Synopsis(NEW).pdf

PDF 89 KB Posted

Attached to
Roof Replacement-STL ATCT
Solicitation number
DTFACN14R00073
Issued by

About this file

Total Small Business Synopsis.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Name: Marshavia Clark (Contractor)

Organization: AAQ-520

Region: ASW - Southwest

Phone Number: 817-222-4641

E-mail: Marshavia.CTR.Clark@faa.gov

Date Posted: May 27, 2014

Solicitation No: DTFACN-14-R- 00073

Phase: Complex Noncommercial

Procurement Method: Request for Proposal – SIR

SECTION I REQUIREMENT SCOPE:

The FAA is seeking competent and qualified general construction contractors to Eliminate Water

Intrusion (Roof Replacement) of the Air Traffic Control Tower (ATCT) at Lambert International

Airport (STL), Bridgeton, MO, in accordance with the specifications and drawings. The contractor will be required to provide all labor, materials, supplies, and equipment (except

Government furnished) to perform this work in accordance with the statement of work and with all local, state, and federal laws.

Work will be done on an operational facility and the contractor shall comply with all procedures, rules and regulations of the facility authorities including limitations on equipment, allowable work hours, and other issues to ensure uninterrupted operations.

Scope of work (Summary):

1. Replace ATCT Cab roofing system: Contractor shall perform a complete full-depth removal and replacement of the existing cab EPDM membrane roofing system at the locations shown in the contract documents with a complete TPO roofing system.

2. Provide OSHA compliant guard rail system to cab roof parapet walls.

3. Seal all the gaps-voids with closed cell spray polyurethane foam materials in between the cab roof insulation materials and the interior face of the cab parapet wall exterior metal panels inside cab parapet walls.

4. Provide minimum 4-inch high semi-permanent water containment berm barrier that encloses the domestic water booster pumps and floor drain located in room TS5 ATCT level 3.

5. Provide minimum 4-inch high semi-permanent water containment berm barrier that encloses the fire suppression system water pumps and floor drain located in room B11 of the base building basement level.

6. Remove existing ATCT cab hatch door (door C2) between and the cab stair and exterior catwalk and replace with insulated exterior door.

mailto:Marshavia.CTR.Clark@faa.gov

7. Locate and repair source of Junction Level south walkway (#3) area storm water drain-piping leak.

8. Seal the gaps-voids with 2-hour UL listed fire rated assembly, suitable for this application, in between the ATCT level 8 concrete floor slabs and interior face of concrete-precast exterior walls.

9. Provide 48-inch high 18 gage T304 stainless steel sheet #4 brushed finish wall protection panels at three mop sinks.

10. Remove and replace approximately 600 LN FT of the existing concrete joint sealant and backer materials.

11. Remove and replace the existing concrete joint sealant and backer rod materials for all the joints for the removable precast concrete panels located above base building areaway room B-17.

All work shall be in accordance with the plans and specifications.

SECTION II- CONTRACT TYPE AND EVALUATION CRITERIA:

1. This project is set-aside for Total Small Business Concerns to all General Construction contractors.

2. The North American Industry Classification System (NAICS) is 236220, Commercial and Institutional Building Construction. The small business size standard is $33.5 million.

3. The project magnitude is between $ $100,000 and $250,000.

4. A mandatory site visit will be required. The date, time, location, and point of contact will are provided in Section I of the solicitation.

5. Contractors must have an active registration in System Award Management (SAM) before award can be made. Contractors can register at www.sam.gov/.

6. Award will be made to the Lowest Priced Offeror receiving a “Go rating” from the criteria listed below.

http://www.sam.gov/

SECTION III- GO/NO GO CRITERIA

AN OFFEROR MUST MEET THE FOLLOWING GO/NO-GO CRITERIA IN ORDER

TO BE ELIGIBLE FOR AWARD:

a. Using the Past Experience/ History Form (Attachment #1), provide a listing of at least 3 completed

Roofing contracts/projects your firm performed valued at least $100,000. Contracts/projects must be completed within the last 3 years. Scope is described above. Offeror shall identify the contracting agency, (FAA, Other Federal, State, local governments, or private), and provide the contract number or project identifier, which includes a point of contact and phone number.

b. Complete and return the Business Declaration form (Attachment #2).

c. Complete and return the Security Notice to Prospective Offerors (Attachment #3) The information provided will also be used as part of the responsibility determination.

FAILURE TO SUBMIT ALL REQUIRED INFORMATION WILL DEEM THE

REQUEST FOR SOLICITATION AS NON-RESPONSIVE.

Requests must be emailed to marshavia.ctr.clark@faa.gov no later than June 3rd, 2014 at 2:00pm

CST. Please place “Attention: Roof Replacement-STL ATCT” in the subject line of your email.

Requests received after this date and time will not be honored. No telephone requests will be accepted.

mailto:marshavia.ctr.clark@faa.gov