This is a Statement of Work for asbestos pipe insulation removal and replacement at Facility 566's crawlspace. The project requires removal of approximately 375 linear feet of asbestos-containing materials (ACM) pipe insulation and replacement with new, non-asbestos insulation.

The contractor must perform comprehensive asbestos abatement including thorough inspection of the work area, establishment of a regulated work area with containment barriers and negative air pressure systems, implementation of worker decontamination enclosure systems, wet removal methods to minimize fiber release, proper containerization and disposal of ACM waste at licensed facilities, and air monitoring throughout the process. The insulation replacement phase requires installation of new non-asbestos pipe insulation meeting all applicable building codes and energy efficiency standards, with proper fitting and securing of materials. Site restoration includes thorough cleaning using HEPA vacuums and wet methods, final visual inspection and clearance air sampling, and removal of all containment equipment to restore the work area to original condition. Work shall be conducted during normal business hours (0700-1600 hours, Monday through Friday, excluding federal holidays), with any outside-hours work requiring written Contracting Officer approval.

The contractor must possess a valid state asbestos abatement license, with all on-site personnel trained and certified in asbestos abatement per EPA and OSHA regulations. Proof of adequate insurance including general liability, workers' compensation, and asbestos-specific liability coverage is required. Pre-work submittals include an Asbestos Abatement Plan, Site-Specific Safety Plan, Personnel Certifications, and Waste Disposal Plan. Upon completion, the contractor shall provide Waste Shipment Records, Final Air Clearance Report, and Certificate of Completion. All work must comply with EPA (including NESHAP), OSHA, and applicable state and local environmental and safety regulations.

View the file

Other files

File Type Posted
Sources Sought Notice - Asbestos Removal.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Project Title: Asbestos Pipe Insulation Removal and Replacement at Facility 566 Crawlspace

1. Introduction/Background

Facility 566, has identified the presence of asbestos-containing pipe insulation within the crawlspace. An asbestos survey has confirmed the presence of these materials, necessitating a comprehensive abatement and replacement project to ensure the safety of all personnel and compliance with environmental regulations. There is approximately 375 linear feet of ACM pipe insulation to be removed and disposed of.

2. Objective

The primary objective of this project is to safely remove all asbestos-containing pipe insulation and replace it with new, non-asbestos insulation in the crawlspace of Facility 566. The contractor shall provide all necessary labor, materials, equipment, and supervision to complete the work in accordance with all applicable federal, state, and local regulations.

3. Scope of Work

The contractor shall perform the following tasks:

• Asbestos Abatement:

• Thoroughly inspect the work area to confirm the quantity and location of asbestos-containing materials.

• Establish a regulated work area with proper containment, including critical barriers and negative air pressure systems, to prevent the spread of asbestos fibers.

• Implement a worker decontamination enclosure system.

• Utilize wet methods to minimize fiber release during removal.

• Properly containerize, label, and dispose of all asbestos-containing waste at a licensed disposal facility.

• Conduct air monitoring throughout the abatement process to ensure compliance with permissible exposure limits.

• Insulation Replacement:

• Install new, non-asbestos pipe insulation that meets all applicable building codes and energy efficiency standards.

• Ensure all new insulation is properly fitted and secured.

• Site Restoration:

• Thoroughly clean the work area using HEPA vacuums and wet cleaning methods until no visible residue remains.

• Conduct a final visual inspection and clearance air sampling to confirm the area is safe for re-occupancy.

• Remove all containment and equipment, restoring the work area to its original condition.

4. Period of Performance

Work shall be conducted during normal business hours, 0700-1600hrs, Monday through Friday, excluding federal holidays. Any work outside of these hours must be approved in writing by the Contracting Officer.

5. Contractor Qualifications

The contractor must meet the following minimum qualifications:

• Possess a valid state license for asbestos abatement.

• All on-site personnel, including supervisors and workers, must be trained and certified in asbestos abatement in accordance with EPA and OSHA regulations.

• Provide proof of adequate insurance, including general liability, workers' compensation, and asbestos-specific liability coverage.

6. Submittals

Prior to the commencement of work, the contractor shall submit the following documents for review and approval:

• Asbestos Abatement Plan: A detailed plan outlining the procedures for asbestos removal, containment, and disposal.

• Site-Specific Safety Plan: A comprehensive plan addressing all potential hazards and safety measures.

• Personnel Certifications: Copies of all licenses and certifications for personnel who will be on-site.

• Waste Disposal Plan: Information on the licensed disposal facility to be used.

Upon project completion, the contractor shall provide:

• Waste Shipment Records: Copies of all manifests from the disposal facility.

• Final Air Clearance Report: The results of the final air monitoring tests.

• Certificate of Completion: A document certifying that the work has been completed in accordance with all regulations.

7. Governing Regulations

All work shall be performed in strict compliance with the regulations of the following agencies:

• U.S. Environmental Protection Agency (EPA), including the National Emission Standards for Hazardous Air Pollutants (NESHAP).

• Occupational Safety and Health Administration (OSHA).

• All applicable state and local environmental and safety regulations.