DRAFT SOW 590-24-450.pdf

PDF 97 KB Posted

Attached to
Z2DZ--590-24-450 Renovate Transitional Residences
Solicitation number
36C24626Q0754
Issued by

About this file

This is a Draft Statement of Work for a construction renovation project at the Hampton VA Healthcare System. The project, identified as Project 590-24-450, involves general residential construction services for four transitional residences: three located in Hampton, VA (TR-2, TR-3, and TR-4) and one in Norfolk, VA (TR-1). All work must be performed in accordance with attached plans and specifications.

The contractor must complete all work within 365 calendar days from the Notice to Proceed, including submittals and final cleanup. The scope encompasses 32 construction divisions covering general requirements, existing conditions management (demolition, asbestos abatement, lead-based paint removal), concrete, masonry, metals, carpentry, thermal and moisture protection, openings, finishes, specialties, furnishings, fire suppression, plumbing, HVAC, electrical, electronic safety and security, earthwork, and exterior improvements. Specific site requirements include contractor and subcontractor completion of OSHA 10-hour training (30-hour for superintendents) and Integrity and Compliance Awareness Training (TMS course 43790). Construction activities must occur during normal business hours (Monday-Friday, 7:00 AM to 4:30 PM) with no weekend or holiday work except scheduled utility outages. Noise-generating work must be scheduled to minimize impact on patients and staff. All new materials must be on-site before demolition begins in any area. The contractor must comply with the attached Hampton Construction Safety Handbook, submit required documentation per sections 01 33 23 and applicable trade sections, maintain quality control standards per section 01 45 00, and implement environmental and waste management practices per sections 01 57 19 and 01 74 19.

View the file

Other files

File Type Posted
36C24626Q0754.docx DOCX document
590-24-450 Stamped Specifications.pdf PDF
590-24-450 Stamped Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment - Sources Sought Notice

DRAFT STATEMENT OF

WORK

Renovate Transitional

Residences Project 590-24-450

Scope: Provide construction services for the renovation of four (4) Hampton VA Healthcare System Transitional Residences (TR). Three (3) Transitional Residences are located in Hampton, VA, while the fourth Transitional Residence is located in Norfolk, VA. Contractor shall perform all associated work as per attached plans and specifications.

(a) General: The following is a brief summary of the Work:

1. General residential construction

(b) Place of Performance: Tasks will be performed at Hampton and Norfolk, VA at the following locations:

• TR-1 at 1200 Stockley Gardens, Norfolk, VA 23517

• TR-2 at 18 Roland Dr., Hampton, VA 23669

• TR-3 at 301 Ireland St., Hampton, VA 23663

• TR-4 at 22 Roland Dr., Hampton, VA 23669

(c) Specific requirements (see drawings for area of work):

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 01 33 23 Shop Drawings, Product Data, and Samples 01 35 26 Safety Requirements for Major Projects 01 42 19 Reference Standards 01 45 00 Quality Control 01 45 29 Testing Laboratory Services 01 45 35 Special Inspections 01 57 19 Temporary Environmental Controls 01 74 19 Construction Waste Management 01 91 00 General Commissioning Requirements

DIVISION 02 – EXISTING CONDITIONS

02 41 00 Demolition 02 82 11 Traditional Asbestos Abatement 02 83 33.13 Lead-Based Paint Removal and Disposal

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete

DIVISION 04 – MASONRY

04 01 00 Maintenance of Masonry 04 05 13 Masonry Mortaring 04 05 16 Masonry Grouting 04 20 00 Unit Masonry

DIVISION 05 – METALS

05 50 00 Metal Fabrications 05 51 00 Metal Stairs

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00 Rough Carpentry 06 20 00 Finish Carpentry

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 01 50.19 Preparation for Re-Roofing 07 21 13 Thermal Insulation 07 31 13 Asphalt Shingles 07 31 26 Slate Shingles 07 60 00 Flashing and Sheet Metal 07 71 00 Roof Specialties 07 92 00 Joint Sealants

DIVISION 08 - OPENINGS

08 14 00 Interior Wood Doors 08 51 13 Aluminum Windows 08 80 00 Glazing

DIVISION 09 – FINISHES

09 05 16 Subsurface Preparation for Floor Finishes 09 22 16 Non-Structural Metal Framing 09 23 00 Gypsum Plastering 09 29 00 Gypsum Board 09 30 13 Ceramic/Porcelain Tiling 09 65 19 Resilient Tile Flooring 09 91 00 Painting

DIVISION 10 – SPECIALTIES

10 28 00 Toilet, Bath, and Laundry Accessories

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS

12 24 00 Window Shades 12 32 00 Manufactured Wood Casework

12 36 00 Countertops

DIVISION 13 - SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14– CONVEYING EQUIPMENT (NOT USED)

DIVISION 21- FIRE SUPPRESSION

21 13 13 Wet-Pipe Sprinkler Systems

DIVISION 22 – PLUMBING

22 05 11 Common Work Results for Plumbing 22 05 12 General Motor Requirements for Plumbing Equipment 22 05 19 Meters and Gages for Plumbing Piping 22 05 23 General-Duty Valves for Plumbing Piping 22 05 33 Heat Tracing for Plumbing Piping 22 07 11 Plumbing Insulation 22 11 00 Facility Water Distribution 22 11 23 Domestic Water Pumps 22 13 00 Facility Sanitary and Vent Piping 22 33 00 Electric Domestic Water Heaters 22 40 00 Plumbing Fixtures

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 23 05 12 General Motor Requirements for HVAC and Steam Generation Equipment 23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 11 HVAC and Boiler Plant Insulation 23 08 00 Commissioning of HVAC Systems 23 23 00 Refrigerant Piping 23 31 00 HVAC Ducts and Casings 23 34 00 HVAC Fans 23 37 00 Air Outlets and Inlets 23 40 00 HVAC Air Cleaning Devices 23 81 43 Air-Source Unitary Heat Pumps

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 26 05 20 Cables 26 05 26 Grounding and Bonding for Electrical Systems

26 05 33 Raceway and Boxes for Electrical Systems 26 05 41 Underground Electrical Construction 26 24 16 Panelboards 26 27 26 Wiring Devices 26 29 21 Enclosed Switches and Circuit Breakers 26 43 13 Surge Protective Devices 26 51 00 Interior Lighting

DIVISION 27 – COMMUNICATIONS (NOT USED)

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 31 00 Fire Detection and Alarm

DIVISION 31 – EARTHWORK

31 20 11 Earthwork (Short Form)

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 32 12 16 Asphalt Paving 32 31 23 Vinyl Fences and Gates CUSTOM 32 90 00 Planting

DIVISION 33 – UTILITIES (NOT USED)

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)

(d) Period of Performance: Contractor shall commence work under this contract promptly after Notice to Proceed (NTP), execute the work diligently, and achieve final completion and acceptance including final cleanup of the premises within three hundred sixty-five (365) calendar days including submittals.

(e) Specific site requirements: Contractor and all subcontractors shall provide proof of completion from an approved OSHA 10-hour training course (30-hour for superintendent), complete and provide certificate of training for Integrity and Compliance Awareness Training for all Non-Revenue Staff (TMS course 43790).

No demolition is to begin in an area unless all new materials needed to complete the new work are in contractor’s possession.

(f) Work Hours: Plan construction activities during normal business hours (Monday thru Friday, 7am to 4:30pm). No work is to be scheduled on holidays or weekends with the exception of utility outages which must be scheduled at a day/time to minimize impact on staff and patients. Work that generates noise will need to be scheduled to minimize impact on patients/staff.

(g) Construction Safety Requirements: - see attached Hampton Construction Safety Handbook in section 01 35 26A

(h) Submittals: - see sections 01 00 00, 01 33 23, and all applicable trade sections

(i) Quality Control: - see section 01 45 00

(j) Schedules: - see section 01 32 16 .15

(k) Environmental and Waste Management: - see sections 01 57 19, and 01 74 19

Renovate Transitional Residences
Project 590-24-450

File details come from the government source that posted it. Updated .