DRAFT_SOW_Helicopter Engine Wash Pads.pdf
PDF 381 KB Posted
- Attached to
- Helicopter Engine Wash Pads
- Solicitation number
- N00244-24-Q-0070
About this file
This document is a Statement of Work (SOW) for the design, delivery, and installation of containment wash pads for helicopter engines at Naval Air Station North Island (NASNI) and Marine Corps Base Kaneohe, Hawaii (MCBH). The purpose of the containment pads is to meet Environmental Protection Agency regulations for hazardous material containment of wash water from aircraft engine flushing operations, as the flight lines at these locations are adjacent to inland waterways.
The SOW requires the contractor to provide six containment wash pads in total, with two 30'L x 15'W x 2"H pads and two 23'L x 15'W x 2"H pads for NASNI, and two 30'L x 15'W x 2"H pads for MCBH. All pads are to have integral 12" ramps on both 15' ends. The period of performance for delivery is 10-12 weeks from the time of award, and the contractor is responsible for installing the pads at the specified delivery locations. The government will accept the pads upon successful installation and demonstration that they meet all performance requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Souces Sought Service_Helicopter Engine Wash Pads.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW)
COMHSMWINGPAC
NAS NORTH ISLAND
Introduction
COMHSMWINGPAC IS IN NEED OF: Containment wash pads for helicopter engines.
This SOW outlines the requirements for the design, delivery, and installation of containment wash pads at specified locations.
Purpose
The containment pads are required to meet Environmental Protection Agency regulations for Hazardous Material containment of wash water from aircraft engine flushing operations. The flight lines at Naval Air Station North Island (NASNI) and Marine Corps Base Kaneohe, Hawaii, (MCBH) are located adjacent to inland water ways. Due to the saltwater corrosive environment the aircraft fly in, the squadrons are required to perform engine washes after every flight or series of flights. Without the containment pads, the engine wash affluent can easily migrate into those water ways causing environmental pollution and potential EPA violations for the U.S. Navy.
Additionally, the installation of containment pads on MCBH provide the HSM-37 a time savings of 90 minutes per evolution, enabling the squadron to significantly reduce turn-around times for post-flight maintenance activities.
Scope of Work
The contractor shall provide the following containment wash pads:
- Two (2) containment wash pads measuring 30’L x 15’W x 2”H with integral ramps (12”up/12”down) on both 15’ ends for Naval Air Station North Island (NASNI), San Diego, CA.
- Two (2) containment wash pads measuring 23’L x 15’W x 2”H with integral ramps (12”up/12”down) on both 15’ ends for Naval Air Station North Island (NASNI), San Diego, CA.
- Two (2) containment wash pads measuring 30’L x 15’W x 2”H with integral ramps (12”up/12”down) on both 15’ ends for Marine Corps Base Hawaii (MCBH) Kaneohe Bay, HI.
The wash pads are surface mounted, spill containment pads assembled from prefabricated modular steel panels, encapsulated in 1/16" nominal fiberglass protective coating. The 30' wash pads have 4 panels and the 23' wash pads have 3 panels which are approximately 7'6" each. All panels are 15' wide. Price includes: 2"-Trilinear sidewalls, bolts and caulking, 4 each hold-down clips. They are designed to facilitate the washing and maintenance of helicopter engines while preventing environmental contamination.
Period of Performance
The period of performance for the delivery of the containment wash pads is 10-12 weeks from time of award.
Statement of Work (SOW)
NAS NORTH ISLAND
Delivery:
Naval Air Station North Island Building 662, BAY 3 San Diego, CA 92135
ATTN: REDACTED
COMMANDING OFFICER
HSM-37
1ST STREET, HANGAR 101, TOOLROOM
KANEOHE BAY, HI 96863-4006
ATTN: REDACTED
- COMHSMWINGPAC and HSM-37 Points of Contact will provide specific installation locations upon delivery of the product to the individual sites.
Installation Requirements
-The contractor is responsible for the installation of the containment wash pads at the delivery locations. The installation shall be completed in a manner that ensures the pads are fully operational and meet all safety and environmental regulations.
-The contractor shall adhere to all applicable standards and regulations for the manufacturing and installation of containment wash pads. The contractor must ensure that the pads are durable, resistant to the chemicals used in engine washing, and capable of supporting the weight of helicopter engines.
-The government will accept the containment wash pads upon successful installation and demonstration that they meet all the performance requirements specified in this SOW.
-The contractor shall provide a detailed pricing schedule for the containment wash pads, including costs for materials, labor, delivery, and installation.