Drawing for H20-00528-0J.pdf
PDF 1 MB Posted
- Attached to
- Replace LED lights and install electric panel board and w iring system at Golf Course, Carroll FOS
- Solicitation number
- W90VN921R0031
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W90VN921R0031.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXTERIOR LIGHTING POLE PLAN
CARROLL FOS (SEONG JU), SITE MAP 1/7
FEWR NO. H20-00533-0J
LOCATION : CARROLL FOS.
Bldg #1020Bldg #1030
(Lighting Pole #1-1 Thru 1-6 and 10-1 Thru 10-3)
FEWR NO. H20-00533-0J
LOCATION : CARROLL FOS.
PAVEMENT PLAN
< Scope of Works >
1. Saw cut existing asphalt concrete pavement 3’-0”W x 30’-0”L with excavation of 3’-0”W x 3’-0”H x 30’-0”L including backfill, compaction & removal and install concrete encasement 2’-7”W x 1’-0”H x 30’-0”L with 4”dia x 30’-0”L x 3ea, 6”dia x 30’-0”L x 1ea steel pipes for lighting power line of electric pole #10-1 and communication Line.
3. Saw cut existing asphalt concrete pavement 1’-0”W x 30’-0”L with excavation of 1’-0”W x 3’-0”H x 30’-0”L including backfill, compaction & removal and install concrete encasement 1’-0”W x 1’-0”H x 30’-0”L with 6”dia x 30’-0”L x 1ea steel pipes for communication line.
4. Excavate 1’-0”W x 3’-0”D x Approx. 500’-0”L including backfill, compaction & removal from lighting pole for electric pole #10-1 to Bldg. #1020 and 1’-0”W x 3’- 0”D x 300’-0”L from lighting pole #1-1 to Bldg. #1020.
5. Remove 3’-0”W x 30’-0”L existing asphalt concrete pavement and construct 3’- 0”W, 285mm thick Portland cement concrete(PCC) pavement with 330mm thick base course for lighting power line of electric pole #10-1.
7. Remove 1’-0”W x 30’-0”L existing asphalt concrete pavement and construct 1’- 0”W, 285mm thick Portland cement concrete(PCC) pavement with 330mm thick base course for communication line.
2. Saw cut existing asphalt concrete pavement 1’-0”W x 30’-0” L with excavation of 1’-0”W x 3’-0”H x 30’-0”L including backfill, compaction & removal and install concrete encasement 1’-0”W x 1’-0”H x 30’-0”L with 4”dia x 30’-0”L x 1ea steel pipes for lighting power line of electric pole #1-1..
Scope of work #2,4 & 6
Scope of work #3 & 7
6. Remove 1’-0”W x 30’-0”L existing asphalt concrete pavement and construct 1’- 0”W, 285mm thick Portland cement concrete(PCC) pavement with 330mm thick base course for lighting power line of electric pole #1-1.
Scope of work #1, 4 & 5
2/7
Bldg #1020
Bldg #1030
< Scope of Works >
1. Install 4ea concrete manholes 3’W x 3’L x 3’D x 6”thk. for lighting power line and communication line.
Concrete manhole for lighting power & comm. line
MANHOLE PLAN
FEWR NO. H20-00533-0J
LOCATION : CARROLL FOS.
New manhole
3/7
LOCATION : CARROLL FOS. Install C/B (3P-220V-60A) with power line (cable #6-3C) from existing ACB & MCCB to new lighting contractor for lighting pole #10-1.
Install lighting contactor (3P-220V-150A, combination C/B type).
To lighting pole #10-1.
(Underground wiring system)
New cable #6-3C in 1- 1/2” conduit(Interior)
New cable #2-3C in 2” ELP PVC pipe(Exterior)
To lighting pole #1-1 (Underground wiring system)
POWER PLAN FOR EXTERIOR LIGHT
Install C/B (3P-220V-70A) with power line (cable #2-3C) from existing ACB & MCCB to new lighting contractor for lighting pole #1-1.
New cable #2-3C in 2” conduit(Interior)
New cable #6-3C in 1-1/2” ELP PVC pipe(Exterior)
4/7
Electrical room in basement
Existing ACB & MCCB
LIGNTING PLAN
< Scope of Works >
1. Remove existing 40ea metal halide 1500watt lighting fixtures with cross-arm and 9ea ballasts on the lighting pole (Pole #10-1 Thru 10-3 and 1-1 Thru 1-6).
2. Install 40ea LED lights, 600Watt LED Flood Light, Input Power : AC 120-277V, 60HZ, 600Watt, 496mm (L)x 360mm (W) x 229 mm (H), Luminous Flux: 72,000, Color Temperature : 5,000K, Working Temp. -30 Thru +45, Luminous Flux :
72,000(70Ra), 66,000(80Ra), CRI : Over 70, Housing Material : Aluminum, Water Proofing Type, Weight : 23.4Kg, Beam Angel : 15, 22, 30, 45, 60 DEG, Adjustable, Lamp Reinforced Glass, Model(Part) #F600TG, MFR : DLS global, or Equally approved product(UL Listed), steel double cross-arm (Square type) 3” x 3” x 8’L with arm ties and connect power line (Cable #12-3C) from LED light to new pull box (Pole #10-1 Thru 10-3 and 1-1 Thru 1-6).
3. Install 9ea pull boxes (12” x 12” x 6”D, Stainless steel #20GA, NEMA 3R, Lock style, “KS” and 1-1/2” dia., 4ea holes to connect power line with conduit on Pole #10-1 Thru 10-3 and 1-1 Thru 1-6 (The pull box will be installed six feet above ground).
4. Install new underground power line (Cable #6-3C in 1-1/2” ELP PVC pipe and Steel conduit) from pole #10-1 to Bldg #1020 (Electrical room in basement) and circuit breaker 3P-220V-60A-60HZ (UL Listed) in existing ACB & MCCB.
5. Install new underground power line (Cable #2-3C in 2” ELP PVC pipe and Steel conduit) from pole #1-1 to Bldg. #1020 (Electrical room in basement) and circuit breaker 3P-220V-70A-60HZ (UL Listed) in existing ACB & MCCB.
6. Install combination lighting contactor including fusible type, disconnect Switch, 3P-150A-60HZ, circuit breaker, timer, magnetic contactor with power line and all necessary accessories (UL Listed) for LED lightings (Pole #10-1 thru 10-3 and 1-1 thru 1-6).
7. Install 5/8” x 8’L x 9ea grounding rods with wire #8 in 3/4” conduit (Pole #10-1 Thru 10-3 and 1-1 Thru 1-6) for lightning protection system.
5/7
To new panel board.
(Underground wiring system)
Install power line 4-#1/0 in 2-1/2” conduit(Interior)
POWER PLAN FOR COMMUNICATION EQUIPMENT
Install circuit breaker (3P-380V-150A) with power line (4-#1/0 in 2-1/2”C) from existing ACB & MCCB to new transformer.
Install new transformer 15KVA Dry Type 220/110V, Pad MTD, 3P-4W- 60HZ Primary 380/220V, Secondary 380V with power line(4-#1/0 in 2- 1/2”C) from new transformer to new panel board.
Existing ACB & MCCB
Install power line 4-#1/0 in 2-1/2” ELP PVC pipe(Exterior)
6/7
Electrical room in basement
Scope of work
1. Install panel board 3P-4W-150A-220/110V main C.B, 60HZ, w/SN & GRD, SURE MTG type, NEMA 3R, circuit breaker 3P-100A-1ea, 3P-60A-1ea, 3P- 30A-1ea, 2P-60A-2ea, 2P-30A-2ea, 1P-20A-1ea, number of spaces 18 for communication equipment.
2. Install safety switch, non-fusible type, 3P-3W-600VAC-150AF, S&N, GND, NEMA 3R encl. (stainless steel) with power line. UL listed, for communication equipment.
3. Install 5/8” x 8’L grounding rod with wire #4 in 3/4” conduit on existing Panel board for lightning protection system.
4. Fabrication and install steel frame 5’H x 1’6”W for panel board(P/N) and safety switch.
FEWR NO. H20-00533-0J
LOCATION : CARROLL FOS.
2 1/2”x 2-1/2” x ¼”thick SQ steel pipe, Rigid galvanized
Safety switch
GL GL
Front view Side view
’-0
Steel pipe frame 1’6”’W x 8’H for panel board and safety switch
’-0
Steel frame for P/N & safety switch
New panel board and safety switch
Panel board
#20 protected sheet metal 10W
12” x 12” x 3’D concrete foundation
7/7PANEL BOARD AND SAFETY SWITCH PLAN FOR COMMUNICATION EQUIPMENT