This draft statement of work and related federal contract opportunity call for architectural and engineering design services for the complete remodel of Dormitory 333 at Holloman Air Force Base in New Mexico. The statement of work requires the selected firm to provide 35% design drawings, specifications, cost estimates, and supporting analysis for gutting and renovating the 34,056 square foot dormitory, including new HVAC, plumbing, electrical, and fire protection systems as well as interior and exterior repairs. Responses are due by February 15, 2024. The total small business set-aside opportunity is issued by the Department of the Air Force Air Combat Command.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

ARCHITECT-ENGINEER (A-E) SERVICES FOR DESIGN

OF

KWRD20-0089

REPAIR DORMITORY B333

10 January 2024

1. GENERAL STATEMENT OF SERVICES: The objective of this project is to completely remodel Dormitory 333 at Holloman AFB, NM. Dormitory 333 is a 34,056 SF, 72-person three-story dormitory built in 1953 and used for housing enlisted airman undergoing training at Holloman AFB. The Architect-Engineer (A-E) shall perform the services set forth herein and as described in the contract Statement of Work.

2. SCOPE of WORK: The 35% design shall be based on the project description and other data furnished under Paragraph 4, and information covered during a criteria review meeting held prior to fee negotiations or the start of design. The project shall be designed so as not to exceed the programmed design budget.

3. The Architect-Engineer shall perform the following services:

A. The A-E shall provide all services necessary to provide 35% drawings and specifications, complete cost estimate and supporting design analysis based on the requirements set forth in this statement of work. Any as-built drawings and design calculations provided by the Government to the A-E are intended as guidance and not to be interpreted as the only solution. See the contract Statement of Work for detailed design instructions. The government will provide any available information it has to help in the execution of this design. For example, project location plans, utility maps, base standards, forms and sheet layouts, and as-built drawings.

B. Special emphasis is being placed on sustainable design and construction principles in this project, with emphasis given to energy and water conservation, environmentally beneficial material selections, and reuse/recycling. This emphasis is added to comply with various executive directives meant to help alleviate negative impacts to natural resources and the environment. The A-E shall develop drawings and specifications consistent with policies described in Engineering Technical Letter (ETL) 08-13, Incorporating Sustainable Design and Development (SDD) and Facility Energy Attributes in the Air Force Construction Program and AFSOC/CV Energy Policy Memo dated 17 Feb 09.

C. The A-E shall prepare two separate 35% designs with separate cost estimates. Design A shall retain the current configuration of one restroom shared between two sleeping rooms. Design B shall make modifications to the floor plan to provide separate restrooms for each sleeping room. As a possible floor plan for Design B, the plans for Dorm 334, currently undergoing this modification, shall be provided as part of the supporting material to the A-E.

D. SUBMITTALS: Upon completion of each phase of the work, the A-E shall furnish all documents in the manner described in the contract Statement of Work. The specific phases/submittals required are listed in the table below; each submittal is required within the calendar days allowed as indicated. The numbers of days shown under Gov’t Review are the estimated government review time. "On-board" means the review will be conducted in a review meeting following that design phase. A-E shall schedule this meeting one week prior to the submittal due date. The A-E will attend project reviews at Holloman AFB for each phase as indicated by a yes or no; quantities of drawing sets/other items required as indicated.

PHASE

NUMBER

OF DAYS

EST. GOVT.

REVIEW (DAYS)

ONBOARD

REVIEW

SUBMITTAL FORMAT AND QUANTITIES

10 60 14

35 60 14 Yes Two sets of bound ½ scale dwgs and design analysis; one digital PDF (single file of each)

TOTAL 120 28

E. A Sample Board will will not X be required for this project.

4. PROJECT DESCRIPTION:

The work shall include the following:

A. Complete remodel of B333 to include gutting all rooms to the walls, new finishes, new doors and windows, and exterior repairs to walls, walks, awnings, porticoes, and signage.

B. Provide new finishes for floors, walls, and ceilings in all rooms.

C. Provide new HVAC systems, including boilers, chillers, pumps, fan coils, exhaust fans, and controls.

D. Provide new plumbing fixtures, drain-waste-vent system, sewer connections, hot and cold-water systems.

E. Provide new outlet boxes, dryer vents and electrical outlets in the laundry rooms to support the minimum required number of washers and dryers.

F. Provide new electrical panelboards, outlets, conduit, wiring, lighting, switches, and main distribution panel.

G. Provide interior cables and outlets for telephone, internet, and cable TV.

H. Provide wet-pipe sprinkler system protection for all interior spaces in accordance with UFC

3-600-01.

I. Furnish new combined fire alarm/mass notification system with smoke and heat detectors, speaker-strobes, and other notification devices.

J. Exterior utility work to include potable water, sanitary sewer, natural gas, electrical, and storm water.

Prepare a Class 3 cost estimate using Parametric Cost Engineering System (PACES) in support of preparing the DD Form 1391. This cost estimate must be certifiable by AFCEC/COSC.

Design shall include all civil engineering, structural engineering, environmental engineering, mechanical engineering, fire protection, and electrical engineering required in completing this project.

The AE shall adapt government designs, drawings, specifications, and standards, as necessary, to meet the requirements of this project. The AE will have access to the following materials by the government:

A. Air Force Guidance Memorandum to AFI 32-6005, Unaccompanied Housing Management.

B. Holloman Air Force Base Installation Facility Standards (IFS).

C. Holloman Air Force Base Installation Development and Design (IDS) D. Holloman Air Force Base Design Compatibility Standard (latest version) E. Utility Plans and Maps.

F. As-Built drawings and photos pertaining to existing building affected to the extent available.

G. UFCs and Air Force manuals and regulations.

H. Historic Asbestos Containing Material (ACM) Reports

END OF SOW