RHV - 31L and 13L PAPIs - Construction Specification.pdf
PDF 197 KB Posted
- Solicitation number
- DTFAWN-16-R-01112
About this file
RHV - 31L and 13L PAPIs - Construction Specification (pdf)
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 16 1442-PAPI REID HILLVIEWdoc.pdf | ||
| CA29.txt | TXT text file | |
| customer satisfaction survey .docx | DOCX document | |
| BusinessDeclaration 2016.pdf | ||
| ! RHV 13L and 31L PAPIs - construction drwgs.pdf | ||
| DTFAWN-16-R-011112.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION SPECIFICATIONS
AND DRAWINGS
Installation of TWO
Precision Approach Path Indicator’s to serve Runways 31L and 13L at the Reid-Hillview Airport in San Jose, California
November 16, 2015
Prepared by:
FEDERAL AVIATION ADMINISTRATION
AIR TRAFFIC ORGANIZATION
TECHNICAL OPERATIONS UNIT
WESTERN SERVICE AREA
ENGINEERING SERVICES
NAVAIDS ENGINEERING GROUP
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
01010 SUMMARY OF WORK
DIVISION 2 - SITE WORK
02100 SITE PREPARATION
02200 EARTHWORK
02505 GRANULAR PAVING
DIVISION 3 - CONCRETE
03100 CONCRETE FORMWORK
03200 CONCRETE REINFORCEMENT
03300 CAST-IN-PLACE CONCRETE
DIVISION 16 - ELECTRICAL
ATTACHMENTS:
CONSTRUCTION DRAWINGS
RHV / RWY’S 31L AND 13L – PAPI’S
01010 - PAGE 1
SECTION 01010
SUMMARY OF WORK
TABLE OF CONTENTS
GENERAL
1.1 SCOPE OF WORK
1.1.1 Installation of the runway 31L and runway 13L PAPI’s
1.1.2 Removal/Demolition of the existing VASI’s
1.2 REFERENCES
1.3 DRAWINGS
1.3.1 Construction Drawings Provided
1.3.2 As-Built Drawings
1.4 SUBMITTALS
1.4.1 Material
1.4.2 Schedule
1.4.3 Schedule of Values
1.4.4 Safety Plan
1.4.5 Work Plan
1.4.6 Testing
PRODUCTS
2.1 GOVERNMENT FURNISHED MATERIAL
2.1.1 Inventory and Inspection of GFM
2.2 CONTRACTOR FURNISHED MATERIAL
2.3 MATERIAL
2.3.1 External Hardware
2.3.2 Galvanized Rigid Metal Conduit (GRMC)
2.3.3 Anti-oxidant compound
2.3.4 Asbestos Free Material
2.3.5 Rotomill Material
EXECUTION
3.1 SCHEDULES
3.1.1 Construction Duration
3.1.2 Work Start
3.1.3 Construction Duration
01010 - PAGE 2
3.1.4 Weekly Look Ahead Work Schedule
3.1.5 Deviation from Work Schedule
3.1.6 Daily Construction Log
3.2 PRE-CONSTRUCTION MEETING
3.3 LAYOUT
3.4 SPECIAL REQUIREMENTS
3.4.1 Special Precautions
3.4.2 Safety Requirements
3.4.2.1 Runway Safety and Object Free Areas
3.4.2.2 not used
3.4.2.3 Construction Vehicle Traffic
3.4.2.4 Unauthorized Structures
3.4.2.5 Hazard Marking
3.4.2.6 Safety Plan
3.4.3 Radio Communications
3.4.4 Work Limitations
3.4.4.1 Trenches, Holes, and Excavations
3.4.4.2 not used
3.4.5 Work Plan
3.5 PROTECTION OF EXISTING UTILITIES AND CABLES
3.6 INSTALLATION AND WORKMANSHIP
3.7 TEMPORARY FACILITIES
3.7.1 Temporary Water
3.7.2 Temporary Toilets and Sanitation
3.7.3 Temporary Trash Dumpsters
3.8 AIRPORT SECURITY, BADGING, AND ACCESS
3.9 SAFETY
3.10 SEDIMENTATION, EROSION, AND DUST CONTROL
3.11 ENVIRONMENTAL REQUIREMENTS
3.12 DEBRIS CONTROL AND CLEAN-UP
3.13 INSPECTION & ACCEPTANCE
01010 - PAGE 3
1.1 SCOPE OF WORK
The work covered under this specification SECTION 01010
SUMMARY OF WORK
PART 1 GENERAL
includes the installation of a TWO Precision Approach Path Indicator’s (PAPI’s) to serve runways 31L and 13L at the Reid-Hillview Airport in San Jose, CA.
The contractor is required to furnish all labor, materials (except Government furnished), services, equipment, insurance, bonds, security notifications, licenses, permits, and fees in accordance with applicable federal, state and local regulatory requirements to complete the specified work. Any miscellaneous labor, equipment and/or materials not specifically detailed or specified, but required to complete the project, shall be provided as an integral part of the work.
The dimensions, measurements, and quantity of materials listed in this specification and on the construction drawings are estimated and are presented to give the contractor an idea of the total scope of work. The contractor is responsible for assuring that the bid reflects all work required to accomplish this project.
1.1.1 Installation of the runway 31L and runway 13L PAPI’s
Contractor shall install the two PAPI’s as indicated on the construction drawings. Work includes: Installation of the PAPI Power & Control Stations and LHA’s (Light Housing Assembly’s), Installation of the power service for the PAPI’s, and the installation of maintenance areas for the PAPI’s.
1.1.2 Removal/Demolition of the existing VASI’s
The old runway 31L and 13L VASI equipment shall be completely removed and disposed of by the construction contractor. Work includes the removal of all above ground structures, foundations, pull boxes, and underground conduit and cabling (conduit and cable within 10 ft of the structures) associated with these. The sites shall be restored to match the surrounding grade, compaction, and condition. All work shall be to the satisfaction of the FAA and the Airport.
The contractor shall provide documentation to the FAA Project Engineer certifying that all material has been disposed of properly.
1.2 REFERENCES
01010 - PAGE 4
Airport Ground Vehicle Operations Guide available from: http://www.faa.gov/runwaysafety/asw/downloads/AGVO-guide.doc
1.3 DRAWINGS
Callouts on the construction drawings indicate work to be done under this contract unless specifically noted "installed by others" or "existing". Callouts indicating work to be done do not always include the word "install".
1.3.1 Construction Drawings Provided
Drawings applicable to this project are attached.
1.3.2 As-Built Drawings
The contractor shall provide three complete sets of As-Built drawings to the FAA Project Engineer at the end of the project. The following color codes shall be used:
Green -to indicate adding new text and/or new graphics or changes to existing text and/or graphics.
Red - to indicated the removal of existing text and or/ graphics.
Blue - to indicated general information to the Drafter.
Any additional diagrams and/or schematics that would be helpful for the maintenance of the facility should also be included.
1.4 SUBMITTALS
1.4.1 Material
The contractor shall submit for approval; catalog data, cut-sheets, samples, and any other relevant information on the contractor furnished material to be used on this project. Two copies of the submittal package shall be given to the FAA Project Engineer for approval. Submittals on materials shall include, but is not limited to:
- Coated galvanized rigid steel conduit
- Cement concrete material
- Geotextile fabric
- Aggregate material
- Rotomilled asphalt material
- Contractor furnished manholes/pull boxes
- Contractor furnished hardware
- Contractor furnished electrical fittings and components
- Contractor furnished cable and wire
- Labels
01010 - PAGE 5
- Additional items deemed necessary by the FAA Project Engineer
1.4.2 Schedule
Prior to start, the contractor shall submit a schedule and work plan to the Project Engineer for approval. See section 3.1.1 for the maximum time allowed to complete this project. The schedule shall show start dates, duration, and finish dates for each work activity.
The FAA reserves the right to modify the contractor’s sequence of activities in the interest of facility operation and airport safety.
1.4.3 Schedule of Values
The contractor’s proposal shall include a schedule of values, showing at a minimum, a breakdown of cost for each work activity. Cost for each item should include bonding, insurance, profit, and overhead. The cost for the contractor’s efforts towards Airport security, badging, insurance, and mobilization shall be itemized separately.
1.4.4 Safety Plan
The contractor shall submit a safety plan per paragraph 3.4.2.6 of this section.
1.4.5 Work Plan
The contractor shall submit a work plan per paragraph 3.4.5 of this section.
1.4.6 Testing
The contractor shall complete, at his own expense, all testing as required by these specifications.
The results shall be submitted to the FAA Project Engineer. Required testing includes, but is not limited to, the following:
- Cable insulation resistance test (see FAA-C-1217, current version)
- Earth resistance test (see FAA-STD-019, current version)
- All Required Concrete Testing (performed by an independent testing company).
- Soil Compaction Testing (performed by an independent testing company).
PART 2 PRODUCTS
Reference herein or in the construction drawings to any specific commercial product, process, or service, any trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the Federal Aviation Administration.
The contractor may submit a request for substitution of a product, process, or service specifically called out. Such request shall be through the submittal process.
2.1 GOVERNMENT FURNISHED MATERIAL
01010 - PAGE 6
Government furnished material (GFM) for this project is listed as follows:
** Items listed are Per PAPI.
PAPI Equipment (* re-use existing):
Power & Control Cabinet 1 each Light Housing Assembly 4 each
Remote Radio Control Equipment:
Air/Ground – Receiver/Controller 1 each Radio Interface Unit 1 each Ground/Ground Decoder 1 each Ground/Ground Receiver 1 each Ground/Ground Receiver Antenna 1 each
2.1.1 Inventory and Inspection of GFM
The contractor shall sign a copy of the Government furnished material (GFM) list acknowledging receipt of the furnished material, noting any discrepancies if necessary. When the contractor signs for custody, he acknowledges receipt in good condition and assumes responsibility for any subsequent loss or damage. The contractor shall return all GFM that is not installed to the location where the material was picked up.
2.2 CONTRACTOR FURNISHED MATERIAL
The contractor shall furnish all material that is required and not otherwise indicated to be Government furnished. Materials furnished by the contractor shall be new, the standard products of manufacturers regularly engaged in the production of such materials, and of the manufacturer’s latest designs that comply with the specification requirements.
The contractor is responsible for making their own arrangements for material delivery and receiving. The contractor shall not have any material delivered to any FAA offices. Delivery to the Airport address shall only be done with the prior approval from the FAA Project Engineer and the Airport Management.
2.3 MATERIAL
2.3.1 External Hardware
All external hardware shall be stainless steel. All cut edges shall be filed smooth and treated with a cold galvanizing compound.
01010 - PAGE 7
2.3.2 Galvanized Rigid Metal Conduit (GRMC)
All galvanized rigid metal conduit (GRMC) shall be factory coated. Taping and/or painting the GRMC will not be allowed.
2.3.3 Anti-oxidant compound
USE AN APPROVED ANTI-OXIDANT COMPOUND ON ALL INSTALLED HARDWARE
WITH EXTERNAL/INTERNAL THREADS, AND WHERE EMT IS INSERTED INTO
FRANGIBLE COUPLINGS. FAILURE TO DO THIS WILL RESULT IN THE
CONTRACTOR REPLACING ANY ITEMS DAMAGED DUE TO SEIZED, GALLED, OR
STRIPPED THREADS OR CONNECTIONS.
2.3.4 Asbestos Free Material
The Contractor shall not use any asbestos containing material (ACM) at any time during the construction. The Contractor shall verify that all material, including those supplied by third parties, are asbestos free materials. A written certification letter shall be provided by the Contractor to the FAA certifying that the finished work is asbestos free.
2.3.5 Rotomill Material
Rotomill material shall contain a 1 inch maximum aggregate size, and be clean, uniform, and free of foreign debris (including free of concrete, road base, and fabric). Finished rotomilled surfaces shall be compacted and level with straight edges. All material must be approved by the FAA Project Engineer prior to placement.
PART 3 EXECUTION
3.1 SCHEDULES
3.1.1 Construction Duration
All work shall be completed within 19 calendar days after the Notice to Proceed (NTP).
3.1.2 Work Start
The contractor shall not start any work, and the FAA will not schedule any hard start dates for a work start; Until the contractor has met all of the Airport’s requirements for badging and access for all employees and equipment; and actually has in hand the badges and access permits necessary to access and work at the airport.
(See requirements for Airport Security, Badging, and Access below).
Once the contractor has met all of the requirements for the Airport’s security, badging, and access – the FAA Project Engineer will schedule the actual start date for construction. This will
01010 - PAGE 8
be dependent on such matters as facility availability, existing work and operations at the airport, availability of key FAA and airport and personnel, and environmental concerns.
3.1.3 Work schedule
No work shall be scheduled on Saturdays, Sundays or legal holidays without prior approval from the FAA Project Engineer.
The contractor shall furnish the FAA Project Engineer with emergency (24 hour) contact phone numbers for the contractor’s superintendent and an alternate individual. Such numbers will be used if the contractor needs to be contacted outside of normal working hours.
3.1.4 Weekly Look Ahead Work Schedule
On a weekly basis, the contractor shall submit a schedule showing activities desired to be performed during the upcoming week. These work activities shall be approved by the FAA Project Engineer.
3.1.5 Deviation from Work Schedule
The FAA and/or Airport Management reserve the right to suspend or stop construction as necessary for the safety of aircraft or airport property. In addition, the FAA may adjust the work schedule and hours to satisfy the facility operations, weather conditions, and maintenance moratoriums.
3.1.6 Daily Construction Log
The Contractor shall keep a Daily Construction Log. At a minimum, the daily log shall contain:
Items accomplished for that day.
Start and stop time of work.
Name of workers (including sub-contractors), and hours they worked for that day.
Weather (including sky, ground moisture conditions, and temperature).
Material received.
Documents and photographs showing the progress of work, and as required.
The Daily Construction Logs shall be turned over to the FAA Project Engineer on a weekly basis.
3.2 PRE-CONSTRUCTION MEETING
Prior to the start of any work and the contractor's access to the work site, the contractor shall be required to attend a pre-construction meeting. Attendees at the meeting may include, but is not limited to, the FAA Project Engineer, Resident Engineer, FAA Contracting Officer, the Airport Manager, Airport Operations, FAA maintenance, and other interested parties as determined by
01010 - PAGE 9
the Project Engineer. Topics at the meeting will include site access, airport security, work safety, work schedule, project expectations, work procedures, emergency plans, and other items relating to the execution of the project.
3.3 LAYOUT/SURVEYING
All layout work shall be accomplished by a Professional Land Surveyor.
The contractor shall verify the field measurements and coordinates indicated on the drawings with the FAA Project Engineer before starting any layout. The contractor shall lay out his work from base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection therewith.
Facility layout shall be relative to the runway ends. This will require the contractor’s surveyors to physically occupy both ends of a runway. In order to do this while minimizing the time required, and maximizing accuracy – the contractor’s surveyors must us GPS methods.
The contractor shall furnish, at his own expense, all stakes, templates, platforms, equipment, tools, materials and labor as may be required in laying out any part of the work. The contractor is to properly maintain the specified layouts to assure proper alignment of the construction.
Roads indicated to be installed under this contract shall be laid out and clearly marked at the beginning of the project and used as access roads during construction so as to minimize the disturbance to the surrounding areas.
3.4 SPECIAL REQUIREMENTS
3.4.1 Special Precautions
The contractor shall conform to the rules and regulations of the airport and shall coordinate all work with the FAA Project Engineer.
Note: Unscheduled interruptions of the electrical service to FAA facilities may cause aircraft accidents and loss of life. Work requiring a temporary or permanent de-energization of equipment shall be scheduled in writing with the FAA Project Engineer and the onsite FAA maintenance personnel. Only onsite FAA maintenance personnel are authorized to energize/de-energize equipment, or to operate a circuit breaker, switch, or fuse in an FAA facility.
3.4.2 Safety Requirements
Aviation Safety is a primary consideration during airport construction. The Contractor is completely responsible for complying with the Airport’s safety and operation procedures, as dictated by the Airport.
During the performance of this contract, the airport runways, taxiways, and aircraft parking aprons shall remain in use by aircraft to the maximum extent possible, CONSISTENT WITH CONTINUAL SAFETY. The contractor shall not allow employees, subcontractors, suppliers, or
01010 - PAGE 10
any other unauthorized person to enter or remain in any airport area which would be hazardous to persons or to aircraft operations.
3.4.2.1 Runway Safety and Object Free Areas
Prior to commencement of work, the contractor shall delineate the boundaries of the safety area with 3/8" x 1 1/2" x 4' long pointed lath (survey sticks) and bright orange flagging.
The contractor shall not be allowed into the Runway Safety Area without prior approval from the FAA Project Engineer and the Airport Manager. In general, no workers or equipment shall be allowed inside the safety area when aircraft are using the runway. Work to be done inside the safety area shall be scheduled and closely coordinated with the FAA Project Engineer and the Airport manager.
The contractor shall not be allowed to place vehicles and/or equipment inside the Runway Object Free Area (OFA) without the approval of the FAA Project Engineer.
In addition to the restrictions of working in the Runway Safety area and Object Free Area, the Airport Manager and/or the FAA Project Engineer may impose more restrictive requirements as needed to maintain airport safety.
3.4.2.2 Not used
3.4.2.3 Construction Vehicle Traffic
The contractors' vehicles and equipment shall enter the work site and construction areas at approved locations, and by way of authorized routes. The use of runways, aprons, taxiways, ramps, will not be permitted unless specifically approved by the FAA Project Engineer and the Airport Manager. The contractor shall inform all personnel that aircraft have the right-of-way at all times. The contractor shall be responsible for maintaining control and security at each entry point, as approved.
At a minimum, all vehicles and motorized equipment that enter the Airport Operations Area (AOA) shall be marked per AC 150/5210-5B (or latest version). In general, all vehicles shall be marked with the Contractor’s name/logo (4” high min lettering) on both sides, and have an approved yellow flashing beacon. Construction equipment, such as backhoes, skid steers, and trailers shall be marked with a three foot by three foot flag with international orange and white 12 inch squares displayed in full view above the equipment. Additional and/or more restrictive requirements may be mandated by the airport.
In addition, no personnel will be permitted to drive on the airside of the airport unless he/she has read, and certified that he/she has read, “ A Guide to Ground Vehicle Operations on an Airport” (DOT/FAA/AS-90-3). A copy of this document is attached at the end of this specification.
THE AIRPORT AND/OR THE FAA MAY HAVE ADDITIONAL REQUIREMENTS FOR
VEHICLES, EQUIPMENT, AND PERSONNEL OPERATING INSIDE THE AOA.
01010 - PAGE 11
3.4.2.4 Unauthorized Structures
The contractor shall install no fences or other physical obstructions on or around the project work area without the approval of FAA Project Engineer.
3.4.2.5 Hazard Marking
The contractor shall use barricades, flashers, flags, traffic cones, signs, etc., for the following:
- To prevent aircraft from taxiing onto a closed runway, taxiway or apron.
- To outline construction/maintenance areas.
- To identify isolated hazard areas such as open manholes, ditches, potholes, waste areas, etc.
- To identify FAA and Airport facilities, cables, power lines, ILS Critical areas, and other sensitive areas, in order to prevent damage, interference and facility shutdown.
All hazard markings shall be furnished and setup by the contractor. Barricades inside the runway safety area shall be lightweight and frangible. For daytime use, barricades should be supplemented by flags; for night time use, they shall have flashing yellow lights. Night time barricades shall not penetrate the approach surface. All markings shall be to the approval of the FAA Project Engineer.
3.4.2.6 Safety Plan
Prior to commencement of work, the contractor shall submit a Safety Plan Compliance Document SPCD per AC 150/5370-2F. This document shall be approved by the Airport and the FAA. The Safety Plan Compliance Document shall detail how the contractor shall comply with the Airport’s Construction Safety and Phasing Plan (CSPP), or absent of a CSPP, shall provide the information in a typical SPCD as indicated in AC 150/5370-2F. The plan shall include, but is not limited to; access to the site, hours of operation, personnel working for the contractor, electrical safety, removal and disposal of material, erosion and dust control, a plan for dealing with hazardous material, and a plan to insure that existing facilities and equipment are not interrupted.
3.4.3 Radio Communications
01010 - PAGE 12
The contractor's superintendent (or someone appointed by the superintendent) shall be required to monitor a transceiver radio at all times when the contractor is operating inside the runway safety area. The transceiver shall be contractor furnished with a frequency range of 118-136 Mhz and tuned to the local ATCT/Unicom frequency, as required.
3.4.4 Work Limitations
See Section 3.1.3 regarding work limitations within the Runway Safety Area.
3.4.4.1 Trenches, Holes, and Excavations
The condition of the material to be excavated, bored, drilled, etc., must be determined by the construction contractor. Excavation may require ripping, blasting, cutting, or other means beyond the use of a normal backhoe or drilling equipment.
Trenches, holes, and any other type of excavation within the runway safety area (RSA) are not allowed without the permission and approval of the FAA and Airport Operations. Any work inside the RSA shall be done with the understanding that the area may have to be vacated at any time.
All trenches, holes, and excavation shall be marked, covered and protected, as approved.
3.4.4.2 Not used
3.4.5 Work Plan
Prior to commencement of work, the contractor shall submit a work plan for approval by the Project Engineer (see 1.4). An acceptable work plan shall take into account all areas discussed in this section.
3.5 PROTECTION OF EXISTING UTILITIES AND CABLES
The existing utility lines, utility structures and all underground cables, as may be shown on the drawings are approximate and incomplete. Where excavation occurs in the vicinity of existing utilities or cables, the contractor shall use whatever means necessary, including the use of a private third party cable locator, to locate the existing utilities or cables prior to any excavation.
The contractor shall stake all utility or cable crossings and such areas shall be hand excavated.
The contractor shall immediately repair any damage done by the contractor or suppliers to utilities or cable within the work area.
3.6 INSTALLATION AND WORKMANSHIP
01010 - PAGE 13
All work shall be performed according to the intent of the contract, and normal and accepted industry and Government standards.
All work shall be accomplished by skilled workers regularly engaged in this type of work.
Where required by local regulations, the workers shall be properly licensed. Electrical terminations and splices shall be done by a qualified electrician.
The contractor shall give constant attention to the work to facilitate the progress thereof, and shall cooperate with the Project/Resident Engineer in every way possible. The contractor shall have a competent superintendent on the work site at all times who is fully capable of reading and thoroughly understanding the plans and specifications and shall receive and fulfill instructions from the Project/Resident Engineer.
An initial inspection shall be conducted when a representative sample of work has been completed. This work shall be approved by the FAA Project Engineer or his representative, prior to the commencement of additional work.
All conduits shall be completely cleaned prior to installing cable. A flexible mandrel shall be used to clean out mud, dirt, and debris from the raceways.
Underground conduits shall be installed so that no water can be trapped in the raceway (water must able to drain out of one end).
All foundations, pull boxes, equipment racks, and other above ground structures shall be installed square (perpendicular and parallel) to the runway centerline, prevailing structure or road as indicated on the drawings unless specifically indicated to be otherwise. Unless otherwise indicated, the horizontal tolerance for the locations of structures and embedded hardware shall be +/- 1/16 of an inch and the vertical tolerance for the elevations of surfaces and embedded hardware shall be +/- 1/16 of an inch. Elevated conduits and structures (those extending above grade) shall be installed level and plumb. Unless otherwise indicated, maximum tolerance for vertical plumbness is 1/8” horizontal for every four feet vertical. Exposed raceways shall be installed parallel to or at right angles with the lines of the finished structure, unless otherwise indicated.
Tops of foundations, cans, pull boxes, manholes, vaults, etc., shall be uniform with the tops of concrete at the surrounding structures, natural grade or as indicated on the drawings or as directed by the Project Engineer. Unless otherwise indicated, top of foundations, cans, pull boxes, manholes, etc. shall be level with a maximum tolerance of 1/16” per foot.
Road curves shall be as indicated on the drawings or as indicated by the Project Engineer. Edges of roads, walkways and graveled areas shall be clean, sharp, and well defined. Installed surface material shall not be allowed to spill outside the defined edges.
Installed foundations, structures, walkways, and roads not meeting the above requirements shall be removed, disposed of, and re-installed correctly at the contractor’s expense.
01010 - PAGE 14
3.7 TEMPORARY FACILITIES
The contractor shall provide and pay for all temporary services and facilities as specified below and as necessary for the proper and expeditious execution of the work. The contractor shall make, or have made, all connections to existing services and sources of supply as necessary and/or indicated and pay all charges for same. All work under this Section shall comply with applicable laws, rules, regulations, codes, ordinances, and orders of all Federal, State, and Local authorities having jurisdiction for the safety of persons, materials and property. The contractor shall remove all such temporary installations and connections when no longer necessary for the project work.
3.7.1 Temporary Water
The contractor shall make arrangements to furnish a potable water supply for workers and project work, and pay for all water and services.
3.7.2 Temporary Toilets and Sanitation
The contractor shall provide ample and suitable on site sanitary conveniences with proper enclosures for the use by the workers, FAA personnel, and FAA support personnel. Such conveniences shall be kept clean, properly ventilated and installed and maintained in conformity with requirements of all laws and ordinances governing such installations. Locations shall be subject to the FAA Project Engineer's approval. After completion of the work such conveniences shall be removed from the site.
3.7.3 Temporary Trash Dumpsters
The contractor shall provide ample and suitable on site trash dumpsters capable of containing all of the contractor’s trash and debris.
3.8 AIRPORT SECURITY, BADGING, AND ACCESS
The contractor is solely responsible for determining, complying with, and paying all associated cost required to work on and have access to the construction site. This includes complying with all of the Airport’s security, badging, and insurance requirements. The time and cost required for this effort must be accounted for in the contractors initial bid price.
The FAA may provide a letter indicating that the contractor has a need to work on the airport.
Otherwise, the contractor is completely responsible for meeting the terms required by the airport.
Only direct construction support personnel, vehicles and/or equipment will be allowed to the work site. The FAA will not provide escorts for the contractor, his subcontractors, or suppliers.
Any required contractor escorts, due to the Airport’s access restrictions to non-FAA personnel, 01010 - PAGE 15 shall be at the availability, discretion, and convenience of the FAA personnel authorized to escort. Availability and timeliness of any FAA escort personnel is NOT guaranteed.
The contractor shall use only the access gates and haul roads that are designated by the FAA Project Engineer. The contractor shall be required to keep access gates guarded and closed during construction hours. The gate may be opened only for authorized vehicle traffic flow. At such times as this gate is not guarded, it shall be closed and securely locked as approved by the Airport and the FAA.
3.9 SAFETY
All work shall be accomplished in accordance with OSHA Regulations (Standards – 29 CFR), Part 1926, Safety and Health Regulations for Construction.
Protective Equipment, including personal protective equipment for eyes, face, head, and protective clothing shall be used wherever it is necessary by reasons of hazards or environment [1926.95].
Head protective equipment (helmets) shall be worn in areas where there is a possible danger of head injuries from impact, flying or falling objects, or electrical shock and burns [1926.100].
Eye and face protection equipment shall be worn when machines or operations present potential eye or face injury [1926.102].
Specific work and operations requiring the mandatory use of personnel protective equipment shall be determined by the FAA Project Engineer.
3.10 SEDIMENTATION, EROSION, AND DUST CONTROL
The Contractor shall comply with all of the airport’s requirements for sedimentation, erosion, and dust control. This may include the use of silt fencing and/or hay bales to filter sediments from runoff and the application of water as needed to control dust.
3.11 ENVIRONMENTAL REQUIREMENTS
The Contractor shall be responsible for complying with all local, state, and federal environmental rules and regulations applicable to this project.
3.12 DEBRIS CONTROL AND CLEAN-UP
01010 - PAGE 16
The work site shall be kept clean and orderly during the progress of work. All debris, excess material, and trash shall be completely cleaned up at the end of every day – no exceptions.
Special attention shall be exercised to prevent the production of FOD (foreign object debris) which could cause damage to aircraft and/or airport equipment. Prior to the Contract Final Inspection, the contractor shall clean all areas of the construction site. This shall include but is not limited to the dress-up, sweep-up, and re-seeding of all areas disturbed during construction.
A NEAT FINAL APPEARANCE OF THE INSTALLED FACILITIES (INTERIOR AND
EXTERNAL) SHALL BE EMPHASIZED! All clean-up work shall be to the approval of the FAA Project Engineer.
Upon completion of work, the contractor shall be required to obtain a letter from the Airport Manager indicating that the work area has been left in an acceptable condition. A copy of the letter shall be given to the FAA Project Engineer.
3.13 INSPECTION & ACCEPTANCE
The Contractor shall maintain an adequate inspection system and perform such inspections to ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government.
THE PRESENCE OR ABSENCE OF A GOVERNMENT INSPECTOR DOES NOT RELIEVE
THE CONTRACTOR FROM ANY CONTRACT REQUIREMENT.
The Government inspections and tests are for the sole benefit of the Government and do not- Relieve the Contractor of responsibility for providing adequate quality control measures;
Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
Constitute or imply acceptance.
The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements. The Contractor shall promptly segregate and remove rejected material from the premises.
END OF SECTION