This is a Performance Work Statement (PWS) for maintenance and repair services of vehicles and equipment at Air Force Wildland Fire Branch (AFWFB) installations throughout the Continental United States (CONUS). The contractor shall provide preventive maintenance (PM) inspections at minimum annually and corrective maintenance (CM) repair services on an as-needed basis for designated equipment and vehicles utilized at Wildland Support Modules (WSMs). The contractor must be ASE-certified, including specific certifications for heavy equipment mechanics, diesel engines, hydraulics, and electrical systems as applicable. The contractor is responsible for sourcing and providing all parts, fluids, tools, materials, supplies, transportation, supervision, and hazardous waste disposal necessary to maintain equipment to manufacturer specifications. PM services should be scheduled during WSM off-seasons aligned with normal business hours (Monday-Friday, 0700-1600), while emergency repair requests must receive a 24-hour response time. Corrective maintenance work must be completed within a maximum of 30 days depending on complexity.

The contract period consists of a base year plus four one-year option periods and a six-month extension period. The contractor must comply with all federal, state, and local regulations, obtain required licenses, permits, and insurance prior to commencing work, and meet all security requirements for installation access including background checks and Common Access Card (CAC) requirements where applicable. Deliverables include Preventive Maintenance Service Reports and Corrective Maintenance Service Reports, both submitted within 30 days of work completion to the Module Fire Management Officer, Assistant Fire Management Officer, and designated points of contact. Reports must document initial condition assessments, services performed, parts utilized, work time expended, total costs, and recommendations. The contractor must maintain original invoices and maintenance records available for Government audit upon request and shall not charge for unauthorized work.

View the file

Other files

File Type Posted
Attachment_B_-_Equipment_Inventory_1.xlsx XLSX spreadsheet
Attachment_C_-_Geographic_Locations_of_WS_Modules_1.docx DOCX document
Attachment_D_-_WSM_Off_Seasons_1.docx DOCX document
Attachment_A_-_AFWFB_Module_Locations_1.xlsx XLSX spreadsheet
AFWFB_Repair_and_Maintenance_RFI_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement

For

Maintenance and Repair of Vehicles and Equipment

At

Various Air Force Installations, CONUS

Air Force Civil Engineer Center (AFCEC) Wildland Fire Branch (WFB)

1.0 Introduction

This Performance Work Statement (PWS) provides the details of the services to be provided at various Air Force Installations throughout the Continuous United States (CONUS) in support of the Air Force Wildland Fire Branch (AFWFB).

2.0 Background

The primary mission of the Air Force’s Wildland Fire Management Program is to conduct prescribed fire and mechanical fuel reduction for the purposes of ecosystem management and hazardous fuels reduction on all lands managed by the Air Force, on its installations located in all states and territories, in accordance with all Federal environmental laws and regulations, including the Sikes Act. As such, the AFWFB utilizes various vehicles and equipment on a daily basis that must be maintained and/or repaired when necessary. Thus, it is necessary to provide ongoing preventative maintenance and corrective maintenance or repair services when required.

3.0 Objective

In carrying out work assignment(s) issued under this PWS, the Contractor shall provide for the servicing, maintenance, and repair, including minor and major repairs (e.g. overhaul, modification, or refurbishing), of designated equipment, vehicles, and associated items currently being utilized at our Wildland Support Modules (WSMs). See Attachment C for geographic locations. For this PWS, the Contractor can be the manufacturer or its approved vendor. The Contractor and its vendors shall be, at a minimum, ASE (Automotive Service Excellence) certified, including specific certifications for heavy equipment mechanics, as well as those covering diesel engines, hydraulics, and electrical systems, if applicable. The intention of this PWS is to obtain said services on an as needed basis. The Contractor shall perform such services at a time mutually agreed upon by the WSMs and Contractor. The Contractor must provide all management, supervision, labor, parts, material, tools, incidental engineering services, and transportation necessary to perform maintenance, repair, inspection, testing, and component replacement to keep equipment operating as originally specified by its manufacturer or modified with the approval of the Air Force.

For the purpose of this requirement, preventive maintenance (PM) is a proactive, scheduled approach designed to prevent equipment failure through routine inspections and applicable tasks. Corrective maintenance (CM) is reactive, repairing equipment after it breaks down, including major repairs. Generally, the objective of PM is to maximize the life of the equipment and reduce downtime while CM’s goal is to restore functionality.

4.0 Scope

The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, and non-personal services necessary to perform PM and repair services (CM), including disposal of hazmat (i.e. oils, lubricants, sealants, etc.). The Contractor shall make requested purchases needed to perform the periodic/impromptu corrective maintenance or repair of equipment. Additionally, the Contractor, without additional expense to the Government, must obtain all licenses, permits, and insurance required to perform the work in this PWS, if necessary. The Contractor must comply with all applicable federal, state, and local laws. If necessary, evidence of insurance, licenses, and permits must be provided to the Contracting Officer prior to commencing work. Final approval of estimates/repairs is needed by the COR.

4.1 Inspection and Scheduled Preventive Maintenance:

The Contractor shall provide periodic PM inspections as defined by equipment specifications, for at a minimum annually, with an option to request service visits for unexpected maintenance request and PM service support to ensure proper and serviceable operation of equipment. All PM services times and schedule would best be aligned during the AFWFB Module “off seasons” (see Attachment D). The contractor shall stay in accordance with original equipment manufacturer (OEM) guidance and approved industry/commercial practices and standards. The Government will provide uninterrupted access to vehicles or equipment that is maintained. If the Contractor cannot complete this task on the installation, the Government may be able to ship equipment to the contractor’s facility. However, prior notice (30 days minimum) will need to be provided.

The Contractor shall source/provide any parts and fluids necessary for scheduled PM, and perform any repairs, replacement and/or modifications necessary to return the equipment to fully serviceable/operational capability.

Any additional repairs/parts needed not specified in scheduled PM shall be immediately reported to the authorized personnel of the serviced WSM. Authorization to proceed must be provided prior to beginning work or ordering parts. See section 4.2.

The Contractor shall provide maintenance service reports to the CO/COR of all PM services performed a maximum of 30 days after completion (See section 7.1).

4.2 Repair and Unscheduled Corrective Maintenance:

The Contractor shall source/provide any parts and fluids necessary for repair, and perform any repairs, replacement and/or modifications necessary to return the equipment to fully serviceable/operational capability. The Government will provide uninterrupted access to vehicles or equipment that is maintained. If the Contractor cannot complete this task on the installation, the Government may be able to ship equipment to the contractor’s facility. However, prior notice (30 days minimum) will need to be provided.

Any repairs/parts needed and not specified in scheduled maintenance shall be reported to the COR with a written estimate to include all elements (labor hours, parts, consumables, etc.) to complete the repair and return the equipment to fully serviceable/operational capability. Depending on complexity of repairs, completion of CM/repair and return of equipment is expected to be within a maximum of 30 days.

The Contractor shall respond to any request for emergency repairs/CM within 24 hours of receiving said request. Repair services shall be performed at a time mutually agreed upon by authorized personnel of the serviced WSM and Contractor.

The Contractor shall provide maintenance service reports to the CO/COR of all PM services performed a maximum of 30 days after completion (See section 7.2).

5.0 Hazardous Materials/Waste

During maintenance and repair on Air Force (AF) property, the Contractor shall be responsible for complying with all federal, state, and local regulations regarding hazardous materials (HAZMAT) and hazardous waste (HAZWASTE) if any, as outlined in AFI 90-821 Sections 1.2.1.2, 1.2.1.3 . The Contractor shall be responsible for the safe handling, storage, and proper disposal of hazardous materials they bring onto and/or leave with the installation, including maintaining Material Safety Data Sheets (MSDS) and complying with OSHA regulations (29 CFR 1910.1200). Additionally, the Contractor shall properly dispose of all hazardous materials (i.e. petroleum, oils, lubricants, sealants, etc.) derived as a result of maintenance and/or repair of equipment and engines. Upon completing any work, the Contractor shall leave the area clean, neat, and orderly.

6.0 Place of Performance and Hours of Operations:

Place of performance for services shall be performed at Government owned facilities as specified in Attachment A - AFWFB Module Locations and Attachment C – Geographic Locations. Normal working/business hours will be Monday to Friday 0700-1600, except federal holidays. All PM services times and schedule would best be aligned during the AFWFB Module “off seasons” (see Attachment D).

6.1 Period of Performance

Duration of this task is for a base year, plus four one-year option periods, and a six-month extension period in accordance with FAR 52.217-8, if necessary. The Government reserves the right to modify the contract at each option year if new equipment must be added.

Additionally, the Contractor, without additional expense to the Government, must obtain all licenses, permits, and insurance required to perform the work in this PWS, if necessary. The Contractor must comply with all applicable federal, state, and local laws. If necessary, evidence of insurance, licenses, and permits must be provided to the Contracting Officer prior to commencing work.

6.2 Contracting Officer’s Representative (COR) Designation

Before task order award, the Contracting Officer will appoint a COR and issue a COR Designation Letter stating the authority of the COR. The Contractor will receive a copy of the written designation.

6.3 Government Furnished Property (GFP) and Responsibilities

The Government will provide only the vehicles, equipment, and information delineated in the PWS at Attachment B - Equipment Inventory, described herein as GFP. GFP consists of equipment and information. The Government will not source any parts, materials, tools, or any associated items related to maintenance or repair. Acquisition of such items will be the responsibility of the Contractor.

6.4 Personnel

IAW 18 United States Code (USC) § 1382, the authority of any officer of person in charge in command or charge thereof to control and deny an employee entry to all. or part of the installation is absolute. If an employee is removed from the job site or dismissed from the premises, the Contractor is not relived of the requirement to provide sufficient personnel to perform the services required by the PWS. The individual removed or denied has no right to appeal.

All personnel shall be able to read, write, speak, and comprehend the English language. The Contractor shall provide a workforce posing the skills, knowledge, and training to satisfactorily perform the services required by this contract. Personnel performing work under this PWS shall not be considered employees of the Government.

All contractor/subcontractor personnel shall be required to wear company picture identification badges to distinguish themselves from Government employees.

6.5 Installation Access Passes and Badges

The Contractor must be able to pass all security requirements, including background checks, IAW the installation Security Forces (SFS) Policy to gain access to the installation when work is required on the installation. The Contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, USAF, and/or local policy.

The Contractor shall verify that identification credentials presented by all contractor and subcontractor employees to obtain security badges, passes, cards, or decals used during the duration of this contract are current and correct. As a minimum, verification should be conducted with the Social Security Administration (http://www.ssa.gov/employer/ssnv.htm), the Federal Bureau of Investigation (FBI) Criminal Justice Information Services, Identification & Investigative Services Section (304-635-5590), and Form I-9 Employment Eligibility Verification (http://www.uscis.gov/portal/site/uscis). The contractor shall monitor its employees to ensure all information remains current and to ensure all security badges or passes are returned to the installation POC upon expiration of the badge, upon completion of the project, or when possession of the badge is no longer authorized (e.g., upon removal of contracted personnel from specific projects).

The Contractor shall obtain installation identification and vehicle passes for contractor and subcontractor personnel, as appropriate, in accordance with AFFARS 5352.242-9000, Contractor Access to Air Force Installations. The Contractor shall maintain a list of approved personnel for each project location and shall monitor access passes for the duration of this contract. Requirements for Common Access Cards (CACs) will be specified at the call order level, if appropriate. The Contractor shall comply with AFFARS 5352.242-9001 to obtain CACs for applicable contract and subcontract personnel.

7.0 Deliverables

Deliverable/Paragraph Reference
Transmittal Form and Quantity
Schedule
Delivery To
Preventative Maintenance Service Report (MSR)
Contractor Format/Email; Quantity: as many as necessary
Within 30 days of work completion
Module Fire Mgmt Officer (FMO) and Assistant Fire Mgmt Officer (AFMO), T. Cooper, B. Higbee
MSR Addendum – Multipoint Inspection
Contractor Format/Email; Quantity: as many as necessary
Within 30 days of work completion
FMO, AFMO, T. Cooper, B. Higbee
Corrective Maintenance Service Report (CSR)
Contractor Format/Email; Quantity: as many as necessary
Within 30 days of work completion
FMO, AFMO, T. Cooper, B. Higbee

7.1 Preventive Maintenance Service Report (MSR)

The preventative MSR should include an initial condition assessment, the dates and type service performed, parts acquired/utilized, work time expended, total costs required, and general description of services performed and any other relevant information such as recommendations. As an addendum to the report, it shall include a multi-point inspection consisting of a comprehensive safety check of the vehicle or equipment’s major systems including fluids, tires, brakes, battery, filters, lights, belts, hoses, and other items critical to its function. The inspection should include information and/or recommendations of each item’s current status and/or future maintenance.

The Government will not pay for unauthorized charges. Original invoices shall be maintained by contractor, detailing work completed. The contractor must be able to provide maintenance records upon request from the Government to support charges when made available to Government auditors upon request.

7.2 Corrective Maintenance Service Report (CSR)

The CSR shall include an initial condition assessment, the date of unscheduled CM/repair performed, parts acquired/utilized, work time expended, total costs required, and general description of services performed and any other relevant information such as recommendations. The Government will not pay for unauthorized charges. Original invoices shall be maintained by the Contractor, detailing repairs completed. The Contractor must be able to provide corrective maintenance records upon request from the Government to support charges when made available to Government auditors upon request.

7.3 Problem Resolution

The Contractor shall bring problems, or potential issues, affecting performance to the attention of the COR and Contracting Officer as soon as possible. Verbal reports will be followed up with written reports when directed. This notification shall not relieve the Contractor of its responsibility to correct problems for which they are responsible. The Contractor will work cooperatively with the Government to resolve issues as they arise.

7.4 Attachments:

· Attachment A – WSM POC List and Locations

· Attachment B - Equipment Inventory

· Attachment C – Geographic Locations of WSMs

· Attachment D – WSM Off Seasons