Attachment 4 - Past Experience History.pdf
PDF 198 KB Posted
- Attached to
- Fire Life Safety Maintenance for Denver International Airport Air Traffic Control Tower and Base Building
- Solicitation number
- DTFASA-17-R-00368
About this file
Attachment 4 - Past Experience History (pdf)
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTFASA-17-R-00368
Attachment No. 4
, include size and number of window panes installed or replaced:
, include size and number of window panes installed or replaced
Project #1
Firm’s Name:
Name of Project:
Location of Project:
Owner/Organization:
General Scope of Construction Project
Height above ground level
Is this an FAA Contract Yes No
Summary of Your Role in this Project: Prime Subcontractor
Original Completion Date Final Completion Date
Original Contract Amount Final Contract Amount
Extent and Type of Work You Subcontracted:
Were You Terminated or Assessed Liquidated Damages? (if yes, explain)
Owner’s Point of Contact for Reference (Name and Company)
Current Telephone Number of Reference POC and current email address:
Project #2
Firm’s Name:
Name of Project:
Location of Project:
Owner/Organization:
General Scope of Construction Project
Height above ground level
Is this an FAA Contract Yes No
Summary of Your Role in this Project: Prime Subcontractor
Original Completion Date Final Completion Date
Original Contract Amount Final Contract Amount
Extent and Type of Work You Subcontracted:
Were You Terminated or Assessed Liquidated Damages? (if yes, explain)
Owner’s Point of Contact for Reference (Name and Company)
Current Telephone Number of Reference POC and current email address:
DTFASA-17-R-00368
Attachment No. 4
, include size and number of window panes installed or replaced
Project #3
Firm’s Name:
Name of Project:
Location of Project:
Owner/Organization:
General Scope of Construction Project
Height above ground level
Is this an FAA Contract Yes No
Summary of Your Role in this Project: Prime Subcontractor
Original Completion Date Final Completion Date
Original Contract Amount Final Contract Amount
Extent and Type of Work You Subcontracted:
Were You Terminated or Assessed Liquidated Damages? (if yes, explain)
Owner’s Point of Contact for Reference (Name and Company)
Current Telephone Number of Reference POC and current email address: