This is a draft Performance Work Statement (PWS) dated December 10, 2024, for the demolition and extraction of Building 2 at NOAA's Beaufort Laboratory in Beaufort, NC. The project involves a two-story, 20,000 GSF building constructed in the 1950s that was closed due to structural deficiencies caused by seawater research operations.

The scope includes four main tasks: (1) salvaging and extraction of government property including laboratory equipment, IT peripherals, and office items from the structurally unsafe building; (2) environmental hazards survey and abatement of known asbestos-containing materials in the crawlspace; (3) building demolition while preserving adjacent Building 3 and the transformer room, including rerouting electrical services; and (4) site restoration with gravel pad installation. The contractor must provide temporary structural stabilization, handle hazardous materials, coordinate utility work, obtain required permits, and follow all federal/state/local safety requirements. Key deliverables include a project schedule within 14 days of award, safety plan within 21 days, and regular progress meetings and reports. The work requires specialized expertise in demolition with temporary shoring and environmental hazard remediation while maintaining operations of connected facilities.

View the file

Other files

File Type Posted
Sources Sought - Beaufort Laboratory Building.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(P0448) Beaufort BLDG 2 Extraction and Demolition DRAFT -Performance Work Statement (PWS)

Version 12.10.2024

National Oceanic and Atmospheric Administration U.S. Department of Commerce

PERFORMANCE WORK STATEMENT

for

FY 25 NOAA / NOS / NCCOS

for

(P0448) Beaufort Laboratory Building 2 Extraction and Demolition

Date Version

December 10, 2024 1.0

Table of Contents

PART I: INFORMATION 3

1.0. PROJECT IDENTIFICATION 3

1.1. BACKGROUND 3

1.2. PURPOSE AND SUMMARY 4

PART II: SCOPE REQUIREMENTS 4

2.0 TECHNICAL REQUIREMENTS 4

2.1 TASK001 – Salvaging and Extraction of Property 5

2.2 TASK002 – Environmental Hazards Survey and Abatement 5

2.3 TASK003 – Building Demolition 6

2.4 TASK004 – Site Restoration 6

2.5 ATTACHMENTS 6

2.6 REFERENCES 6

PART III: DELIVERABLES 8

3.1. SCHEDULE OF DELIVERABLES 8

3.2. Post Award Kickoff Meeting/Periodic Contract Meetings 9

3.3. Submittals 9

PART IV: GENERAL REQUIREMENTS 10

4.1. GENERAL 10

4.2. WORKING HOURS 10

4.3. COORDINATION WITH UTILITIES AND WORK UNDER OTHER CONTRACTORS 10

4.4. ACCESS TO THE WORKSITE 10

4.5. SAFETY AND SECURITY 10

PART V: GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES 11

5.0. GENERAL 11

PART I: INFORMATION

1.0. PROJECT IDENTIFICATION

Project Name: (P0448) Beaufort Laboratory Building 2 Extraction and Demolition

Project Location: NOAA Beaufort Laboratory

101 Pivers Island Rd, Beaufort, NC 28516

1.1. BACKGROUND

Ecology Laboratory Building #2 (Bldg. 2) is a 2-story building constructed in the late 1950s with a footprint of approximately 20,000 Gross Square Feet which was most recently utilized for both marine biological research and administrative office space. The building is constructed of Concrete Masonry Units (CMU) load bearing walls, thin poured concrete slabs supported on open web steel joists. The first floor is elevated over an approximately 4-foot high crawl space, where the building sits on concrete beams panning pile caps. The building received structural retrofit around 1993, to repair a section of the first-floor slab in the Southeast quadrant of the building where seawater research operations lead to significant corrosion of steel structural elements, and to strengthen the exterior of the building by adding an additional reinforced CMU wall on all exterior building faces.

After the 1993 retrofit, seawater research operations continued for another 15-20 years. Recent inspections of the crawl space showed concerning levels of concrete degradation for load bearing members, in correlation to the breakdown of structural steel elements in the Southeast quadrant of the building underneath the area previously utilized for seawater research. The building was immediately closed and no longer occupied.

A main electrical feed from the site’s automatic transfer switch (ATS) runs underneath Bldg. 2 and feeds into Bldg. 2’s transformer room, where it steps down and gets distributed to other neighboring buildings to the north and east of building 2. Additionally, just north of Bldg. 2 is a T-Shaped building used for administrative office space known as Building 3. Building 3 was constructed after Bldg.2 and was originally a standalone, unconnected structure. At some point in time, the separation between building 2 and building 3 was enclosed to allow a connected interior corridor for personnel.

1.2. PURPOSE AND SUMMARY

The high-level primary objective for solicitation is two-fold: 1) retrieval of government and personnel property within a building with structural deficiencies; and 2) demolitions of the building with structural deficiencies with known Asbestos Containing Material (ACM) with the building’s crawlspace.

NOAA is seeking services from for a contractor to retrieve government and personnel property in a building that has designated as structurally unsafe for normal occupancy. The contractor will be responsible for means and methods to mitigate hazards (may require Professional Structural Engineering service for temporary shoring) and ensure contractor employees are safe, in compliance with Federal and

Local requirements, while conducting salvaging and retrieval operations within the building.

After retrieval of designated property, the contractor is to demolish the building and will be responsible for environmental survey and proper handling of ACM in compliance with federal and local requirements. The contractor properly demolition and capping of all utilities servicing the building. Additionally, the contractor will be responsible for preserving and maintaining connected structures (building 3 and transformer room), developing plans and rerouting electrical service feeds to maintain existing electrical distribution and continuity of services to other portion of the property.

The contractor will be responsible obtaining all permits required for demolition and disposal activity, responsible for proper disposal of all demolition debris at the appropriate offsite facility, and restoration of the property disturbed by the demolition activity including a gravel pad at the footprint of the demolished building unless construction stormwater permits require a differing restoration surface.

PART II: SCOPE REQUIREMENTS

2.0 TECHNICAL REQUIREMENTS

Provide all labor, material, equipment and services to demolish and properly dispose of Bldg. 2 in compliance with all federal, state and local requirements and achieve the following requirements. The contractor must:

i. Temporarily stabilize the building structure as required, may require obtaining Structural PE stamped shoring plans, to make it safe for workers to enter for extraction of property and commence any hazardous material abatement/removal operations prior to demolition;

ii. Plan and execute removal and disposal of hazardous building material (asbestos) known existing within the crawlspace with limited access, with potentially existing asbestos containing material within CMU walls, with handling and disposing of common laboratory chemicals;

iii. Plan and execute selective demolition of bldg. 2 that preserves adjoining structures and functionality of building 3 and the building 2’s transformer room;

iv. Cap and abandon utility services to Bldg. 2 prior to demolition and reroute other site utilities to maintain continuity of service to other buildings impacted by Bldg. 2 demolition;

v. Demolish Bldg. 2 to grade, dispose of all demolition debris offsite at appropriate landfill, regrade and restore site with gravel layer.

2.1.1. Provide detailed cost estimates for all enhancements and/or construction as outlined for each TASK separately.

TASK001 - Salvaging and Extraction of Property TASK002 - Environmental Hazards Survey and Abatement TASK003 - Building Demolition and Offsite Disposal TASK004 - Site Restoration

a) Proposal shall clearly show labor, including hourly rates, and materials breakouts for all major scopes (TASK) and phases of the project, including subcontractor and consultant costs.

b) Proposal shall include an electronic copy of the associated cost information output in a Microsoft Excel format.

2.1 TASK001 – Salvaging and Extraction of Property

The contractor must provide all labor and services required to retrieve government and personnel property within Building 2. In general, items include tabletop laboratory equipment, IT peripherals (printers, monitors, etc), tools, personnel field equipment, office items. This includes developing and submitting work plans for approval, coordinating with stakeholders for identify items to be removed or can remain in place, for logistics on location staging/retrieval, etc.

The contractor will be responsible for means and methods to mitigate hazards (may require Professional Structural Engineering service for temporary shoring) and ensure contractor employees are safe, in compliance with Federal and Local requirements, while conducting salvaging and retrieval operations within the building.

2.2 TASK002 – Environmental Hazards Survey and Abatement

An environmental survey of Building 2 was completed in 1993. All non-plumbing related Asbestos Containing Material (ACM) identified in the survey has been previously abated – which consisted of ceiling and floor tiles. There is a segment of previously identified ACM plumbing insulation within the crawlspace that is known to remains. The 1993 report only surveyed accessible spaces.

The contractor is to assume, the interior wall cells are free of ACM. The contractor must conduct an environmental survey and conduct selective demolition to validate the plumbing insulation within walls do not contain ACM. Environmental survey report must be submitted to the government for evidence of compliance with federal regulation.

The contractor is to develop and submit work plans for conducting environmental survey, abatement activity of known ACM in the crawlspace, and abatement plan if ACM is encountered during selective demolition for surveys of potential in-wall ACM piping material.

The contractor will be responsible for means and methods to mitigate hazards (may require Professional Structural Engineering service for temporary shoring) and ensure contractor employees are safe, in compliance with Federal and Local requirements, while conducting environmental surveys within the building.

2.3 TASK003 – Building Demolition and Offsite Disposal

The contractor must provide all service, labor, material to provide demolition and proper offsite disposal of Building 2. The contractor must develop and submit workplans such as mobilization plan, proposed limit of demolition activity (laydown area, truck hauling routes, etc), site specific safety plans, dust control, stormwater protection, selective demolition plan for preserving connected structures (Building 3, and Building 2 Transformer Room) and any minor construction to preserve the structure remaining and the integrity of building envelop, and plans for utility disruption for demolition or rerouting to preserve services to other affected facilities.

All utilities (sewer, water, electrical, etc.) and conduits must not be abandoned in place. All utility infrastructure must be taken back to the nearest service distribution point, node, branch line, tee, etc.

where it is capped and must be annotated in as-built site utility plans and turned over to the owner at the end of the project.

Maintain existing electrical distribution function from Building 2’s transformer room to other neighboring building. Prior to demolition activity, trench and provide new underground conduit and electrical feeds from the Building 2 Transformer Room main distribution panel to the campus Automatic Transfer Switch (ATS) – must comply with local standards for underground utilities.

The contractor is responsible for preserving the structural and building envelop integrity of connected structures: i) Building 3, and ii) Building 2 Transformer Room. The contractor is responsible for developing and submitting planning and providing means and methods to demolish Building 2 while preserving these structures and any minor construction activity to restore structural and envelop integrity.

The contractor will be responsible for demolition and disposal offsite of all Building 2’s structure, equipment, and material to the natural grade. At the end of demolition, prior to site restoration, the only evidence of building 2 is the tops of the foundation pile caps.

2.4 TASK004 – Site Restoration

The must adhere to any conditions required by local/state/federal construction stormwater protection permits. At a minimum, the contractor must restore the site (minor cut/fill, minor imported topsoil/fill, gravel) such that the existing lawn is restored to its pre-project condition so that it is level and re-seed/sod if required.

The footprint of demolished of building 2 is to receive 2-inches depth of 3/8” gravel, with all utilities demolished outside the building footprint, taken back to the nearest in-service utility distribution point and capped below grade (where possible).

2.5 ATTACHMENTS

TBD

2.6 REFERENCES

Code Requirements

The Contractor shall perform all work in accordance with nationally recognized standard, codes, and/or regulations. Where requirements or standards conflict, the more restrictive standard or requirement must be followed, unless the Contractor brings these conflicts to the attention of the COR for clarification and resolution.

● Occupational Safety and Health Standards (OSHA) safety requirements.

29 CFR 1910 Occupational Safety and Health Standards - General Construction 29 CFR 1926 Occupational Safety and Health Standards - Construction Industry

● International model codes: International Building Code (IBC), IECC; IMC; IPC; IFC; and NEC.

● Local, state and federal codes and standards.

PART III: DELIVERABLES

3.1. SCHEDULE OF DELIVERABLES

The following items should be delivered to the government to consider the project substantially complete:

Deliverable Frequency Medium Format Copies

Project Schedule Within ten (14) calendar days after post-award meeting

ONLINE PDF and Digital File

N/A

Kick-Off Meeting Within (14) Calendar Days of Award ONLINE ONLINE N/A

Progress Meetings NEGOTIATED (Bi-weekly or weekly depending on activity in progress)

ONLINE ONLINE N/A

Safety Plan Within (21) Calendar Days of Award EMAIL PDF N/A

Meeting Minutes AFTER EACH MEETING EMAIL PDF 1

Progress Reports and schedule update

Monthly with Invoice EMAIL PDF 1

As Built Drawings Prior to Submission of Final Invoice EMAIL PDF N/A

Identification of Employees and Equipment

30 Days Prior to Arrival On-Site EMAIL TBD N/A

Identification of Equipment Delivery

3 Days Prior to Arrival EMAIL TBD N/A

Progress Invoices Monthly unless otherwise negotiated and approved by the CO

EMAIL PDF 1

Final Inspection Two (2) calendar days prior to planned completion date

Additional Items TBD TBD TBD TBD TBD

All deliverables listed above shall be submitted to the COR at the frequency, by the medium, and in the format and quantity listed above.

3.2. Post Award Kickoff Meeting/Periodic Contract Meetings

The contractor must attend post award kickoff meeting convened by the Contracting Officer (CO). The

CO, COR, and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. These meetings maybe used to apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced and appropriate action to be taken to resolve outstanding issues.

These meetings shall be at no additional cost to the government.

3.3. Submittals

The contractor shall provide the following submittals for Government review and approval before any onsite work can begin. Submittals shall be transmitted electronically and must be compatible with Microsoft Office applications, unless otherwise approved by the COR. All construction drawing submittals shall also include a hard copy. Upon approval of submittals, the COR will notify the contractor.

Required Pre-Construction Submittals:

a) List of Contract Personnel

(Appointment letters for Project Manager, Site Superintendent, and SSHO)

b) Schedule of Values

c) Detailed Project Schedule

d) Site Specific Safety Plan

e) As-built drawings

f) Submittals as listed in the submittal register in the specifications.

PART IV: GENERAL REQUIREMENTS

4.1. GENERAL

The Contractor must provide on-site supervision of all Contractor employees, subcontractors, or other affiliates of the Contractor while on Government property for the duration of the contract period of performance. At no time shall a NOAA representative provide direction/supervision of the Contractor employees or subcontractors. The Contractor is responsible for obtaining all permits required by local agencies and pay all fees which may be required for the performance of the work. The Government does not warranty any documents provided to be free from discrepancies, ambiguities, errors, omissions, or changing conditions. It is the responsibility of the Contractor to confirm existing conditions and resolve discrepancies between documents.

4.2. WORKING HOURS

Regular working hours TBD. “Regular Working Hours” means hours a contractor can expect to be allowed to perform work on site, or be able to contact the office.

Anything outside “Regular Working Hours” must be done by permission of the Contracting Officer’s Representative (COR) only and request must be submitted 14 calendar days prior to such work to allow arrangements to be made by the Government for potential impacts of the work in progress, giving the specific dates, hours, location, and type of work to be performed. Based on the justification provided, the COR may approve work outside regular hours.

Observance of Legal Holidays and Site Closure Information The Contractor shall observe any federal holidays set forth in the Department of Labor Wage Determinations, if the holiday falls within the period of performance of this contract. In the event of a site dismissal or closure due to weather, emergency or other circumstances, the Contractor is instructed to contact the COR.

4.3. COORDINATION WITH UTILITIES AND WORK UNDER OTHER CONTRACTORS

The Contractor shall, as needed, coordinate and cooperate with Public Utilities and adhere to their work requirements. The Contractor should work closely and early with local utility providers to ensure the work is completed on time. The Contractor must not use a utility’s scheduling to justify delays.

The Contractor must cooperate with other contractors performing work at federal facility. All work related to electrical or mechanical items must be coordinated with the COR and designated onsite government representative with advance notification - unless stated elsewhere, minimum of 5 business days’ notice.

4.4. ACCESS TO THE WORKSITE

4.5. SAFETY AND SECURITY

All work shall be conducted in a safe manner and shall comply with station regulations, Department of Labor Standards, local and state requirements. The government will not provide safety equipment to the contractor. The Contractor’s work site may be inspected during performance of the contract for EPA, OSHA and station safety violations. It will be the contractor’s responsibility to rectify any violations immediately.

The contractor shall report any accidents that occur during the performance of the contract to the COR or a designated representative, within 24-hours of an occurrence.

Security and Work In Progress

The Contractor is responsible for its own security arrangement including its subcontractor’s material, equipment, and personnel. The Contractor is responsible for the protection and safe keeping of all work in progress prior to occupancy or final acceptance by the Government. The Contractor must use plastic sheeting where required to prevent the spread of dust and grime to the surrounding work spaces or into ventilation systems

4.5.1. Safety

The contractor must develop a site-specific safety plan in addition to complying with the requirements of Occupational Safety and Health Administration (OSHA) 29 CFR, Part 1926, Safety and Health Regulations for Construction. The Contractor is responsible to ensure its work does not affect the safety of the public or employees of the Government and at its own expense furnish, install, and maintain such guards, fences, barricades, railing, light, signs, or other devices necessary to prevent accidents, injury to personnel or damage to equipment. Neither the Government nor its representatives shall bear any responsibility for safety precautions at the project work site.

PART V: GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

5.0. GENERAL

There will not be Government Furnished Equipment (GFE) for this contract. When utilities at the facility are available for the contractor’s use in performance of duties outlined in this PWS. The contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities.