This document provides a Statement of Work (SOW) for Architect-Engineer services to develop 100% design documents for the construction of a Unisex Toilet/Shower Facility at Joint Base Elmendorf-Richardson in Alaska. The A-E firm will be required to provide comprehensive building analysis, drawings, specifications, cost estimates, and administrative support through construction. Key deliverables include concept, intermediate, pre-final, and final design submissions within defined schedules. The concept submission is due 30 days after design charrette approval and must include floor plans, narratives, and a parametric cost estimate. Subsequent submissions at 65% and 100% completion are due 30 days after government approval of the prior submission. The final submission requires stamped drawings and specifications ready for bidding. The selected A-E firm will work closely with JBER stakeholders and attend coordination meetings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AE Synopsis Toilet_Shower Facility.pdf | ||
| Past Performance Questionnaire Template.pdf | ||
| SF330-A and E Qualifications Template.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARCHITECT-ENGINEER SERVICES
STATEMENT OF WORK (A-E SOW)
FXSB XX-XXX Shower/Toilet Unisex Facility Joint Base Elmendorf-Richardson (JBER)
Alaska
PROJECT WORK DESCRIPTION
SCOPE: Provide professional Architect-Engineer (A-E) services in accordance with the original A-E Next Standard Operating Procedures (SOP), excluding exceptions and including addenda stated in this section, to develop a design to construct a Shower/Toilet Unisex Facility.
PROJECT DESCRIPTION:
Project Identification: FXSB XX-XXXX, Shower/Toilet Unisex Facility at JBER, AK. Current Programmed Amount (PA) for this project is $1 . All expended funds are to be used for, and in support of, the effort to do an in-house construction project for a Shower/Toilet Unisex Facility. The building will be located on JBER-Elmendorf at Camp Mad Bull.
DESIGN INSTRUCTIONS:
Priorities: Provide a design concept to meet requirements for a shower/toilet unisex facility:
The design also should not leave general items open for interpretation such as, “as required” or “as needed”. Items, materials, and intended systems along with necessary and implied construction procedures must be clearly indicated in the design documents.
Design schedule must be maintained to ensure the documents are completed and ready for government contracting not later than 9 months after Notice to Proceed
(NTP).
The construction project will be accomplished as a “Troop Training Project” with the use of both military and Department of Defense (DoD) civilian employees.
Specific Design and Administrative Requirements:
The A-E shall prepare complete 100% sealed design documents for the Shower/Toilet Unisex Facility. Services shall include preparation of design analysis, drawings, specifications, and cost estimate for Materials only.
The A-E shall perform administrative duties as required during the JBER Contracting Squadron Back-Check phase. At a minimum, this work may include corrections and/ or changes required from JBER Contracting Office or JBER Legal Staff review. This may include errors or deficiencies identified which would preclude the package from being successfully advertised or awarded due to significant comments.
DRAFToilet Unisex oilet Unisex Facility . All expendedexpe fu use construction project fouse construction proje on JBER-Elmendorf on JBER-El atat CC oncept toto meetmeet requiremerequireme hould hould not leave general not leave ge s needed”. Items, materias needed”. Items, ma ndnd impliedimplied construction pconstruction ocuments.ents.
ignign scheduleschedule must be maust be eadyeady for government contfor government cont
TP).TP).
nstruction nstruction pp hh militmilit
(c) The A-E shall perform administrative support during the construction phase. This work is expected to include but is not limited to the following:
1. Serving as the professional technical consultant and advisor to the Government during the construction process.
2. Attending periodic site visits to ensure conformance with Contract Documents.
3. Being responsible for the professional review and approval or rejection of construction: shop drawings, material submittals, samples, and other submittals to determine conformance with the specific portions of the construction contract documents under which the submittal was made.
Deviation from the construction contract documents on submittals or otherwise observed by the A-E shall be brought to the attention of the Government and concurrence received from the Government before any approval is given. Review of submittals shall be completed and returned within 10 working days of receipt. The A-E is responsible for submittal activity conducted by its consultants in the same manner as if such review were made by the A-E.
4. Reviewing the result of all testing, including quality assurance testing, conducted during or after construction and reporting to the Government whether these results meet the design intent, and the requirements of the construction contract documents.
5. Being responsible for the coordination and performance of on-site services performed by consultants employed by the A-E and reviewing reports and other data submitted by such consultants.
6. Necessary professional services required to solve problems caused by design errors, omissions, ambiguities, etc.
7. Reviewing RFI’s and responding within 5 working days of receipt.
(d) The project specific design and investigative scope of work shall include at a minimum:
(i) BUILDING ANALYSIS & SURVEYS:
1. Evaluate the existing well and septic systems for compliance with current standards and upgrade if needed to meet the requirements of the new facility.
2. BUILDING DESIGN REQUIREMENTS:
a. Size:
i. Max roof truss size cannot exceed 32 feet in length.
ii. Assume 300 military personnel to use the facility any given day within a 24-hour period.
b. Utilities/Equipment: (All to be sized by design engineers)
i. Propane fired units.
ii. Well water (Existing may need to be upgraded)
iii. Septic tank (Existing may need to be upgraded)
DRAFT
hall behall b
AA--E is respE is ame manner asame ma sting, including quality assting, including quality a construction and reportinconstruction and reportin meet the design the design intent, an documents.nts.
ble for the coordination anor the coordination a y consultants employed bants employed b submitted by such consusubmitted by such ssary professional servicssary professional serv sign errors, omissions, amgn errors, omissions, am
Reviewing RFI’s and rReviewing RFI’s e project specific dee project specific um:um:
NGNG
iv. Try to limit electrical use as much as possible based on design.
v. Utility corridor between “shower pods” see sketch.
vi. Surface mounted piping.
vii. Utility trough under facility for piping
viii. Two macerating pumps in duplex.
ix. High efficiency propane on demand boilers/water heaters: fired in stages, minimum two.
x. High efficiency on demand water heater if not combine with boilers.
xi. Stainless steel plumbing fixtures.
xii. Stainless steel walls for “shower pods.”
xiii. Two hand dryers per exit. NO PAPER TOWEL DISPENSERS
xiv. In floor heating, concrete slab, with under slab insulation and radiant barrier.
xv. Snow melt at each entry/exit.
xvi. Stainless Steel Trough Sinks.
xvii.Pex piping to the fullest extent Hydronic and domestic fluids.
xviii. Glycol for heating system.
xix. No piping underfloor, piping to be routed in trenches with covers for maintenance access.
c. Design Considerations:
i. Cold Roof.
ii. Poured concrete walls with thermal envelop exterior.
iii. Mechanical room with exterior access, double door no mullion.
iv. Number of “Shower Pods” to be determined by the A/E team based on the expected occupancy.
v. Sturdy mirrors.
vi. Duplex for all heating equipment.
vii. Limit roof penetrations/ sidewall wherever possible.
viii. Exterior doors protected from falling roof snow.
ix. Use Air Admittance devices to eliminate plumbing roof penetrations.
x. Possibility of inside domestic cold-water storage.
xi. To be constructed by military personnel.
d. “Shower Pod” Definition: A self-contained unit with toilet and shower capability. Floor to ceiling enclosure, as this is a unisex facility. Independent floor drain, lighting, and ventilation. Sized for minimum footprint. No wheelchair requirements needed. All stainless steel wherever possible.
(e) All designs shall conform to applicable laws, standards and regulations, to specifically include the most recent versions of IBC, and NFPA 101-Life Safety Code, as well as all applicable UFCs and JBER criteria listed in the SOW.
1. Unified Facilities Criteria (UFC): All UFC’s can be found at:
https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
2. UFC 1-200-01 DoD Building Code (General Building Requirements) shall govern the use of IBC and NFPA 101 in code analysis as required.
4) MEETINGS AND COORDINATION: The A-E design team shall be required to meet with subject matter experts including but not limited to: JBER 673 Civil Engineer Group (CEG) engineers, architects, maintenance personnel, various JBER stakeholders, and users.
i) The A-E team shall attend and participate in all meetings and design review conferences as required in the SOW. Design review conferences shall be required at the conclusion of the concept design period, intermediate design review period, and pre-final design review period.
DRAFT
bbe routed e ro walls with thermal envelowalls with thermal envelo m with exterior access, dith exterior
Shower Pods” to be deterShower Pods” t pected occupancy.ected occupancy.
mirrors.ors.
ex for all heating equipmel heating equipm mit roof penetrations/ sidemit roof penetrations/ side Exterior doors protected Exterior doors prot
.. Use Air Admittance deUse Air Admittance
x. Possibility of insidePossibility of inside
xi. To be constructeTo be constructe
d. “Shower Pod” Shower Pod” Definition: A selfn: A self ceiling enclosuceiling enclo and ventilatand ventila needed. needed.
Refer to section 6. DESIGN SUBMISSION SCHEDULE. Meetings and design review conferences may be held via teleconference, or in person at JBER, as deemed appropriate.
ii) Meeting Minutes and Design Review Comments: During the course of the contract, the A-E shall be required to prepare meeting minutes from all meetings and design review conferences related to the project. The minutes shall also include list of attendees, pertinent instructions, actions items, and information received verbally or otherwise. A-E shall provide a copy of all minutes to the Government with five (5) business days.
5) DESIGN SUBMITTAL DESCRIPTION:
i) TECHNICAL DESIGN DRAWINGS: Technical drawings shall be stamped and sealed “For Construction”. Drawings shall include all disciplines as required to provide a complete set of “For Construction” documents.
ii) TECHNICAL SPECIFICATIONS: The A-E shall prepare applicable technical specifications (Divisions 2-40) in accordance with the current Construction Specifications Institute Manual of Practice. The Government shall provide JBER specific specifications for insertion in Division 01 General Conditions. All documents and specifications are to be complementary and compatible.
iii) DESIGN ANALYSIS: The A-E shall provide a design analysis in narrative format. The design analysis shall include narratives for all disciplines. The design analysis shall include all meeting minutes and supporting product information, “catalogue cuts”, and any engineering calculations, as required.
iv) COST ESTIMATE: The A-E shall prepare construction cost estimates that include a breakdown of individual line items that accurately reflect the unit of measure, quantities, unit cost,. Unit costs for materialand equipment shall be shown. Cost estimate shall be organized by CSI Master Format. Cost estimate shall assume Fiscal year 2024 construction.
(a) Construction cost estimates shall be submitted with each design review and with the final submission. The current working estimates (CWE) should evolve and reflect a greater level of detail provided at the various stages. CWE’s shall reflect contingencies appropriate at each design stage.
(i) All cost estimates shall be confidential and shall be submitted as a separate file electronically.
v) SUBMITTAL REGISTER: The A-E shall be required to populate the AF Form 66 Submittal Register (Excel Format), which shall include all submittals included in the Technical Specifications. The submittal register shall be used during construction management to manage the Contractor’s submittal obligations. Refer to appendix for AF Form 66 Submittal Register.
6) DESIGN SUBMISSION SCHEDULE: The Government reserves the right to use up to fourteen (14) calendar days review time for the all-milestone reviews. Stakeholders shall have seven (7) days review time, followed by comment resolution period, which shall involve A-E participation in design review meetings as required to resolve comments. The A-E is not responsible for government review time.
DRAFT
pplicapplic ction Specction ic specificationsic specif cations are to be comcations are to e a design analysis e a design ana in na isciplines. The design anplines. The uct information, “cataloguuct information hall prepare constructionpare constructio e items that accurately ree items that accurately re erialand equipment shall erialand equipment
t. Cost estimate shall asst. Cost estimate shall a ction cost estimates shalltion cost estimates shall submission. The current wsubmission. The cu eateeater level of detail providr level of detail prov ontingencies appropriateontingencies appropriate l cost estimatel cost estimat ronicallyronically
i) Concept Level Submittal (20%): This submittal shall be delivered to the government within thirty (30) calendar days after the A-E receives written approval of design charrette.
(a) The A-E Contractor shall submit a preliminary version of the Design Analysis addressing items defined in the contract, this document, and the more detailed
(b) Discipline-Specific UFCs. Include drawings and documents, with detail illustrated, as defined by the Specific UFCs and as applicable to the project.
1. The first draft DESIGN ANALYSIS should include but not be limited to the following topics: Project Description, User Requirements, Building Code Analysis, and Project Site Analysis.
(c) Parametric Cost Estimate capturing all major scope of work items shall be provided.
The parametric estimate shall include sufficient detail to allow the Government to make decisions and prioritize the scope of work going forward in accordance with the construction budget. The estimate should include major scope of work items, and any alternate design solutions, broken out, for evaluation.
ii) Intermediate Design Submittal (65%): This submittal shall be advanced accordingly from the concept level design stage and be delivered to the Government within thirty (30) calendar days after the A-E receives written approval of the concept level submittal.
iii) Pre-Final Design Submittal (100%): This submittal shall be advanced accordingly from the intermediate design level and be delivered for review within thirty (30) calendar days after the A-E receives written approval of the intermediate design submittal. A meeting will be required no later than fourteen (14) calendar days after submission to the government. The intent of the pre-Final submittal is to provide a complete set of drawings and specifications.
iv) Final “For Construction” Design Submittal: The A-E shall provide all “Final” design documents, stamped “For Construction”. This submittal shall be advanced accordingly from the pre-final design stage and be delivered to the Government within fourteen (14) calendar days after the A-E receives written approval of the pre-final design submittal. This submittal complete and in accordance with the basic contract and as amended by this SOW. The Final Submittal provides a complete and final set of contract documents ready for construction. All previous government review comments must have been addressed.
(a) The A-E shall make any corrections or changes as required by the JBER Contracting Officer or JBER Legal office if it is determined the contract package cannot be advertised or awarded due to any errors or deficiencies. These corrections may include preparation of addendum, cost estimates, and changes to specifications and drawings during the bidding period, which may be required as a result of such comments, errors, or deficiencies.
(b) All corrections required shall be incorporated into the original documents when turned in to the Government.
7) DESIGN SUBMITTAL CONTENTS:
i) Under the provisions of this contract, the A-E shall furnish the number of design documents as specified by the distribution/mailing list to the addresses listed. The A-E shall furnish the specified number of drawings (half-size), design analysis, technical specifications, and cost estimate for each specified submittal.
DRAFT
on. on.
shall be advancshall be Government within t Government he concept level submitthe concept level su ubmittal shall be advanceubmittal shall be advance red for review within thirtyor review w ntermediate design submntermediate de r days after submission tdays after submiss vide a compla complete set of draete set of dr esign Submittal: The Aesign Submittal: Th -E or Construction”. This subor Construction”. Th age and be delivered to tage and be delivered to receives written approvalceives written approval accordance with the ccordance wi bas vides a complete and finavides a complete a overnment review commeovernment review comm
A A--E shall make anE shall make or JBER Legor JBER Leg ed or awaed or awa parapara
ii) Format for electronic drawing submittals shall be in both PDF and AutoCAD format as described in the Joint Base Elmendorf-Richardson CAD/GIS Record Drawing As-Built Standard.
iii) Conceptual Design Documents for “For Construction” Design documents. At this level the A- E shall submit results of comprehensive building analysis, two (2) sets of drawings, outline specifications, design narratives, and parametric cost estimate. All submitted prints shall be legible half-size prints.
(1) Architectural
(a) Concept Floor Plans with notes
(b) Concept Building Elevations with notes
(c) Concept Building Sections with notes
(d) Preliminary Design Narrative
(2) Structural
(a) Geotechnical investigation plan
(b) Conceptual Plans with notes
(c) Preliminary Design Narrative
(3) Civil
(a) Conceptual Site Plan with notes
(b) Preliminary Design Narrative
(4) Mechanical
(a) Conceptual floor plans
(b) Preliminary Design Narrative
(5) Electrical
(a) Preliminary Design Narrative
iv) Conceptual Outline Specifications
(1) Provide outline specifications, in the form of a list of specification sections the A-E intends to use for the project.
v) Conceptual Construction Schedule
(1) Provide a conceptual schedule of the estimated Construction Contract period, including an initial critical path project schedule describing the construction phasing and primary construction work elements organized by the cost estimate CSI structure and narrative WBS describing the construction activities for the purpose of pre-construction evaluation.
(2) Parametric Cost Estimate
vi) Intermediate Design for “For Construction” Design documents. At this level the A-E shall provide two (2) sets of half-size drawings, specifications, design analysis and cost estimate.
This submittal must include requirements of the previous submittal plus additional detail to bring them to the required completion percentage. Include the following as a minimum:
(1) Architectural
(a) Floor Plans: Provide floor plans, new and demolition, indicating room names and dimensions.
(b) Building Elevations: Provide building elevations as required.
(c) Sections: Typical building, wall, & slab sections: Provide sufficient wall and slab section(s) to indicate all materials and different conditions.
arrative esign Narrative esign Narrati ine SpecificationsSpecificatio utline specifications, in thutline specification for the project. for the project.
Construction ScheConstruction Sc conceptual scconceptual sc cal cal pathpath rk erk e
(2) Structural
(a) Geotechnical findings and recommendations
(b) Foundation Plans with legends and notes
(c) Floor Plans with legends and notes
(d) Roofing Plans with legend and notes
(e) Details
(3) Civil
(a) Survey control sheet
(b) Site Plan with Legend and Notes
(c) Existing Conditions
(d) Utility Plan if required.
(e) Civil Section(s) if required.
(f) Details
(4) Mechanical
(a) HVAC floor plan(s) with legend and notes
(b) Plumbing floor plan(s) with legend and notes if required.
(c) Mechanical Room Plan
(d) Details
(5) Electrical
(a) Floor Plans with legend and notes
(b) Existing Site and Demolition Plan as required.
(c) Lighting Plan(s)
(d) Power Plan(s)
(e) Single Line Diagram
(f) Additional Plans/Risers
(g) Details
(6) Intermediate Specifications for “For Construction” Design
(a) Provide draft specifications, updated from concept design level, the A-E intends to use in the project. Provide the document as described in the UFC for Design.
(7) Intermediate Calculations for “For Construction” Design
(a) Provide calculations as defined in detail by the Discipline-Specific UFCs.
(8) Intermediate detailed cost estimate for “For Construction” Design
(9) Intermediate Construction Schedule for “For Construction” Design
(a) Estimate of Construction Contract Time, including a critical path project schedule describing the construction phasing and primary construction work elements organized by the cost estimate CSI structure and narrative WBS describing the construction activities for the purpose of pre-construction proposal evaluation.
(10)Intermediate Design Analysis for “For Construction” Design, including updated narratives (by discipline), catalogue cuts, product data, hazardous materials survey, previous meeting minutes, and engineering calculations to date.
(11)Intermediate AF Form 66 submittal register coordinated with Technical Specifications.
vii) Pre-Final Design Submittal 100% Design documents. At this stage the A-E shall submit four
(4) sets of half-size prints, technical specifications, and design analysis. The A-E shall submit
DRAFT
required.requi an as required.required.
rs cifications for “For Constcifications for “For Cons raft specifications, updatespecifications, update hee project.project. ProvideProv the do mediate Calculations for “Fmediate Calculations for “ ovide calculations as ovide calculations e detailed e detailed two (2) copies of the Estimate of Construction Cost, AF Form 66 Submittal Register, and other items in accordance with basic contract SOW as amended by this section: and one (1) electronic set of drawings and specifications on a CD. The intent of the Pre-Final submittal is to provide a complete set of drawings and specifications. The following are the minimal requirements of a Pre-Final Submittal. Drawings shall be 100% complete, minus final signatures, and modified to reflect the responses to previous review comments. The drawings shall be complete to the extent that they may be released for bid or constructed as submitted.
Provide complete set of construction drawings organized by discipline as described in the discipline-specific UFCs. In addition to requirements described in the discipline-specific UFCs, and as applicable, provide the following:
(1) Architectural
(a) Legend and Abbreviation
(b) Floor Plans: Provide floor plans, new and demolition, indicating room names and dimensions.
(c) Building Elevations: Provide building elevations as required, indicating new and demolition with dimensions.
(d) Sections: Typical building, wall, & slab sections: Provide sufficient wall and slab section(s) to indicate all materials and different conditions
(2) Structural
(a) Foundation Plans with legends and notes
(b) Floor Plans with legends and notes
(c) Roofing Plans with legend and notes
(d) Details
(3) Civil
(a) Survey control sheet
(b) Site Plan with Legend and Notes
(c) Existing Conditions
(d) Utility Plan if required.
(e) Civil Section(s) if required.
(4) Mechanical
(a) Legend and Abbreviation
(b) HVAC floor plan(s) with legend and notes
(c) Plumbing floor plan(s) with legend and notes if required.
(d) Mechanical Room Plan
(e) HVAC Equipment Schedule if required.
(f) Plumbing Equipment Schedule if required.
(5) Electrical
(a) Legend and Abbreviation
(b) Existing Site and Demolition Plan
(c) Lighting Plans and Details
(d) Lighting Fixture Schedule
(e) Power Plans and Details
(f) Panel Board Schedule
(g) Power – Single Line Diagram
(6) Pre-Final Specifications for “For Construction” Design
(a) Provide edited, red-lined specification sections, showing deletions from and additions to the CSI formatted specification sections. Pre-Final submittal should be complete at this stage and require only minor corrections if any.
DRAFT
: Provide s: Prov nt conditions nt condit notesnotes ss notess end and Notes end and Notes ons ons required.requi on(s) if requireds) if required..
alal gend and Abbreviation gend and Abbreviation
VAC floor plan(s) with leVAC floor plan(s) with le mbing flombing or plan(s) an( anical Room Panical Room P quipmentquipment quiqui
viii) Pre-Final Color and Finish Selections for “For Construction” Design
ix) Design Analysis & Calculations: Provide revised calculations as required to reflect resolution of all previous government review comments. Provide Design Analysis that is 100% complete. Provide calculations for each discipline in additions to the following detailed requirements.
(1) Pre-Final Cost Estimate for “For Construction” Design
(2) Revised detailed Construction Cost Estimate Breakdown that reflects resolution of all previous government review comments.
(3) Pre-Final Construction Schedule for “For Construction” Design
(4) Revised schedule that reflects resolution of all previous government review comments.
x) Final “For Construction” Bid Documents: The design submittal shall be stamped and shall become the Bid Documents for construction. Documents shall include a complete set of design documents and shall include one (1) set of full size drawings IAW Joint Base Elmendorf-Richardson CAD/GIS Record Drawing As-Built Standard, two (2) sets of half-size drawings on paper and originals of the design analysis and the following:
(1) Final Drawings for “For Construction: Design
(a) Provide complete construction drawings (detailed in the Pre-Final Design Phase) organized by discipline in accordance with UFC and Discipline-Specific UFCs. Each drawing shall only be signed, sealed, and dated by the Registered Architect or the Professional Engineer who is registered to practice in the particular field involved for work depicted on that drawing, serves as the Designer of Record for that work, and complies with requirements of FAR 52.236-26.
(b) Final Specifications for “For Construction” Design
(c) Provide complete, final specifications with redlines executed. Organize and compile the package as specified in the UFC as well as on CDs.
(d) Final Color and Finish documentation for “For Construction” design indicating all proposed material and color selections.
(2) Final Calculations for “For Construction” Design
(a) Revise and update Design Analysis and calculations as required to reflect resolution of all previous government review comments and as required by this document and the discipline-specific UFCs.
(3) Final Cost Estimate
(a) Revised detailed Construction Cost Estimate Breakdown that reflects resolution of all previous government review comments on CDs.
(4) Final Construction Schedule “For Construction” Design
(a) Revised schedule that reflects resolution of all previous government review comments.
(5) Final AF Form 66 Submittal Register
8) All submittals shall be submitted to the COR, 673 Contracting Squadron, and to 773
CES/CEOE.
DRAFT
drawdraw uilt Standaruilt St is and the followis and th signsign wings (detailed in the Prewings (detailed in the Pre dance with UFC and Discce with UFC sealed, and dated by thesealed, and da o is registered to practice is registered to pra rawing, serves as the Desng, serves as the De ments of FAR 52.236f FAR 52.236--2626 ons for “Fons for “For Constructionor Constr plete, final specifications wplete, final specification ge as specified in the UFCas specified in the UFC
Color and Finish documeColor and Finish d oposed opose material and colorerial and col alculations for “For alculations for “F e and update De and update vious govvious gov nene--ss
9) Attachments:
a) AF Form 66 Submittal Register Template
b) JBER CAD/GIS Record Drawing As-Built Standard
DRAFT