SECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK
C.1 ACRONYMS
CAP Contractor Acquired Property CNG Compressed Natural Gas CPTI Contractor Purchased Test Items COR Contracting Officer’s Representative DOT Department of Transportation FAR Federal Acquisition Regulation FMVSS Federal Motor Vehicle Safety Standard NHTSA National Highway Traffic Safety Administration NPRM Notice of Proposed Rulemaking OVSC Office of Vehicle Safety Compliance QA/QC Quality Assurance/Quality Control TP Test Procedures
C.2 BACKGROUND
The purpose of this Contract is to procure testing services, inspection services, and reports so that the Government can determine whether CNG fuel containers comply with the requirements of Federal Motor Vehicle Safety Standard (FMVSS) No. 304, “Compressed Natural Gas Fuel Container Integrity”.
FMVSS No. 304 applies to each passenger car, multipurpose passenger vehicle, truck, and bus that uses CNG as a motor fuel and to each container designed to store CNG as motor fuel on-board any motor vehicle. The services under this contract are necessary to determine conformance of CNG fuel containers with the applicable requirements of FMVSS No. 304. The standard was created to reduce the number of deaths and serious injuries occurring from fires that result from fuel leakage during and after motor vehicle crashes.
C.3 DEFINITIONS
Government Furnished Test Items (GFTI) – Refers to test items (CNG fuel containers) owned or acquired by the Government and subsequently provided to the Contractor for use in the performance of the contract. The government is the owner of all GFTI.
Contractor Purchased Test items (CPTI) – Refers to test items (CNG fuel containers) purchased by the Contractor for use in the performance of the contract. For the purpose of this contract, CPTI and Contractor Acquired Property (or “CAP”) mean the same thing. Title to CPTI vests with the government.
Non-Conforming Test – Refers to a Contractor-performed test that does not comply with applicable Office of Vehicle Safety Compliance (OSVC) test procedure (TP) requirements and contract requirements applicable to that test. Refer to Section H.2 for instructions on how non-conforming tests are to be handled.
Compliance Testing of Fuel Containers to FMVSS No. 304
Test Passed – Refers to testing that the Contractor conducted successfully and the item (CNG fuel containers) being tested met the FMVSS standards.
Test Failure – Refers to testing that the Contractor conducted correctly, but the item (CNG fuel containers) being tested failed to meet the FMVSS standards. Refer to Section F.8, for instructions on how test failures are to be handled.
C.4 GENERAL REQUIREMENTS
The services under this contract are necessary to determine conformance of CNG fuel containers with the applicable requirements of Federal Motor Vehicle Safety Standard No. 304, “Compressed Natural Gas Fuel Container Integrity.”
The Contractor shall furnish the necessary qualified technical personnel, facilities, materials, equipment, and services to perform the procurement, receipt, inventory, inspection, testing, reporting, storage and disposal of CNG fuel containers provided to the Contractor as Government Furnished Test Items (GFTI) or purchased by the Contractor as Contractor Purchased Test Items (CPTI).
The Contractor shall provide additional information specific to the tests conducted for NHTSA, including, but not limited to: test data, photos, video, details about the test set up, test observations, or details about the test item configuration, etc.
If a test failure is identified, NHTSA representatives may contact the Contractor and request information to support its investigation of the test results (See Section F.4.1, Item 4.) and may schedule a visit to witness additional testing or inspection of test samples with or without the manufacturer present. The Contractor shall respond to these information requests within 5 days of the original request. The Contractor may be requested to:
a) provide test data, pictures, videos, or other information necessary to support an investigation
b) answer questions to fully assist OVSC in conducting its investigation
c) answer manufacturer’s questions and requests relating the failed test
d) permit meetings in support of inspection of test samples and equipment at no additional cost to the Government.
Subcontracting is not permitted under this contract with the exception of calibration services as required under this contract. Subcontracting of tests or any portion of a test is NOT permitted (Section H.9).
C.5 KICK OFF MEETING
Within two (2) weeks of the effective date of the contract, the Contractor shall participate in a Kickoff meeting with the Contracting Officer’s Representative (COR), Contracting Officer (CO), and other NHTSA staff. The Kickoff meeting shall take place via teleconference. This meeting will be approximately two hours in length. The Contractor shall make a brief presentation of their understanding of the contract requirements. After the presentation, the parties shall discuss basic contract requirements, including the schedule for testing and test procedures.
C.6 PRELIMINARY DOCUMENTS
Within four (4) weeks of the effective date of the contract, the Contractor shall provide one copy of the following documents*:
• Contractor Test Procedure for each Enforcement Test;
• Checklist for conducting each Enforcement Test;
• Calibration procedure for instrumentation per the requirements stated in the OVSC Test
Procedure (TP-304-03). Guidelines for setting up and maintaining a test instrumentation calibration system are described in ANSI/NCSL Z540-1-199, Calibration Systems Requirements. All measuring and recording instruments and standards shall be calibrated by the Contractor, or by a commercial facility at the Contractor’s expense, against a higher order standard at periodic intervals not exceeding twelve (12) months.
• A list of measurement and test equipment used for enforcement testing; the list shall provide the following information for each item of measurement and test equipment:
1. Manufacturer name
2. Model number
3. Function of the item
4. Calibration interval
The Contractor shall not begin testing until all preliminary documents have been reviewed and approved by the COR.
Any problems associated with the above documents must be resolved with the COR prior to the start of testing.
Copies of the above documents shall be submitted electronically via email, unless otherwise specified by the COR.
*Contractors should provide the preliminary documents as soon as possible after the start of the contract. Once approval of the preliminary documents has been provided, the Contractor may begin testing immediately consistent with the other terms of the contract.
C.7 PROCURING TEST ITEMS - CPTI/SERVICE CHARGE
The Contractor shall procure test items, CPTI, in accordance with the terms of a Delivery Order.
Each delivery order that includes CPTI will identify the CNG fuel containers’ make and model, number of CNG fuel containers required, and estimated cost. The Contractor shall place the order for each CPTI in accordance with the timeframe specified in Section F.4, Performance Milestones and Deliverables, after receipt of a delivery order.
The Contractor shall complete all transactions required to purchase the CPTI, including but not limited to:
• Placing the purchase order for the CPTI with the suggested manufacturer/vendor.
• Providing the manufacturer/vendor with special order/instructions as needed.
• Inspecting the CPTI when received and resolving deficiencies or any identified issues with the supplier. Deficiencies may include damage in transit, missing info/parts, etc.
• Paying the manufacturer/vendor for the CNG fuel container ordered once any deficiencies have been resolved.
The Contractor shall notify the COR of all purchase orders placed as well as receipt of the purchased test items in accordance with the timeframes specified in Section F.4. The Contractor shall retain all documents for each CPTI until disposition instructions are provided by the COR.
The CPTI identified in the delivery order is subject to change by the NHTSA COR provided that
(1) the cost for the test item does not exceed the funds available for procuring the CPTI and that
(2) the Contractor has not begun fulfilling the order.
The cost of obtaining the CPTI charged to the government will equal the actual cost paid by the Contractor to the CNG fuel container manufacturer/vendor for the test items (plus any associated shipping and handling costs, as applicable) along with the firm-fixed price service charge identified in the price schedule. The procurement of multiple CNG fuel containers from a single manufacturer, of the same model, shall incur a single service charge. The Contractor’s invoice shall include copies of the CNG fuel container manufacturer/vendor’s invoice(s).
Title to CPTI will vest with the government.
C.8 RECEIVING AND INSPECTING TEST ITEMS
The Contractor shall verify that the CPTI and GFTI delivered were not damaged in transit or show evidence of mishandling during shipment (e.g., test items were properly secured for shipping; test items are the correct type and quantity ordered; and, if the test items were not shipped completely assembled, the shipment is complete, containing all required bolt-on components, hardware, etc.). The Contractor shall document any discrepancy or damage identified, e.g., incorrect/incomplete items, and notify the Government. The parties will determine the appropriate steps to replace CPTI and GFTI damaged in transit.
In the event of discrepancies or damage related to the CPTI and GFTI received, the Contractor shall ensure that the manufacturer/vendor resolves any issues. The Contractor shall return items to the manufacturer/vendor, if required, and shall ensure that the manufacturer/vendor provides correct replacement items in return to the Contractor.
C.9 STORAGE/DISPOSING AND INVENTORY/SECURITY OF CPTI/GFTI
C.9.1 Storage/Disposing
All CPTI and GFTI shall be stored and disposed at no additional cost to the Government. The Contractor shall store all CPTI and GFTI until receipt of disposition instructions from the Government. Typically, disposition instructions will be provided by the COR via e-mail after all testing, inspection and acceptance of the final test report has been completed.
Test items which have “failed” compliance requirements, and also any unused test items identical to test items which have “failed” compliance requirements, shall be stored by the Contractor until the end of the contract term. Storage of test samples for this period of time shall be at no additional cost to the Government.
Upon direction by the COR and in preparation for disposal, the Contractor shall render the test items unusable in a motor vehicle, at no additional cost to the Government.
C.9.2 Security of Test Items and Data
The Contractor shall provide security measures to protect GFTI or CPTI during the entire testing and storage periods. Theft or damage not due to testing, and acts of vandalism must be reported to the COR immediately after discovery. The Contractor may be held responsible for the repair or replacement of any GFTI or CPTI that is damaged or missing.
C.10 TESTING
C.10.1 Enforcement Tests
There are three types of enforcement tests required: Enforcement Test 1 – Pressure Cycling Test, Enforcement Test 2 – Hydrostatic Burst Test, and Enforcement Test 3 – Bonfire Test. The purpose of enforcement testing is to determine whether CNG fuel containers comply with the requirements of FMVSS No. 304. A description of each test is provided below.
• Enforcement Test 1 – Pressure Cycling Test: Refers to a CNG fuel container that is hydrostatically pressurized to not more than 10 percent of service pressure for 13,000 cycles.
• Enforcement Test 2 – Hydrostatic Burst Test: Refers to a CNG fuel container that is hydrostatically pressurized to the minimum prescribed burst pressure and held constant for 10 seconds.
• Enforcement Test 3 – Bonfire Test: Refers to a CNG fuel container that is filled with compressed natural gas placed over a fire source.
The Contractor shall conduct testing in accordance with this section and shall complete this testing within the timeframes specified in Section F.4. The Contractor shall submit separate test reports for each model of CNG fuel container tested. Test reports shall be submitted in accordance with Sections F.4 through F.10. The final determination of “passed” or “failed” shall be made by the COR upon acceptance of the Final Test Report.
C.10.2 Test Procedures
The Contractor shall perform all testing in accordance with the requirements of FMVSS No. 304 contained in the Office of Vehicle Safety Compliance (OVSC) Test Procedure TP-304-03, “Laboratory Test Procedure for FMVSS No. 304, Compressed Natural Gas (CNG) Fuel Container Integrity,” dated December 8, 2003, or any subsequent revisions to the test procedure as published by NHTSA.
The OVSC Test Procedure TP-304-03 is attached (Section J) and is incorporated into this contract. The testing procedures specified in FMVSS No. 304 and TP-304-03, will be referred to hereinafter as the “OVSC Enforcement Test Procedure”.
Any test procedures used by the Contractor which are “in-house” procedures or which are different from the OVSC Enforcement Test Procedure as defined above, will be referred to hereinafter as “Contractor Enforcement Test Procedure.”
Any issue with the test procedures prescribed herein must be presented to the COR for discussion and resolution prior to conducting a test. The Contractor shall notify the COR by email of any issue with the test procedures, e.g., question, apparent conflict or ambiguity.
Failure to agree on a resolution shall be resolved in accordance with the Disputes Clause of the contract.
C.10.3 Deviation from OVSC Test Procedures
The Contractor shall conduct testing only in accordance with the approved test procedures (i.e., OVSC Enforcement Test Procedure and Contractor’s Enforcement Test Procedure) and the applicable FMVSS and shall notify the COR, in advance, if any deviation from the approved test procedures are necessary. The Contractor shall receive approval from the COR prior to initiating any deviations from the test procedures. The COR is authorized to approve and require deviations from approved test procedures as long as that deviation does not affect the prices stated in this contract.
C.11 MEASUREMENT AND TEST EQUIPMENT
All measurement and test equipment and standards used in the performance of services under this contract shall be labeled with the following information:
• Date and place of last calibration.
• Date of next scheduled calibration.
• Name of technician or commercial business performing the calibration.
• Full scale measurement range.
• Accuracy and tolerance over the entire measurement range or within the range used for testing.
Accuracy and tolerance of measured values shall be indicated on all charts, graphs, tracings, data printouts, and other hard copy output of test measurements and results.
The Contractor shall maintain records which show the traceability of calibrated measurement and test equipment to standards maintained by the National Institute of Standards and Technology.
(End of Section C)
SECTION F - DELIVERIES OR PERFORMANCE
F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/?q=/browse/far/52
Federal Acquisition Regulation (FAR) Clauses:
52.242-15 Stop Work Order (AUG 1989) 52.247-35 F.o.b. Destination, Within Consignees Premises (APR 1984)
F.2 PERIOD OF PERFORMANCE
All work and services required hereunder shall not exceed 60 months from the effective date of the contract inclusive of one (1) two-year Base Period and one (1) three-year Option Period that may be exercised at the Government’s discretion.
Base Period (Contract Year 1): Date of Award through 12 Months Thereafter Base Period (Contract Year 2): End of Contract Year 1 through 12 Months Option Period (Contract Year 3): End of Contract Year 2 through 12 Months Option Period (Contract Year 4): End of Contract Year 3 through 12 Months Option Period (Contract Year 5): End of Contract Year 4 through 12 Months
Any Delivery Order issued prior to the expiration date of the contract shall be completed by the Contractor within the period of performance specified in the Delivery Order in accordance with Section I.3.3, FAR 52.216-22, Indefinite Quantity (OCT 1995).
**Is there a clause we can add explaining the option to extend the POP, if needed.
F.3 PLACE OF PERFORMANCE/PHYSICAL LOCATION
The work performed under this Contract and any Delivery Orders issued under this Contract shall be accomplished at the Contractor’s facilities and those facilities shall be located within the continental United States. There shall be no deviation from or waiver of this requirement.
https://www.acquisition.gov/?q=/browse/far/52
F.4 PERFORMANCE MILESTONES AND DELIVERABLES
F.4.1 Deliverables. All deliverables are to be submitted electronically (PDF, Word, Excel, as appropriate) to the COR in accordance with the schedule below. File formats shall meet the compatibility requirements of Section F.9.2, Specifications for Electronic Files. The following is a list of all deliverables which are considered to be significant in the performance of this contract (Note: days are defined to mean business days).
*The Contractor shall submit to the COR a final report, photographs, electronic data, and video for each test performed under this contract.
NOTE: OVSC is in the process of developing a portal based tool through which deliverables and other communications between lab personnel and COR shall be conducted. When that system is launched, the electronic submission of deliverables shall be made through the lab portal.
DELIVERABLES
Item Section Number
Deliverable
Due Date
1 C.6 Preliminary Documents Within 4 weeks of the effective date of the contract 2 F.6 Evidence of receipt of
CPTI/GFTI (See Section C.7)
Within 5 days of receipt
3 F.7 Monthly Status Report By the 15th of each month, following the month being reported
4 F.8 Test Failure Report Summary notification within 4 hours of the failure. Written notification, including the relevant data, within 24 hours of the failure.
5 F.9 Draft Final Test Report in electronic format
Within 2 weeks after completion of test
6 F.9 Final Test Report, Video, and Data
Within 7 days after receipt of COR’s comments on Draft Final Test Report (see Deliverable 5 above)
F.4.2 Milestones. The following is a list of all milestones which are considered to be significant in the performance of this contract, and their due dates (Note: days are defined to mean business days).
MILESTONES
Item Section Number
Milestone
Due Date
1 C.5 Kickoff Meeting Within 2 weeks of the effective date of the contract 2 F.6 Contractor to order CPTI Within 5 days of delivery order award 3 F.6 Contractor notifies COR that CPTI was ordered Within 5 days of ordering the CPTI (Item 2)
4 F.6 Contractor notifies COR of receipt of CPTI and test schedule
Within 5 days after receiving CPTI
5 F.6 Contractor to initiate testing
Within 2 weeks after receipt of CPTI
6 F.6 Contractor to complete testing
Within 5 days of initiating test
7 F.8 Notice of Test Failure Summary notification within 4 hours of the failure.
Written notification within 24 hours of the failure.
8 Contractor completion of Delivery Order
TBD at the delivery order level.
F.5 PLACE OF DELIVERY OF REPORTS
Unless otherwise specified, all deliverables shall be delivered electronically, under transmittal letter, to the assigned COR at the following address:
To be filled in at time of award
A copy of the transmittal letters for all deliverables and the monthly progress report shall be delivered to the Contract Specialist at the following address:
To be filled in at time of award
NOTE: OVSC is in the process of developing a portal based tool through which deliverables and other communications between lab personnel and COR shall be conducted. When that system is launched, the electronic submission of deliverables shall be made through the lab portal.
F.6 TESTING SCHEDULE/CONDUCT
Upon the issuance of a Delivery Order, the Contractor shall commence fulfilling the order and shall complete it in accordance with the terms and conditions of the Delivery Order and Section F.4.
The Contractor shall complete all testing in the time allotted in Section F.4. The Contractor shall submit separate test reports for each model of CNG fuel containers. Each report shall combine the results for the testing performed correctly for that model, as ordered on a single delivery order, unless instructed otherwise by the COR. Test reports shall be submitted in accordance with Sections F.4 through F.10. The final determination of “passed” or “failed” shall be made by the COR upon acceptance of the Final Test Report.
The Contractor shall order CPTI within 5 days of delivery order receipt.
The Contractor shall notify the COR of CPTI purchase within 5 days of ordering CPTI.
The Contractor shall notify the COR within 5 days after receiving the CPTI, and provide a test schedule.
Within two (2) weeks after receipt of CPTI, the Contractor shall initiate testing. Within five (5) days of initiating testing, the Contractor shall complete all testing required by the delivery order.
The Contractor shall not deviate from the test schedule unless authorized in writing by COR.
F.7 MONTHLY STATUS REPORTS
Monthly status reports shall be submitted to the COR and the Contract Specialist indicating which test items have been ordered, anticipated receipt date, actual receipt date, test schedule, the status of each test, test reports, and disposal status for the calendar month and shall be submitted not later than the 15th day of each month, following the month being reported. The monthly status report shall indicate the contract number and the time covered. The Contractor shall continue to submit monthly status reports until all final test reports are accepted by the Government. Specifically, Monthly Status Reports shall include the following:
• Number of tests, inspections, and reports scheduled for the reporting period and completed during the reporting period.
• Schedule for tests, inspections, and reports for the next reporting period.
• Brief description of test failures which occurred during the reporting period.
• Problems or delays that the Contractor experienced during the reporting period which are related to the supplies and services required under this contract.
• Specific action which the Contractor proposes to correct problems or delays identified.
F.8 TEST FAILURE REPORTS
Within 4 hours of a test failure, the Contractor shall provide summary notification of that failure to the COR. This summary notification may be transmitted via telephone, e-mail or facsimile.
Within 24 hours of a test failure, the Contractor shall provide the COR with a written notification that includes the following information: FMVSS test type, test date, laboratory, contract number, project engineer’s name, test failure description, actual data, e.g., charts, any data relevant to the failure including video and/or photographs, charts including (plots and values), etc., section of the standard failed, date of COR notification, and the name of the individual that provided COR notification. A sample form will be provided by the COR upon request.
F.9 DRAFT AND FINAL TEST REPORTS
Draft test reports shall be submitted to the COR for review and acceptance within two (2) weeks of completion of all phases of compliance testing and inspection of each test item. Test reports shall be prepared in accordance with instructions contained in the OVSC Laboratory Test Procedure. Reports that do not meet these requirements will be returned to the Contractor. The COR shall review the draft test report and provide suggested edits and questions within ten (10) business days. The Contractor shall work with the COR to resolve issues. When all issues have been resolved and the test report is accepted by the COR, the Contractor shall issue a final electronic .pdf copy to include the COR’s signature and report number designating it as the final test report. NHTSA may withhold payment of a Contractor’s invoice until the final test report is accepted by the COR. If a final test report is returned to the Contractor for technical or format corrections, the report date shall be changed to reflect the date of resubmission.
Delivery of the final test reports shall accompany data files containing raw data of all tests (in electronic format, i.e., Excel spreadsheets, CSV, or other comparable format) and videos.
F.9.1 Electronic Test Reports
An electronic draft test report is required after completion of each test. The test report and content shall comply with the applicable test procedures. The organization and content of test data sheets in the report shall be consistent with the applicable test procedures. Typically, these reports can be e-mailed to the COR. However, if the submission of the report and accompanying data files is too large to be e-mailed, it shall be provided on transmittable media such as a flash drive, a CD-ROM or DVD that NHTSA can receive and use. Upon approval of the COR, other electronic means, including a NHTSA designated file transfer site, can also be utilized.
FRONT COVER
A case shall be used for the protection of any flash drive or CD-ROM / DVD provided. The information required on the cover of a test report is as follows (please also include this information on any CD-ROM or DVD cases provided):
A. Final Report Number such as 304-ABC-XX-00X, where:
304 FMVSS tested, ABC NHTSA assigned 3-digit code the test laboratory XX Fiscal Year of the test program 00X Group Number (001 for the 1st test, 002 for the 2nd test, 003 for the 3rd test, etc.)
B. Final Report Title and Subtitle (example):
Safety Compliance Testing for FMVSS No. 304
CNG Fuel Containers CNG Fuel Container Manufacturer
Model xyz
C. Contractor’s Name and Address (example):
ABC LABORATORIES, INC.
405 Main Street Detroit, Michigan 48070
NOTE: DOT SYMBOL WILL BE PLACED BETWEEN ITEMS (C) AND (D)
D. Date of Final Report completion
E. The words "FINAL REPORT"
F. The sponsoring agency’s name and address as follows –
U. S. DEPARTMENT OF TRANSPORTATION
National Highway Traffic Safety Administration
Equipment Division Office of Vehicle Safety Compliance Mail Code: NEF-220 1200 New Jersey Avenue, SE Washington, DC 20590
FIRST PAGE AFTER FRONT COVER
A disclaimer statement and an acceptance signature block for the COR shall be provided as follows:
“This publication is distributed by the U.S. Department of Transportation, National Highway Traffic Safety Administration, in the interest of information exchange. The opinions, findings and conclusions expressed in this publication are those of the author(s) and not necessarily those of the Department of Transportation or the National Highway Traffic Safety Administration. The United States Government assumes no liability for its contents or use thereof. If trade or manufacturers’ names or products are mentioned, it is only because they are considered essential to the object of the publication and should not be construed as an endorsement. The United States Government does not endorse products or manufacturers”.
Prepared By:
Approved By:
Approval Date:
FINAL REPORT ACCEPTANCE BY OVSC:
Accepted By:
Acceptance Date:
SECOND PAGE AFTER FRONT COVER
A completed Technical Report Documentation Page (Form DOT F1700.7) shall be completed for those items that are applicable with the other spaces left blank. Sample data for the applicable block numbers of the title page follow:
Block 1 — REPORT NUMBER 304-ABC1-0X-00X
Block 2 — GOVERNMENT ACCESSION NUMBER Leave blank
Block 3 — RECIPIENT'S CATALOG NUMBER
Block 4 — TITLE AND SUBTITLE Final Report of FMVSS 304 Compliance Testing of CNG Fuel Containers from Tank Manufacturer, Model XYZ
1 “ABC” is the NHTSA assigned 3-character code for the laboratory
Block 5 — REPORT DATE Month DD, 20XX
Block 6 — PERFORMING ORGANIZATION CODE ABC
Block 7 — AUTHOR(S) John Smith, Project Manager Bill Doe, Project Engineer
Block 8 — PERFORMING ORGANIZATION REPORT NUMBER ABC-DOT-XXX-00X
Block 9 — PERFORMING ORGANIZATION NAME AND ADDRESS ABC Laboratories, Inc.
405 Main Street Detroit, MI 48070
Block 10 — WORK UNIT NUMBER
Block 11 — CONTRACT OR GRANT NUMBER DTNH22-22-D-XXXXX
Block 12 — SPONSORING AGENCY NAME AND ADDRESS United States Department of Transportation National Highway Traffic Safety Administration Equipment Division Office of Vehicle Safety Compliance Mail Code: NEF-220 1200 New Jersey Avenue, SE Washington, DC 20590
Block 13 — TYPE OF REPORT AND PERIOD COVERED Final Test Report Month DD to Month DD, 20XX
Block 14 — SPONSORING AGENCY CODE NEF-220
Block 15 — SUPPLEMENTARY NOTES Leave blank
Block 16 — ABSTRACT Compliance tests were conducted on CNG Fuel Container from [Tank Manufacturer] in accordance with the specifications of the Office of Vehicle Safety Compliance Test Procedure No. TP-304-0X for the determination of FMVSS 304 compliance. Test failures identified were as follows:
None (or, if any, describe)
NOTE: Above wording shall be shown with appropriate changes made for a particular compliance test. Any questions shall be resolved with the COR.
Block 17 — KEY WORDS Compliance Testing CNG Fuel Container Safety
FMVSS 304
Block 18 — DISTRIBUTION STATEMENT Copies of this report are available from the following:
U.S. Department of Transportation NHTSA Technical Information Services (TIS) Mail Code: NIO-120, Room W51-217 1200 New Jersey Avenue, SE Washington, DC 20590 Telephone No. (202) 366-2245
Block 19 — SECURITY CLASSIFICATION OF REPORT Unclassified
Block 20 — SECURITY CLASSIFICATION OF PAGE Unclassified
Block 21 — NUMBER OF PAGES Add appropriate number
Block 22 — PRICE
THIRD PAGE AFTER FRONT COVER
TABLE OF CONTENTS
Sample Test Report Table of Contents:
Section 1 — Purpose of Compliance Test Section 2 — Compliance Test Data Summary Section 3 — Test Data (including acceleration and velocity plots) Section 4 — Test Failure Details (if applicable) Appendix A — Photographs Appendix B — Test Equipment List and Calibration Information
Within seven (7) days of receiving the COR’s comments on the draft test report, the Contractor shall implement changes and resubmit the report to the COR. If the report and supporting documentation are too large to be e-mailed, the Contractor shall submit two (2) copies of the final report by flash drive, CD-ROM or DVD to the COR.
NOTE: Prior to submission of the flash drive, CD-ROM or DVD of the final report, the draft and final reports shall be electronically transmitted to the COR to facilitate review and acceptance. The COR shall provide a signature page to the Contractor for inclusion in the electronic file for the final report, which shall be e-mailed or placed on a flash drive, CD-ROM or DVD, depending on file size.
The final report shall be in PDF format that can be printed by NHTSA personnel.
F.9.2 Specifications for Electronic Files
Electronic file copies of the Final Test Report shall be provided in accordance with the following:
A. Electronic Master File:
An electronic version of the final report shall be used as the “Master” report copy. The hard-copy and electronic reports shall be generated from this electronic master file. A copy of the electronic master file shall be provided to the NHTSA COR.
B. System Compatibility:
1. All electronically submitted final report copies shall be formatted in PDF format for transmission in accordance with F.4.1. The final test report (containing all signatures and ready for publishing) shall be secured so that it cannot be further edited.
2. All parts of the test report, including images (photographs, charts, graphs, etc.) shall be clear and legible, and the final submitted document shall be compressed without unreasonable degradation.
C. For the duration of the contract, NHTSA reserves the right to change the media and software requirements stated above, such that submitted electronic files continue to be compatible with computer systems utilized by the Office of Vehicle Safety Compliance.
If a Final Test Report is returned to the laboratory for correction, the report date shall be changed to the date of re-submission. Delivery of an unacceptable Final Test Report will not be construed as meeting the due date specified in Sections F.4 and F.9. In no event shall the return of a report for correction be deemed to waive the Government’s right to specific performance of the contract, with respect to any other deliverables required under this contract. NHTSA will withhold payment of a Contractor’s invoice until the Final Test Report is approved by the COR.
F.10 COMPLIANCE WITH REHABILITATION ACT
The Contractor may be required to ensure that electronic documents it prepares will meet the requirements of Section 508 of the Rehabilitation Act. The Rehabilitation Act requires that all electronic products prepared for the Federal Government be accessible to persons with disabilities, including those with vision, hearing, cognitive, and mobility impairments. When an electronic document developed under this effort has been identified by NHTSA as necessary and required to meet the requirements of Section 508, it is understood that all reasonable costs incurred by the Contractor that are associated with meeting the requirements for Section 508 compliance will be fully reimbursed by the Government.
The Contractor should review Section 508 of the Rehabilitation Act and Federal IT Accessibility Initiative (Home Page) website at http://www.section508.gov for further information on these requirements.
(End of Section F) http://www.section508.gov/
| F.1 FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) |
| F.5 PLACE OF DELIVERY OF REPORTS |
| Unless otherwise specified, all deliverables shall be delivered electronically, under transmittal letter, to the assigned COR at the following address: |
| To be filled in at time of award |
| A copy of the transmittal letters for all deliverables and the monthly progress report shall be delivered to the Contract Specialist at the following address: |
| To be filled in at time of award |