under this task order; introducing another contractor to the effort would have a detrimental effect from an economy and efficiency perspective. Through its work to date on the base task order, this contractor is the only offeror with the knowledge essential to properly document the transaction and ensure the Government’s interests are adequately protected and accurately documented. A new contractor would not have the requisite knowledge of the prior dealings leading from the task order issuance to date, in order to economically and efficiently complete the work under the order.
D) Determination by the Contracting Officer that the anticipated cost to the Government will be fair and reasonable
The anticipated cost to the Government for this modification, $300,000 is considered fair and reasonable. This modification impacts the labor-hour component of the task order, and the anticipated cost corresponds to an expected increase in labor-hours (in various categories) multiplied by the labor rates in effect under the task order. These labor rates were approved at time of award as fair and reasonable. The proposed/accepted labor rates were achieved in a highly competitive environment—all seven awardees under the set of IDIQ contracts were given a fair opportunity to compete.
E) Any other facts supporting the justification
There are no other relevant facts supporting the justification, not otherwise included above.
F) A statement of the actions, if any, the agency may take to remove or overcome any barriers that led to the exception to fair opportunity before any subsequent acquisition for the supplies or services is made.
For subsequent acquisitions of legal advisory services under this set of IDIQ contracts, the Agency may consider providing ranges of labor hours as an advisory to the offerors, for the negotiations tasking. Experience has revealed that the nature of the negotiations work is often more protracted than initially expected/proposed by the contractors. Considering special factors (complexity, political sensitivity) that might warrant higher initial estimates/award ceilings would lessen the need for subsequent modifications using this logical follow-on justification.
G) The contracting officer’s certification that the justification is accurate and complete to the best of the contracting officer’s knowledge and belief.
Certification: _________________________________________ Samantha Reizes, Contracting Officer Date
H) Evidence that any supporting data that is the responsibility of technical or requirements personnel (e.g., verifying the Government’s minimum needs or requirements or other rationale for an exception to fair opportunity) and which form a basis for the justification have been certified as complete and accurate by the technical or requirements personnel.
The Contracting Officer’s Representative, Ms. Cortney Arnold, asked that the program office she supports prepare an approved Procurement Request to the contracting activity, including a certification of funding availability for the value of the modification. The Procurement Request was supported by a document fully justifying the rationale for the modification, from a technical requirements perspective. The Procurement Request was received by the contracting activity on November 2, 2016.
DETERMINATION
Based on the foregoing information, I hereby determine that the circumstances in FAR 16.505(b)(2)(i)(C) applies to the subject modification.
Samantha Reizes Date Contracting Officer Office of Contracting Operations Office of Acquisition and Grants Management Federal Highway Administration
APPROVAL
Pursuant to FAR 16.505(b)(2)(ii)(C),The ordering activity contracting officer’s certification that the justification is accurate and complete to the best of the ordering activity contracting officer’s knowledge and belief will serve as approval. No higher approval level is established in accordance with agency procedures. Therefore, see section (G) of this justification, above.