PERFORMANCE WORK STATEMENT

Title: Training Center Hampton Roads (TCHR) Fall Protection Tower Maintenance

1.0 SCOPE OF WORK:

The Contractor shall provide all personnel, certifications, supplies, transportation, supervision, and non-personal services necessary to perform preservation work, qualification work, and needed additions to TCHR’s Fall Protection Towers located at Fort Eustis Virginia. There are two steel (painted) towers with ladders and deck grating. One tower is 40’ tall. The second tower is 20’ tall.

2.0 References (all needed references will be obtained by vendor from appropriate source, MSC cannot provide)

2.1 American National Standards Institute (ANSI) Z359.6-2016 Specifications and Design Requirements for Active Fall Protection Systems (ASSP.org)

2.2 ANSI Z359.18-2017 Safety Requirements for Anchorage Connectors for Active Fall Protection Systems (ASSP.org)

2.3 Antenna Products Technical Manual for Safety Climbing Equipment (Free Download from antennas.com)

2.4 American institute for steel construction (AISC)

3.0SPECIFIC TASKS:
3.1The Contractor shall:
3.1.1Conduct work on one tower until completion. When one tower is complete, work on the second tower shall begin. One tower will be used to conduct training while the other is being worked on.
3.1.2Be certified to work on steel structures and follow industry guidelines for welds and structural tests. (AISC)
3.1.3Erect scaffolding and containment as necessary to complete all work.
3.1.4Remove all deck grating from the 40’ tower.
3.1.5Inspect deck grating for compromised areas and replace or repair as needed.
3.1.6Remove all ladder safety systems from both towers.
3.1.7Remove all ladders from both towers and inspect ladder rung welds. Re-weld any rungs not passing inspection.
3.1.8Remove all rust and old paint near rust areas from tower.
3.1.9Verify all welds using industry standard (AISC) and replace any compromised welds, steel, or bolts.
3.1.10Re-install deck grating, ladders and ladder safety systems.
3.1.11Install four (4) new engineered anchorages on 20’ tower. (See attached photos for position of anchorages and anchorage type)
3.1.12Tighten and mark all bolts.
3.1.13Weight test all Fall Protection anchorages to 5,000 lbs. in accordance with (2.2) ANSI Z359.18-2017
3.1.14Replace any anchorages not meeting the 5000 lb. requirement. (See photos for anchorage type) These anchorages can be welded or bolted on.
3.1.15Prepare and prime any areas where paint has been removed or bare metal is showing and paint entire 40’ tower gray.
3.1.16Prepare and prime any areas where paint has been removed or bare metal is showing and paint entire 20’ tower gray.
3.1.17Remove scaffolding, debris and trash.
3.1.18Provide reports for all tests and installed anchorages in accordance with ANSI Z359.
3.2The Contractor shall submit reports as follows:
3.2.1Email a maintenance report to TCHR Representative (TBD) within 14 days of job completion detailing all issues noticed and work completed.
3.2.2Email an invoice to TCHR Representative (TBD) and submit your invoice to WAWF within three days of completion of services. Invoice should state all work performed. Also, all charges should be clearly identified and explained.
3.3The contract personnel will be required to obtain and maintain a DD 1172-2 Common Access Card (CAC). The CAC is required for access to military installations.
4.0DELIVERABLES
4.1The Contractor shall:
4.1.1Email a maintenance report within 14 business days of service to TCHR Representative (Section 3.2.1).
4.1.2Email an invoice to TCHR Representative within three business days of service. (Section 3.2.2).
4.1.3Submit an invoice to WAWF within three days of completed service. (Section 3.2.2)
5.0DELIVERABLES SCHEDULE
Title
Due Date
Maintenance Report
14 days after completion of maintenance
Invoice to TCHR Rep
Three days after all services complete
Invoice to WAWF
Three days after all services complete

6.0 PERFORMANCE LOCATION:

Training Area 9, Fall Protection Tower, Schultz Place, Fort Eustis VA 23604

7.0 PERFORMANCE PERIOD:

The Period of Performance for this service will be from 1 July 2023 - UTC

8.0 TCHR Representative Contact Information:

TBA

20’ Tower showing anchorage 40’ Tower showing anchorage test positions test positions

20’ Tower – New anchorages shall be addedComment by Ellis, James P (Jim) JR CIV USN COMSC NORFOLK VA (USA): Missing picture?Comment by Kordyjak, William E CIV USN COMSC NORFOLK VA (USA): No
where the yellow straps are located

Example of anchorage point. Can be welded instead of bolted.

image4.jpeg image5.jpeg image1.jpeg image2.jpeg image3.jpeg

File details come from the government source that posted it. Updated .