This document outlines specifications for a federal contract opportunity issued by the Department of the Army Corps of Engineers Engineering District Japan. The solicitation number is W912HV-23-R-0004 and seeks products and services to support Theater Aircraft Corrosion Control Prep Hangar LXEZ 1076699. The specifications are contained in a 16MB PDF file titled Draft W912HV23R0004_RTA Specifications_Volume 2 and pertain to pre-solicitation requirements for maintaining aircraft hangars to prevent corrosion. Key details in the specifications include performance standards for corrosion prevention activities, materials lists, inspection procedures, and maintenance schedules. The opportunity is open to all contractors but has not yet reached the solicitation stage.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT
Solicitation No. W912HV-23-R-0004
US Army Corps of Engineers
Japan District
FINAL DESIGN CONSTRUCTION
THEATER AIRCRAFT CORROSION CONTROL
PREP HANGAR
KADENA AIR BASE, JAPAN
SPECIFICATIONS
RTA DESIGN
DATE: AUGUST 2023
DRAFTTHIS PAGE INTENTIONALLY LEFT BLANK
Theater Aircraft Corrosion Control Prep Hangar Kadena Air Base, Japan
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.00 10 GENERAL CONTRACT REQUIREMENTS
01 14 00 11/11, CHG 13: 08/21 WORK RESTRICTIONS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01.00 10 02/15 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 33 23.33 08/18, CHG 1: 02/21 AVIATION FUEL SYSTEM SPECIFIC
SUBMITTAL REQUIREMENTS
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 42 15 METRIC MEASUREMENTS
01 45 00.00 10 11/16 QUALITY CONTROL
01 45 00.15 10 11/16 RESIDENT MANAGEMENT SYSTEM CONTRACTOR
MODE (RMS CM)
01 45 35 02/15 SPECIAL INSPECTIONS
01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19.01 04/21 TEMPORARY ENVIRONMENTAL CONTROLS -
KADENA AIR BASE
01 74 19 CONSTRUCTION AND DEMOLITION WASTE
MANAGEMENT
01 78 00 05/19 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
01 91 00.15 10 05/16 TOTAL BUILDING COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 05/10, CHG 2: 02/19 DEMOLITION
02 61 13 02/10, CHG 1: 02/21 EXCAVATION AND HANDLING OF
CONTAMINATED MATERIAL
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 00 04/21 ASBESTOS REMEDIATION (tailored for
Japan)
02 82 00.00 30 ASBESTOS REMEDIATION 18 WING SUPPLEMENT
02 83 00 4/21 LEAD REMEDIATION (tailored for Japan)
02 83 00.00 30 LEAD REMEDIATION
02 84 33 04/06 REMOVAL AND DISPOSAL OF
POLYCHLORINATED BIPHENYLS (PCBs)
DIVISION 03 - CONCRETE
03 30 00 02/19 CAST-IN-PLACE CONCRETE
03 41 33 11/16, CHG 1: 11/18 PRECAST STRUCTURAL PRETENSIONED
CONCRETE
03 45 00 05/16, CHG 1: 05/21 PRECAST ARCHITECTURAL CONCRETE
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 23.13 10 08/18 ULTRASONIC INSPECTION OF WELDMENTS
PROJECT TABLE OF CONTENTS Page 1
Kadena Air Base, Japan
05 05 23.16 08/18 STRUCTURAL WELDING
05 12 00 08/18 STRUCTURAL STEEL
05 12 19 02/23 BUCKLING-RESTRAINED BRACES (BRB)
05 50 13 05/17 MISCELLANEOUS METAL FABRICATIONS
05 51 00 02/17, CHG 1: 05/17 METAL STAIRS
05 51 33 02/16 METAL LADDERS
05 52 00 02/18 METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
06 73 01 05/18 FIBERGLASS REINFORCED PLASTIC (FRP)
GRATING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 08/19 PRESSURE TESTING AN AIR BARRIER SYSTEM
FOR AIR TIGHTNESS
07 14 00 02/12 FLUID-APPLIED WATERPROOFING
07 21 16 11/11, CHG 4: 08/18 MINERAL FIBER BLANKET INSULATION
07 27 10.00 10 08/19, CHG 1: 02/20 BUILDING AIR BARRIER SYSTEM
07 27 36 05/17, CHG 2: 08/20 SPRAY FOAM AIR BARRIERS
07 41 63 11/16 FABRICATED ROOF PANEL ASSEMBLIES
07 57 12 09/21 LIQUID APPLIED ELASTOMERIC SILICONE
WALL COATING
07 57 16 09/21 LIQUID APPLIED ELASTOMERIC ACRYLIC
ROOFING
07 60 00 05/17 FLASHING AND SHEET METAL
07 84 00 05/10, CHG 1: 08/13 FIRESTOPPING
07 92 00 08/16 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 11 16 05/17 ALUMINUM DOORS AND FRAMES
08 14 00 08/16 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 23 08/20 OVERHEAD COILING DOORS
08 34 16.10 05/17 STEEL SLIDING HANGAR DOORS
08 51 13 05/19 ALUMINUM WINDOWS
08 51 23 08/20 STEEL WINDOWS
08 71 00 02/16 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16 GYPSUM BOARD
09 30 10 08/17 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 65 00 08/10 RESILIENT FLOORING
09 90 00 05/11 PAINTS AND COATINGS
09 97 13.17 02/10, CHG 1: 08/17 THREE COAT EPOXY INTERIOR COATING OF
WELDED STEEL PETROLEUM FUEL TANKS
PROJECT TABLE OF CONTENTS Page 2
Kadena Air Base, Japan
09 97 13.27 02/21 HIGH PERFORMANCE COATING FOR STEEL
STRUCTURES
DIVISION 10 - SPECIALTIES
10 14 00.10 08/17 EXTERIOR SIGNAGE
10 14 00.20 08/17 INTERIOR SIGNAGE
10 21 13 08/17 TOILET COMPARTMENTS
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/17 TOILET ACCESSORIES
10 44 19 04/23 FIRE EXTINGUISHER CABINETS
10 56 13 04/06 STEEL AND MOBILE STORAGE SHELVING
DIVISION 11 - EQUIPMENT
11 24 40 09/21 FALL ARREST SYSTEMS
11 31 13 08/17, CHG 1: 08/18 ELECTRIC KITCHEN EQUIPMENT
11 50 10 09/21 HANGAR BAY PAINT SPRAY BOOTH
11 50 11 09/21 PLASTIC MEDIA BLAST BOOTH
11 50 13 11/21 COMPONENT PAINT SPRAY BOOTH
DIVISION 12 - FURNISHINGS
12 21 00 08/17, CHG 2: 11/18 WINDOW BLINDS
12 48 13 08/17 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 21 15 09/21 DECONTAMINATION AIR SHOWERS
13 48 73 05/20, CHG 1: 08/20 SEISMIC CONTROL FOR MECHANICAL
EQUIPMENT
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 30 00 04/08 FIRE PUMPS
DIVISION 22 - PLUMBING
22 00 00 11/15 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 15 02/14 COMMON PIPING FOR HVAC
23 05 48.19 05/18, CHG 2: 08/20 SEISMIC BRACING FOR HVAC
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 02/19, CHG 3: 05/21 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15, CHG 2: 05/21 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 02/19, CHG 1: 02/20 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 23 00 10/07 REFRIGERANT PIPING
23 25 00 05/21 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 30 00 05/20 HVAC AIR DISTRIBUTION
PROJECT TABLE OF CONTENTS Page 3
Kadena Air Base, Japan
23 52 00 04/08, CHG 5: 11/19 HEATING BOILERS
23 64 10 11/16 WATER CHILLERS, VAPOR COMPRESSION TYPE
23 64 26 08/09 CHILLED, CHILLED-HOT, AND CONDENSER
WATER PIPING SYSTEMS
23 81 00 05/18 DECENTRALIZED UNITARY HVAC EQUIPMENT
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.23 11/17 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS UTILITY MONITORING AND
CONTROL SYSTEM TO INCLUDE HVAC
25 10 10 02/19, CHG 1: 05/21 UTILITY MONITORING AND CONTROL SYSTEM
(UMCS) FRONT END AND INTEGRATION
DIVISION 26 - ELECTRICAL
26 05 48.00 10 10/07 SEISMIC PROTECTION FOR ELECTRICAL
EQUIPMENT
26 08 00 08/08, CHG 2: 08/21 APPARATUS INSPECTION AND TESTING
26 11 16 11/21 SECONDARY UNIT SUBSTATIONS
26 13 00 05/21 SF6/HIGH-FIREPOINT FLUIDS INSULATED
PAD-MOUNTED SWITCHGEAR
26 20 00 02/14 INTERIOR DISTRIBUTION SYSTEM
26 24 13 05/15 SWITCHBOARDS
26 27 13.10 30 10/07, CHG 2: 08/18 ELECTRIC METERS
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
26 32 15.00 05/20 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 51 00 05/16 INTERIOR LIGHTING
26 56 00 05/13 EXTERIOR LIGHTING
26 56 20 02/19 AIRFIELD AND HELIPORT LIGHTING AND
VISUAL NAVIGATION AIDS
DIVISION 27 - COMMUNICATIONS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 51 16 05/20 PUBLIC ADDRESS SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 00 00 08/08 EARTHWORK
31 05 19 08/08 GEOTEXTILE
31 11 00 11/18 CLEARING AND GRUBBING
31 21 13 11/18 RADON MITIGATION
31 31 16.19 02/16 TERMITE CONTROL BARRIERS
31 32 41 A/E SOIL CEMENT COLUMNS
DIVISION 32 - EXTERIOR IMPROVEMENTS
PROJECT TABLE OF CONTENTS Page 4
Kadena Air Base, Japan
32 01 11.51 05/16, CHG 2: 08/17 RUBBER AND PAINT REMOVAL FROM AIRFIELD
PAVEMENTS
32 01 16.71 02/17 COLD MILLING ASPHALT PAVING
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 11 23 08/17 AGGREGATE BASE COURSES
32 11 23.23 08/17 BASE COURSE DRAINAGE LAYERS
32 11 36.13 11/19 LEAN CONCRETE BASE COURSE
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 12 15.13 11/20 ASPHALT PAVING FOR AIRFIELDS
32 12 16.16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS
32 13 11.01 11/15 CONCRETE FOR HANGAR FLOORS
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 13 14.13 08/19 CONCRETE PAVING FOR AIRFIELDS AND
OTHER HEAVY DUTY PAVEMENTS
32 13 73.19 11/19 COMPRESSION CONCRETE PAVING JOINT
SEALANT
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23 08/16, CHG 5: 11/18 PAVEMENT MARKINGS
32 31 13 11/16 CHAIN LINK FENCES AND GATES
32 31 13.53 02/20 HIGH-SECURITY FENCES (CHAIN LINK AND
ORNAMENTAL) AND GATES
32 92 23 04/06, CHG 1: 08/21 SODDING
32 93 00 08/17, CHG 1: 08/21 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 01 50.31 02/20 LEAK DETECTION FOR FUELING SYSTEMS
33 08 53 08/18 AVIATION FUEL DISTRIBUTION SYSTEM
START-UP
33 11 00 02/18 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
33 40 00 02/10 STORM DRAINAGE UTILITIES
33 46 16 05/18 SUBDRAINAGE PIPING
33 52 10 11/18, CHG 1: 11/20 FUEL SYSTEMS PIPING (SERVICE STATION)
33 52 23.15 11/18 POL SERVICE PIPING WELDING
33 52 43.13 08/18, CHG 1: 02/21 AVIATION FUEL PIPING
33 52 80 02/10 LIQUID FUELS PIPELINE COATING SYSTEMS
33 56 10 05/19, CHG 1: 11/20 FACTORY-FABRICATED FUEL STORAGE TANKS
33 61 13.13 02/16 PREFABRICATED UNDERGROUND HYDRONIC
ENERGY DISTRIBUTION
33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.19 04/22 JIB CRANES
41 22 23.19 05/20 MONORAIL HOISTS
DIVISION 46 - WATER AND WASTEWATER EQUIPMENT
46 05 14 09/21 AIRCRAFT WASH AND WASTEWATER RECOVERY
SYSTEMS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 5
Kadena Air Base, Japan
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 6
Theater Corrosion Control Prep Hangar D3449300KADCCHP2 August 01, 2023 3:16 PM
ATTACHMENT LIST
This report lists all attachments in the text.
HINT: With this file opened as a report from the SI Processed Files folder, double-clicking a Section number will open the Section in the Editor.
SECTION SUBPART ATTACHMENT
01 11 00.00 10 1.11.4 01 11 00.00 10-A "UXO Emergency Mitigation Steps and Survey Policies"
01 33 00 1.5.1 01 33 00-A ENG FORM 4025-R
01 33 00 Part 3 01 33 00-B "Submittal Register" 01 33 29 1.4 01 33 29-A "GBCI GPA Checklist" 01 33 29 1.4 01 33 29-B "Sustainability Requirements
Scoresheet" 01 35 26 1.7 01 35 26-A "Form A-02 Accident Prevention
Plan Checklist" 01 45 35 1.2 01 45 35-A "Statement of Special
Inspections" 01 45 35 1.2 01 45 35-B "Schedule of Special Inspections" 01 50 00 2.1.1 01 50 00-A 01 57 19.01 1.7.5 01 57 19.01-A "HAZMAT Inspection Report" 01 78 00 3.9 01 78 00-A "Draft DD FORM 1354" 01 91 00.15 10 3.1.2 01 91 00.15 10-A "Design Phase
Commissioning Plan"
Attachment List
Theater Corrosion Control Prep Hangar D3449300KADCCHP2 August 01, 2023 3:16 PM
THIS PAGE INTENTIONALLY LEFT BLANK
Attachment List
Kadena Air Base, Japan
SECTION 21 13 13
WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION
08/20
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)
ASME B16.1 (2020) Gray Iron Pipe Flanges and Flanged Fittings Classes 25, 125, and 250
ASME B16.3 (2016) Malleable Iron Threaded Fittings, Classes 150 and 300
ASME B16.4 (2016) Standard for Gray Iron Threaded Fittings; Classes 125 and 250
ASME B16.21 (2021) Nonmetallic Flat Gaskets for Pipe Flanges
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C104/A21.4 (2016) Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water
AWWA C110/A21.10 (2012) Ductile-Iron and Gray-Iron Fittings for Water
AWWA C111/A21.11 (2017) Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings
AWWA C203 (2008) Coal-Tar Protective Coatings and Linings for Steel Water Pipelines - Enamel and Tape - Hot-Applied
ASTM INTERNATIONAL (ASTM)
ASTM A47/A47M (1999; R 2018; E 2018) Standard Specification for Ferritic Malleable Iron Castings
ASTM A53/A53M (2020) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A135/A135M (2021) Standard Specification for Electric-Resistance-Welded Steel Pipe
ASTM A153/A153M (2016a) Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel
W912HV-23-R-0004 SECTION 21 13 13 Page 1 Jacobs D3449300
Kadena Air Base, Japan
Hardware
ASTM A183 (2014; R 2020) Standard Specification for Carbon Steel Track Bolts and Nuts
ASTM A536 (1984; R 2019; E 2019) Standard Specification for Ductile Iron Castings
FM GLOBAL (FM)
FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/
MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS
INDUSTRY (MSS)
MSS SP-71 (2018) Gray Iron Swing Check Valves, Flanged and Threaded Ends
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 13 (2019) Standard for the Installation of Sprinkler Systems
NFPA 24 (2019; TIA 19-1) Standard for the Installation of Private Fire Service Mains and Their Appurtenances
NFPA 33 (2021) Standard for Spray Application Using Flammable or Combustible Materials
NFPA 291 (2019) Recommended Practice for Fire Flow Testing and Marking of Hydrants
NFPA 1963 (2019) Standard for Fire Hose Connections
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES
(NICET)
NICET 1014-7 (2012) Program Detail Manual for Certification in the Field of Fire Protection Engineering Technology (Field Code 003) Subfield of Automatic Sprinkler System Layout
UNDERWRITERS LABORATORIES (UL)
UL 199 (2020) UL Standard for Safety Automatic Sprinklers for Fire-Protection Service
UL 312 (2010; Reprint Mar 2018) UL Standard for Safety Check Valves for Fire-Protection Service
UL 405 (2013; Bul. 2020) UL Standard for Safety Fire Department Connection Devices
UL 668 (2004; Reprint Jul 2016) UL Standard for Safety Hose Valves for Fire-Protection
W912HV-23-R-0004 SECTION 21 13 13 Page 2 Jacobs D3449300
Kadena Air Base, Japan
Service
UL Fire Prot Dir (2020) Fire Protection Equipment Directory
JAPANESE INDUSTRIAL STANDARDS (JIS)
JIS B 2301 (2013) Screwed Type Malleable Cast Iron Pipe Fittings
JIS B 2311 (2015) Steel Butt-Welding Pipe Fittings for Ordinary Use
JIS G 3454 (2019) Carbon Steel Pipes for Pressure Service (Amendment 1)
1.2 SYSTEM DESCRIPTION
Provide wet pipe sprinkler system(s) in all areas of the building .
Except as modified herein, the system must meet the requirements of NFPA 13 .
Pipe sizes which are not indicated on the Contract drawings must be determined by hydraulic calculations.
1.2.1 Hydraulic Design
1.2.1.1 Basis for Calculations
A waterflow test was performed on 10 March 2021 at Building 3534. The results are as indicated on the design drawings. Perform a fire hydrant flow test prior to shop drawing submittal in accordance with NFPA 291 .
Results must include hydrant elevations relative to the building and hydrant number/identifiers for the tested hydrants, including which were flowed, which had a gauge. This information must be presented in a tabular form if multiple hydrants were flowed. The results must be included with the hydraulic calculations. Hydraulic calculations must be based upon the Hazen-Williams formula with a "C" value noted in NFPA 13 for piping. Hydraulic calculations must be based on operation of the fire pump(s) provided in Section 21 30 00 FIRE PUMPS.
1.2.1.2 Hydraulic Calculations
a. Water supply curves and system requirements must be plotted on semi-logarithmic graph (N^1.85) paper so as to present a summary of the complete hydraulic calculation.
b. Provide a summary sheet listing sprinklers in the design area and their respective hydraulic reference points, elevations, minimum discharge pressures and minimum flows. Elevations of hydraulic reference points (nodes) must be indicated.
c. Documentation must identify each pipe individually and the nodes connected thereto. Indicate the diameter, length, flow, velocity, friction loss, number and type fittings, total friction loss in the pipe, equivalent pipe length and Hazen-Williams coefficient for each pipe.
d. Where the sprinkler system is supplied by interconnected risers , the sprinkler system must be hydraulically calculated using the hydraulically most demanding single riser. The calculations must n ot assume the simultaneous use of more than one riser.
W912HV-23-R-0004 SECTION 21 13 13 Page 3 Jacobs D3449300
Kadena Air Base, Japan
e. For gridded systems, calculations must show peaking of demand area friction loss to verify that the hydraulically most demanding area is being used. A flow diagram indicating the quantity and direction of flows must be included.
1.2.1.3 Design Criteria
Hydraulically design the system to discharge a minimum density over the hydraulically most demanding floor areaas indicated on the drawings.
Hydraulic calculations must be in accordance with the Area/Density Method of NFPA 13. Add an allowance for exterior hose streams shall be as indicated on design drawing at the point of connection to the existing water system.
1.2.2 Sprinkler Coverage
Sprinklers must be uniformly spaced on branch lines. Provide coverage throughout 100 percent of the building. This includes, but is not limited to, telephone rooms, electrical equipment rooms (regardless of the fire resistance rating of the enclosure), boiler rooms, switchgear rooms, transformer rooms, attached electrical vaults and other electrical and mechanical spaces. Coverage per sprinkler must be in accordance with NFPA 13 . Provide sprinklers below all obstructions in accordance with NFPA 13 . Sprinklers beneath obstructions must be served by the same sprinkler system as the obstructed area being served.
1.2.3 Qualified Fire Protection Engineer (QFPE)
An individual who is a licensed professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has relevant fire protection engineering experience. Services of the QFPE must include:
a. Reviewing SD-02, SD-03, and SD-05 submittal packages for completeness and compliance with the provisions of this specification. Working (shop) drawings and calculations must be prepared by, or prepared under the immediate supervision of, the QFPE. The QFPE must affix their professional engineering stamp with signature to the shop drawings, calculations, and material data sheets, indicating approv al prior to submitting the shop drawings to the DFPE.
b. Provide a letter documenting that the SD-02, SD-03, and SD-05 submittal package has been reviewed and noting all outstanding comments.
c. Performing in-progress construction surveillance prior to installation of ceilings (rough-in inspection).
d. Witnessing pre-Government and final Government functional perfo rmance testing and performing a final installation review.
e. Signing applicable certificates under SD-07.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designati on;
submittals not having a "G" designation are for Contractor Quality Control
W912HV-23-R-0004 SECTION 21 13 13 Page 4 Jacobs D3449300
Kadena Air Base, Japan approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Partial submittals and submittals not fully complying with NFPA 13 and this specification section must be returned disapproved without review.
SD-02, SD-03 and SD-05 must be submitted simultaneously.
Shop drawings (SD-02), product data (SD-03) and calculations (SD-05) must be prepared by the designer and combined and submitted as one complete package. The QFPE must review the SD-02/SD-03/SD-05 submittal package for completeness and compliance with the Contract provisions prior to submission to the Government. The QFPE must provide a Letter of Confirmation that they have reviewed the submittal package for compliance with the contract provisions. This letter must include their professional engineer stamp and signature. Partial submittals and submittals not reviewed by the QFPE must be returned disapproved without review.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Qualified Fire Protection Engineer (QFPE); G
Sprinkler System Designer; G
Sprinkler System Installer; G
SD-02 Shop Drawings
Shop Drawing; G
SD-03 Product Data
Pipe
Fittings
Valves, including gate, check, butterfly, and globe
Relief Valves
Sprinklers
Pipe Hangers and Supports
Sprinkler Alarm Switch
Valve Supervisory (Tamper) Switch
Fire Department Connection
Air Vent
Seismic Bracing
Nameplates
Float Control Valve
W912HV-23-R-0004 SECTION 21 13 13 Page 5 Jacobs D3449300
Kadena Air Base, Japan
SD-05 Design Data
Seismic Bracing; G
Load calculations for sizing of seismic bracing
Hydraulic Calculations; G
SD-06 Test Reports
Test Procedures; G
SD-07 Certificates
Verification of Compliant Installation; G
Request for Government Final Test; G
SD-10 Operation and Maintenance Data
Operating and Maintenance (O&M) Instructions
Spare Parts Data
SD-11 Closeout Submittals
As-built drawings; G
1.4 QUALITY ASSURANCE
1.4.1 Preconstruction Submittals
Within 36 days of contract award but no less than 14 days prior to commencing work on site, the prime Contractor must submit the following for review and approval. SD-02, SD-03 and SD-05 submittals received prior to the review and approval of the qualifications will be returned Disapproved Without Review.
1.4.1.1 Shop Drawing
4 copies of the shop drawings, no later than 28 days prior to the s tart of system installation. Working drawings conforming to the requiremen ts prescribed in NFPA 13 and must be no smaller than the Contract Drawings.
Each set of drawings must include the following:
1. A descriptive index with drawings listed in sequence by number. A legend sheet identifying device symbols, nomenclature, and conventions used in the package.
2. Floor plans drawn to a scale not less than 1:100 clearly showing locations of devices, equipment, risers, and other details required to clearly describe the proposed arrangement.
3. Actual center-to-center dimensions between sprinklers on branch lines and between branch lines; from end sprinklers to adjacent walls; fr om walls to branch lines; from sprinkler feed mains, cross mains and b ranch lines to finished floor and roof or ceiling. A detail must show th e dimension from the sprinkler and sprinkler deflector to the ceiling in finished areas.
W912HV-23-R-0004 SECTION 21 13 13 Page 6 Jacobs D3449300
Kadena Air Base, Japan
4. Longitudinal and transverse building sections showing typical branch line and cross main pipe routing, elevation of each typical sprinkler above finished floor and elevation of "cloud" or false ceilings in relation to the building ceilings.
5. Plan and elevation views which establish that the equipment will fit the allotted spaces with clearance for installation and maintenance.
6. Riser layout drawings drawn to a scale of not less than 1:25 to show details of each system component, clearances between each other and from other equipment and construction in the room.
7. Details of each type of riser assembly, pipe hanger, sway bracing for earthquake protection, and restraint of underground water main at point-of-entry into the building, and electrical devices and interconnecting wiring. The dimension from the edge of vertical piping to the nearest adjacent wall(s) must be indicated on the drawings when vertical piping is located in stairs or other portions of the means of egress.
8. Details of each type of pipe hanger, seismic bracing/restraint and related components.
9. Include fire pump curve with shop drawings and hydraulic calculations.
1.4.1.2 Product Data
2 copies of annotated catalog data to show the specific model, type, and size of each item. Catalog cuts must also indicate the NRTL listing. The data must be highlighted to show model, size, options, and other pertinent information, that are intended for consideration. Data must be adequate to demonstrate compliance with all contract requirements. Product data for all equipment must be combined into a single submittal.
1.4.1.3 Hydraulic Calculations
Calculations must be as outlined in NFPA 13 except that calculations must be performed by computer using software intended specifically for fire protection system design using the design data shown on the drawings.
Include fire pump curve with submittal.
1.4.1.4 Operating and Maintenance (O&M) Instructions
Submit in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA as supplemented and modified by this specification section.
Provide six manuals and one pdf version on electronic media. The manuals must include the manufacturer's name, model number, parts list, list of parts and tools that should be kept in stock by the owner for routine maintenance, troubleshooting guide, and recommended service organiz ation (including address and telephone number) for each item of equipment . Each service organization submitted must be capable of providing 4-hour on-site response to a service call on an emergency basis.
Submit spare parts data for each different item of material and equ ipment specified. The data must include a complete list of parts and supp lies, and a list of parts recommended by the manufacturer to be replaced after 1-year and 3 years of service. Include a list of special tools and test
W912HV-23-R-0004 SECTION 21 13 13 Page 7 Jacobs D3449300
Kadena Air Base, Japan equipment required for maintenance and testing of the products supplied.
1.4.2 Qualifications
1.4.2.1 Sprinkler System Designer
The sprinkler system designer must be certified as a minimum Level III Technician by National Institute for Certification in Engineering Technologies (NICET) in the Water-Based Systems Layout subfield of Fire Protection Engineering Technology in accordance with NICET 1014-7 .
1.4.2.2 Sprinkler System Installer
The sprinkler system installer must be regularly engaged in the installation of the type and complexity of system specified in the contract documents, and must have served in a similar capacity for at least three systems that have performed in the manner intended for a period of not less than 6 months.
1.4.3 Regulatory Requirements
Equipment and material must be listed or approved. Listed or approved, as used in this Section, means listed, labeled or approved by a Nationally Recognized Testing Laboratory (NRTL) such as UL Fire Prot Dir or FM APP GUIDE. The omission of these terms under the description of an item or equipment described must not be construed as waiving this requirement. All listings or approvals by testing laboratories must be from an existing ANSI or UL published standard. The recommended practices stated in the manufacturer's literature or documentation are mandatory requirements.
1.5 DELIVERY, STORAGE, AND HANDLING
Protect all equipment delivered and placed in storage from the weather, excessive humidity and temperature variations, dirt and dust, or other contaminants. All pipes must be either capped or plugged until installed.
1.6 EXTRA MATERIALS
Spare sprinklers and wrench(es) must be provided as spare parts in accordance with NFPA 13 .
PART 2 PRODUCTS
2.1 MATERIALS AND EQUIPMENT
2.1.1 Standard Products
Provide materials, equipment, and devices listed for fire protection service when so required by NFPA 13 or this specification. Select material from one manufacturer, where possible, and not a combinati on of manufacturers, for a classification of material. Material and equi pment must be standard products of a manufacturer regularly engaged in the manufacture of the products for at least 2 years prior to bid.
2.1.2 Nameplates
Major components of equipment must have the manufacturer's name, ad dress, type or style, model or serial number, catalog number, date of
W912HV-23-R-0004 SECTION 21 13 13 Page 8 Jacobs D3449300
Kadena Air Base, Japan installation, installing Contractor's name and address, and the contract number provided on a new name plate permanently affixed to the item or equipment. Nameplates must be etched metal or plastic, permanently attached by screws to control units, panels or adjacent walls.
2.1.3 Identification and Marking
Pipe and fitting markings must include name or identifying symbol of manufacturer and nominal size. Pipe must be marked with ASTM designation. Valves and equipment markings must have name or identifying symbol of manufacturer, specific model number, nominal size, name of device, arrow indicating direction of flow, and position of installation (horizontal or vertical), except if valve can be installed in either position. Markings must be included on the body casting or on an etched or stamped metal nameplate permanently on the valve or cover plate.
2.1.4 Pressure Ratings
Valves, fittings, couplings, alarm switches, and similar devices must be rated for the maximum working pressures that can be experienced in the system, but in no case less than 1724 kPa.
2.2 UNDERGROUND PIPING COMPONENTS
2.2.1 Pipe
Pipe must comply with NFPA 24 . Minimum pipe size is 150 mm. Piping more than 1.50 meters outside the building walls must comply with Section
33 11 00 WATER UTILITY DISTRIBUTION PIPING.
2.2.2 Fittings and Gaskets
Fittings must be ductile-iron conforming to AWWA C110/A21.10 with cement mortar lining conforming to AWWA C104/A21.4 . Gaskets must be suitable in design and size for the pipe with which such gaskets are to be used.
Gaskets for ductile-iron pipe joints must conform to AWWA C111/A21.11 .
2.2.3 Buried Utility Warning and Identification Tape
Provide detectable aluminum foil plastic backed tape or detectable magnetic plastic tape manufactured specifically for warning and identification of buried piping. Tape must be detectable by an ele ctronic detection instrument. Provide tape, 80 mm minimum width, color cod ed for the utility involved with warning and identification imprinted in b old block letters continuously and repeatedly over the entire tape length.
Warning and identification must read "CAUTION BURIED WATER PIPING B ELOW" or similar wording. Use permanent code and letter coloring unaffected by moisture and other substances contained in trench backfill material.
2.2.4 Float Control Valve
Provide float control valve with remote mounted pilot for automatic tank fill and shutoff. Valve must be a single-seated, line pressure operated, diaphragm actuated, pilot controlled valve. Valve must seal by means of a corrosion resistant seat. Main valve must be corrosion resistant.
Provide stilling well for remote mounted pilot in tank.
W912HV-23-R-0004 SECTION 21 13 13 Page 9 Jacobs D3449300
Kadena Air Base, Japan
2.3 ABOVEGROUND PIPING COMPONENTS
2.3.1 Steel Piping Components
2.3.1.1 Steel Pipe
Except as modified herein, steel pipe must be black as permitted by NFPA 13 and conform to the applicable provisions of ASTM A53/A53M, ASTM A135/A135M , ASTM A153/A153M , or JIS G 3454 - STPG370.
Steel pipe must be Schedule 40 only. Galvanized pipe is not permitted.
2.3.1.2 Fittings
Fittings must be welded, threaded, or grooved-end type. Threaded fittings must be cast-iron conforming to ASME B16.4 , malleable-iron conforming to ASME B16.3 or JIS B 2301 , ductile-iron conforming to ASTM A536, or steel butt-welded fittings to JIS B 2311 . Plain-end fittings with mechanical couplings, fittings that use steel gripping devices to bite into the pipe, steel press fittings and field welded fittings are not permitted.
Fittings, mechanical couplings, and rubber gaskets must be supplied by the same manufacturer. Threaded fittings must use Teflon tape or manufacturer's approved joint compound. Reducing couplings are not permitted except as allowed by NFPA 13 . Galvanized fittings are not permitted.
2.3.1.3 Grooved Mechanical Joints and Fittings
Joints and fittings must be designed for not less than 1724 kPa service and the product of the same manufacturer. Field welded fittings must not be used. Fitting and coupling housing must be malleable-iron conforming to ASTM A47/A47M, Grade 32510; ductile-iron conforming to ASTM A536, Grade 65-45-12. Rubber gasketed grooved-end pipe and fittings with mechanical couplings are permitted in pipe sizes 50 mm and larger. Gasket must be the flush type that fills the entire cavity between the fitting and the pipe. Nuts and bolts must be heat-treated steel conforming to ASTM A183 and must be cadmium-plated or zinc-electroplated.
2.3.1.4 Flanges
Flanges must conform to NFPA 13 and ASME B16.1 . Gaskets must be non-asbestos compressed material in accordance with ASME B16.21 , 1.6 mm thick, and full face or self-centering flat ring type.
2.3.2 Flexible Sprinkler Hose
The use of flexible hose is not permitted.
2.3.3 Pipe Hangers and Supports
Provide galvanized pipe hangers, supports and seismic bracing and s upports in accordance with NFPA 13 . Design and install seismic protection in accordance with the requirements of NFPA 13 section titled "Protection of Piping Against Damage Where Subject to Earthquakes for Seismic Design Category E.
2.3.4 Valves
Provide valves of types approved for fire service. Valves must ope n by
W912HV-23-R-0004 SECTION 21 13 13 Page 10 Jacobs D3449300
Kadena Air Base, Japan counterclockwise rotation.
2.3.4.1 Control Valve
Manually operated sprinkler control/gate valve must be outside stem and yoke (OS&Y) type or butterfly type and must be listed.
2.3.4.2 Check Valves
Check valves must comply with UL 312 . Check valves 100 mm and larger must be of the swing type, have a clear waterway and meet the requirements of MSS SP-71 , for Type 3 or 4. Inspection plate must be provided on valves larger than 150 mm.
2.3.4.3 Hose Valve
Valve must comply with UL 668 .
2.3.5 Riser Check Valves
Provide riser check valve, pressure gauges and main drain.
2.4 ALARM INITIATING AND SUPERVISORY DEVICES
2.4.1 Sprinkler Alarm Switch
Vane-type flow switch(es) with two SPDT (Form C) contacts in weather/UV/flame resistant enclosure. Connection of switch must be by the fire alarm installer. Vane type alarm actuating devices must have mechanical diaphragm controlled retard device adjustable from 10 to 60 seconds and must instantly recycle.
2.4.2 Valve Supervisory (Tamper) Switch
Switch must be integral to the control valve or suitable for mounting to the type of control valve to be supervised open. The switch must be tamper resistant and contain SPDT (Form C) contacts arranged to transfer upon removal of the housing cover or closure of the valve of more than two rotations of the valve stem.
2.4.3 Waterflow Alarm
Electrically operated, exterior-mounted, waterflow alarm bell shall be provided and installed in accordance with NFPA 13 . Waterflow alarm bell shall be rated 24 VDC and shall be connected to the Fire Alarm Control Panel (FMCP) in accordance with Section 28 31 76 INTERIOR FIRE ALAR M AND
MASS NOTIFICATION SYSTEM.
2.5 FIRE DEPARTMENT CONNECTION
Fire department connection must be wall-mounted, projecting type wi th cast-brass body, matching escutcheon lettered "Auto Spkr" with a polished-brass finish. The connection must have individual self-closing clappers, caps with drip drains and chains. Female inlets must have 65-mm diameter American National Fire Hose Connection Screw Threads (NH) per NFPA 1963 . Comply with UL 405 .
W912HV-23-R-0004 SECTION 21 13 13 Page 11 Jacobs D3449300
Kadena Air Base, Japan
2.6 SPRINKLERS
Sprinklers must comply with UL 199 and NFPA 13 . Sprinklers with internal O-rings are not acceptable. Sprinklers in high heat areas including attic spaces or in close proximity to unit heaters must have temperature classification in accordance with NFPA 13 . Sprinklers in the hangar bays must have a temperature rating of 79.4 degrees C. Sprinklers in the hangar bay, light and ordinary hazard areas will be quick-response;
sprinklers in Extra hazard areas will be standard-response. Sprinklers within the hangar bay must be polytetrafluoroethylene (PTFE) coated.
Sprinklers in paint hangars and other paint spray areas must be protected with cellophane bags per NFPA 33 .
2.6.1 Pendent Sprinkler
Pendent sprinkler must be recessed type with nominal K-factor of 80 in light hazard areas, 115 in ordinary hazard areas, and 160 in extra hazard areas. Pendent sprinklers must have a polished chrome or white polyester finish. Assembly must include an integral escutcheon.
2.6.2 Upright Sprinkler
Upright sprinkler must be brass and have a nominal K-factor of 80 in light hazard areas, 115 in ordinary hazard areas, and 160 in extra hazard areas.
2.6.3 Concealed Sprinkler
Concealed sprinkler must be chrome-plated and have a nominal K-factor of 80 in light hazard areas and 115 in ordinary hazard areas. Coverplate must be white.
2.7 ACCESSORIES
2.7.1 Sprinkler Cabinet
Provide spare sprinklers in accordance with NFPA 13 and must be placed in a suitable metal or plastic cabinet of sufficient size to accommodate all the spare sprinklers and wrenches in designated locations. Spare sprinklers must be representative of, and in proportion to, the number of each type and temperature rating of the sprinklers installed as required by NFPA 13 . At least one wrench of each type required must be provided.
2.7.2 Pendent Sprinkler Escutcheon
Escutcheon must be one-piece metallic type with a depth of less than 19 mm and suitable for installation on pendent sprinklers. The escutcheo n must have a factory finish that matches the pendent sprinkler.
2.7.3 Pipe Escutcheon
Provide split hinge metal plates for piping entering walls, floors, and ceilings in exposed spaces. Provide polished stainless steel plate s or chromium-plated finish on copper alloy plates in finished spaces. Provide paint finish on metal plates in unfinished spaces.
2.7.4 Sprinkler Guard
Listed guard must be a steel wire cage designed to encase the sprin kler and protect it from mechanical damage. Guards must be provided on
W912HV-23-R-0004 SECTION 21 13 13 Page 12 Jacobs D3449300
Kadena Air Base, Japan sprinklers located within 2.1 meters of the floor.
2.7.5 Relief Valve
Relief valves must be listed and installed at there riser in accordance with NFPA 13 .
2.7.6 Air Vent
Air vents must be of the automatic type and piped to drain to the building exterior. Install air vents in accordance with NFPA 13 .
2.7.7 Identification Sign
Valve identification sign must be minimum 150 mm wide by 50 mm high with enamel baked finish on minimum 1.214-mm steel or 0.6-mm aluminum with red letters on a white background or white letters on red background. Wording of sign must include, but not be limited to "main drain", "auxiliary drain", "inspector's test", "alarm test", "alarm line", and similar wording as required to identify operational components. Where there is more than one sprinkler system, signage must include specific details as to the respective system.
PART 3 EXECUTION
3.1 VERIFYING ACTUAL FIELD CONDITIONS
Before commencing work, examine all adjoining work on which the contractor's work that is dependent for perfect workmanship according to the intent of this specification section, and report to the Contracting Officer's Representative a condition that prevents performance of first class work. No "waiver of responsibility" for incomplete, inadequate or defective adjoining work will be considered unless notice has been filed before submittal of a proposal.
3.2 INSTALLATION
The installation must be in accordance with the applicable provisions of NFPA 13 , NFPA 24 and publications referenced therein. Locate sprinklers in a consistent pattern with ceiling grid, lights, and air supply diffusers.
Install sprinkler system over and under ducts, piping and platforms when such equipment can negatively affect or disrupt the sprinkler disch arge pattern and coverage.
a. Piping offsets, fittings, and other accessories required must be furnished to provide a complete installation and to eliminate interference with other construction.
b. Wherever the contractor's work interconnects with work of other trades the Contractor must coordinate with other Contractors to insure all Contractors have the information necessary so that they may properl y install all necessary connections and equipment. Identify all work items needing access (dampers and similar equipment) that are concealed above hung ceilings by permanent color coded pins/tabs in the ceiling directly below the item.
c. Provide required supports and hangers for piping, conduit, and equipment so that loading will not exceed allowable loadings of structure. Submittal of a bid must be a deemed representation that
W912HV-23-R-0004 SECTION 21 13 13 Page 13 Jacobs D3449300
Kadena Air Base, Japan the contractor submitting such bid has ascertained allowable loadings and has included in his estimates the costs associated in furnishing required supports.
3.2.1 Waste Removal
At the conclusion of each day's work, clean up and stockpile on site all waste, debris, and trash which may have accumulated during the day as a result of work by the contractor and of his presence on the job.
Sidewalks and streets adjoining the property must be kept broom clean and free of waste, debris, trash and obstructions caused by work of the contractor, which will affect the condition and safety of streets, walks, utilities, and property.
3.3 UNDERGROUND PIPING INSTALLATION
The fire protection water main must be laid, and joints anchored, in accordance with NFPA 24 . Minimum depth of cover must be 900 mm or the frost line, whichever is deeper. In addition, joints must be anchored in accordance with NFPA 24 . Buried steel components must be provided with a corrosion protective coating in accordance with AWWA C203. Piping more than 1500 mm outside the building walls must meet the requirements of Section 33 11 00 WATER UTILITY DISTRIBUTION PIPING.
3.4 ABOVEGROUND PIPING INSTALLATION
The methods of fabrication and installation of the aboveground piping must fully comply with the requirements and recommended practices of NFPA 13 and this specification section.
3.4.1 Protection of Piping Against Earthquake Damage
Seismic restraint is required.
3.4.2 Piping in Exposed Areas
Install exposed piping without diminishing exit access widths, corridors or equipment access. Exposed horizontal piping, including drain piping, must be installed to provide maximum headroom.
3.4.3 Piping in Finished Areas
In areas with suspended or dropped ceilings and in areas with conce aled spaces above the ceiling, piping must be concealed above ceilings. Piping must be inspected, hydrostatically tested and approved before being concealed. Risers and similar vertical runs of piping in finished areas must be concealed.
3.4.4 Pendent Sprinklers
a. Drop nipples to pendent sprinklers must consist of minimum 25-m m pipe with a reducing coupling into which the sprinkler must be threaded.
b. Where sprinklers are installed below suspended or dropped ceilings, drop nipples must be cut such that sprinkler ceiling plates or escutcheons are of a uniform depth throughout the finished space. The outlet of the reducing coupling must not extend below the underside of the ceiling.
W912HV-23-R-0004 SECTION 21 13 13 Page 14 Jacobs D3449300
Kadena Air Base, Japan
c. Recessed pendent sprinklers must be installed such that the distance from the sprinkler deflector to the underside of the ceiling must not exceed the manufacturer's listed range and must be of uniform depth throughout the finished area.
d. Pendent sprinklers in suspended ceilings must be located in the center of the tile (+/- 2 inches).
e. Where the maximum static or flowing pressure, whichever is greater at the sprinkler, applied other than through the fire department connection, exceeds 6.9 bar and a branch line above the ceiling supplies sprinklers in a pendent position below the ceiling, the cumulative horizontal length of an unsupported armover to a sprinkler or sprinkler drop must not exceed 300 mm for steel pipe and 1500 mm for copper tube.
3.4.5 Upright Sprinklers
Riser nipples or "sprigs" to upright sprinklers must contain no fittings between the branch line tee and the reducing coupling at the sprinkler.
3.4.6 Pipe Joints
Pipe joints must conform to NFPA 13 , except as modified herein. Not more than four threads must show after joint is made up. Welded joints will be permitted, only if welding operations are performed as required by NFPA 13 at the Contractor's fabrication shop, not at the project construction site. Flanged joints must be provided where indicated or required by NFPA 13 . Grooved pipe and fittings must be prepared in accordance with the manufacturer's latest published specification according to pipe material, wall thickness and size. Grooved couplings, fittings and grooving tools must be products of the same manufacturer. The diameter of grooves made in the field must be measured using a "go/no-go" gauge, vernier or dial caliper, narrow-land micrometer, or other method specifically approved by the coupling manufacturer for the intended application. Groove width and dimension of groove from end of pipe must be measured and recorded for each change in grooving tool setup to verify compliance with coupling manufacturer's tolerances.
3.4.7 Reducers
Reductions in pipe sizes must be made with one-piece tapered reduci ng fittings. When standard fittings of the required size are not manufactured, single bushings of the face or hex type will be permi tted.
Where used, face bushings must be installed with the outer face flush with the face of the fitting opening being reduced. Bushings cannot be used in elbow fittings, in more than one outlet of a tee, in more than two outlets of a cross, or where the reduction in size is less than 13 mm.
3.4.8 Pipe Penetrations
a. Cutting structural members for passage of pipes or for pipe-han ger fastenings will not be permitted. Pipes that must penetrate concrete or masonry walls or concrete floors must be core-drilled and provided with pipe sleeves. Each sleeve must be Schedule 40 galvanized stee l, ductile-iron or cast-iron pipe and extend through its respective wa ll or floor and be cut flush with each wall surface. Sleeves must provide required clearance between the pipe and the sleeve per NFPA 13 .
The space between the sleeve and the pipe must be firmly packed wit h
W912HV-23-R-0004 SECTION 21 13 13 Page 15 Jacobs D3449300
Kadena Air Base, Japan mineral wool insulation.
b. Where pipes and sleeves penetrate fire walls, fire partitions, or floors, pipes/sleeves must be firestopped in accordance with Section
07 84 00 FIRESTOPPING.
c. In penetrations that are not fire-rated or not a floor penetration, the space between the sleeve and the pipe must be sealed at both ends with plastic waterproof cement that will dry to a firm but pliable mass or with a mechanically adjustable segmented elastomer seal.
3.4.9 Escutcheons
Escutcheons must be provided for pipe penetration in finished areas of ceilings, floors and walls. Escutcheons must be securely fastened to the pipe at surfaces through which piping passes.
3.4.10 Inspector's Test Connection
The test connections consist of 25-mm pipe connected at the riser as a combination test and drain valve; a test valve located approximately 2 meters above the floor; a smooth bore brass outlet equivalent to the smallest orifice sprinkler used in the system; and a painted metal identification sign affixed to the valve with the words "Inspector's Test". All test connection piping must be inside of the building and penetrate the exterior wall at the location of the discharge orifice only. The discharge orifice must be located outside the building wall no more than 0.6 meters above finished grade, directed so as not to cause damage to adjacent construction or landscaping during full flow discharge, or to the sanitary sewer. Discharge to the exterior must not interfere with exiting from the facility. Water discharge or runoff must not cross the path of egress from the building. Do not discharge to the roof.
Discharge to floor drains, janitor sinks or similar fixtures is not permitted.
Provide concrete splash blocks at all drain and inspector's test connection discharge locations if not discharging to a concrete surface.
Splash blocks must be large enough to mitigate erosion and not become dislodged during a full flow of the drain. Ensure all discharged water drains away from the facility and does not cause property damage.
3.4.11 Drains
a. Main drain piping must be provided to discharge at a safe point outside the building, no more than 0.6 meters above finished grade.
Provide a concrete splash block at drain outlet. Discharge to the exterior must not interfere with exiting from the facility. Water discharge or runoff must not cross the path of egress from the building.
b. Auxiliary drains must be provided as required by NFPA 13 . Auxiliary drains are permitted to discharge to a floor drain if the drain is sized to accommodate full flow (min 151 L/min). Discharge to service sinks or similar plumbing fixtures is not permitted.
3.4.12 Installation of Fire Department Connection
Connection must be mounted on the exterior wall approximately 900 m m above finished grade. The piping between the connection and the check va lve
W912HV-23-R-0004 SECTION 21 13 13 Page 16 Jacobs D3449300
Kadena Air Base, Japan must be provided with an automatic drip in accordance with NFPA 13 and piped to drain to the outside or a floor drain within the same room.
3.4.13 Identification Signs
Signs must be affixed to each control valve, inspector test valve, main drain, auxiliary drain, test valve, and similar valves as appropriate or as required by NFPA 13 . Main drain test results must be etched into main drain identification sign. Hydraulic design data must be etched into the nameplates and permanently affixed to each sprinkler riser as specified in NFPA 13 . Provide labeling on the surfaces of all feed and cross mains to show the pipe function (e.g., "Sprinkler System", "Fire Department Connection", "Standpipe") and normal valve position (e.g. "Normally Open", "Normally Closed"). For pipe sizes 100 mm and larger provide white painted stenciled letters and arrows, a minimum of 50 mm in height and visible from at least two sides when viewed from the floor.