DRAFT HRMC-022-23_Redacted.pdf

PDF 2 MB Posted

Attached to
Rigid Hull Inflatable Boats (RHIBs) Repair
Solicitation number
N32253-23-Q-0016
Issued by

About this file

This pre-solicitation notice announces an upcoming request for quote for repair services on rigid hull inflatable boats. The Navy intends to issue solicitation N32253-23-Q-0016 for repairs to be completed at the contractor's facility between February and July 2023. The requirement is set aside for small businesses with a NAICS code of 336611 and size standard of 1,250 employees. Questions are due by February 6th and offers shall be submitted in accordance with the forthcoming solicitation. A ship check is available on January 31st and RSVPs are requested by January 30th. The draft work package HRMC-022-23 is provided as an appendix with technical details regarding the required repairs.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

SHIP: ITEM NO: 077-11-001

COAR: 26 PCN: SERV-L101

SERV-L102

CMP: NONE

SSP: HRMC-022-23 1 of 4 ITEM NO: 077-11-001

1. SCOPE:

1.1 Title: Hazardous Waste Produced on Naval Vessels; control

1.2 Location of Work:

1.2.1 Throughout the Ship

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Resource Conservation and Recovery Act (RCRA)

2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act

2.3 Applicable Hazardous Waste Manifest Form

2.4 10 U.S.C. 7311

3. REQUIREMENTS:

3.1 Manage and dispose of all hazardous waste listed in 3.5 in accordance with 2.1 and 2.2.

3.1.1 When a Navy generator number is required by this Work Item, submit the original of 2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.

3.1.2 Manage and transport for Navy disposal, Navy-generated

hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.

3.1.3 Submit one legible copy of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.

3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.

3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor shall notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor shall use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.

3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy shall notify the contractor within three business days of receipt of notification by the state. The contractor shall dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.

SHIP:

SSP: HRMC-022-23 2 of 4 ITEM NO: 077-11-001

3.5 Hazardous waste, as identified in 2.1, expected to be produced during performance of this Job Order:

AMOUNT

TYPE NAVY CO-GENERATED CONTRACTOR

Acid Solutions (may include _____ ____________ __________ spent sulfamic, citric, chromic, nitric, sulfuric, hydrochloric, etc.)

Ethylene Glycol (Antifreeze) _____ ____________ __________

Sodium Hydroxide _____ ____________ __________

Cleaning Solvents _____ ____________

Sodium Phosphates (Tri, Bi, _____ ____________ or Mono)

Fluorocarbons _____ ____________ __________

Morpholine _____ ____________ __________

Sodium Chromates _____ ____________ __________

Hydrazine _____ ____________ __________

Methyl Ethyl Ketone _____ ____________ __________

Spent Abrasive Blast Material _____ ____________ __________

(contaminated with a known hazardous waste)

Trichloroethane _____ ____________ __________

Miscellaneous Chemicals _____ ____________ __________

(Ignitable)

Miscellaneous Chemicals _____ ____________

(Corrosive)

Miscellaneous Chemicals _____ ____________ __________

(TCLP Toxic)

Miscellaneous Chemicals _____ ____________ __________

(Reactive)

Oil (Synthetic) _____ ____________ __________

Paints (Enamel, Latex, _____ ____________ __________

Epoxy, thinners, oil based, rubber paint, nonskid, lacquer, remover, varnishes)

Paints (May include lead, _____ ____________ __________ cadmium, or chrome)

SSP: HRMC-022-23 4 of 4 ITEM NO: 077-11-001 are not estimates of the amount of the work involved in generating that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.

4.2 Hazardous wastes are determined by one or more of the following methods:

4.2.1 Chemical analysis which shows that the material

characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.

4.2.2 Reference to a Material Safety Data Sheet (MSDS).

4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.

4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated shall be included in 3.5.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

1. None.

SHIP: ITEM NO: 236-11-001

COAR: 26 PCN: SERV-L100

SERV-L099

SSP: HRMC-022-23 1 of 7 ITEM NO: 236-11-001

1.1 Title: Outboard Engines; replace

1.2 Location of Work:

1.2.1 Throughout Vessel

1.3 Identification:

1.3.1 Quantity (one EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1407

1.3.2 Quantity (one EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1408

2. REFERENCES:

2.1 Standard Items, (FY-24)

2.2 300-5107858 Rev A, Standard Electrical Installation Requirements and Nomenclature

2.3 MIL-STD-2003, Electric Plant Installation Standard Methods for Surface Ships and Submarines

2.4 TO300-AU-SPN-010 Rev A, Fabrication, Welding, and Inspection of Small Boats and Craft, Aluminum Hulls

2.5 Evinrude E-Tech, BRP Service Manual

2.6 11X42-DI-CC-01 Rev A, 11X AM Series Drawing Index

2.7 11X42-OB-CC-01 Rev A, Outboard Plan and Profile

2.8 11X42-HS-CC-01 Rev A, Structure Arrangement

2.9 11X42-CA-CC-01 Rev A, Console Electronics Arrangement

2.10 11X42-CO-CC-01 Rev A, Collar System Plan View

2.11 11X42-E-CC-01 Rev A, Electrical Systems

2.12 11X42-AS-CC-01 Rev A, Auxiliary Systems

2.13 11X42-F-CC-01, Fuel System

2.14 11X42-H-CC-01 Rev A, Hoisting Arrangement

2.15 11X42-D-CC-01 Rev A, Miscellaneous Parts

2.16 Ignition Switch, Wiring

2.17 Fuel Tank, Cap

2.18 Suzuki Engine Manual, K13-DF250AP-300AP-99011-98J20-03BEN

2.19 Console Face, Layout

2.20 Systems and Specifications, SSPC Painting Manual, Volume 2

2.21 DOL, OSHA STD 29 CFR 1915, Occupational Safety and Health Standards for Shipyard Employment

SSP: HRMC-022-23 2 of 7 ITEM NO: 236-11-001

3. REQUIREMENTS:

3.1 All removed fasteners shall be replaced with new corrosion resistant steel (CRES), ASTM A276, Type 316 fasteners, unless otherwise specified.

All nuts shall be self-locking type, unless otherwise specified. One CRES washer shall be used under each bolt head and under each nut. Bolt/stud length shall not exceed less than 1-1/2 threads or more than 5 threads beyond the nut with full thread engagement for each vessel listed in 1.3.

3.1.1 Apply anti-seize compound, Loctite 34026 marine grade anti-seize or equal to all stainless-steel threaded fasteners.

3.2 All equipment mounted to aluminum shall have corrosion protection tape (3M Scotchrap #51) installed between the mating surfaces unless otherwise noted for each vessel listed in 1.3.

3.3 Accomplish an operational test and inspection of each existing engine for the vessels identified in 1.3 prior to removal. An authorized Evinrude technician shall perform diagnostic testing and resolve any service codes in accordance with 2.5.

3.3.1 Accomplish an operational and technical inspection of each engine and identify any additional items recommended for repair or replacement. Repair or replacement items include, but are not limited to propellers, knobs, handles, switches, cylinders, valves, pumps, bearings and gears, etc.

3.3.2 The operational and technical inspection shall be performed to sufficiently determine additional items needing repair or replacement not covered in paragraphs 3.3.3 to 3.3.18 in order to return the unit to a reliable, operational condition that meets OEM specifications.

3.3.3 Accomplish 500 hour maintenance in accordance with OEM

Inspection and maintenance schedule.

3.3.4 Inspect the engine mounted wiring harness and connections for damage and corrosion.

3.3.5 Verify starter output voltage is 55 volts as per OEM

specifications.

3.3.6 Accomplish an Engine Management Module (EMM) function test.

3.3.7 Accomplish engine cylinder dry and wet compression tests.

3.3.8 Accomplish engine cylinder leak down test.

3.3.9 Accomplish an inspection of the reed block.

3.3.10 Remove existing engine zinc anodes and install with new engine zinc anodes.

3.3.11 Open and inspect the lower unit internal components, order and replace all wearable/broken items to include gaskets/seals and any rotating or sliding component showing signs of excessive wear or damage.

3.3.12 Remove existing water pump, thermostat and thermostat gasket from the engine cooling system and install new cooling system water pump, thermostat and thermostat gasket.

3.3.13 Remove existing engine water inlet screens and install new high flow water inlet screens part number 5010501.

3.3.14 Accomplish a pressure and vacuum test of the gear case.

SSP: HRMC-022-23 3 of 7 ITEM NO: 236-11-001

3.3.15 Remove existing engine gear case oil and plug gasket and install new gear case oil and plug gasket.

3.3.16 Accomplish Trim and Tilt system service in accordance with procedures starting on page 323 of 2.5 BRP Service Manual to include replacing filters and O-rings.

3.3.17 Ensure all existing Evinrude engine mounting brackets, wiring, hoses and assemblies are removed prior to installation of new port and starboard Suzuki engines for each vessel listed in 1.3.

3.3.18 Remove existing Evinrude remote oil tanks, oil level

converter kits and senders, system hoses, associated fittings, hose clamps, and engine oil in the remote tanks for each vessel listed in 1.3.

3.3.19 Ensure overhauled Evinrude engines are placed in long term storage in accordance with manufacturer’s recommendations. Place each engine in a crate suitable for long term storage and deliver to LOGSU8 local point of contact.

3.3.19.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing results of the requirements of 3.3.1 through 3.3.19 to the SUPERVISOR.

3.3.19.2 Reports shall include all discrepancies, diagnostic

results, recommendations and material required to repair any discrepancies.

3.4 Retain all removed items for disposition instructions by SUPERVISOR.

At the discretion of SUPERVISOR, box all removed items for turnover upon boat/trailer turnover for each vessel listed in 1.3.

3.5 Accomplish the requirements of 009-90 of 2.1 for Suzuki engine installation, setup and to verify all engine related work.

3.6 Procure and install new port and starboard Suzuki engines (Suzuki part number DF250APXX0) for each vessel listed in 1.3 in accordance with 2.18.

3.6.1 Install new Seastar Tournament Series Adjustable tie bar kit for 15” to 20.5” (part number TFX HO6822) for each vessel listed in 1.3.

3.6.2 Install new port and starboard propellers Suzuki-990C0-0081L- 185 (Prop Suzuki 3 x 16 x 18.5L Left Hand) and Suzuki-990C0-00810-185 (Prop Suzuki 3 x 16 x 18.5R Right Hand) and two (2) propeller hub kits (Suzuki part number 57630-92L00) for each vessel listed in 1.3 in accordance with 2.18.

3.6.3 Remove existing port and starboard engine cable protective hoses and procure and install new port and starboard engine cable protective hoses. Template exact size, length, configuration and location from existing boat conditions using 2.18 for guidance.

3.6.4 An authorized Suzuki dealer shall setup and verify all engine related work listed in Paragraph 3.6 through 3.6.3 in accordance with

2.18 and 009-90 of 2.1. Contractor shall estimate two separate setups, one per craft.

3.7 Remove existing engine and trim control cables, binnacle, gauges, engine harnesses, engine GPS Antenna, and associated hardware.

3.7.1 Install new Dual Engine SPC Kit (Suzuki part number 67200-

SSP: HRMC-022-23 4 of 7 ITEM NO: 236-11-001

98JG6), 31’ Harness (Suzuki part number 36620-98J41), 6’ Harness extension (Suzuki part number 36620-98J20), Dual Adapter 250AP (Suzuki part number 990C0-88132), SPC Dual Engine Kit (Suzuki part number 990C0-96L76-KIT), Multifunction Gauge (Suzuki part number 990C0-96L16), 2’ N2K cable (Suzuki part number 990C0-88104), Backbone T (Suzuki part number 990C0-88110), 2nd Gauge Adapter (Suzuki part number 36667-96L11), Fluid Level Sensor (Suzuki part number 990C0- 88217), GPS Module (Suzuki part number 990C0-88122), and all additional cabling and hardware in accordance with the manufacturer’s instructions for installing the Suzuki DF250APXX engines. GPS Module antenna shall be installed on the starboard side of the hardtop, outboard of the radar scanner.

3.7.2 Contractor is responsible to install all components necessary to convert each vessel to Suzuki DF250APXX engines in accordance with manufacturer specifications, using 2.18 for guidance.

3.8 Remove existing ignition switch, kill switch and Evinrude dual switch panel assembly and associated cabling. Install new ignition switch (Honeywell part number 1TL1-2D), kill switch (Sierra part number MP40970-1), dual switch panel assembly (Suzuki part number 37100-98J21), and cabling in accordance with manufacturer’s instructions. The new ignition switches, kill switch, and dual switch panel assembly shall be connected to the new Suzuki system using 2.18 for guidance. Connect switches to the new engine wiring harness using Deutsch connectors vice cutting the harness.

3.8.1 All harnesses installed shall be procured in accordance with appropriate length for each vessel. No connections shall take place in bilge bottom.

3.8.2 Technical Representative shall update the display software to the current version.

3.9 Remove the existing steering system in its entirety to include steering wheel, tilt helm pump, power assist pump, and hydraulic lines.

Install new steering wheel, steering wheel cap, steering wheel knob, tilt helm pump (Teleflex part number HH6543), power assist pump (Teleflex part number PA1200-2), and port and starboard steering cylinders (Teleflex part number HC6845), Hardware mounting kit (Teleflex part number HA6804), 3FT steering hose (8 EA), 6FT steering hose (2 EA), and 32FT Steering hose (3 EA), through fittings class 3000 aluminum Cplg ¼ (4 EA), Compression fittings straight (3 BG), Compression fittings elbow (3 BG), Liquid TieBar Valve (SeaStar part number HA5471-2, and 8FT steering hose (SeaStar part number HO7508), using 2.12, 2.18 and manufacturer’s instructions as guidance. Template exact size, length, configuration and location from existing vessel conditions. New hydraulic lines shall be routed to new port and starboard engine in accordance with manufacturer’s instructions.

3.9.1 Fill and bleed the hydraulic steering system and refill to proper level with new steering fluid using 2.12, 2.18 and manufacturer’s instructions as guidance.

3.9.2 A certified Suzuki technician ensure the display and engine software is the current version.

3.9.3 An authorized Suzuki dealer shall setup and verify all

controls and steering related work listed in paragraphs 3.9 through

3.9.2 in accordance with 2.18.

SSP: HRMC-022-23 5 of 7 ITEM NO: 236-11-001

3.10 Dress and secure all engine and steering control system

hoses/cables throughout the vessel, including chaffing protection at all penetrations for each vessel listed in 1.3.

3.11 Drain, clean, ventilate, certify gas free, and inspect fuel tank on each vessel listed in 1.3, in accordance with the requirements of 2.21.

3.11.1 Clean interior surfaces free of loose rust, dirt, grease, lint and other foreign matter.

(V)(G) "CLEANLINESS INSPECTION"

3.12 Accomplish a visual inspection after cleaning of interior surfaces of each fuel tank cleaned in 3.11 Method for inspection shall be visual and by use of a borescope. Accept criteria for cleanliness shall be in accordance with paragraph 3.11.1

3.12.1 Submit one legible copy, in hard copy or approved

transferable media, of a report listing the results of 3.12 to the

SUPERVISOR.

(V)(G) "PRELIMINARY FUEL TANK PRESSURE TEST"

3.13 Accomplish a pressure test of the fuel tank for each vessel listed in 1.3, within the first 10 days of the start of the availability. Test pressure shall be 2 PSI, holding pressure for 10 minutes. Pressure shall not exceed 2.5 PSI. Allowed pressure drop: NONE. Apply a soapy solution that is non-corrosive and nontoxic solution to inspect for leakage.

Inspect all seams and attachments for leakage. Record results.

3.13.1 Upon completion of the preliminary tank test, blank all tank openings until final installation of fuel system fittings, hoses and hardware to prevent foreign object entry.

3.13.2 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing the results of 3.13 and

3.13.1 to the SUPERVISOR. Report shall include type, extent and locations of defects found.

3.14 Remove existing and install new fuel system, lines, fittings, filters, gauges, gaskets and filter housings using the same size and type of that removed for each vessel listed in 1.3, in accordance with 2.13.

This includes but not limited to fuel fill cap with key and sounding rod, fuel vent, fuel supply, fuel fill hoses, hose clamps, cable clams, fuel gaskets, water filter separator housings and filters, fuel shut-off valves, gauges, carbon canister and fuel tank fittings.

3.14.1 Do not procure and install in-line fuel ball pumps.

3.15 Double CRES 316 stainless steel hose clamps shall be installed at any hose to fitting connection for the oil and fuel system for each vessel listed in 1.3.

3.16 Dress and secure all fuel and oil system hoses throughout the vessel, including chaffing protection at all penetrations for each vessel listed in 1.3.

3.17 All fuel and oil hoses shall be templated from existing, shall meet appropriate length for vessel and continuous from fitting to fitting for each vessel listed in 1.3. No connections shall take place in bilge bottom.

(V)(G) "FINAL FUEL TANK PRESSURE TEST"

SSP: HRMC-022-23 6 of 7 ITEM NO: 236-11-001

3.18 After fuel tank installations are complete, accomplish a final pressure test for each vessel listed in 1.3. Pressure test fuel tank to 2 PSI, holding pressure for 10 minutes. Pressure shall not exceed 2.5 PSI.

Allowable Pressure drop: NONE. Apply a soapy solution that is non-corrosive and non-toxic solution to inspect for leakage. Inspect all seams and attachments for leakage. Record test results.

3.18.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing results of the requirements of 3.18 and 3.18.1 to the SUPERVISOR.

(V)(G) "FINAL VISUAL INSPECTION"

3.19 Completion walk thru with the SUPERVISOR prior to accomplishing Customer waterborne trials, for each vessel listed in 1.3. Contractor shall have all work and discrepancy work list compete, all electrical/electronic, and steering, propulsion equipment and safety systems tested satisfactory prior to waterborne Customer Trials. Provide a complete list of equipment that has been successfully tested prior to waterborne trials to the SUPERVISOR.

3.19.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing results of the requirements of 3.19 to the SUPERVISOR within 3 days of waterborne trials.

3.19.2 Contractor shall turn over all warranty and registration documentation at the end of the availability for the newly installed engines.

(V)(G) "WATERBORNE TRIALS"

3.20 Provide qualified personnel to operate each vessel listed in 1.3.

Provide 250 gallons of fuel for each vessel prior to waterborne trials.

Accomplish a two-hour waterborne trial for each vessel to test engines, all electrical and mechanical equipment. The Contactor shall conduct independent waterborne trials prior to customer acceptance trials to verify all work has been accomplished successfully and all systems/components are operating properly. The contractor shall top off the fuel tank between each waterborne trial.

3.20.1 Contractor shall provide a QA inspection report certifying each waterborne trial completion, and work completion, including any discrepancies identified during each waterborne trial.

3.20.2 Submit one legible copy, in approved transferrable media, of a report listing results of the requirements of 3.20 and 3.20.1 to the SUPERVISOR within 2 days of each waterborne trial completion.

3.21 Clean and degrease the bilge of each vessel listed in 1.3.

Thoroughly wash-down each vessel and bilge with soap and fresh water, rinse the seawater from all components after each waterborne trial has been performed.

3.22 Flush engine cooling system with freshwater after each waterborne trial has been performed. NO WATER IS TO BE LEFT IN THE BILGES. CLEANING

IS TO BE ACCOMPLISHED AFTER ALL TRIALS AND PRIOR TO FINAL ACCEPTANCE.

3.23 Accomplish the requirements of 009-32 of 2.1 for each new and

SSP: HRMC-022-23 7 of 7 ITEM NO: 236-11-001 disturbed surface for each vessel listed in 1.3.

4. NOTES:

4.1 Work in conjunction with 11MSC1407 and 11MSC1408 work items 321-11- 001, 583-31-002 and 631-11-001

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ITEM NO: 321-11-001

COAR: 26 PCN: SERV-L098

SERV-L097

SSP: HRMC-022-23 1 of 7 ITEM NO: 321-11-001

1.1 Title: RHIB'S Silver Ships Electrical System; replace

1.2 Location of Work:

1.2.1 Throughout Vessel

1.3 Identification:

1.3.1 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1407

1.3.2 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1408

1.3.3 Quantity (One EA), 11 Meter RHIB Trailer, Trailer Serial Number: 42XBK3631EB114671

1.3.4 Quantity (One EA), 11 Meter RHIB Trailer, Trailer Serial Number: 42XBK3635EB114673

2. REFERENCES:

2.1 Standard Items, (FY-24)

2.2 300-5107858 Rev A, Standard Electrical Installation Requirements and Nomenclature

2.3 MIL-STD-2003, Electric Plant Installation Standard Methods for Surface Ships and Submarines

2.4 TO300-AU-SPN-010 A, Fabrication, Welding and Inspection of Small Boats and Craft, Aluminum Hulls

2.5 11X42-DI-CC-01 Rev A, 11X AM Series Drawing Index

2.6 11X42-OB-CC-01 Rev A, Outboard Plan and Profile

2.7 11X42-IB-CC-01 Rev A, Inboard Plan and Profile

2.8 11X42-HS-CC-01 Rev A, Structure Arrangement

2.9 11X42-CA-CC-01 Rev A, Console Electronics Arrangement

2.10 11X42-CO-CC-01 Rev A, Collar System Plan View

2.11 11X42-E-CC-01 Rev A, Electrical Systems

2.12 11X42-AS-CC-01 Rev A, Auxiliary Systems

2.13 11X42-F-CC-01 Rev A, Fuel System

2.14 11X42-H-CC-01 Rev A, Hoisting Arrangement

2.15 11X42-T-CC-01 Rev A, Towing Arrangement

2.16 11X42-TR-CC-01 Rev A, Transport Drawings

2.17 11X42-D-CC-01 Rev A, Miscellaneous Parts

2.18 SHOXS 6800, Operation & Service Manual

SSP: HRMC-022-23 2 of 7 ITEM NO: 321-11-001

2.19 Ignition Switch, Wiring

2.20 Fuel Tank, Cap

2.21 Underwater Lights, Mounting Plates

2.22 Suzuki Engine Manual, K13-DF250AP-300AP-990111-98J20-03BEN

2.23 BOATMASTER, Operations Manual Trailer: SS11M-180

2.24 Suzuki, Console Face Layout

2.25 Bow Section, Assembly Layout

2.26 Systems and Specifications, SSPC Painting Manual, Volume 2

2.27 DOL, OSHA STD 29 CFR 1915, Occupational Safety & Health Standards for Shipyard Employment

3. REQUIREMENTS:

(I) "PRELIMINARY ELECTRICAL INSPECTION AND OPERATIONAL TEST"

3.1 Accomplish a complete inspection, and an operational test of all installed mechanical and electrical equipment, including each electrical component, lighting, navigational equipment, wiring/cabling, pump, piping, hose and label plate, using 2.2 through 2.25 as guidance, for each vessel listed in 1.3, and the location identified in 1.2. Record results.

3.1.1 Submit one legible copy, in approved transferable media, of a report listing the results of the inspection and testing requirements of 3.1 to the SUPERVISOR, within 5 days of testing.

3.1.1.1 The report shall include electrical/mechanical component item number, as identified on its associated reference, reference number, component location, condition, and the testing results of each component tested.

3.2 Prior to component removal, record each component name, as identified on its associated reference, reference number, location, and electrical connection (Disconnect Log) for each vessel listed in 1.3.

3.2.1 Retain all removed items, the SUPERVISOR shall determine disposition. At the discretion of SUPERVISOR, box each item removed for turnover upon vessel/trailer turnover to the GOVERNMENT.

3.2.1.1 Submit one legible copy, in approved transferable media, of a report listing the results of the requirements of 3.2 to the

SUPERVISOR.

3.3 All new electrical installations shall meet the electrical installation requirements of 2.2, 2.3, 2.11, 2.12, 2.13, 2.22, 2.23 and

2.24 for each vessel listed in 1.3.

3.3.1 No electrical connection shall take place in the bilge bottom.

3.3.2 All new electrical connections shall have heat shrink style connections or shall have heat-shrink tubing installed on terminal ends to weatherize.

3.3.3 All new battery and main power connections shall have

protective boots installed.

3.3.4 All new equipment, electrical components, label plates, cable markers, and wire markers, shall be installed, and wire ways and

SSP: HRMC-022-23 3 of 7 ITEM NO: 321-11-001 cableways shall be strapped and installed in accordance with 2.2, 2.3, 2.11, 2.12, 2.13, 2.22, 2.23 and 2.24 prior to operational testing for each vessel listed in 1.3.

3.3.4.1 All new cabling shall be labeled to include circuit

identification at each end.

3.3.4.2 All new wiring shall be labeled to include component

identification on each wire connection/termination point.

3.3.5 Remove corrosion on existing and coat all new and existing electrical terminals and connections, including, battery switch terminals, engine positive and negative terminals, battery connection terminals, gauge terminals, positive and negative terminal blocks, negative bus terminals, circuit breaker connections, switch connections, reset push buttons, receptacles, connectors using No-Ox (NSN 8030-00-598-5915) for each vessel listed in 1.3. Ensure all electrical connections are tight.

3.3.6 Groom, dress, and secure all existing and new cabling and wiring to ensure wire/cable runs do not interfere with access to components that are removable for each vessel listed in 1.3.

3.3.7 Install chafe protection to existing and new wires/cables entering cableways and/or where chaffing may occur for each vessel listed in 1.3.

3.3.8 Split Conduit shall be installed for each cableway, where previously installed for each vessel listed in 1.3.

3.3.9 Ensure all cable penetration are packed properly throughout each vessel listed in 1.3 in accordance with manufacturer’s instructions.

3.3.10 Ensure all exterior electrical connections are properly weatherproofed on each vessel listed in 1.3 in accordance with 2.2 and 2.3.

3.4 All new equipment mounted to aluminum shall have corrosion protection tape (3M Scotchrap #51) installed between each mating surface unless otherwise noted for each vessel listed in 1.3.

3.5 Each new threaded fastener shall be corrosion resistant steel (CRES), ASTM A276, Type 316, unless otherwise specified. Each nut shall be self-locking, unless otherwise specified. One CRES washer shall be used under each bolt head and under each nut. Bolt/stud thread protrusion shall not extend less than 1-1/2 threads or more than 5 threads beyond the nut with full thread engagement, for each vessel listed in 1.3.

3.5.1 Apply anti-seize compound, Loctite 34026 marine grade anti-seize or equal to each new stainless-steel threaded fastener.

3.6 Remove existing and install new batteries for the vessels listed in 1.3, in accordance with 2.11. Install new battery connection hardware using standard nuts and lock washers.

3.7 Procure and install new full enclosure type battery boxes for all new batteries for each vessel listed in 1.3.

3.8 Remove existing and install new battery isolator for each vessel listed in 1.3 using the same size and type of that removed.

3.9 Remove existing and install new negative bus bar for each vessel

SSP: HRMC-022-23 4 of 7 ITEM NO: 321-11-001 listed in 1.3 using the same size and type of that removed.

3.10 Accomplish the requirements of 009-90 of 2.1, for replacement of the Furuno Navigation System components, for each vessel listed in 1.3, in accordance with the manufacturer’s instructions.

3.10.1 Remove existing and install new NavNet TZTouch display (Furuno part number TZTL12F), and remote control (Furuno part number

MCU002).

3.10.1.1 Install latest version of software and charts on Furuno navigation system in accordance with manufacturer’s instructions.

3.10.1.2 Ensure navigation system is electrically connected to the existing VHF Marine Band Radio at the existing NMEA terminal strip in order to display position data at radio, installation shall be in accordance with 2.11 and 2.12 and manufacturer’s instructions.

3.10.1.3 GPS receiver shall be mounted on the port side of the radar mast, outboard of the radar scanner and connected directly to the NMEA 2000 backbone in the console, in accordance with the manufacturer’s instructions.

3.10.1.4 Navigation system shall be connected to the new Suzuki system in accordance with manufacturer’s instructions in order to display engine information.

3.10.1.5 Navigation system shall be connected to the existing NMEA terminal strip for the VHF marine band radio in accordance with 2.11 and 2.12 and manufacturer’s instructions in order to send position data to the radio.

3.10.1.6 Remove existing and replace with new NMEA 2000 backbone in accordance with 2.11 and manufactures instructions.

(Q)(G) "VISUAL INSPECTION"

3.10.1.7 An authorized Furuno technician shall verify

installation and calibration of all navigation related work.

3.10.2 Install new bus extender (Maretron Part Number NBE100) in the console in order to separate the engine NMEA 2000 from the Furuno NMEA 2000, for each vessel listed in 1.3, in accordance with the manufacturer’s instructions.

3.11 Remove existing and install new forward and aft bilge pump system, including, bilge pumps, float switches, NEMA boxes, label plates, associated cabling, hoses, hose clamps and overboard thru-hull fittings using the same size and type of that removed for each vessel listed in 1.3, and in accordance with 2.11 and 2.12.

3.11.1 Double CRES316 stainless steel hose clamp shall be installed at each hose to fitting connection.

3.11.2 Dress and secure each bilge system hose throughout the boat, including chaffing protection at each penetration.

3.11.3 All bilge hoses installed shall be templated from existing, ensuring appropriate length for the vessel and continuous from fitting to fitting.

(V)(G) "VISUAL INSPECTION"

SSP: HRMC-022-23 5 of 7 ITEM NO: 321-11-001

3.11.4 Perform manual/auto function bilge test to ensure the float switch operated properly.

3.12 Remove existing and install new fuel sending unit in the fuel tank using the same size and type of that removed for each vessel listed in 1.3, in accordance with 2.12, 2.13, 2.17, 2.20 and manufacturer’s instructions.

3.13 Remove existing and install new fuel gauge for vessels listed in 1.3, in accordance with 2.12, 2.13, 2.17, 2.20 and manufacturer’s instructions.

3.14 Install 46 each new appropriately sized toggle switch boot on each switch located on the console at Distribution Panel DP1, Control Panel 1 and battery voltage selector switch for each vessel listed in 1.3.

3.15 Remove existing and install new fasteners for UHMW mounting board inside of console for vessel listed in 1.3.2 using the same size and type of that removed.

3.16 Remove existing and install new ICOM handset and clip inside console for each vessel listed in 1.3 using the same size and type of that removed in accordance with 2.9.

3.17 Remove existing and install new ICOM COMMANDMIC and clip on console face for each vessel listed in 1.3 using the same size and type of that removed in accordance with 2.9.

3.18 Remove existing and install new NMEA bus for each vessel listed in

1.3 using the same size and type of that removed.

3.19 Remove and replace with new complete windshield wiper/washer system (motor Ongaro P/N 30991, wiper arms Ongaro P/N 33650, blades Ongaro P/N 33018, washer 2.5L Ongaro P/N 31130, spray jet Ongaro P/N 31157) and fluid supply hoses for each vessel listed in 1.3, and in accordance with

2.12 and manufacturers instruction..

3.20 Remove existing and install new Black Oak light bars and wiring including switches, using the same size and type of that removed in accordance with 2.11 and manufacturer’s instructions.

3.21 Remove existing and install new FWD search light receptacle with dust cap and lanyard on each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.11.

3.22 Remove existing and install new handheld Aqua Signal Bremen LED Search Light and mount for each vessel listed in 1.3.

3.23 Remove existing and install new AFT search light receptacle with dust cap and lanyard located on the aft deck transom for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.11.

3.24 Remove existing and install new Port and Stbd console search light receptacles with dust caps and lanyards for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.11.

3.25 Remove existing and install new 12V outlet on console for each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.11.

3.26 Remove existing and install new forward and aft bilge, and bilge blower indicator lights on the console for each vessel listed in 1.3, in

SSP: HRMC-022-23 6 of 7 ITEM NO: 321-11-001 accordance with 2.11.

3.27 Remove existing and install new hailer control head on each vessel listed in 1.3, in accordance with manufacturer’s instructions and in accordance with 2.11.

3.28 Remove existing and install new Whelen microphone and microphone clip (Whelen part number 01-026D286-06) for each vessel listed in 1.3, in accordance with manufacturer’s instructions and in accordance with 2.11.

3.29 Remove existing and install new Whelen loud hailer speaker for each vessel listed in 1.3, using the same type and size as that removed and in accordance with 2.11.

3.30 Remove existing and install new loud hailer amplifier for each vessel listed in 1.3 in accordance with 2.11.

3.31 Remove existing and install new navigation horn for each vessel listed in 1.3, using the same size and type as that removed and in accordance with 2.11.

3.32 Remove existing and install new dimmer module on each vessel listed in 1.3, using same type and size in accordance with 2.11.

3.33 Remove existing and install new Control Panel 1 Face Plate for each vessel listed in 1.3, in accordance with 2.11. Ensure new breaker labels are incorporated into new control panel.

3.34 Remove existing and install new Distribution Panel 1 face plate, for each vessel listed in 1.3, in accordance with 2.11. Ensure new breaker labels are incorporated into new distribution panel.

3.35 Remove existing and install new FWD bilge pump breaker for vessel listed in 1.3.1 with same type and size in accordance with 2.11.

3.36 Remove existing and install new CB1-150A and CB2-50A breakers for vessel listed in 1.3.2 with same type and size in accordance with 2.11.

3.37 Remove existing and install new battery voltage gauge and switch for each vessel listed in 1.3 with same type and size in accordance with 2.11.

3.38 Remove existing and install new Tiger Communications headset helmet jack and dust covers port and starboard side of console for each vessel listed in 1.3, using the same size and type as that removed and in accordance with 2.9.

3.39 Remove existing and install new console overhead dome light on each vessel listed in 1.3 and in accordance with manufacturer’s instructions and in accordance with 2.11.

3.40 Remove existing and install new lights for navigation mast for each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.11.

3.41 Remove existing and install new lights for dive restricted mast for each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.11.

3.42 Install new port Tiger Communications yellow PTT pushbutton cover Port and Starboard for each vessel listed in 1.3, using the same size and type as that removed.

3.43 Remove existing force protection light mounting brackets, clean, preserve, and reinstall force protection light mounting brackets with new

SSP: HRMC-022-23 7 of 7 ITEM NO: 321-11-001 hardware for each vessel listed in 1.3, using the same size and type of that removed in accordance with 2.11.

3.44 Remove existing and install new seven-way flat pin, round cable harness for each trailer listed in 1.3, in accordance with 2.23. Cable harness shall be spliced in accordance with 2.2.

3.45 Remove existing and install new brake solenoid, wiring and hardware for each trailer listed in 1.3, in accordance with 2.23.

3.46 Remove existing and install new port and starboard taillights for each trailer listed in 1.3, using the same size and type of that removed and in accordance with manufacturer’s instructions and 2.23.

3.47 Remove existing and install new aft center light for each trailer listed in 1.3, using the same size and type of that removed and in accordance with manufacturer’s instructions and 2.23.

(V)(G) "TRAILER LIGHTS OPERATIONAL TEST"

3.48 Operationally test each trailer light to ensure they are functioning properly.

3.48.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing the operational testing results of 3.48 within 3 days of test completion.

(V)(G) "ELECTRICAL EQUIPMENT OPERATIONAL TEST"

3.49 Coordinate with ships force and accomplish an Operational Test of each piece of newly installed electrical equipment, each electrical device, and each newly installed component listed in the contractor's furnished report requirement of 3.1.1.1, Testing shall be in accordance with 2.2 through 2.25 and the manufacturer's instructions, for each vessel listed in 1.3.

3.49.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing the operational testing results of 3.49.

3.50 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface for each vessel listed in 1.3.

4. NOTES:

4.1 Work in conjunction with 11MSC1407 and 11MSC1408 work packages 236- 11-001, 583-31-002 and 631-11-001.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

SHIP: ITEM NO: 583-31-001

COAR: 26 PCN: SERV-L092

SERV-L091

SSP: HRMC-022-23 1 of 2 ITEM NO: 583-31-001

1.1 Title: Vessel and Trailer Custody Transfer; accomplish

1.2 Location of Work:

1.2.1 Contractor's Facility

1.3 Identification:

1.3.1 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1407

1.3.2 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1408

1.3.3 Quantity (One EA), 11 Meter RHIB Trailer, Trailer Serial Number: 42XBK3631EB114671

1.3.4 Quantity (One EA), 11 Meter RHIB Trailer, Trailer Serial Number: 42XBK3635EB114673

2. REFERENCES:

2.1 Standard Items, (FY-24)

2.2 Attachment (A), Boat and Trailer Custody Form

3. REQUIREMENTS:

3.1 The Government will deliver custody of each vessel and trailer listed in 1.3 to the contractor at the place designated in the specifications, and upon completion of availability will pick-up and accept custody of the vessel and trailer at the place designated in the specifications.

3.1.1 The contractor shall be responsible for each vessel and trailer from the time of delivery to the contractor, to the return of the vessels and trailers to the GOVERNMENT.

3.2 Upon receiving custody of the vessels and trailers listed in 1.3 from the activity, complete Part A of 2.2. Submit one copy, in approved transferrable media, of 2.2 to the SUPERVISOR within 24 hours after delivery of the vessels.

3.3 After returning custody of the vessels and trailers listed in 1.3 to the activity, complete Part B of 2.2. Submit one copy, in approved transferrable media, of 2.2 to the SUPERVISOR, within 24 hours after redelivery of the vessels.

4. NOTES:

4.1 None.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

SSP: HRMC-022-23 2 of 2 ITEM NO: 583-31-001

5.2 PUSH MATERIAL:

1. None.

SHIP: ITEM NO: 583-31-002

COAR: 26 PCN: SERV-L095

SERV-L096

SSP: HRMC-022-23 1 of 8 ITEM NO: 583-31-002

1.1 Title: RHIB Silver Ships; repair

1.2 Location of Work:

1.2.1 Throughout the Vessel.

1.3 Identification:

1.3.1 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1407

1.3.2 Quantity (One EA), 11 Meter RHIB, (OPEN), Hull Identification Number: 11MSC1408

1.3.3 Quantity (One EA), 11 Meter RHIB Trailer, Trailer Serial number: 42XBK3631EB114671

1.3.4 Quantity (One EA), 11 Meter RHIB Trailer, Trailer Serial number: 42XBK3635EB114673

2. REFERENCES:

2.1 Standard Items, (FY-24)

2.2 300-5107858 Rev A, Standard Electrical Installation Requirements and Nomenclature

2.3 MIL-STD-2003, Electric Plant Installation Standard Methods for Surface Ships and Submarines

2.4 TO300-AU-SPN-010 Rev A, Fabrication, Welding and Inspection of Small Boats and Craft, Aluminum Hulls

2.5 11X42-DI-CC-01 Rev A, 11X AM Series Drawing Index

2.6 11X42-OB-CC-01 Rev A, Outboard Plan and Profile

2.7 11X42-IB-CC-01 Rev A, Inboard Plan and Profile

2.8 11X42-HS-CC-01 Rev A, Structure Arrangement

2.9 11X42-CA-CC-01 Rev A, Console & Electronics Arrangement

2.10 11X42-CO-CC-01 Rev A, Collar System Plan View

2.11 11X42-E-CC-01 Rev A, Electrical

2.12 11X42-AS-CC-01 Rev A, Auxiliary Systems

2.13 11X42-F-CC-01 Rev A, Fuel System

2.14 11X42-H-CC-01 Rev A, Hoisting Arrangement

2.15 11X42-T-CC-01 Rev A, Towing Arrangement

2.16 11X42-TR-CC-1 Rev A, Transport Drawings

2.18 SHOXS 6800, Operation & Service Manual

SSP: HRMC-022-23 2 of 8 ITEM NO: 583-31-002

2.19 Ignition Switch, Wiring

2.20 Fuel Tank, Cap

2.21 Underwater Lights, Mounting Plates

2.22 Suzuki Outboard Motor, K13-DF250AP-300AP-99011-98J20-03BEN

2.23 BOATMASTER, Operations Manual Trailer: SS11M-180

2.24 Suzuki, Console Face Layout

2.25 Bow Door, Bow Section Updates 11M NSW

2.26 Systems and Specifications, SSPC Painting Manual, Volume 2

2.27 DOL, OSHA STD 29 CFR 1915, Occupational Safety & Health Standards for Shipyard Employment

3. REQUIREMENTS:

3.1 Retain all removed items for disposition instructions by SUPERVISOR, for each vessel listed in 1.3. At the discretion of the SUPERVISOR, box all removed items for turnover upon vessel/trailer turnover.

3.1.1 Submit one legible copy, in a hard copy or approved

transferrable media, of a report listing the results of the requirements of 3.1 to the SUPERVISOR within 3 days of inspection completion.

3.2 All new threaded fasteners shall be corrosion resistant steel (CRES), ASTM A276, Type 316, unless otherwise specified. All nuts shall be self-locking type, unless otherwise specified. One CRES washer shall be used under each bolt head and under each nut. Bolt/stud length shall not exceed less than 1-1/2 threads or more than 5 threads beyond the nut with full thread engagement, for the vessel listed in 1.3.

3.2.1 Apply anti-seize compound, Loctite 34026 marine grade anti-seize or equal to all stainless steel threaded fasteners, for the vessel listed in 1.3.

3.3 All new equipment mounted to aluminum shall have corrosion protection tape (3M Scotchrap #51) installed between the mating surfaces unless otherwise noted, for the vessel listed in 1.3.

3.4 Remove existing bow door seating gasket and install new gasket for each vessel listed in 1.3 using 2.17 as guidance. Template exact size, length, configuration and location from existing vessel conditions.

Ensure bow door is watertight.

3.5 Remove existing and replace with new anchor stowage lift-off hatch assembly and gasket for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.17.

3.6 Remove existing and replace with new forward bilge compartment lift-off hatch assembly and gasket for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.17.

3.7 Remove existing anchor chain, and shackles. Install new anchor chain, and shackles for each vessel listed in 1.3, using the same size and type of that removed, using 2.17 and manufacturer’s instructions as guidance.

3.8 Remove existing and replace with new forward bilge manual pump and securing bracket for each vessel listed in 1.3 using the same size and

SSP: HRMC-022-23 3 of 8 ITEM NO: 583-31-002 type of that removed.

3.9 Remove existing (2 EA) forward inspection soft patch for each vessel listed in 1.3. Drill and tap any sheared screws. Install new hardware using same size and type of that removed and in accordance with 2.17.

Ensure panel is watertight.

3.10 Remove existing (2 EA) bow inspection soft patch for each vessel listed in 1.3. Drill and tap any sheared screws. Install new hardware using same size and type of that removed and in accordance with 2.17.

Ensure panel is watertight.

3.11 Remove existing SCUBA tank holders and hardware on port and starboard side bow and replace with new SCUBA tank holders and hardware using the same size and type of that removed in accordance with 2.6.

3.12 Remove existing console cover latches, hinges, and hardware.

Install new latches, hinges, and hardware using same size and type of that removed to vessel listed in 1.3.2 in accordance with 2.17.

3.13 Remove existing and install new transom scupper cleats, hardware and line for each vessel listed in 1.3, in accordance with 2.7.

3.14 Conduct 600-hour SHOXS seats maintenance on all seats for each vessel listed in 1.3 in accordance with Section 4 of 2.18.

3.14.1 Submit one legible copy, in hard copy or approved

transferrable media, of a report listing results of 600-hour SHOXS seat maintenance for the vessel listed in 1.3 to the SUPERVISOR.

3.15 Remove existing SHOXS seat springs, hardware, armrests, backrests, and any component showing signs of corrosion and accomplish the surface preparation of the existing component and hardware, in accordance with SSPC SP 10/NACE No. 2, Near White Metal Blast using garnet or aluminum oxide or crushed glass or walnut shells for each vessel listed in 1.3. .

3.15.1 Ensure all oxidation and corrosion is removed and there is no pitting or cracks in existing equipment.

3.15.2 Preserve all components that required surface preparation with like color of that removed to prevent future corrosion.

3.16 Remove existing non-skid on footrests and rungs throughout and replace with new on each vessel listed in 1.3 using same size and type of that removed and in accordance with manufacturer’s instructions.

3.17 Remove existing SHOXS seat bottom cushion and hardware and install new seating cushion and hardware, (One EA) Gel 6100 Cushion Part No.

124613, (4 EA) LAN Flat Washer Part No. FW LAN-0.250-316SS and (4 EA) BHCS-HX-0.250-20x0.750-316SS, for each vessel listed in 1.3 in accordance with 2.18.

3.18 Remove existing SHOXS seat bottom side cushion bolsters and hardware and install new seat bottom side cushion bolsters and hardware, (one) Right Cushion Bolster Assembly Part No. 100192, (one) Left Cushion Bolster Assembly Part No. 100295, (6 EA) LAN Flat Washer Part No. FW LAN- 0.250-316SS, (6 EA) Button Head Cap Screw Part No. BHCS-HX-0.250- 20x0.750-316SS, for each vessel listed in 1.3 and in accordance with 2.18.

3.19 Remove existing SHOXS seat backrest cushion and hardware and install new seat backrest cushion and hardware, (One EA) Backrest Assembly Part No. 100185, (4 EA) LAN Flat Washer Part No. FW LAN-0.250-

SSP: HRMC-022-23 4 of 8 ITEM NO: 583-31-002

316SS and (4 EA) BHCS-HX-0.250-20x0.750-316SS, for each vessel listed in

1.3 and in accordance with 2.18.

3.20 Remove existing SHOXS backrest side cushion bolsters and hardware and install new backrest side cushion bolsters and hardware, (One EA) Right Backrest Bolster Assembly Part No. 100188, (One EA) LH Backrest Bolster Assembly Part No. 100297, (8 EA) LAN Flat Washer Part No. FW LAN- 0.250-316SS, (8 EA) Button Head Cap Screw Part No. BHCS-HX-0.250- 20x0.750-316SS, for each vessel listed in 1.3 and in accordance with 2.18.

3.21 Remove existing SHOXS seat arm rest cushions and hardware and install new arm rest cushions and hardware (2 EA) Armrest Bolster Part No. 100206, (6 EA) LAN Flat Washer Part No. FW LAN-0.250-316SS, and (6 EA) Button Head Cap Screw Part No. BHCS-HX-0.250-20XO.750-316SS for each vessel listed in 1.3 and in accordance with 2.18.

3.22 Remove existing Ritchie compass hardware and retaining ring and replace with new on vessel listed on 1.3 using the same size and type of that removed and in accordance with manufacturer’s instructions.

3.23 Record location and engraved info and remove existing label plates throughout craft and replace with new label plates changing any that state Evinrude with Suzuki throughout each vessel listed in 1.3 using the same size and type of that removed.

3.24 Remove existing dive flag mast pin and lanyard and install new pin and lanyard for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.6.

3.25 Remove two (2 EA) mast and (One EA) VHF antenna retainers (Quick Fist) and hardware on cabin top and replace with new for each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.6.

3.26 Remove existing and replace with new VHF antenna for each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.6.

3.27 Remove existing and replace with new VHF antenna ratchet mount for each vessel listed in 1.3 using the same size and type of that removed and in accordance with 2.6.

3.28 Remove existing navigation light mast pin and lanyard and install new pin and lanyard for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.6.

3.29 Remove existing dive restricted light mast pin and lanyard and install new pin and lanyard for each vessel listed in 1.3, using the same size and type of that removed and in accordance with 2.6.

3.30 Remove existing (2 EA) boat hook holders and hardware and install (2 EA) new boat…