Draft PWS_ RTLS Remediation.pdf

PDF 174 KB Posted

Attached to
J035--Real-Time Location System (RTLS) Remediation MEDVAMC
Solicitation number
36C25626Q0904
Issued by

About this file

This is a Performance Work Statement (PWS) for Real-Time Location System (RTLS) remediation services at Michael E. DeBakey VA Medical Center.

The contractor must provide full restoration, installation, and configuration of IT infrastructure across the hospital's main campus to support clinical operations, administrative functions, and security systems. Work encompasses replacement of network switches (core, distribution, and access), wireless access points and controllers, firewalls, routers, UPS devices, patch panels, structured cabling (Cat6/OM4), optical modules, racks, and server appliances. The contractor is responsible for developing engineered designs, conducting site surveys, and delivering as-built documentation. Hardware restoration requires OEM compliance, compatibility verification with existing topology and VA standards, and restoration of network closets (IDFs/MDFs) with proper cable management and labeling. Configuration work includes loading OEM-supported operating systems, applying VA-provided templates for VLANs and security baselines, integrating devices into monitoring tools (NMS, syslog, SIEM), and validating wireless provisioning. The contractor must develop a Validation Test Plan with minimum acceptance criteria including 100% hardware operational status, ≥98% port-level functionality pass rate, ≥95% wireless coverage, 100% cable certification compliance, and ≥99% infrastructure availability after 30-day stabilization. Specific RTLS hardware line items include one Low Frequency Exciter (ITDK-340), eight CenTrak 900 MHz Stars (ITK-103), 29 Multi-Mode IR/BLE Monitors (ITK-313L), and 138 Virtual Walls (ITK-323L), along with associated services for survey, design, installation, POE cable pulls, configuration, engineering review, project management, certification, testing, and user acceptance testing.

Performance standards require OEM-certified personnel with ≥2 years RTLS installation and maintenance experience, and compliance with NFPA-99, UL, OSHA, IEEE, JCAHO, and VA standards. Standard hours are Monday-Friday 8:00 AM–6:00 PM CST, excluding federal holidays. The contractor is liable for operational losses from system downtime caused by performance issues and must submit monthly or quarterly invoices in triplicate. All deliverables, data, and documentation are government property with unlimited use rights, and the contractor must comply with records management policies, Privacy Act requirements, and federal records preservation standards.

View the file

Other files

File Type Posted
36C25626Q0904.docx DOCX document
Sources Sought - RTLS Remediation - MEDVAMC.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Real-Time Location System (RTLS) Remediation at

Michael E. DeBakey VA Medical Center

Performance Work Statement (PWS)

I. GENERAL REQUIREMENT

The Michael E. DeBakey VA Medical Center requires full restoration, installation, and configuration of all missing or damaged information technology infrastructure devices necessary to support clinical operations, administrative functions, security systems, and enterprise network services across the main hospital campus. This project shall ensure that all infrastructure components including network switches, wireless access points, routers, firewalls, structured cabling, optics, rack equipment, and power protection systems are replaced, installed, configured, and validated in accordance with OEM specifications and VA technical standards. The work shall deliver fully operational, standards-compliant infrastructure capable of supporting required availability, performance, security, and interoperability across all dependent hospital systems.

II. DESCRIPTION OF WORK

The Contractor shall provide all labor, materials, equipment, tools, cabling, transportation, software, professional services, technical support, testing instruments, on-site and remote support, and travel necessary to install, configure, validate, and place into operation all infrastructure devices required to restore full functionality. The Contractor shall comply with all OEM hardware/software requirements and maintain authorized access to OEM tools, documentation, and configuration utilities. Completion shall be defined as full replacement, configuration, validation, documentation, and acceptance of all restored infrastructure systems.

A. Existing Infrastructure

The Michael E. DeBakey VA Medical Center operates an enterprise-class IT environment consisting of:

• Network switches (core, distribution, and access)

• Wireless access points and controllers

• Firewalls and security appliances

• Routers, gateways, and uplink equipment

• Copper and fiber cabling infrastructure

• Patch panels, jacks, termination blocks, and structured cabling pathways

• SFP/SFP+/QSFP optical modules

• Racks, rack components, UPS units, and PDUs

• Server appliances supporting management, telemetry, and syslog

The Contractor shall evaluate the current infrastructure condition; identify all missing, damaged, nonfunctional, or technically noncompliant devices; and implement the following actions:

1. Hardware Replacement and Restoration

a. Replace missing or damaged switches, access points, routers, firewalls, UPS devices, patch panels, and cabling components.

b. Install replacement devices following OEM spacing, airflow, grounding, and mounting requirements.

c. Verify compatibility with existing topology, addressing, VLANs, routes, security policies, wireless architecture, and VA enterprise standards.

d. Install optics, patch cords, and cabling necessary for full restoration of network paths.

e. Restore all network closets (IDFs/MDFs) to operational conditions, including cable management and labeling.

2. Configuration and Software Alignment:

a. Load OEM-supported operating systems and firmware.

b. Apply VA-provided configurations or templates, including VLANs, routing, wireless profiles, and security baselines.

c. Integrate devices into monitoring tools (NMS, syslog, SIEM).

d. Confirm successful authentication via RADIUS, Active Directory, or certificate-based access where applicable.

e. Validate wireless provisioning, including SSID broadcast, PoE allocation, and signal performance.

3. Structured Cabling Restoration

a. Identify damaged cables, improperly terminated connections, and mislabeled ports.

b. Replace damaged copper or fiber cabling with new Cat6 or OM4 cabling meeting TIA standards.

c. Re-terminate, test, and label cable connections to TIA-568 and TIA-606-B standards.

d. Produce cable certification reports for all replaced cable runs.

4. Testing and Acceptance

The Contractor shall develop a Validation Test Plan (VTP) covering connectivity, throughput, wireless coverage, security policy application, redundancy paths, and device telemetry. The following minimum acceptance criteria apply:

a. Network device operational status: 100% of replaced hardware fully online and reachable

b. Port-level functionality: ≥ 98% pass rate for data, PoE, and negotiated link speeds

c. Wireless testing: ≥ 95% coverage success in validated areas

d. Cable compliance: 100% pass rate on certification tests for replaced cable

e. Device uptime baseline: ≥ 99% infrastructure availability after 30-day stabilization

f. Documentation accuracy: 100% of devices labeled, mapped, and included in as-built package

The contractor shall submit full-as-built documentation, port maps, test results, rack elevations, network diagrams, and configuration backups.

B. Areas of Expansion

The Contractor shall expand infrastructure capacity where required to ensure operational reliability.

At minimum:

• Improve coverage and device availability at nurse stations, reception/waiting rooms, inpatient units, and additional patient-facing areas identified by the COR.

• Restore and reinforce infrastructure serving high-dependency departments, including the Inpatient

Mental Health (6th floor) and Emergency Department (1st floor).

• Confirm power redundancy, PoE capacity, and wireless saturation in all restored areas.

• Perform site-specific validation and provide location-specific as-builts for each closet and department.

C. Integrations

Where required, the Contractor shall integrate all restored infrastructure with supported VA systems including:

• Active Directory

• Network Access Control (NAC)

• Wireless controllers

• Firewall rule sets and logging systems

• SIEM/SOC monitoring platforms

• DHCP, DNS, NTP, and certificate services

The Contractor shall:

• Provide an integration plan detailing technical steps and dependencies

• Validate policy enforcement, authentication, and event logging

• Confirm failover behavior and redundancy

III. DESIGN/LINE ITEMS

As a Performance Work Statement, the Contractor is responsible for producing final engineered designs ensuring fully functional infrastructure at all designated locations.

The following line items are required to execute this scope:

Preliminary line items expected to complete this scope (final quantities to be confirmed via the

Contractor’s detailed design and site surveys). Any changes post-award require coordination among the

Contractor, Contracting Officer (CO), and the contractor Officer’s Representative (COR).

Part Number/Description Qty

Low Frequency Exciter - ITDK-340 1

CenTrak 900 MHz Stars - ITK-103, to replace existing 8

Monitors, Multi-Mode IR/BLE - ITK-313L 29

138 Virtual Walls, Multi-Mode IR/BLE - ITK-323L 138

Services Qty

Survey – Design – As Built 1

Install above listed hardware devices 1

POE Cable Pulls for Stars 8

Configuration of above listed hardware devices 176

Engineer Review 1

Project Management 1

Certification and Testing of above listed hardware devices 1

User Acceptance Testing 1

IV. CONFORMANCE STANDARDS:

A. The contractor shall ensure equipment and software operate in full compliance with OEM specifications, including all updates/patches.

B. Work shall conform to applicable Federal, State, and Local requirements, including but not limited to: AAMI, The Joint Commission (JCAHO), NFPA-99, CDRH, AHA, IEEE, UL, OSHA, CAP, and VAMC SOPs.

C. System performance shall comply with the latest editions of NFPA-99, UL, OSHA, VA, and

CDRH requirements.

V. HOURS OF COVERAGE

A. Standards hours of performance are Monday-Friday 8:00 AM – 6:00 PM CST, excluding federal holidays.

B. The Government observes Federal holidays: New Year’s Day, Martin Luther King Jr. Day, Presidents Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day, and any other day designated by Federal statute, Executive Order, or Presidential proclamation.

VI. CONTRACT DISCREPANCY REPORT (CDR) AND DAMAGES

A. The Contractor shall be liable for losses in operational capability resulting from significant system downtime caused by Contractor performance issues.

B. A CDR shall be issued for performance below Acceptable Quality Levels (AQL). The Contractor shall provide a corrective action plan within five (5) business days. Continued deficiencies will be reported to the CO.

C. The Contractor shall be liable for any damage to Government property caused by its personnel.

VII. PAYMENT

Invoices shall be submitted in arrears on a monthly or quarterly basis and shall include, at minimum:

Contract Number, Purchase Order Number, item(s) covered (including serial numbers where applicable), and service period. Each invoice shall be provided in triplicate.

VIII. COMPETENCY OF PERSONNEL SERVICE EQUIPMENT:

A. The Contractor shall maintain an established business with a staffed office and full-time personnel, including a primary and backup Field Service Engineer (FSE).

B. “Fully Qualified” personnel shall be OEM-certified by Centrak and possess ≥ 2 years of RTLS experience (installation, calibration, preventive and corrective maintenance).

C. All work shall be performed by OEM-authorized, fully qualified personnel. The Contractor shall provide credentials and proof of certification upon request. The Government reserves the right to reject personnel lacking proper certification or qualifications.

D. Any subcontractor(s) must be preapproved by the COR and submitted to the CO for approval prior to use.

IX. PRIVACY/SECURITY

The Contractor will require access to VA systems for software upgrades and maintenance, which may involve exposure to PHI (e.g., screenshots, databases). All electronic storage devices (e.g., hard drives) shall be turned into the Information System Security Officer (ISSO) upon replacement or repair and shall not be removed from VA property.

The following standard items relate to records generated in executing the contract and should be included in a typical Electronic Information Systems (EIS) procurement contract:

1. Citations to pertinent laws, codes and regulations such as 44 U.S.C chapters 21, 29, 31 and 33;

Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and

Part 1228.

2. Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.

3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.

4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the

Freedom of Information Act.

5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.

6. The Government Agency owns the rights to all data/records produced as part of this contract.

7. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.

8. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974.

These policies include the preservation of all records created or received regardless of format

[paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].

9. No disposition of documents will be allowed without the prior written consent of the Contracting

Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.

10. Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract.

The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.

Source: The National Archives Records Administration (NARA). http://www.archives.gov/records-mgmt/handbook/records-mgmt-language.html

(End of PWS) http://www.archives.gov/records-mgmt/handbook/records-mgmt-language.html http://www.archives.gov/records-mgmt/handbook/records-mgmt-language.html

File details come from the government source that posted it. Updated .