Draft SOO (Peterson OSP Red Fiber) Sources Sought.pdf
PDF 2 MB Posted
- Attached to
- Peterson AFB; OSP Red Fiber Install Federal contract opportunity
- Solicitation number
- FA251721CSOSPRF20
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sources Sought OSP Red Fiber 27 Feb.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sources Sought: Attachment 1
STATEMENT OF OBJECTIVES (SOO)
For
TDKA 2019-00003, Peterson Outside Plant (OSP) Red Fiber
(Provide 36 Strands SM FOC Each from ITB 1038 to ITB 2025, EB 920, and EB 863) at
Peterson AFB, CO
10 Oct 2019 Rv 1
Prepared By 38
ES/ENII
4064 Hilltop Road Tinker
AFB OK 73145-2713
Table of Contents
1. SCOPE 4
2. REQUIREMENTS 4
2.1. GENERAL REQUIREMENTS 4
2.1.1. Safety Requirements 4
2.1.2. Site Coordination 4
2.1.2.1. Confined Space 4
2.1.2.2. Accident/Incident Reporting and Investigation 4
2.1.2.3. Work Area(s) 4
2.1.2.4. Traffic control 4
2.1.3. Security Requirements 4
2.1.3.1. Security Clearances 5
2.1.4. Environmental Compliance 5
2.1.5. Permits 5
2.1.6. Integrated Process Team (IPT) 5
2.1.7. Quality Assurance 5
2.1.8. Contractor Personnel 6
2.1.8.1. Project Management 6
2.1.8.2. Site Point of Contact (POC) 6
2.1.8.3. Personnel Requirements 6
2.1.9. Electronic Contractor Manpower Reporting Application (ECMRA) 6
2.1.10. Warranty 6
2.2. SPECIFIC REQUIREMENTS 6
2.2.1. Maintenance Holes (MHs) and Hand Holes (HHs) 7
2.2.2. Measurements 7
2.2.3. Splice Conductors 7
2.2.4. Cable Racks and Cable Rack Supports 7
2.2.5. Labeling 7
2.2.6. Cable Tags 7
2.2.7. Pulling Tape 8
2.2.8. Cable Terminations 8
2.2.9. FOC Maintenance Loop(s) 8
2.2.10. New Hand Holes (N/A) 8
2.2.11. Grounding 8
2.2.12. Underground Conduit System 8
2.2.12.1. Composition. 8
2.2.12.1.1. Typical Situations 8
2.2.12.1.2. Unique/Site Specific Situations 9
2.2.12.2. Installation 9
2.2.12.3. Bends and Sealing 9
2.2.12.4. Utility Separation 9
2.2.12.5. Spacers and Tracer Wire 9
2.2.12.6. Entrance Conduits into Existing Maintenance Holes 10
2.2.12.7. Excavation/Building Penetrations 10
2.2.13. Outside Plant Installation 10
2.2.13.1. Infrastructure Installation 10
2.2.13.1.1. Hand Holes (N/A) 10
2.2.13.1.2. Ductbank Infrastructure 10
2.2.13.1.3. Geo-textile Fabric (or Innerduct) Installation 11
2.2.13.2. Fiber Optic Cable Installation 13
2.2.13.2.1.1. Fiber Optic Cable Between ITB 1038 and ITB 2025 13
2.2.13.2.2. ITB 1038 13
2.2.13.2.3. ITB 2025 13
2.2.13.2.3.1. Fiber Optic Cable Between ITB 1038 and EB 920 13
2.2.13.2.4. EB 920 13
2.2.13.2.4.1. Fiber Optic Cable Between ITB 1038 and EB 863 14
2.2.13.2.5. EB 863 14
2.2.14. Site Restoration/Debris Removal 14
2.2.15. Service Outages 14
2.2.16. Identification/Marking 14
2.2.17. Installation Schedules 14
2.2.18. Weekly Status Reports 14
2.2.19. As-Built Drawings 15
2.2.20. Test and Acceptance/Installation Test Plan 15
2.2.21. Acceptance/Installation Test Report 15
2.2.22. Final Acceptance 15
2.2.23. As-Built Documentation in CVC 15
3. GENERAL INFORMATION 15
3.1. Period of Performance 15
3.2. Place of Performance 15
3.3. Hours of Operation 15
3.4. Holidays/Down Days 16
3.5. Base Support 16
3.6. Minimum Contractor Qualifications. 16
APPENDIX A: APPLICABLE STANDARDS 17
APPENDIX B: DELIVERABLES 18
APPENDIX C: LIST OF ACRONYMS 19
APPENDIX D: DRAWINGS 21
1. SCOPE
This SOO defines the requirement for the Contractor to engineer, furnish, install and test
(EFI&T) single mode (SM) fiber optic cable (FOC) from Information Transfer Building (ITB)
1038 to ITB 2025, End Building (EB) 920, and to EB 863, and associated terminating equipment, conduits to connect existing and new maintenance hole/conduit system components to the end building. The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOO. All electronics equipment, supplies, and materials to be installed shall be new and not refurbished.
2. REQUIREMENTS
2.1. GENERAL REQUIREMENTS
2.1.1. Safety Requirements
2.1.2. Site Coordination
The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.
2.1.2.1. Confined Space
The Contractors entering spaces on Peterson AFB are responsible for the safety of their personnel and for their own confined spaces permit program as outlined in AFI 91-203. All confined space operations must be coordinated with the Base Safety Office prior to start of work.
2.1.2.2. Accident/Incident Reporting and Investigation
The Contractor shall record and report all available facts relating to each instance of injury to the
Base Safety Office. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the
Government personnel until the investigation is completed.
2.1.2.3. Work Area(s)
At day’s end, the Contractor shall remove all debris and surplus materials from the work place.
Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the work day. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not cause a safety hazard.
2.1.2.4. Traffic control
In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall make appropriate notifications NLT 10 calendar days in advance to 21
CS/SCXP of the planned disruptions.
2.1.3. Security Requirements
The Contractor shall process and provide a Site Visit Request Letter to 21 CS/SCXP within 5 calendar days after contract award. This spreadsheet shall identify the names (as shown on the driver’s license), driver’s license numbers and state of issue, and birth date of the personnel whowill be performing work under this SOO, company name, address, phone number and contract number, start date and end date. This information is required to grant access to the base.
If required by the base, the Contractor shall provide identification badges for their employees.
All Contractor personnel shall wear these badges while on duty on the Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as
Contractor and be in accordance with base regulations.
2.1.3.1. Security Clearances
Stated work and associated products shall be performed at the UNCLASSIFIED level. However, some of this work will take place in secure areas where Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least 24 hours ahead of time with the 21 CS/SCX PM. It is the Government's responsibility to provide escorts.
2.1.4. Environmental Compliance
The Contractor shall comply with the most stringent environmental federal, state, and local laws and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Peterson AFB.
2.1.5. Permits
The Contractor shall complete and process all permits required to complete the installation prior to any trenching, or modifications to a facility, maintenance hole or hand hole; for example, the
Base Civil Engineering Work Clearance Request, a digging permit, (AF Form 103) and Base
Civil Engineer Work Request (AF Form 332). AF Form 103 and AF Form 332 {and any other required permits (as determined by Base Civil Engineering (BCE) or 21 CS/SCXP, etc.)} shall be submitted at IAW local procedures. All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage. The form(s)/permits shall be submitted within 10 calendar days after award.
2.1.6. Integrated Process Team (IPT)
The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the 38
ES Cyberspace Integrator-Base (CSI-B), the 38 ES System Engineer (SE), 38 ES Project
Manager, the 21 CS/SCXP Project Manager (PM), and other base personnel as required. The
Contractor shall provide an agenda and a worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees.
2.1.7. Quality Assurance
The Contractor shall provide Quality Assurance Support for the life of the project. The
Contractor’s quality assurance evaluator shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and /or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.
2.1.8. Contractor Personnel
2.1.8.1. Project Management
The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.
2.1.8.2. Site Point of Contact (POC)
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site
POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the
Government, including quality, safety, and discrepancy matters.
2.1.8.3. Personnel Requirements
The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English. All reporting and documentation shall be in English.
2.1.9. Electronic Contractor Manpower Reporting Application (ECMRA)
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for Peterson AFB single mode
(SM) fiber optic cable (FOC) from ITB 1038 to ITB 2025 and ITB 1038 to EB 920 and EB 863 via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address http://www.ecmra.mil
Reporting inputs will be for the labor executed during the period of performance during each
Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the ECMRA help desk.
2.1.10. Warranty
The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one year workmanship warranty.
The warranty period shall start from the date of system and/or project acceptance. The
Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.
2.2. SPECIFIC REQUIREMENTS
The Contractor shall EF&I one (1) 36 strand SM FOC each from ITB 1038 to ITB 2025, EB 920, and EB 863 along with associated fiber optic distribution panels in ITB 1038, ITB 2025, EB 920, and EB 863 plus all associated splicing and terminations. In addition, to support the installation of the three (3) 36 strand, approximately 1555 feet of new 2-way duct bank, 5465 feet of three
3X3” (Total of 9) Geo-textile fabrics, and 280 feet of two 3X3” (Total of 6) Geo-textile fabrics.
http://www.ecmra.mil/
2.2.1. Maintenance Holes (MHs) and Hand Holes (HHs)
The Contractor shall pump out water as required. Water shall be drained IAW BCE and base environmental requirements.
2.2.2. Measurements
Any distances provided in this SOO are approximations and should NOT be used for ordering materials or determining duct lengths.
2.2.3. Splice Conductors
All fiber splicing shall be performed in accordance with RUS Bulletin 1735F-401, Standards for
Splicing Copper and Fiber Cable. The fusion splice method shall be used for all splicing and terminations of fiber optic cable. Fiber optic cables shall be terminated via fusion splice to pigtails with SC connectors.
2.2.4. Cable Racks and Cable Rack Supports
Cable racks shall be installed in maintenance holes and hand holes as required – this includes new and existing MHs/HHs. Splices shall not be supported by the cables that enter each end of the splice case. The splices shall be supported by cable hooks under the splice case.
Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips.
All cables shall be supported using racking clips, cable racks, and cable hooks.
2.2.5. Labeling
The Contractor shall label all equipment and cables they install and cables identified for re-use
IAW TIA-606-B-2012 and as directed by the base communications organization. New ducts shall be permanently labeled on the wall of each building/maintenance hole indicating the connecting building/maintenance hole at the other end of the duct (for example, “To MH-200”).
Tagging and labeling of new cables shall be IAW the following:
A48L8.3F
FO 1234-5678, 1-48
Line One: A = Armored Sheath (otherwise leave blank) 48 = Fiber Count. L = Loose Tube
Buffer or T = Tight Tube Buffer. 8.3 = Single Mode. F = Filled core (otherwise leave blank).
Line Two: 1234-5678 = From-To Building numbers. 1-48 = Cable/strand Count.
2.2.6. Cable Tags
All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a Maintenance Hole, put a tag on the cable, approximately
2 feet from each duct entrance. Information on the cable tag shall identify cable by size, type, cable number and count. See Para 2.2.5 (above) for nomenclature for tagging.
2.2.7. Pulling Tape
All newly installed ducts left vacant shall be provided with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings (1250 lb. pulling strength) for future cable installations. The pull tape shall extend into the maintenance holes/hand holes and be secured to a cable rack or pulling iron, etc.
2.2.8. Cable Terminations
Fiber optic cables shall be terminated via fusion splice to pigtails with SC connectors. The pigtails shall be sized the same as the OSP fiber they are spliced to, i.e., 125/8.3 micron to
125/8.3 micron. The pigtails shall be duplex (or simplex) unless otherwise agreed to by 21
CS/SCXP.
2.2.9. FOC Maintenance Loop(s)
The Contractor shall install a minimum of a 50 foot fiber optic cable maintenance loop at the first MH from the building, at every splice point MH location and at every 3rd MH in the route.
The maintenance loop slack shall be properly labeled, securely supported to the cable ladder and off the MH floor.
2.2.10. New Hand Holes (N/A)
Unless otherwise stated, Hand Holes (HHs) shall have a minimum interior dimension of 4 feet W x 4 feet L x 4 feet H. HHs shall be furnished with cable racks and a grounding system. HHs shall meet the requirements of TIA -758A, paragraph 4.2.2. Prefabricated HHs are preferred.
HH covers shall be labeled with 1/8 inch raised letters stating “COMMUNICATIONS”. All
HHs shall be of concrete construction –polymer concrete (i.e., Quazite) construction is NOT authorized. Coordinate numbering/labeling of new HHs with 21 CS/SCXP.
2.2.11. Grounding
Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.
necessary to properly bond/ground the cable in HHs shall be provided by the Contractor.
Reference ANSI/TIA 607.
2.2.12. Underground Conduit System
The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. The Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Directional drilling shall be used for major road crossings, taxiways, runways, etc. Otherwise, crossing of paved surfaces may be performed by pavement cuts and resurfacing with appropriate matching road material. This does not prevent the Contractor from using directional drilling if it is more cost effective. Ducts will be appropriately protected when placed under paved surfaces (i.e., concrete encasement).
2.2.12.1. Composition.
2.2.12.1.1. Typical Situations
The ducts shall be 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell-end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirements.
2.2.12.1.2. Unique/Site Specific Situations
The ducts shall be 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-80-PVC (Schedule 80) IAW NEMA TC-2; high density polyethylene (HDPE)
SIDR 13.5, Galvanized Iron Pipe (GIP) or “thickwall” stainless steel. Schedule 80 PVC shall be limited to risers, all above ground conduit and under the roadway/parking pavement. High density polyethylene (HDPE) SIDR 11.5 shall be used when directional boring is used. GIP or stainless steel shall be used under major roadways, taxiways, and runways. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell-end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Host Base/site specific requirement.
2.2.12.2. Installation
Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS
Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. In a MH with knockouts, ducts shall start at the bottom knockout, allowing for upward expansion in the
MH. All ducts not installed under roads, sidewalks, parking areas, or areas to be paved, etc. shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts shall be accomplished IAW RUS Bulletin 1751F-643. All conduits shall be continuous between MH/HHs (i.e., no breaks or separations in the conduit runs between MH/HHs).
2.2.12.3. Bends and Sealing
All bends between MHs shall be a minimum of ten times (10X) the diameter of the duct size
(i.e., 4 inch duct = 40 inches) with the sum of bends in all directions not exceeding a total of 90 degrees, where practical. Coordinate with 21 CS/SCXP if runs have bends that total more than
90 degrees is required. Ducts shall have bell-ends and enter a MH perpendicular to the surface of the wall through which it is entering. All ducts/inner-ducts entering MH shall be sealed.
Universal duct plugs or removable putty sealants may be used. Upon completion of conduit sections, a rigid 12” long test mandrel ¼” (6.4mm) smaller than the inside diameter of the conduit shall be pulled through two diagonally opposite ducts to ensure proper alignment. In addition, all ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.
2.2.12.4. Utility Separation
When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well-tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.
2.2.12.5. Spacers and Tracer Wire
Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at five (5) foot intervals and cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route. The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message. At least one duct shall have tracer wire or be otherwise locatable from the surface.
2.2.12.6. Entrance Conduits into Existing Maintenance Holes
When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if a knockout does not exist. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the maintenance hole floor or ceiling, if practical. The minimum bending radius for entry conduit/ducts shall be no less than 10 times the inside diameter of the conduit. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.
2.2.12.7. Excavation/Building Penetrations
All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.
2.2.13. Outside Plant Installation
This section describes the underground cables, flexible geotextile multiple cell fabric, innerduct and MH/HH plus conduit system installation requirements. The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in accordance with
ANSI/TIA-758-A. Each cable installation shall be coordinated with 21 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the
Contractor’s discretion.
2.2.13.1. Infrastructure Installation
The Contractor shall install the following new infrastructure; 2-4” conduits approximately 1555 feet, three 3 X 3” Geo-textile fabrics approximately 5465 feet, two 3 X 3” Geo-textile fabrics approximately 280 feet, one (1) 144 ports Fiber Optic Distribution Panel (FODP), three (3) 36 ports FODP and one 19” relay rack (coordinate exact location with 21 CS/SCXP).
2.2.13.1.1. Hand Holes (N/A)
2.2.13.1.2. Ductbank Infrastructure
Install 4” PVC and/or HDPE SIDR 11.5 duct banks IAW the following Table:
From
Maintenance
Hole/Bldg.
To
Maintenance
Hole/Bldg.
Quantity Size
(inches)
Approx.
Distance
(Feet)
Figure Comment
MH-22A B863 2 4 205 1 35’ of HDPE SIDR 11.5 will be installed underneath the roadway, 90’ concrete encased in the grass area, and 80’ of schedule 80 in the parking lot.
B1038 MH-100 2 4 115 2 70’ of HDPE SIDR 11.5 will be installed underneath the roadway and 45’ concrete encased.
MH-100 MH-101 2 4 540 2 40’ of HDPE SIDR 11.5 will be installed underneath the roadway and
500’ concrete encased.
MH-101 MH-102 2 4 580 2 110’ of HDPE SIDR 11.5 will be installed underneath the roadway, 30’ schedule 80 under the driveway, and
440’ concrete encased.
MH-119 B2025 2 4 115 4 115’ concrete encased from the manhole to the building.
2.2.13.1.3. Geo-textile Fabric (or Innerduct) Installation
Install Geo-textile fabrics IAW the following Table:
From Maintenance
Hole/Building
To Maintenance
Hole/Building
Quantity Approx.
Distance
(Feet)
Figure Comment
MH-75 B1038 3 70 1 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the vacant 4” conduits.
MH-75 MH-130 3 200 1 Install three-3x3” Geo-textile fabrics (one is detectable type) in the vacant conduit.
MH-130A MH-130B 3 275 1 Install three-3x3” Geo-textile fabrics (one is detectable type) in the vacant conduit.
MH-130B MH-22A 3 375 1 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the three vacant conduits.
MH-22A B863 3 205 1 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the two new vacant 4” conduits.
B1038 MH-100 3 115 2 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the two new vacant 4” conduits.
MH-100 MH-101 3 540 2 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the two new vacant 4” conduits.
MH-101 MH-102 3 580 2 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the two new vacant 4” conduits.
MH-113 MH-114 2 280 3 Install two-3x3” Geo-textile fabrics (one is detectable type) using the 2 vacant innerducts to pull through.
MH-139 Through MH-140, MH-
141, MH-142, MH-143
to MH-119
3 2990 3,4 Install three-3x3” Geo-textile fabrics (one is detectable type) in the vacant conduit.
MH-119 B2025 3 115 4 Install three-3x3” Geo-textile fabrics (one is detectable type) in one of the two new vacant 4” conduits.
2.2.13.2. Fiber Optic Cable Installation
Install outside plant FOC as described in the following paragraphs. The cable shall be all dielectric, loose buffer tube, water blocked, single mode, outside plant (OSP) cable suitable for underground applications. The Contractor shall coordinate each cable installation with the 21
CS/SCXP so as to minimize the impact on building users. The intent is to install the cable in one continuous length, to the extent that it is practical. The Contractor shall determine whether or not there is some practical reason for an intermediate splice in the cable at some maintenance hole/hand hole between the cable end points. If an underground splice is necessary, it shall be accomplished IAW commonly accepted telecommunications industry practices for fusion splicing optical fiber cable and sealed with a splice case suitable for the application. If a splice case is installed in a maintenance hole/hand hole it shall be pressure tested IAW the manufacturer’s instructions. If a splice case leaks, it shall be reinstalled and retested. A coil of
50 feet of cable shall be provided on each cable entering or leaving a splice case in a maintenance hole or hand hole.
2.2.13.2.1.1. Fiber Optic Cable Between ITB 1038 and ITB 2025
The Contractor shall install approximately 12065 feet of 36 strands SM FOC from ITB 1038 through MH-100, MH-101, MH-102, MH-103, MH-104, MH-105, MH-106, MH-107, MH-108, MH-109, MH-110, MH-111, MH-112, MH-113, MH-114, MH-139, MH-140, MH-141, MH-
142, MH-143, MH-119, to ITB 2025.
2.2.13.2.2. ITB 1038
The Contractor shall install one (1) new rack and one (1) 144-port Fiber Optic Distribution Panel
(FODP) on a new rack in the Comm. room of ITB 1038. Terminate the 36 strand SM FOCs to the FODP using fusion splice to pigtails with SC type connectors. Verify the locations of the new equipment rack and the FODP with 21 CS/SCXP.
2.2.13.2.3. ITB 2025
The Contractor shall install one (1) 36-port Fiber Optic Distribution Panel (FODP) on existing rack in the Comm. room of ITB 2025. Terminate the 36 strand SM FOCs to the FODPs using fusion splice to pigtails with SC type connectors. Verify the locations of the equipment rack and the FODPs with 21 CS/SCXP.
2.2.13.2.3.1. Fiber Optic Cable Between ITB 1038 and EB 920
The Contractor shall install approximately 630 feet of 36 strands SM FOC from ITB 1038 through MH-75, MH-130 to EB 920.
2.2.13.2.4. EB 920
The Contractor shall install one (1) 36-port Fiber Optic Distribution Panel (FODP) on existing rack in the Comm. room of EB 920. Terminate one end of the 36 strand SM FOC to the 36-port
FODP in EB 920 and the other end of the 36 strand SM FOC to the 144-port FODP in ITB 1038 using fusion splice to pigtails with SC type connectors. Verify the locations of the equipment rack and the FODP with 21 CS/SCXP.
2.2.13.2.4.1. Fiber Optic Cable Between ITB 1038 and EB 863
The Contractor shall install approximately 1390 feet of 36 strands SM FOC from ITB 1038 through MH-75, MH-130, MH-130A, MH-130B, and MH-22A to EB 863.
2.2.13.2.5. EB 863
The Contractor shall install one (1) 36-port Fiber Optic Distribution Panel (FODP) on existing rack in the Comm. room of EB 863. Terminate one end of the 36 strand SM FOC to the 36-port
FODP in EB 863 and the other end of the 36 strand SM FOC to the 144-port FODP in ITB 1038 using fusion splice to pigtails with SC type connectors. Verify the locations of the equipment rack and the FODP with 21 CS/SCXP.
2.2.14. Site Restoration/Debris Removal
The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. Base grounds restoration requirements shall be complied with. Common use areas shall be restored to their original condition. The Contractor shall be responsible for disposing of all residues from this project off base and in accordance with Federal, state and base environmental laws and regulations. All residue produced by directional drilling operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal, state, local and Peterson AFB environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on Peterson AFB.
2.2.15. Service Outages
The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, interruptions of communications capabilities that are properly identified. The Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
2.2.16. Identification/Marking
The Contractor shall clearly mark all Contractor-Furnished Property and Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign
(minimum 8.5 inches x 11 inches) on large containers, construction equipment, or un-manned rental vehicles while on the Government installation indicating the company name and both the
Contractor and Site POC's names and local telephone numbers.
2.2.17. Installation Schedules
The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub-projects associated with the installation of the components and system.
2.2.18. Weekly Status Reports
The Contractor shall prepare a Weekly Status Report in English and shall distribute. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.
2.2.19. As-Built Drawings
The Contractor shall submit red line drawings showing the “as-built” configuration in format specified by base SCX project manager. The base communications squadron will provide baseline drawings. The Contractor shall provide As-Built Rack Elevation, Inside Cable Plant and Outside Cable Plant drawings and distribute.
2.2.20. Test and Acceptance/Installation Test Plan
The Contractor shall provide a test plan as to how the system shall be pre-tested, in-progress-tested and post-tested to demonstrate to the Government that the system is fully operational ready to be placed into service. The Contractor shall test the system to demonstrate to the
Government quality assurance representative. These tests shall be accomplished prior to the system being placed into service.
2.2.21. Acceptance/Installation Test Report
The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan.
2.2.22. Final Acceptance
The Contractor shall schedule a final project walk-through with the 21 CS/SCXP. This should be scheduled 10 calendar days prior to acceptance.
2.2.23. As-Built Documentation in CVC
The Contractor shall record geospatial data and provide as-built documentation (shape files) of all new installed hand hole system components (including metadata) compatible with the
Cyberspace Infrastructure Planning System (CIPS) Visualization Component (CVC) drawing system. Data points shall be recorded at the center of each manhole/hand hole lid and at intervals not to exceed 25 feet along cable routes. Sufficient data points shall be recorded to capture any change in direction along the route. All GPS coordinates shall have +/- 3 feet accuracy for all readings. The government is responsible for providing the Contractor with a copy of the installation’s most current GeoBase Common Installation Picture (CIP), and current
CVC drawings of the areas of interest. The government will review the shape files in CVC and transcribe the information to the CVC system. Shape files shall be delivered upon project completion.
3. GENERAL INFORMATION
3.1. Period of Performance
The period of performance for the project shall be determined based on the proposed schedule and actual contract award date.
3.2. Place of Performance
The place of performance is from Information Transfer Building (ITB) 1038 to ITB 2025, End
Building (EB) 920, and to EB 863
3.3. Hours of Operation
The Contractor shall routinely work during normal duty hours (0730 – 1630 MST) of the site.
However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the
Contractor to be performed outside normal duty hours shall be coordinated with the 21
CS/SCXP and approved by the Contracting Officer Representative (COR) at least 10 calendar days in advance.
3.4. Holidays/Down Days
The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the COR and coordinated with the 21 CS/SCXP Project
Manager/or COR. These dates are as follows:
New Year’s Day, Martin Luther King Jr’s Birthday, President’s Day, Memorial Day, Independence
Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, or Christmas Day.
3.5. Base Support
The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.
3.6. Minimum Contractor Qualifications.
All work shall be performed by an experienced Telecommunications Contractor. The Contractor shall have a minimum of 3 years of experience in Telecommunications Systems installations.
APPENDIX A: APPLICABLE STANDARDS
The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards
AFI 91-203 – Air Force Consolidated Occupational Safety Instruction
OSHA CFR 29 Part 1910-268 – Telecommunications
NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit
ANSI/TIA-606-B Administration Standard for Telecommunications Infrastructure
TIA-568-C Commercial Building Telecommunications (568C.1, 568C.2, 568C.3) Cabling
Standard
ANSI/TIA-607-B Commercial Building Grounding (Earthing) and Bonding Requirements for
Telecommunications
TIA-569-C - Commercial Building Standard for Telecommunications Pathways and Spaces
TIA-570-C –Residential Telecommunications Infrastructure Standard
TIA-758 B - Customer-owned Outside Plant Telecommunication Infrastructure Standard
BICSI TDM Manual - Building Industries Consulting Services International
Telecommunications Distribution Methods (TDM) Manual
BICSI – Outside Plan Design Reference Manual
RUS Bulletin 1751F-643 - Underground Plant Design
RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications Engineering
Shield Continuity and Construction Manual (TE&CM) 451.2
RUS Bulletin 1751F-801 – Electrical Protection Fundamentals
RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable
Installation
NFPA 70 - National Electric Code
FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National Standard for Spatial Data Accuracy
Unified Facilities Criteria 3-260-01
APPENDIX B: DELIVERABLES
All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this SOO. All deliverables shall be produced using recommended software tools/versions as accepted by the Government.
APPENDIX C: LIST OF ACRONYMS
AASHTO American Association of State Highway and Transportation Officials
AFM Airfield Management (BaseOPS)
Approx Approximately
ATC Air Traffic Control Tower
ATCALS Air Traffic Control and Landing Systems
BCE Base Civil Engineering
CDRL Contract Deliverable
CFE Contractor-Furnished Equipment
CFP Contractor-Furnished Property
CIP Common Installation Picture
CIPS Cyberspace Infrastructure Planning System
CMA Controlled Movement Area
CMHDS Communications Maintenance Hole Duct System
CO Contracting Officer
Comm Communications
CS Communications Squadron
CSI-B Cyberspace Integrator-Base
CVC CIPS Visualization Component
ECMRA Contractor Manpower Reporting Application
EFI&T Engineer, Furnish, Install and Test
FOC Fiber Optic Cable
FODP Fiber Optic Distribution Panels
FOUO For Official Use Only
FY Fiscal Year
HDPE High Density Polyethylene
HH Hand Hole
IAW In Accordance With
ID Inside Diameter
ILS Instrument Landing System
IPT Integrated Process Team
LMR Land Mobile Radio
MH Maintenance Hole
MHDS Maintenance Hole Duct System
NLT No Later Than
NPDES National Pollution Discharge Elimination System
OEM Original Equipment Manufacturer
OPSEC Operational Security
OSHA Occupational Safety & Health Administration
OSP Outside Plant
OSS Operations Support Squadron
OTDR Optical Time Domain Reflectometer
PDF Portable Document Format
PM Project Manager
POC Point Of Contact
Prime Prime Contractor
PSI Pounds per Square Inch
PVC Polyvinyl Chloride
QAE Quality Assurance Evaluator
QCM Quality Control Manager
Qty Quantity
RUS Rural Utilities Service Bulletin
SCOW Supply Chain Operations Wing
SCX Scheduler Planner
SE System Engineer
SM Single Mode
SOO Statement of Objectives
Sub Sub-Contractor
SWPPP Storm Water Pollution Prevention Plan
TIA Telecommunications Industry Association
TMGB Telecommunication Main Ground Bus-Bar
TRD Technical Requirements Document
APPENDIX D: DRAWINGS
Figure 1: Fiber Optic Cable Route from B1038 to B920 and B863.
Figure 2: Fiber Optic Cable Route from B1038 to B2025.
Figure 3: Fiber Optic Cable Route from B1038 to B2025.
Figure 4: Fiber Optic Cable Route from B1038 to B2025.
File details come from the government source that posted it. Updated .