Attachment J.1 AEX_ARSR_REFURB_SPECS and DRAWINGS.pdf
PDF 18 MB Posted
- Attached to
- REFURBISHMENT OF THE ALEXANDRIA (AEX), LA AIR ROUTE SURVEILLANCE RADAR (ARSR) FACILITY BUILDING
- Solicitation number
- DTFAAC-17-R-00143
About this file
Attachment J.1 AEX_ARSR_REFURB_SPECS and DRAWINGS (pdf)
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
HOUSTON TECHNICIAL SUPPORT CENTER (TSC)
SPECIFICATIONS FOR THE REFURBISHMENT OF
OF THE ALEXANDRIA (AEX), LA AIR ROUTE SURVEILLANCE
RADAR (ARSR) FACILITY BUILDING
Prepared by: Kenneth Graves, HOU TSC
16600 JFK BLVD
Houston, TX 77032 Phone: 281-230-6356
DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION (FAA)
CENTRAL SERVICE AREA
SPECIFICATION FOR
REFURBISHMENT OF THE AEX ARSR FACILITY
BUILDING
1-1 Contractor Scope of Work - The contractor shall provide all labor, materials (unless otherwise specified), equipment, transportation, and services, required to perform the following as specified below and shown on the following drawings:
AEX-ARSR-G09 Drawing Index AEX-ARSR-C02 Elevation Views of ARSR & E/G Building AEX-ARSR-C03 ARSR First Floor Plan AEX-ARSR-C04 ARSR Second Floor Plan AEX-ARSR-C05 ARSR Second Floor Plan Electrical & Floor Repair AEX-ARSR-C06 ARSR Third Floor Plan AEX-ARSR-C07 ARSR Fourth Floor Plan AEX-ARSR-E019 ARSR Electrical Panel Schedules
NOTE 1: The AEX ARSR is an operational National Airspace (NAS) facility, and as such, all work that is accomplished at the ARSR must be done in accordance with procedures outlined in this specification; so as to minimize the impact on the facilities customers. Some of the contractor’s work activities within this facility will require a RADAR equipment outage. In an effort to minimize the number and duration of FAA equipment outages; the contractor will be required to perform all electrical breaker panel replacement work during the same time period. Any scheduled outage of greater than 8 hours must be coordinated with our NAS customers a minimum of 30 days prior to the requested outage. This scheduling requirement shall be taken into account when planning the project schedule.
NOTE 2: Part of the requirement under this contract involves the replacement of various existing light fixtures and the installation of new fixtures.
Currently some of the existing light units are not controlled by room switches (they remain on all the time). It shall be the contractor’s responsibility to ensure that all light fixtures (new and existing) are controlled by operational room light switches. In some instances this will require that the contractor identify and correct switch problems. Tracing cable and conduit runs from switches to lighting fixtures and back to power panels is fairly straight forward; since most runs are installed in conduit and not behind walls. NOTE: The contractor shall ensure that duplex wall receptacles are operational.
NOTE 3: All dimensions and materials quantities listed in this document are approximate. It shall be the contractor’s responsibility to field verify all values prior to purchasing project materials.
I. Work Required on 1st Floor of ARSR Building
NOTE 4: The contractor shall remove and dispose of all trash located in all 1ST floor areas. The Contracting Officer Representative (COR) will instruct the contractor as to which items to remove. For estimating purposes the contractor can figure about 15 yards of existing trash.
A.) Exterior 1st Floor Work
1.) Clean and paint the ARSR’s main entrance door, interior and exterior sides. The contractor shall also, clean and paint the wall surface area of the main door’s vestibule area. Paint color shall match exterior wall area of 1st floor storage and TELCO rooms. The door is made of metal material.
2.) Replace main entrance door flood light with new high efficiency LED light unit.
B.) Work in Storage Room
1.) Remove existing wire mesh which is covering storage room ceiling joist.
2.) Temporarily remove room supply and return air conditioning registers as required to install new ceiling OSB sheathing.
3.) Remove existing fluorescent light fixtures.
4.) Attach new 2”x6” joist boards to existing 2”x4” joist using appropriate fasteners.
5.) The contractor shall level the room’s 2”x4”/6” ceiling joist, which are sagging in the middle. See note 2 on DWG C03 for a recommended leveling fix.
The leveling fix is a recommendation, the contractor can provide an alternative solution for approval.
5.) Contractor shall provide and install the following: a. ½” plywood board which shall be installed on top of the storage room’s ceiling joist, as outlined on DWG AEX-ARSR-C03. b. Provide 2”x4” wooden wall studs and wooden stud floor plate, which shall be installed on back side of storage room wall (see DWG C03 for stud and floor plate placement details).
6.) Reinstall ceiling mounted return and supply air conditioning registers.
7.) Install new fluorescent light fixtures. The contractor shall also install two (2)duplex wall receptacle.
8.) The contractor must rework the storage room’s electrical infrastructure as follows: a. Remove an existing power strip which is identified on DWG C03.
b. Provide and install new ¾” EMT conduit and #12 AWG solid power cable.
Cable and conduit shall run from and existing metal j-box to a newly installed light switch, light fixtures and a new wall mounted 20 Amp, 120 volt duplex wall receptacle.
9.) The contractor must paint exterior storage room wall area. The wall is composed of plywood sheathing.
10.) The contractor shall repair and paint the storage room’s existing wooden entrance door. Repair shall include replacing door hardware (hinges and door knob).
C.) Work in TELCO Room
NOTE: Some of the contractor’s work activities within this room will require a RADR equipment outage. Please see Note 1 for additional details. Prior to ceiling/roof work the contractor shall be required to cover all equipment racks to protect against dust, dirt and debris during repair work.
1.) Provide and install approximately 35 square feet of missing ceiling plywood.
2.) The contractor shall raise, level and stabilize the TELCO room’s ceiling at the locations which are indicated on DWG C03.
3.) Remove all existing batt insulation which is installed between room roof joists. Remove all trash and debris on room’s roof.
4.) Attach new 2”x6” joist boards to existing 2”x4” joist using appropriate fasteners.
5.) The contractor shall level the room’s 2”x4”/6” ceiling joist, which are sagging in the middle. See note 7 on DWG C03 for a recommended leveling fix.
The leveling fix is a recommendation, the contractor can provide an alternative solution for COR approval.
6.) Install new batt insulation between room’s ceiling joist.
7.) Contractor shall provide ½” plywood board which shall be installed on top of the TELCO room’s ceiling joist.
8.) The contractor shall paint TELCO room’s interior and exterior wooden walls. The contractor shall also paint the room’s wooden ceiling.
9.) Replace the TELCO room’s breaker panel.
10.) The contractor shall replace the existing power feed for the TELCO panel.
The panel’s new power feed shall include 1.5” EMT conduit, 3-#2 AWG and 1-#8 AWG (ground cable). The cable and conduit shall be routed to panel CDP with is located on the 2nd floor. Panel CDP is approximately 250’from the location of the existing TELCO panel.
11.) The contractor shall also replace the existing #12 AWG stranded power cables that power the TELCO equipment rack; with new #12 AWG solid conductors.
The existing ¾” conduit shall remain for reuse with the new power panel and cables. The new power panel will be located approximately 15’ feet from the existing equipment rack.
C.) Work in 1st floor Common Area
1.) The contractor shall replace the air conditioning power panel (MCH), with a new power panel. The new panel shall be Square D series HCM or approved equal. See project drawings and this specification for additional details on MCH panel replacement.
The contractor shall also relocate the power feed for air conditioning condensing unit #2. The new feed shall include installation of new cable and conduit and shall originate from new panel MCH. See project drawings for additional feed replacement details.
2.) The contractor shall purchase and install a new Raycap or approved equal panel surge protection device.
3.) The contractor shall remove 6 existing high bay light fixtures and install 6 new fixtures.
4.) The contractor shall install a new light switch at the top of the stairs leading to the second floor. The new switch shall be wired in a 3-way configuration to work in conjunction with the existing light switch which controls the ceiling mounted lights. The contractor shall provide all conduit and cable to make the 3-way connection. See DWG C03 for additional details.
II. Work Required on 2nd Floor of ARSR Building
A.) Work Required in Quite Room
1.) Contractor shall replace the quite room ceiling tile.
2.) The contractor shall paint room walls and 2 support columns.
3.) The contractor shall replace 3 fluorescent light fixtures. The new light fixtures shall be controlled by the existing light switch which is currently inoperative. The contractor shall replace/repair the existing light switch.
(see note 2)
4.) Contractor shall repair/replace all defective duplex room receptacles.
5.) The contractor shall remove approximately 140 sq. ft. of carpet tile and tile adhesive. Remove adhesive to the extent necessary to allow for the application of new vinyl tile adhesive. The contractor shall also strip/clean the new floor tile and apply a wax coating. The wax shall be as manufactured by Trewax, Gold Label sealer wax or approved equal.
6.) Contractor shall install approximately 30 linear feet of 2”x12” trim boards along the top of the exterior wall, required to cover exposed ceiling joist.
7.) The contractor shall paint new trim boards and the exterior quite room walls.
B.) Work Required in 2nd Floor Equipment Room
1.) The contractor shall replace 18 fluorescent light fixtures. The new light fixtures shall be controlled by an existing light switch, which is currently inoperative. The contractor shall replace/repair the existing light switch (see note 2).
2.) The contractors shall clean and paint approximately 500 square feet of rusty equipment room ceiling surface. The ceiling is constructed of sheet metal and horizontal “I” beams. Contractor shall paint existing metal double door which is located in the equipment room.
3.) The contractor shall remove approximately 981 square feet of carpet tile and tile adhesive, remove adhesive to the extent necessary to allow for the application of new vinyl tile adhesive.
4.) The contractor shall install approximately 981 square feet of vinyl tile.
The contractor shall replace all plastic base trim. The contractor shall also strip/clean the new floor tile and apply a wax coating. The wax shall be as manufactured by Trewax, Gold Label sealer wax or approved equal.
5.) The contractor shall replace the building’s lighting power panel. The new CF lighting panel shall be located approximately 20 feet from the existing panel. The contractor shall also install new associated panel conduit and cables. The new panel shall be of the type identified on DWG E019.
6.) The contractor shall be required to provide a temporary generator and lights when cutting over to the new lighting panel. The COR will direct the contractor the exact critical areas of the building that will require lighting, while the panel replacement work is in progress. The areas that require lights are the TELCO room, 2nd floor equipment room, 3rd floor hatch area and inside 4th floor antenna room.
7.) The contractor shall repair approximately 120 square feet of equipment room wall area.
8.) The contractor shall install a 15 amp duplex receptacle and 1 gang surface mounted box on the wall adjacent to the UPS rack.
9.) The contractor shall install a wall mounted metal sink. There are existing water and drain lines that can be used to complete the sink installation.
10.) The contractor shall remove a light switch which is installed inside a surface mounted junction box and all associated wire. The entire run from switch to source of electrical wire shall be removed.
III. Work Required on 3rd Floor of ARSR Building
A.) Work Required in Office Area
1.) The contractor shall replace 4 fluorescent light fixtures. The new light fixtures shall be controlled by an existing light switch, which is currently inoperative. The contractor shall replace/repair the existing light switch (see note 2).
2.) The contractor shall remove and dispose of all trash located in this area.
The COR will instruct the contractor as to which items to remove. For estimating purposes the contractor can figure about 10 yard of trash.
3.) The contractor shall replace all ceiling tiles in office with government furnished (GF) ceiling tiles.
4.) The contractor shall repair wall area in office and paint, interior and exterior.
5.) The contractor shall remove approximately 200 square feet of carpet and install new vinyl tile. The contractor shall also strip/clean the new floor tile and apply a wax coating. The wax shall be as manufactured by Trewax, Gold Label sealer wax or approved equal.
B.) Work Required in 3rd Floor Equipment Room Area
1.) Contractor shall replace approximately 200 square feet of ¾” plywood floor decking material. See DWG C06 for a depiction of affected floor area. Also see note 1 on DWG C06 for additional information on floor decking replacement.
2.) Contractor shall remove approximately 1,600 square feet of existing damaged floor tile and install new vinyl tile. The contractor shall also strip/clean the new floor tile and apply a wax coating. The wax shall be as manufactured by Trewax, Gold Label sealer wax or approved equal.
3.) The contractor shall install approximately 1,500 square feet of paneling on all parameter wall surface areas.
4.) The contractor shall replace 6 fluorescent light fixtures and install 4 new fluorescent fixtures in equipment room area (total of 10 fixtures required). In addition to the new fixtures, the contractor shall be required to install associated conduit and electrical wire. The new light fixtures shall be controlled by an existing light switch, which is currently inoperative. The contractor shall replace/repair the existing light switch (see note 2).
5.) The contractor shall demolish approximately 80% of the metal hatch structure which allows for access to 4th room. After partial demolition of building, the remaining structure and floor shall be painted.
C.) Work Required in 3rd Floor Restroom
1.) The contractor shall replace the toilet, sink and associated Plumbing components.
2.) Replace the existing wall duplex receptacle with a new Ground Fault Interruption (GFI) unit.
3.) Remove an existing hot water heater next to the restroom and all associated water lines, valves and electrical components. Patch all wall holes that remain after plumbing component removal and paint exterior wall surface area.
4.) Install a 4 gallon mini hot water heater next to the new sink.
5.) The contractor shall repair interior restroom walls and paint.
6.) Remove and dispose of an existing paper dispenser.
IV. Work Required in ARSR Antenna Room (4th floor) and on Catwalk Area
1.) The contractor shall install a white LED light string around perimeter of 4th floor metal RADOM wall ring. The light string shall be controlled by a contractor furnished switch which will be installed on the 3rd floor.
2.) Replace 6 exterior flood lights that are installed around the catwalk. The contractor shall also replace associate conduit, conduit bodies and light unit photo cell. The new flood lights shall have photo cell.
1-2 General
1-2.1 Site Location and visit - The AEX ARSR facility is located at England Airpark (Alexandria International Airport) and is about two (2) miles from the Airport terminal building.
It is recommended that the Contractor perform a field inspection prior to bid submission in order to inform themselves of the specific working conditions applicable at the site and to ascertain the correct types/amounts of work to be performed. If the bidder chooses not to visit the site, he will nevertheless be charged with knowledge of conditions that a reasonable inspection would have disclosed. A site visit for prospective bidders will be scheduled by the CO previous to the bid due date.
1-2.2 Allowable Working Hours - Allowable working hours inside and around the ARSR facility shall occur during normal working hours which are from 8:00am to 5:00pm. However, the contractor may be required to work early morning and/or late evening hours to accommodate customer requirements when breaker panel cut-over activities are underway.
All facility outages shall be coordinated with the COR prior to the Preconstruction Conference. Facility services outages, as required by the installation of new breaker panels, will be permitted, but only at a time approved by the COR. The contractor shall promptly notify the COR as soon as the need is determined in order to schedule the required outages.
1-2.3 Project Coordination - The contractor shall prepare a detailed schedule of work and work layout to resolve conflicts and to ensure coordination of work by different trades. It shall be the contractor’s responsibility to resolve all coordination conflicts that arise among his subcontractors.
The contractor shall coordinate all day-to-day schedules in advance with the COR to prevent delays.
1-2.4 Contractor Performance Time - Actual construction time is 90 calendar days. Product submittal and approval is 30 calendar days. Closeout is 15 calendar days.
1-2.5 Testing - When any testing needs to be done, the contractor shall give the COR timely notice of its readiness so that the COR may observe such testing.
1-2.6 Pre-construction Conference - The Contractor shall attend a pre-construction conference at the time and location specified by the CO.
Requirements for material disposal, security and safety will be discussed.
Use of facility restrooms, water, and power will also be discussed.
Compliance with these procedures while on site is mandatory.
1-2.7 Conflict Resolution - The Contractor shall meet standards, specifications, and drawings as specified herein. The specifications and drawings shall rule in all cases. Specifications shall govern over drawings.
If any conflict should exist between site drawings (location-specific drawings) and standard drawings (drawings not referring to a particular location), the site drawings shall govern. In the event of dimensional discrepancies or omissions, the Contractor shall field verify and correct the information, and notify the COR. No work shall be done until agreement has been made with the COR. In cases where regulations and/or contract documents are conflicting, or discrepancies occur, the more stringent requirement shall be followed and enforced.
1-2.8 Access for Inspection - The Contractor shall allow the COR complete access to all portions of the work. Portions of the work buried, enclosed, or disguised, shall be inspected by the COR before being obscured by the next operation of the Contractor. In all cases, the COR shall be informed accordingly and given access to the work. Work obscured before inspection and acceptance by the COR, may, at the option of the COR be opened for inspection at no additional cost to Government.
The COR will inspect all work in progress up to completion and final Contractor’s Acceptance Inspection (CAI) including all materials, tools, and equipment. Such inspection may extend to all or a part of the work for the preparation, fabrication or manufacture of the materials to be used. The COR will notify the Contractor of any non-compliance with the contract specifications and/or drawings, and may reject workmanship or materials accordingly.
1-2.9 Contractor's Acceptance Inspection (CAI) - After substantial completion of all the Contractor's work, a CAI will be conducted between the Contractor and Government. The COR will review the contract documents and verify that the Contractor has completed all required work. If work remains to be completed, an itemized list will be prepared, and the contractor at no additional cost to the Government shall complete the remaining tasks correctly. A Joint Acceptance Inspection (JAI) requires FAA personnel to be present. It may be held concurrently with the CAI.
1-2.10 Layout of Work - The Contractor shall field verify measurements and work from the established base lines and bench marks indicated on the drawings and shall be responsible for all measurements in connection therewith. The Contractor shall furnish, at his/her own expense, all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work from the base lines and bench marks previously established. The Contractor will be held responsible for the execution of the work as detailed in the plans and specifications. It shall be the responsibility of the Contractor to maintain and preserve all stakes and other marks previously established until authorized to remove them.
1-2.11 Compliance with Local and Other Codes - The Contractor shall comply with local and other codes and standards. Where the requirements of the specifications and drawings exceed those of the local or other codes, the Contractor shall comply with the requirements of the specifications and drawings.
1-2.12 Stop Work Orders - When the Contractor or subcontractors are notified by the COR of any non-compliance with the provisions of the contract and the action(s) to be taken, the Contractor shall correct the unsafe or unhealthy condition. Action that are life threatening, that pertain to air monitoring or quality requirements, or other serious violations shall be corrected immediately. Non-serious violations shall be corrected within 24 hours of the non-compliance notice. The COR may stop the work with a “stop work order” if the Contractor fails to comply promptly with all or any part of the work being performed. When, in the opinion of the COR, satisfactory corrective action has been taken to correct the unsafe and unhealthy condition, the Contractor may resume work. The Contractor shall not be allowed any extension of time or compensation for damages by reason of or in connection with such work stoppage. In this circumstance, the entire work area and/or affected surrounding areas can be wet wiped and cleaned by the contractor at no expense to the government or COR.
1-2.13 Schedules
Schedule - The Contractor shall, within ten (10) calendar days from date of award of contract, submit to the CO for approval a practical project schedule.
The schedule shall show the order in which the Contractor proposes to carry out the work, the date on which he/she will start the several salient features (including procurement of materials, plant and equipment) and the contemplated dates for completing the work. The schedule shall be in the form of a progress chart of suitable scale to indicate the approximate percentage of work scheduled for completion at any time. The Contractor shall enter on the chart the actual progress at such intervals as directed by the CO. The project schedule shall include a milestone schedule for payments. The milestones should be stated with requested reimbursement for each milestone (based upon actual costs, overhead and profit).
Progress Schedule - The Contractor, if requested by the CO, shall submit a progress schedule at such intervals as directed by the CO. If the Contractor fails to submit a progress schedule within three (3) business days, the CO may withhold approval of progress payment estimates until the Contractor submits the required progress schedule.
1-2.14 Water/Restroom. - Water source and restroom is available on site.
1-2.15 Cleanup - The work site shall be kept clean and orderly during the progress of work. After final inspection, but before final acceptance of the work, all exterior surfaces of the new work shall be cleaned of dirt, mud, or oil accumulations. All debris shall be removed from the general site area.
1-2.16 O & M - Upon completion of the facility modifications, the Contractor shall provide operation and maintenance instructions for all new materials and equipment. The contractor shall submit a draft electronic copy of O&M’s and upon final approval still submittal two hard copies and one electronic copy to the COR. This information will then be retained by the COR (and the FAA) and used to reflect the as-constructed conditions.
1-2.16 Warranties - Documentation for the warranties shall be provided to the government upon completion of the project. Warranty shall provide for repair or replacement of the complete roofing system, including insulation and flashings, if leaking is caused by defects in materials or workmanship. These Warranties shall be incorporated into the O&M Manuals.
1-3 SAFETY
1-3.1 Safety Plan - OSHA and FAA safety standards will be enforced. In keeping with such standards, the Contractor shall at a minimum provide a Safety Plan with the purpose of maintaining a safe working environment for construction workers employed on site. The safety plan shall require a statement that the current Occupation Safety and Health Act (OSHA) regulations on safety in the construction industry, OSHA Title 29, Part 1910 and Part 1926, as well as FAA safety regulations are followed. The plan will be used by the COR to insure that the work is accomplished in accordance with accepted safety practices.
1-3.2 Trained Personnel - Personnel shall be properly trained in the usage of all equipment for which they will be required to use during the Contract. The COR may request documentation or other evidence of training at any time.
Personnel without adequate training will be prohibited from using such equipment.
1-3.3 Lock-Out/Tag-Out – The Contractor shall employ and detail lock-out/tag-out procedures to employees working with and around electrical systems. When accessing an electrical panel, a FAA technician must be present prior to interrupting and energizing the breakers. Usage of the existing power, outlets and lighting in the work area must be approved in advance by the COR.
The contractor shall coordinate comprehensive lockout procedures regarding power to the work area, with the COR.
1-3.4 Material Safety Data Sheets - The Contractor shall have Material Safety Data Sheets (MSDS) conforming to Federal Standard 313A, written by the manufacturer, for all materials containing chemicals or other substances which may pose a hazard. One (1) copy of each MSDS shall be submitted to the COR and one (1) copy of each MSDS shall be kept on file at the job site at all times. The Contractor and subcontractors will be prohibited from handling any material which does not have an applicable MSDS on file at the site until such MSDS arrives on site.
1-3.5 Safety Equipment - The Contractor shall provide safety equipment including, but not limited to, a Red Cross approved First-Aid kit and the appropriate number of annually inspected, charged fire extinguishers with the proper NFPA rating.
1-3.6 Personal Protective Equipment (PPE): The contractor shall provide employees with PPE in accordance with applicable law. Protective clothing and respiratory protection shall be worn at all times when workers may be exposed to hazardous materials during any phase of the project.
1-3.7 Work Practices - Although OSHA regulations and the Contractor's Safety Plan will usually apply, the COR may consider certain work practices to be unsafe in accordance with Public Law 91-596, Part 5a and 5b. The COR may stop any operation which is in violation of the OSHA standards or fails to comply with the safety plan or other safe work practices.
1-3.8 Designated Foreman - When any construction activity is conducted at the site, the presence of a designated, competent contractor’s foreman is required at the job site. The foreman must be qualified and capable of organizing and coordinating all activities of the Contractor and his subcontractors, and keeping a safe job site.
1-3.9 Work Force - The Contractor shall at all times, when construction activities are conducted, have a substantial number of workers for each task to proceed expeditiously and without generating delay, for lack of man-power.
2-1 Submittal Requirements
2-1 Prior to Notice to Proceed (NTP)– Specific shop drawings and/or submittal data required for various contractor furnished materials shall be submitted to the contracting officer for approval. The following submittal data shall be approved prior to the NTP.
Construction Schedule Wall Materials Ceiling Materials Batt Insulation Paints Bathroom and Plumbing Fixtures and Associated Plumbing Materials Electrical Panels Light Fixture.
Panel Electrical Surge Protection All Associated Electrical Materials
3-1 General
3-1.2 Movement and Storage of Material and Equipment
While on the job site, the contractor shall confine the movement and storage of vehicles, equipment and materials to such routes, times, and locations as may be designated by the COR, or as may be further described elsewhere in the specifications. The contractor shall prevent any abuse, damage, spillage, etc.
of materials, to such areas used, and shall maintain them and restore them to their original condition at the conclusion of the work.
3-1.3 Material and Equipment Storage - Materials or equipment stored within or outside the buildings shall be neatly stacked. If stored within the building, materials shall be so placed that they will not load any part of the structure in excess of the loads for which it was designed, nor interfere with the safe execution of the work. Storage of petroleum products or any other flammable materials inside any part of the building is prohibited.
3-1.4 Debris Removal - No materials, rubbish, or debris will be permitted to drop free, but shall be removed by the use of methods approved by the COR.
Hoists and chutes shall be erected as to prevent damage, staining, or marring of any permanent work.
3-1.5 Shipping Materials – All materials shall be shipped in their original packaging and confirmed by the COR prior to unwrapping. Immediately after unpacking, all packing materials, case lumber, excelsior, wrappings, or other rubbish flammable or otherwise, shall be collected and be removed from the building and the premises.
3-1.6 Service Interruption – Unless a facility service interruption is planned. The contractor shall exercise necessary precautions to prevent disruption of existing services while performing his work.
3-1.7 Dimensions - The contractor, before commencing work, shall verify all dimensions at the site.
4-1 Carpentry
4-1.1 All carpentry work shall be accomplished in a workman like manner. All carpentry items shall be installed level and true.
4-1.2 Fastenings - Galvanize ferrous metal fastenings shall be used, in conjunction with galvanized members and when they penetrate plaster, masonry, treated lumber or concrete.
Stainless steel fasteners shall be used for all exterior work.
4-1.3 Lumber –
Pine – Southern pine grade No. 2 dimensional grade minimum.
Grading and Marking – Lumber and plywood shall bear the grade mark, stamp or other identifying marks indicating grades of materials and rules or standards under which they are produced.
Wood Furring and Blocking – Provide fasteners of the size and quantity for proper support.
Wood Paneling – Shall match as close as possible (in color and texture) to existing paneling that is installed in ARSR building.
5-1 Painting
5-1.1 Preparation – Comply with manufacturer’s instructions and recommendations which are applicable to substrates and paint systems indicated.
Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants.
Steel Substrates: Remove rust and loose mill scale. Clean using methods recommended in writing by paint manufacturer.
Wood Substrates: Scrape and clean knots. Before applying primer, apply coat of knot sealer recommended in writing by topcoat manufacturer for exterior use in paint system indicated. Prime edges, ends, faces, undersides, and backsides of wood. After priming, fill holes and imperfections in the finish surfaces with putty or plastic wood filler. Sand smooth when dried.
Plastic Trim Fabrication Substrates: Remove dust, dirt, and other foreign material that might impair bond of paint to substrates.
5-1.2 Application - Apply paints according to manufacturer's written instructions and recommendations.
Use applicators and techniques suited for paint and substrate indicated.
Paint surfaces behind movable items same as similar exposed surfaces.
Before final installation, paint surfaces behind permanently fixed items with prime coat only. Paint both sides and edges of exterior doors and entire exposed surface of exterior door frames.
Exterior – Do not apply exterior paint in damp, rainy weather or until the surface has dried from the effects of such weather.
5-1.2.1 General Application – Each paint coat shall be applied smoothly, worked evenly and allowed to dry completely before subsequent coat is applied.
5-1.2.2 Schedule of Painting –
Note: If surface to be painted was previously painted, the contractor can omit the first coat specified.
5-1.2.3 Metal surfaces –
Exterior 1st coat Galvanized metal primer (if unpainted) 2nd coat Exterior metal paint (color to be determined) 3rd coat Exterior metal paint
Interior 1st coat Enamel undercoat (primer) 2nd coat Enamel, eg-shel 3rd coat Enamel, eg-shel
5-1.2.4 Wood -
1st coat Wood primer/sealer 2nd coat Alkyd satin wall paint (color to be determined) 3rd coat Alkyd satin wall paint
5-1.2.5 Gypsum Wallboard -
1st coat Wall primer 2nd coat Alkyd satin wall paint (color to be determined)
3rd coat Alkyd satin wall paint
5-1.2.6 Masonry/concrete
1st coat Concrete primer 2nd coat Alkyd satin wall paint (color to be determined) 3rd coat Alkyd satin wall paint
5-1.2.7 Hatch Floor Coating
After surface preparation, the contractor shall apply a high-build epoxy mastic coating to floor. The coating shall be a Steel-Tech High-Build Epoxy Mastic as manufactured by Rust-Oleum or approved equal.
6-1 Plumbing
6-1.1 Domestic Water Piping System Products
NOTE: Not all products identified below will be required on this project.
6-1.2 Submittals – Manufacturer’s product data sheets for pipe, fittings and valves, shall be made available for review and inspection.
6-1.3 Piping - Seamless Type L hard copper water pipe with wrought copper fittings shall be installed. All fitting connections shall be soldered, except fixture connections shall be made using flare or compression fittings.
6-1.4 Flexible Water Supply Lines – Flexible water lines shall be braided stainless steel.
Gate Valves – Shall have bronze body, non-rising, stem and handwheel, inside screw, single wedge or disc, threaded ends.
Globe Valves - Shall have bronze body, non-rising, stem and handwheel, inside screw, renewable composition disc, screwed ends, with backseating capacity.
Ball Valves – Bronze body, full float port, stainless steel ball, telfon seat and stuffing box ring, lever handle and balancing stops, threaded ends.
6-1.5 Plumbing Fixtures Products
6-1.5.1 - Water Closet/Toilet – The toilet shall be two-piece with an elongated bowl and shall be solid white such as manufactured by Kohler model K-3817 or approved equal.
Seat – Solid white plastic, open front, extended back, self-sustaining hinges, brass belts, without cover.
6-1.5.2 – Bathroom Sink – The sink shall be wall mounted, made of vitreous china and have three holes for faucet and valve handles. Sink shall be as manufactured by Kohler model K-12634 or approved equal.
6-1.5.3- Hot Water Heater – Shall be a mini under sink electric unit as manufactured by Ariston model GL4.0 or approved equal.
6-1.5.4 – Wall Mounted Sink (2nd Floor) – The contractor shall install a metal wall mounted hand sink. The sink shall be as manufactured by Advance Tabco
(phone# 800-645-3166), model# 7-PS-50 or approved equal. Bowl size shall be 10”x14” and fabricated from 20 gauge steel, with splash mounted faucet, lever drain with overflow. The faucet shall be the splash mounted type as manufactured by Advanced Tabco, model# K-123 or approved equal.
7-1 Vinyl Composition Tile
7-1.1 RESILIENT TILE FLOORING MATERIALS
Provide vinyl composition tile composed of polyvinyl chloride resin, plasticizers, fillers, stabilizers and pigments with colors and texture dispersed uniformly throughout its entire thickness. Size: [12 in. x 12 in.]
Tile - Shall be Armstrong Excelon. Color of tile shall be Armstrong 51839 Fortress White or equivalent.
Wall Cove Base – Shall be a thermoplastic rubber vinyl and shall be 4-inches high. The base shall be as manufactured by Roppe 700 series or approved equal.
Color shall be Roppe 193 black brown visuelle or other dark shades. Color samples shall be submitted for approval.
7-1.2 ADHESIVES - Provide Armstrong S-750 Premium Floor Tile Adhesive or approved equal and wall Base Adhesive at the wall base as recommended by the flooring manufacturer.
7-1.3 PREPARATION
Subfloor Cleaning: The surface shall be free of dust, solvents, varnish, paint, wax, oil, grease, sealers, release agents, curing compounds, residual adhesive, adhesive removers and other foreign materials that might affect the adhesion of resilient flooring to the concrete or cause a discoloration of the flooring from below. Remove residual adhesives as recommended by the flooring manufacturer. Remove curing and hardening compounds not compatible with the adhesives used, as indicated by a bond test or by the compound manufacturer's recommendations for flooring. Avoid organic solvents. Spray paints, permanent markers and other indelible ink markers must not be used to write on the back of the flooring material or used to mark the concrete slab as they could bleed through, telegraphing up to the surface and permanently staining the flooring material. If these contaminants are present on the substrate they must be mechanically removed prior to the installation of the flooring material.
7-1.4 Installation – The contractor shall install all flooring materials in strict accordance with the flooring material manufacture.
8-1 Insulation
8-1 Insulation - Shall be R-13 Kraft Faced Insulation Batt 15” x 93” as manufactured by Owens Corning or approved equal.
9-1 Electrical Work
9-1.1 Tests
9-1.1.1 General - Unless otherwise indicated, the contractor shall furnish all test instruments, materials and labor necessary to perform the following tests. All tests shall be performed in the presence of the COR. All instruments shall have been calibrated within a period of one year preceding testing.
9-1.1.2 Insulation resistance Cables - Conductors, and wires shall be tested prior to energization. Intrafacility wiring/cabling may be tested with a standard ohm meter set to the highest scale, measuring between phases, phase and neutral, phase and ground. A reading of infinite resistance indicates an acceptable installation. All testing shall be accomplished before connection is made to any existing equipment. Intrafacility wiring/cabling, feeder and branch circuit insulation tests shall be performed after installation, but before connection to fixtures or appliances. Motors shall be tested for grounds or short circuits after installation but before start-up. Testing should be performed using 500-volt DC insulation resistance tester, but may be done with a standard ohm meter set to the highest scale, measuring between phases, phase and neutral, phase and ground. Using the 500-volt DC meter method, a resistance of 30 megaohms or greater indicates an acceptable installation. Using the standard ohm meter method, a reading of infinite resistance indicates an acceptable installation. All conductors shall test free from short circuits and grounds.
9-1.1.3 Load balancing – The contractor shall balance all electrical loads on newly installed breaker panels. The contractor shall redistribute phase loads where there is greater than a 20% difference between readings in any two phases.
9-1.2 Electrical Surge Protection – The contractor shall install a new RAYCAP surge protection device on the new air conditioning panel (MCH). The new panel shall be a RAYCAP part# 120-3Y-M3-4-06-A-H or approved equal. The device shall be installed as per the manufacture’s instructions.
9-1.3 Wiring Methods
All wiring shall consist of insulated copper conductors installed in metallic raceways, unless otherwise specified.
9-1.3.1 Conductor Routing - Panelboards, surge protective devices, disconnect switches, etc., shall not be used as raceway for conductor routing other than conductors that originate or terminate in these enclosures. Per the NEC, grounding conductors for isolated ground receptacles will be allowed to pass through these enclosures as required.
9-1.3.2 Neutral conductor - Shared/common neutral conductors shall not be permitted, i.e., each overcurrent device shall have its own separate neutral conductor. Neutral conductor sizes shall not be less than the respective feeder or phase conductor sizes.
9-1.4 Raceway systems
9-1.4.1 General - Conduit interiors shall be visible clean of debris, and swabbed if necessary, before conductors are installed. Ends of raceway systems not terminated in boxes or cabinets shall be capped. Exposed raceways shall be installed parallel to or at right angles with the lines of the structure, with exceptions as approved by the COR. Crushed or deformed raceways shall not be installed. A pull wire shall be installed in all empty tubing and conduit systems in which wiring is to be installed by others. The pull wire shall be 14 AWG zinc-coated steel, or plastic with a minimum 200-pound tensile strength. A minimum of ten (10) inches of slack shall be left at each end of the pull wire. MULETAPE® of minimum 200-pound pull strength may also be used, with 36” left at each end of the wire pull. Sections of raceways which pass through to damp, concealed, or underground locations shall be of a type allowed for such locations by NEC, and shall extend a minimum of 12 inches beyond the damp, concealed, or underground area. Where raceway has to be cut in the field, it shall be cut square and burrs and sharp edges removed. Where conduits penetrate walls or floors separating the building interior from the exterior, they shall be sealed to prevent moisture and rodent entry and to deter air transfer. In addition, where conduits penetrate walls separating individually controlled temperature or humidity controlled areas, they shall be sealed to prevent air circulation. Sealing methods and sealants shall be in accordance with NEC. Where conduits penetrate fire- resistant-rated walls, partitions, floors, or ceilings, the conduit and openings shall be fire stopped using approved methods to maintain the fire resistance rating.
9-1.4.2 Conduit
Galvanized Rigid Conduit – The contractor shall provide PVC coated galvanized conduit for all 2.5” material specified in the drawings. At all other locations the galvanized rigid conduit will not require PVC coating.
Minimum conduit size for power distribution shall be 1/2 inch unless otherwise specified.
9-1.4.2.1 - Electrical metallic tubing Electrical metallic tubing (EMT) shall be steel and otherwise conform to UL 797. EMT may be used only in dry interior locations, and where not subject to physical damage. EMT shall not be used on circuits above 600 volts. The maximum size of EMT shall be trade size 4 (metric designator 103). Fittings used with EMT shall be standard compression-type fittings designed for this type of EMT, unless otherwise indicated. Set screw-type fittings are not acceptable. Where EMT enters enclosures without threaded hubs, an appropriate connector with threads and cast or machined (not sheet metal) locknut shall be used to securely bond the conduit to the enclosure. The connector body and locknut shall be installed so that firm contact is made on each side of the enclosure. In addition the connectors shall have an insulated-throat, smooth bell shaped end, or a grounding bushing.
9-1.4.2.2 - Flexible metal conduit, including Liquid-tight - Flexible metal conduit shall be ferrous and conform to Federal Specification, A-A-55810.
Flexible metal conduit shall be used for terminal connections to motors or motor driven equipment, and in lengths only up to six (6) feet for other applications permitted by the NEC. A copper equipment grounding conductor (wire) shall be run with the circuit conductors; the conduit is not to be used as the equipment grounding conductor.
Liquid-tight flexible metal conduit shall be used outdoors and in wet locations.
9-1.4.2.3 - Flexible nonmetallic conduit -Flexible nonmetallic conduit shall not be used.
9-1.5 Conductors
9-1.5.1 - Uninsulated conductors - Uninsulated conductors shall be copper and in accordance with
9-1.5.2 - Insulated conductors - Unless otherwise indicated insulated conductors shall be copper with thermoplastic or thermosetting insulation, type THW, THWN, and XHHW for general use, or type THHN for use in dry locations only, all insulated for 600 volts in accordance with Federal Specification A A 59544. Conductors sized 12 AWG and smaller for general use shall be solid. Stranded 12 AWG and smaller conductors are permitted when required for specific equipment installations. Conductors 10 AWG and larger may be stranded. Stranded conductors shall be UL Listed Class B. Minimum branch circuit conductor size shall be 12 AWG. If required specific equipment installations, stranded conductors finer than Class B may be used. Minimum control wire size shall be 14 AWG unless otherwise required by manufacturer or noted on drawings. Conductors 12 AWG and smaller are permitted to be stranded in applications where vibration and flexing may be encountered, with compression fittings installed at appropriate ends.
9-1.5.3 - Fixture wiring - Fixture wiring shall be thermoplastic insulated copper, rated for 600 volts, in accordance with the NEC.
9-1.5.4 - Conductor identification - All feeder and branch circuits, including neutral conductors, shall be identified at both ends of the conductor with panel and circuit number indicated. This shall be accomplished using shrink embossed labels only.
Equipment grounding conductors shall be color coded green. Conductors covered with green insulation with yellow, orange, violet or red tracers shall be used for other grounding systems.
Neutral conductors shall be white insulated for 208/120Y and 120/240 volt systems, and gray insulated for 480/277Y volt systems. For conductors 4 AWG and larger, where appropriate insulation color is not available, color coded tape, half lapped for a minimum length of 3 inches shall be used. Switch leg conductors shall be consistently identified within a facility. All conductor color codes including re-identified conductors shall be visible at all junction boxes, pullboxes, panelboards, outlets, switches, at access locations in closed raceways, every three (3) feet in open raceways, under all raised floors and at all terminations.
9-1.5.5 - Color Coding for Ungrounded Conductors - 120/240, 208Δ, 208/120Y Voltage Systems Standard practice for FAA installations is (1) Black for 120 volt systems; (2) Black and Red for 120/240 volt systems; (3) Black (Phase A), Red (Phase B), and Blue (Phase C) for 208Δ and 208/120Y volt 3-phase systems. This color scheme is generally used within the United States.
9-1.5.6 - 480Δ, 480/277Y Voltage Systems - To ensure safety and proper operation of equipment, only one system shall be used within a facility. For work at an existing facility, the color coding to be used shall match the existing facility color code. For new FAA facilities, the FAA historical practice of Yellow-Brown-Orange for Phase A, B, C is preferred; local practice Brown-Orange-Yellow for Phase A, B, C is permitted. Phase conductor color coding shall be continuous throughout the facility on each phase conductor to its point of utilization so that the conductor phase connection is readily identifiable.
9-1.5.7 - Connectors and Splices - Splices shall be made only at outlets, junction boxes or accessible raceways. Splicing of ungrounded conductors in panelboards is not permitted. All splices shall be accessible. Splices shall be made with solderless connectors conforming to UL 486A-486B, UL 486C, and UL 486E. Insulated wire nuts may only be used to splice conductors sized 10 AWG and smaller. Compression connectors shall be used to splice conductors 8 AWG and larger. All splices, including those made with insulated wire nuts, shall be insulated with electrical tape or shrink tubing to a level equal to that of the factory insulated conductors.
9-1.6 - Wiring devices
9-1.6.1 - Receptacles - All receptacles shall be Federal Specification grade in accordance with W-C-596. Unless otherwise indicated, general purpose duplex receptacles shall be Federal Specification grade, 20 ampere rating, 125 volt, grounding type NEMA 5-20R. Receptacles with push-in connections or a combination of screw-type and push-in connectors are not acceptable. Unless noted otherwise, receptacles shall be installed 12 inches above finished floor. All receptacles, unless they are of the isolated-ground type, shall be grounded by the installation of a green grounding pigtail from the receptacle grounding screw directly to the grounding screw on the outlet box where the green equipment grounding conductor is terminated
9-1.6.2 - Ground Fault Circuit-Interrupter receptacles - Ground fault circuit-interrupter (GFCI) receptacles shall be 125-volt, duplex, UL Group I, Class A, rated for 20 amperes minimum.
9-1.6.3 - Wall switches - Switching devices, such as single-pole, three-way, and four-way wall switches shall be Federal Specification grade, rated 120/277 volts, and shall be fully rated 20 amperes, AC only. Wiring terminals shall be of the screw type. Switches with push-in connections or a combination of screw-type and push-in connections are not acceptable.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .