(CUI)
MXRD 22-0503 SOW
STATEMENT OF WORK
Natural Gas System Resiliency
Hanscom Air Force Base
Project #: MXRD220503 3 May 2022
Controlled by: 66 ABG/CE Controlled by: CEN CUI Category: Critical Infrastructure Distribution/Dissemination Controls: N/A POC: David Wong, 845-2937
STATEMENT OF WORK
Natural Gas System Resiliency
Hanscom Air Force Base
Project #: MXRD220503 3 May 2022
1. INTENT: The intent of this Task Order is to conduct a feasibility study to develop Alternatives for redundant power and heat for the Hanscom AFB natural gas tank station.
2. LOCATION: Hanscom AFB, Bedford, MA
3. PRINCIPLE FEATURES:
3.1. Feasibility Study
3.2. Construction Cost Estimate
4. GENERAL INFORMATION:
4.1. In the event of a conflict between documents provided to the A&Es, the most stringent documentation shall apply.
4.2. All work performed shall meet the intent of the Statement of Work and be done in accordance with the associated referenced codes and regulations.
5. ADMINISTRATION:
5.1. Base Civil Engineering (BCE):
Project Manager (PM):
David P. Wong, P.E., PMP, CCP david.wong.7@us.af.mil 603-714-9637
Alternate Michael Lynch michael.lynch.25@us.af.mil 781-225-6040
6. NORMAL WORKING HOURS:
6.1. The normal working hours for Hanscom AFB are the hours between 7:30 a.m. to 4:15 p.m.
excluding Saturdays, Sundays and Federal Holidays. No on-site work on Saturday, Sunday or legal holidays unless otherwise authorized by the Contracting Officer. The exclusion of work on Saturday, Sunday and legal holidays shall be considered in computing the performance time of this contract. The following federal holidays are observed in 2022:
Date Holiday
Friday, December 31, 2021* New Year's Day
Monday, January 17 Birthday of Martin
Luther King, Jr.
Monday, February 21** Washington’s Birthday
Monday, May 30 Memorial Day
Monday, June 20* Juneteenth National
Independence Day
Monday, July 4 Independence Day
Monday, September 5 Labor Day
Monday, October 10 Columbus Day
Friday, November 11 Veterans Day
Thursday, November 24 Thanksgiving Day
Monday, December 26* Christmas Day
When one of the above designated federal holidays falls on a Sunday, the following Monday will be observed as a federal holiday. When a federal holiday falls on a Saturday, the preceding Friday is observed as a holiday. Requests to perform work at other times shall be made in writing to the Contracting Officer. Every effort will be made to accommodate such requests.
7. PERIOD OF PERFORMANCE
7.1. The Period of Performance for this project is 119 Work Days. Any proposed changes to the period of performance shall be clearly identified in the Contractors proposal. The proposed schedule can be found as Attachment #1.
8 SECURITY:
8.1 The A&E shall comply with the provisions of AFI31-101 USAF Physical Security Program and all security and law enforcement procedures established at Hanscom Air Force Base. All requests for base access must be requested through the Government Representative. Additional information may be required is to a restricted area is required.
9 SITE ACCESS:
9.1 A&E and all consultants shall enter and exit a work area, as determined thru coordination with the Government Representative. Provisions shall be made to minimize disruption to occupants in adjacent areas at all times.
10 MATERIALS SPECIFIED:
10.1 No items specified shall be sole source items. All specified brand name finishes and equipment are to establish grade, quality, and style of required finishes and equipment.
10.2 All products and equipment shall comply with the Government’s Buy American Act provisions. The A&E may request a copy of the Buy American Act from the Government Representative
11 NOTICE TO PROCEED
11.1 Contract award will act as the permission to start work (Notice to Proceed).
12 REVIEW MEETINGS:
12.1 The following review meetings shall be included as part of this Task Order.
12.1.1 Project Kickoff Meeting – Virtual
12.1.2 Design Charrette Meeting – In Person
12.1.3 Draft Feasibility Study Review Meeting – Virtual
12.1.4 Pre-Final Feasibility Study Review Meeting - Virtual
12.2 Virtual meetings will be conducted via MS Teams and will be scheduled by the Government Project Manager.
12.3 In-Person meetings will be conducted in Building 1810 on Hanscom AFB.
12.4 The Contractor shall provide the meeting agendas and presentation materials at least 3 working days prior to the meeting.
13 SUBMITTALS
13.1 The Government will review each submittal. All comments will be reviewed and provided to the Contractor for incorporation into the next submittal.
13.2 The following submittals are expected as part of this Task Order. All submittals will be made electronically.
13.3 Unless relief has otherwise been granted by the Contracting Officer, the Contractor shall provide deliverables by the schedule estimates agreed upon between The Parties in Attachment 1.
Submittal Format
Draft Feasibility Report & Cost Estimate All Files (Adobe PDF)
Pre-Final Feasibility Report & Cost Estimate All Files (Adobe PDF)
Final Report & Cost Estimate All Files (Adobe PDF & Native File Formats)
14 SAFETY:
14.1 The Contractor shall comply with all requirements described and required by the Hanscom Fire Department, Base Safety Officer and OSHA.
14.2 In the event of an emergency, call 911. If dialing from a base land line phone, call 911.
15 MEASUREMENTS:
15.1 The Contractor shall verify all measurements in the field and bring any discrepancies to the attention of the Project Manager.
16 HAZARDOUS MATERIAL SURVEYS:
16.1 Hazardous materials testing is not required under this contract. If through the execution of this contract the Contractor encounters materials in which they suspect may be hazardous they should immediately notify the Government Project Manager.
17 DESCRIPTION OF OTHER SERVICES:
17.1 The Contractor shall develop alternatives to resolve natural gas system deficiencies associated with emergency power to the existing gas heater at RS-1 and a redundant heat source for gas passing through RS-1.
17.1.1 The Contractor shall develop a list of alternatives, to include the Government listed alternatives below, to be presented during the Design Charrette meeting. For each alternative presented the Contractor shall provide:
17.1.1.1 An overview of the work involved.
17.1.1.2 Extent of outages required to support the alternative.
17.1.1.3 A preliminary range of costs associated with the alternative.
17.1.2 At the conclusion of the Design Charrette meeting the Contractor will further develop up to two (2) alternatives for emergency power and three (3) alternatives for heater redundancy.
17.2 Emergency Power
17.2.1 In Jan 2022 Hanscom AFB lost commercial power. As a result it was identified that the Bruest natural gas heater did not have an alternate source of emergency power. One of the goals of this feasibility study is to identify emergency power sources for the Bruest natural gas heater. The Government has identified the following options:
17.2.2 The Contractor shall also review electrical power requirements of all other gas distribution equipment to determine if other equipment should be connected to emergency power.
17.2.3 Alternative #1: Natural Gas Generator
17.2.3.1 Under this alternative the Contractor shall size a natural gas powered emergency generator capable of handling the electrical load of the existing Bruest natural gas heater and any other identified emergency loads.
17.2.4 Alternative 2: Emergency Power Circuit
17.2.4.1 Evaluate the feasibility of extending the existing emergency power circuit located at RS-3 to the Bruest natural gas heater at RS-1 as well as any other identified emergency loads.
17.3 Gas Heater Redundancy
17.3.1 In Feb 2022, Hanscom AFB experienced an extreme winter storm. This storm highlighted the need to have a redundant source of heat in order to eliminate a single point of failure and ensure continuity of system operation. A failure of the Bruest heater affects gas that is being supplied to the Central Plant and to the base distribution system.
The Contractor shall assist the Government with the development of alternatives to ensure redundancy and that our supply system is not at risk due to a failure of the Bruest heater. The Government has identified the following options:
17.3.2 Alternative #1: Redundant Heater
17.3.2.1 This alternative would install a redundant natural gas heater adjacent to RS-1.
17.3.3 Alternative #2: Interconnection of RS-1 & RS-3
17.3.3.1 This alternative would interconnect the gas heating systems located at RS-1 and RS- 3.
17.3.4 Option #3: Interconnection of RS-4 & RS-2
17.3.4.1 Under this alternative, in the event of a failure of the Bruest heater, gas could be supplied to the base distribution by creating a connection between RS-4 and RS-2.
17.3.4.2 It is understood that this option would require the central plant to convert over to oil during the emergency and that the full requirement of gas may not be available to the Heat Recovery Steam Generator located in the cogeneration plant.
17.4 The Contractor shall take the following items into consideration when developing alternatives.
17.4.1 It is desired that the implementation of any proposed alternative does not require an interruption of service to the base distribution system.
17.4.2 In order to facilitate the proposed upgrades the CHP plant can be shut down and the Central Plant can run on fuel oil.
(END OF DOCUMENT)