This Statement of Work (SOW) details the Federal Aviation Administration's (FAA) project to construct a new Airport Traffic Control Tower (ATCT) and Base Building at the Des Moines International Airport in Iowa. The project involves building a 245-foot ATCT with a 440-square-foot eight-sided cab, a 22,900-square-foot single-story base building, a 1,200-foot access road, a stormwater detention pond, parking areas, utilities, and related infrastructure. The construction will be completed using the Design, Bid, Build method, with a total project duration estimated at 730 calendar days (2 years) and an estimated cost range of $50M to $70M.

The project scope includes comprehensive site work such as excavation, grading, utilities installation, security fencing, landscaping, and fiber optic communication infrastructure. The facilities will be compliant with International Building Code (IBC) Risk Category IV and American Society of Civil Engineers (ASCE) Operational 1-A standards. The base building will feature administrative offices, conference rooms, equipment spaces, and a critical power distribution system. The contractor will be responsible for obtaining necessary permits, coordinating with airport operations, managing site access, and ensuring strict adherence to airport safety and environmental regulations throughout the construction process.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

DSM ATCT & BASE BUILDING CONSTRUCTION

Date: August 07, 2025

1.1 SCOPE OF WORK

The Federal Aviation Administration, hereinafter referred to as the Government or FAA is seeking qualified vendors to construct a new Airport Traffic Control Tower (ATCT) and Base building at the Des Moines International Airport (DSM) in Des Moines, Iowa, hereinafter referred to as the Airport. The method of delivery for this project is Design, Bid, Build.

Specifications with referenced standards and drawings specified in the Contract Documents cover the requirements of the FAA for all work associated with the construction of a new FAA Airport Traffic Control Tower, TRACON Base Building, Parking Lot, Perimeter Security, Detention Pond, Access Road and Appurtenances located at DSM. The Contractor shall furnish all labor, materials, services, equipment, insurance, security notifications, licenses, permits, and fees in accordance with the applicable Federal, State, and local regulatory requirements in accordance with the specifications, drawings, contract clauses, and wage rates.

The project consists of the construction of an Airport Traffic Control Tower 245 feet AGL to the top of structure, and approximately 22,900 square foot base building erected on an approximately 6-acre site.

The ATCT and Base Building will be compliant with International Building Code (IBC) Risk Category IV and American Society of Civil Engineers (ASCE) Operational 1-A.

The Base Building is a single-story building of approximately 22,900 square feet. The space will contain administrative offices, bathrooms, conference rooms, shipping and receiving space, storage space, air handlers, equipment racks, electrical space and the critical power distribution system (CPDS1) which includes one engine generator, one facility Uninterruptable Power Supply (UPS) with battery rack, automatic transfer switches, static transfer switches, and redundant critical power panel space.

The project also includes a detention pond for stormwater and a 1200 ft long access road running to the northwest and connecting to SW 42nd Street.

The site improvements include excavation of unsuitable soils, structural fill placement and compaction, grading, seeding, drainage, utilities, duct backs, paving, striping, security fencing, security lighting (including cameras), power and communications duct bank, and landscaping.

The project also includes installation of a new section of fiber optic communication duct bank from the Airport Surveillance Radar to the new ATCT to achieve redundancy and satisfy diversity requirements.

The project site is on airport property West of the airport terminal and outside of the Airport Operations Area (AOA). It is rectangular in shape and is roughly 6-acres in size.

The construction period begins with the effective date of Notice to Proceed (NTP) as issued by the FAA’s Contracting Officer (CO) and ends at the FAA Beneficial Occupancy Date (BOD), which includes one-month Contractor Acceptance Inspection (CAI) and subsequent site restoration. The total duration of this project is estimated to be 730 calendar days (2 years).

The estimated price range of the construction project will be between $50M to $70M. This Screening Information Request (SIR)/Statement of Work (SOW) is considered for full and open competition.

This work includes, but is not limited to:

A. All site work and infrastructure, ATCT, Base Building, including Link Structure.

B. Construct 245 ft AGL (top of structure, to include appurtenances) ATCT

C. 440 square foot eight-sided cab

D. 22,900 square foot Base Building

E. Parking, underground fiber and communications, utilities, and road.

F. Slatwall installed in all operational and training positions in the cab and Base Building.

G. Site improvements to include fill placement, grading, drainage, utilities, duct banks, paving, security fencing, security lights and cameras and landscaping.

H. Installation of a Critical Power Distribution System, CPDS-1

I. Dual machine room-less Fire Service Access Elevators in the ATCT shaft

J. 1200 ft long access road

K. Stormwater detention pond

1.2 CONTRACT DELIVERABLE

The contract deliverable will be a fully constructed ATCT and Base Building ready for occupation short of the FAA-supplied electronic equipment installation, which is scheduled after the BOD (2 years after NTP).

1.3 CONTRACT LINE-ITEM NUMBER (CLIN)

The Work Break-Down Structure (WBS) for this project is 4.5, Construction, with the following Assets each representing a separate contract line-item number.

Bid Item 1 General Requirements 4.5.1

Bid Item 2 Site Work and Infrastructure 4.5.2

Bid Item 3 ATCT 4.5.3

Bid Item 4 TRACON Base Building 4.5.4

Bid Item 5 Roadway and Parking 4.5.5

Bid item 6 Utilities and ancillary site components 4.5.6

Bid Item 7 Landscaping 4.5.7

Bid Item 8 Fiber Optic System 4.5.8

1.4 WORK SEQUENCE

Construction Work stages shall be defined by the Contractor. The following sequence is provided as General Guidance Only. Additional phasing may be necessary due to site availability restrictions.

Portions of Stages may be simultaneous.

Stage Action

1. Establish and make FAA Field Representatives’ (COR) office trailer fully operational

2. Secure site and install erosion control devices

3. Complete site clearing and site demolition

4. Rough grade site

5. Construct permanent and temporary storm drain

6. Construct ATCT foundation

7. Construct ATCT and Base Building

8. Construct utilities and fiber optics

9. Construct road and parking

10. Construct final fence and perimeter security

11. Landscape

12. Remove Temporary Structures and Devices

1.4.1 SCHEDULE

The total duration of the construction phase is estimated to be 730 calendar days (2 yrs) from the NTP to the BOD.

1.5 CONTRACTOR USE OF PREMISES

A. The FAA shall have the right to unlimited access to the premises.

B. The Airport may be constructing other improvements in the vicinity of the ATCT and Base Building during a portion or all of this construction. The Contractor shall coordinate with the Airport and not impede the progress on any existing or planned projects.

C. The Contractor shall coordinate use of premises in accordance with the site availability shown on the plans and as directed by the Contracting Officers Representative (COR).

D. The Contractor shall assume full responsibility for protection and safekeeping of project materials (government and contractor supplied) under this Contract.

E. The Contractor shall obtain and pay for use of additional storage or work areas needed for operations under this Contract.

F. The Contractor shall utilize dumpsters and trash bins with lids to ensure trash/debris do not become wind-blown and leave the construction site. The Airport Operations Area (AOA) surrounding the ATCT and Base Building site are restricted areas with moving aircraft. Foreign Object Debris (FOD) leaving the construction site and being blown onto the AOA can be sucked into aircraft engines, causing considerable damage or loss of life.

G. The Contractor shall not park along existing airport roads.

H. The Contractor shall coordinate with the applicable utility company on the demolition and installation of all utilities.

1.6 ACCESS TO SITE

The Contractor’s access to site will be as shown on the plans or as directed by the COR. The Contractor will have full use of the ATCT and Base Building site and will be responsible for managing deliveries and construction activities as necessary to complete the work. The Contractor shall not permit any unauthorized construction personnel or traffic on the site. The Contractor will be responsible for traffic control to and from the various construction areas on the site. Directional signage at the access gate and along the delivery route to the storage area or work site shall be as directed by the COR. The Contractor will not be allowed to close any traffic lanes, nor will the Contractor be allowed to impede the flow of airport traffic without prior coordination with the COR and the Airport.

1.7 MATERIALS DELIVERY TO THE SITE

Delivery trucks shall not pass in front of the terminal. The Contractor shall prepare and submit to the COR for approval, a delivery plan for all types of delivery. The plan shall define the procedures that will be used to accommodate delivery traffic for all types of deliveries (e.g., concrete/asphalt, steel, precast, earth/aggregate, tractor trailer, city delivery truck) and any staging areas that will be used. Normal flow of traffic, into and out of the airport, shall not be impeded. Deliveries will be suspended at the discretion of the COR.

Delivery for continuous concrete pours, such as foundations and concrete pavement, shall be coordinated with the COR and Airport at least two weeks in advance of anticipated dates.

The Contractor is responsible for immediate clean-up of any debris deposited along the access road as a result of construction traffic. A street sweeper shall always be available on-site for dust-free removal of any spillage.

1.8 CONSTRUCTION AREA LIMITS

The limits of construction, material storage areas, equipment storage areas, parking areas, and other areas as required by the Contractor will be as shown on the plans or as approved by the COR. Should the Contractor find it necessary or advantageous to use any additional offsite area for any purpose whatsoever, the Contractor shall, at their expense, provide and make its own arrangements for the use of such additional offsite areas.

The Contractor shall erect and maintain fencing, marking, and/or warning devices suitable for both day and night use to delineate the perimeter of all such areas.

When the Work requires the Contractor to conduct operations within areas adjacent to active FAA or AOA areas, the Work shall be coordinated with the FAA and Airport through the COR.

Parking will not be allowed along the public right of way or the entrance/exit road. In the event adequate space is not available for parking on the project site, the Contractor shall arrange for off-site parking and provide bus transportation of employees to and from the site. No other areas will be made available for Contractor use for parking, staging, trailers, or storage.

1.9 REQUIRED PERMITS

Listed below are the agencies that govern this project. Unless otherwise noted, the Contractor is responsible for applying for utility services, obtaining required permits, and payment for any associated fees. Compliance is required with the conditions of all permits that have been issued.

Additional permits may need to be obtained by the Contractor.

1. Sanitary Sewer - Permit approval will be provided to the Contractor. Contractor shall comply with all provisions of present approval and the permit plans or obtain new approval. Contractor will not be required to obtain a construction permit. Contractor will pay for connection fees and establish customer service which will be transferred to FAA at no cost at completion of construction contract.

2. Water - Permit approval will be provided to the Contractor. Contractor shall comply with all provisions of present approval and the permit plans or obtain new approval. Contractor will not be required to obtain a construction permit. Contractor will pay for connection fees and establish customer service which will be transferred to FAA at no cost at completion of construction contract.

3. Erosion Control –Permit approval and conditions will be provided to the Contractor. It is the responsibility of the Contractor to notify Iowa Department of Environment and Natural Resources prior to beginning construction activities.

4. Stormwater – Permit approval and conditions will be provided to the Contractor.

5. NDPES approval will be included in the approvals under the Erosion Control permit application made to IADENR. Permit approval and conditions will be provided to the

Contractor. It is the responsibility of the Contractor to notify IADENR prior to beginning construction activities. The contractor is responsible for maintain and complying with the approved NPDES permit. The contractor shall follow the erosion control pans that are included on the Site drawings. Any deviations or changes made to the plans will require a new NPDES permit to be submitted to the Iowa Department of Environmental Quality. All costs to submit a new permit will be the responsibility of the contractor. During construction the contractor is responsible for following and implementing the erosion control plan approved. Any fees resulting from violations of the erosion control will be paid by the prime contractor without any right of reimbursement from the government.

6. Grading Permit - Contractor will not be required to obtain a Grading Permit from the City.

7. Air Space– All permanent and temporary work, including cranes, must comply with FAA Obstruction Evaluation / Airport Airspace Analysis (OE/AAA) requirements. Contractor shall file a Request for Construction for permanent structures on Airport. The Request should be submitted online. The website for more information and to obtain the appropriate forms is https://oeaaa.faa.gov/oeaaa/external/puntal.jsp. Erection of the crane will not be permitted without approval of the form. No claim for delay will be allowed for failure to submit the form in a timely manner. Allow a minimum of sixty (60) days for processing.

Contractor is responsible for follow up with the issuing office after submittal.

8. Fuel Storage Tank and Piping – Contractor shall apply and obtain permits and pay all fees.

Telephone and Electric Service – Obtain permits and pay all fees associated with temporary and permanent services which will be transferred to FAA at no cost at completion of construction contract.

9. Air Permit –The emergency generators will be subject to 40 CFR 60, Subpart IIII, and the facility will need to comply with all applicable emissions limits, fuel requirements, testing, monitoring, recordkeeping, and reporting requirements. Exemption letter and conditions will be provided to the Contractor. It is the responsibility of the Contractor to follow 40 CFR 60, Subpart III as well as comply with all applicable emissions limits, fuel requirements, testing, monitoring, recordkeeping, and reporting requirements related to any activities involving the emergency generators.

1.10 BUILDING PERMIT

This facility will be constructed and owned by the U.S. Government; therefore, a building permit will not be required. All other permits and license requirements apply.

1.11 GOVERNMENT FURNISHED MATERIAL

No government furnished material is expected to be provided for this project.

1.1 SCOPE OF WORK
1.2 CONTRACT DELIVERABLE
1.3 CONTRACT LINE-ITEM NUMBER (CLIN)
1.4 WORK SEQUENCE
1.4.1 SCHEDULE
1.5 CONTRACTOR USE OF PREMISES
1.6 ACCESS TO SITE
1.7 MATERIALS DELIVERY TO THE SITE
1.8 CONSTRUCTION AREA LIMITS
1.9 REQUIRED PERMITS
1.10 BUILDING PERMIT
1.11 GOVERNMENT FURNISHED MATERIAL