DRAFT - CNT11A_A-2_Reservoir_011100_9Nov21.pdf
PDF 608 KB Posted
- Solicitation number
- W912EP22Z0007
About this file
This sources sought synopsis from the U.S. Army Corps of Engineers seeks information from industry for a potential construction project to build a seepage cutoff wall and prepare foundations for an embankment dam in Palm Beach County, Florida. The project is part of the Central Everglades Planning Project and involves clearing, grubbing, demucking, foundation preparation, installation of the cutoff wall, backfilling canals, and related work along approximately 16 miles of foundation. Responses to the synopsis are due by December 14, 2021 and will be used to inform acquisition strategy for the project, estimated between $250-500 million with a performance period of 1,460 calendar days. The applicable NAICS code is 237990. Interested parties should provide details of relevant past project experience, bonding capacity, and small business classification and size standards in a response no more than five pages.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| DRAFT - CNT11A_A-2_Reservoir_Intermediate_Plans_partial_9Nov21.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Central Everglades Planning Project (CEPP) Cnt 11A, EAA A-2 EAAA2RES11A Reservoir Foundation & Cutoff Wall, Palm Beach County, Florida
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.2.3 Safety Requirements
1.2.4 Work Performed by Others
1.2.5 Order of work and Restrictions
1.3 SUBMITTALS
1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.5 LIQUIDATED DAMAGES - CONSTRUCTION
1.6 PHYSICAL DATA
1.6.1 Physical Conditions
1.6.2 Weather, Water, Stage and Tide Data
1.6.3 Contractor Investigation
1.6.4 Construction Sequence Plan
1.7 LAYOUT OF WORK
1.7.1 Established Project Control
1.7.2 Layout
1.7.3 Survey
1.8 DAMAGE TO WORK
1.9 EXISTING WORK
1.10 LOCATION OF UNDERGROUND FACILITIES
1.10.1 Notification Prior to Excavation
1.11 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
1.11.1 Schedule of Monthly Anticipated Adverse Weather Delays
1.11.2 Contractor Responsibility
1.12 UNITS OF MEASURE
1.13 SOUTH FLORIDA WATER MANAGEMENT DISTRICT
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
W912EP21R00__
DRAFT - N
OT FOR C
ONSTRUCTIO
N
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
GDR Section 00 31 32, Geotechnical Data Report forCentral Everglades Planning Project (CEPP) Contract 11A, EAA A-2 Reservoir Foundation and Cutoff Wall Palm Beach County, Florida
EM 385-1-1 Safety and Health Requirements Manual
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes clearing, grubbing, demucking, foundation preparation, installation of a seepage cutoff wall, canal backfilling, and all incidental related work to prepare approximately 16.0 miles of foundation for a 17.3 miles-long embankment dam, to be constructed under separate contract within the Everglades Agricultural Area (EAA). The approximate toe to toe width of the foundation is 260 feet in the north, east, and west; and 235 feet in the south. Dewatering will be required to control the groundwater and conduct work in the dry in accordance with contract specifications.
1.2.2 Location
The project is located in western Palm Beach County, Florida, south of Lake Okeechobee. Access to the site will be from U.S. Highway 27 approximately 13 miles south of the city of South Bay, Florida.
1.2.3 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1 .
1.2.4 Work Performed by Others
See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE
PROCEDURES.
1.2.5 Order of work and Restrictions
This contract is comprised of a base and options. The base contract will be for construction activities between stations 309+00 and 914+76. Option
SECTION 01 11 00 Page 2
W912EP21R00__
DRAFT - N
OT FOR C
1 will be for construction activities between stations 0+00 and 309+00.
Multiple construction contracts managed by both the USACE and SFWMD are ongoing both west and north of the construction limits. To minimize conflict with those contractors, upon successful completion of the demonstration sections as described in later paragraphs of this specification paragraph, work will begin at station 455+00 and may proceed both north and west along the eastern and southern embankment alignments respectively. Upon completion of work on either or both the eastern and southern embankment alignments, work will begin at station 914+76 and proceed south along the western embankment alignment. With issuance of NTP for Option 1, work will begin at station 0+00 and proceed east along the northern embankment alignment. The Contracting Officer or their duly appointed representative may remove any and all restrictions to work location within the limits of construction at any time during the execution of this project.
A 500 linear-foot cutoff wall demonstration section is required between stations 445+00 and 450+00 to prove the proposed means and methods can satisfy the performance requirements specified in Section 02 35 29 CUTOFF
WALL.
A 500 linear-foot Foundation Preparation section is required between stations 460+00 and 465+00 to prove the proposed means and methods can satisfy the performance requirements specified in Section 31 66 10 ROCK FOUNDATION PREPARATION and 31 23 24 CONTROLLED LOW STRENGTH MATERIAL
(CLSM).
As noted on contract drawings, no work is to be performed between stations
(1) 38+00 and 43+00, (2) 81+75 and 112+00, (3) 222+00 and 238+00, (4) 250+00 and 254+00, (5) 322+00 and 338+00, (6) 517+00 and 533+00, and (7) 815+00 and 831+00.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed:
SD-01 Preconstruction Submittals
Construction Sequence Plan ; G, DO
1.4 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
a. Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1. Grass must be established not later than the time stated in the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.5 LIQUIDATED DAMAGES - CONSTRUCTION
Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12) of
SECTION 01 11 00 Page 3
W912EP21R00__
DRAFT - N
OT FOR C
Section 00700 CONTRACT CLAUSES in Volume 1.
1.6 PHYSICAL DATA
Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6.1 Physical Conditions
The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and/or by core borings. When the indicated physical conditions are the result of site investigations by core borings, the core boring logs and laboratory data are in Section 00 31 32 GEOTECHNICAL DATA REPORT ( GDR) and the core boring locations are shown on the drawings. Also, see the GDR for instructions concerning availability of core borings for inspection.
1.6.2 Weather, Water, Stage and Tide Data
See Section 00 33 50 WEATHER, WATER, STAGE AND TIDE DATA. It is the Contractor's responsibility to obtain information concerning rain and wind.
1.6.3 Contractor Investigation
Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (FAR 52.236-3) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.6.4 Construction Sequence Plan
The Contractor must develop a detailed construction sequence plan to demonstrate the approach, sequence, and timing to accomplish the work within the constraints provided in the contract. The plan must contain sufficient detail and be consistent with the Contractor's proposed means and methods and project schedule. The construction sequence must be submitted for review and approval by the Government before the start of construction. Updates to the Contractor's construction sequence must also be submitted to the Government for review and approval.
1.7 LAYOUT OF WORK
Read this paragraph in conjunction with the Clause LAYOUT OF WORK (FAR 52.236-17) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.7.1 Established Project Control
The Government has established monuments along the work site(s). Each monument is represented in the contract drawings by a Designation and in most cases, an alphanumeric Permanent Identifier (PID). Information concerning the location and elevations can be found within the Survey Notes on the plan sheets. The Survey Notes for each included field survey will cite a particular survey number, and specify the control used to conduct that survey.
See Section 00 31 21 CONTROL MONUMENT DESCRIPTIONS.
1.7.2 Layout
From the monuments, control data and elevations established by the Government, complete the layout of the work and obtain all measurements
SECTION 01 11 00 Page 4
W912EP21R00__
DRAFT - N
OT FOR C
that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work.
1.7.3 Survey
Provide equipment, tools, material, labor for laying out any part of the work from the monuments, control data, and elevations established by the Government. Maintain and preserve all monuments, stakes and other marks established by the Contracting Officer until authorized to remove them, and if such marks or monuments are destroyed by the Contractor or through negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at their discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor.
The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
1.8 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work will be as set forth in Clause PERMITS AND RESPONSIBILITIES of Section 00700 CONTRACT CLAUSES in Volume 1. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable Contract unit or job prices as fixed and established in the Contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES of Section 00700 CONTRACT CLAUSES in Volume 1 will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or job prices. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment and plant shall be repaired to the satisfaction of the Contracting Officer at the Contractor's expense, regardless of the cause of such damage.
1.9 EXISTING WORK
In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.10 LOCATION OF UNDERGROUND FACILITIES
All underground utilities within the work limits must be positively
SECTION 01 11 00 Page 5
W912EP21R00__
DRAFT - N
OT FOR C
identified by a private utility locating service. Any utilities found which are not shown on the construction drawings must be brought to the Contracting Officer's attention prior to proceeding with construction.
1.10.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work. Contact "CALL SUNSHINE BEFORE YOU DIG" at 1-800-432-4770. Contractor is responsible for marking all utilities not marked by "CALL SUNSHINE".
1.11 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER (31 OCT 1989)
This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Clause DEFAULT (FIXED-PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1. In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
a. The weather experienced at the project site during the contract period must be found to be unusually severe; that is, more severe than the adverse weather anticipated for the project location during any given month.
b. The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
1.11.1 Schedule of Monthly Anticipated Adverse Weather Delays
The schedule of monthly anticipated adverse weather delays is based upon National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.
See Section 00 33 50 WEATHER, WATER, STAGE AND TIDE DATA to obtain MONTHLY
ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON 5-DAY WORK WEEK.
1.11.2 Contractor Responsibility
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the Contract, record on the daily CQC report the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. Include the number of actual adverse weather delay days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in Section 00 33 50 WEATHER AND WATER STAGE AND TIDE DATA (rounded to the nearest whole number), the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Clause DEFAULT (FIXED PRICE CONSTRUCTION) of Section 00700 CONTRACT CLAUSES in Volume 1.
1.12 UNITS OF MEASURE
The standard U.S. system of measure shall be utilized by the Contractor in
SECTION 01 11 00 Page 6
W912EP21R00__
DRAFT - N
OT FOR C
the performance of work. Any omission or inaccurate use of a unit of measure will not relieve the Contractor of their responsibilities under the Contract terms. The unit of measure used in this specification is the standard U.S. system. The contract drawings denote standard U.S. system.
If no unit of measure is indicated on the drawing such as on ranges, stations, slope elevations, and distance numbers, then they are to be considered the standard U.S. system.
1.13 SOUTH FLORIDA WATER MANAGEMENT DISTRICT
It is understood and agreed by the parties hereto that the project works being performed under this Contract are for the benefit of the South Florida Water Management District, which agency, as the representative of the State of Florida, is responsible for acquisition of lands upon which the construction is to take place. This responsibility is pursuant to authorizing legislation of the Congress of the United States of America.
It is clearly understood that the project works to be constructed herein, upon completion, will be turned over to that agency for operation and maintenance as part of the Government's project agreement obligation.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --