This document outlines requirements for a design-build HVAC replacement project at the Farmingdale Airport Traffic Control Tower facility. Key details include replacing the ACU-2 unit serving the base building and associated electrical work, as well as replacing all supply air diffusers and return air grilles. Submittals and a one-year warranty are required. The related federal contract opportunity is a market survey to identify capable contractors for the project, with responses due by November 16, 2021. Relevant experience, bonding capacity, and business size information should be provided to the Federal Aviation Administration contact.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Farmingdale ATCT HVAC Replacement

Work on this Contract comprises of HVAC replacement and associated electrical work for Airport Traffic Control Tower (ATCT) facility and Base Building at the Farmingdale Republic Airport located in Farmingdale, New York

1. Complete any and all field work required to verify dimensions, clearances and quantities prior to start of work.

2. All work performed by the contractor or sub-contractor shall be in accordance with all industry standards and must be approved by the FAA COR. Contractor shall notify FAA COR, five (5) days prior to completion of all work for final inspection and acceptance.

3. Air Traffic Control function of this facility shall not be interfered with. Demolition and construction noise shall be minimized. FAA has and maintains equipment that is critical to its operation throughout this facility. Work schedules will be coordinated with the FAA COR daily. Any demolition work will be completed daily to a stage which leaves the area safety. All debris shall be removed and area clean of dust created from construction facility.

4. Site specific demolition Work shall be done at night between the hours of 11 AM-6PM. Contractor shall include this provision in their offer.

5. Complete all technical and administrative submittal requirements. The Contractor shall note that payment(s) shall not be made until both technical and administrative requirements are fulfilled. This task includes providing a detailed construction schedule that will be used to track progress and shall be tied to payment schedule. Technical submittals shall include all manufacturers’ warranties and certificates as specified in the technical sections of the Specifications.

6. Contractor shall remove and replace ACU-2 serving Base Building with new unit.

7. Contractor shall remove and replace all supply air diffusers and return air grilles served by ACU-2 in Base Building as outlined on Contract Drawings.

8. Contractor shall clean and sanitize all existing ductwork served by ACU-2.

9. Contractor shall provide TAB (testing, adjusting & balancing) and commissioning for ACU-2 installed to meet design requirements.

10. Provide dumpster for daily cleanup.

11. Provide crane/man-lift as required for rooftop deliveries/rigging/removal, etc.

12. Contractor shall perform all electrical demolition related to HVAC demolition work as part of this project.

13. Electrical connections and terminations for newly added or replaced HVAC equipment shall be furnished.

14. Update single line diagram and panel schedules.

15. Contractor shall provide one (1) year warranty on parts and labor on all work performed.